Y. SAVARIMUTHU Vs THE STATE OF TAMIL NADU .
Bench: HON'BLE MR. JUSTICE ROHINTON FALI NARIMAN, HON'BLE MR. JUSTICE VINEET SARAN
Judgment by: HON'BLE MR. JUSTICE ROHINTON FALI NARIMAN
Case number: C.A. No.-004495-004496 / 2019
Diary number: 30659 / 2015
Advocates: M. A. CHINNASAMY Vs
B. BALAJI
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
‘REPORTABLE’ IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.4495-4496 OF 2019 (Arising out of SLP (C)Nos. 30945-30946 of 2015)
Y. SAVARIMUTHU Appellant(s)
VERSUS
STATE OF TAMIL NADU & ORS. Respondent(s)
J U D G M E N T
R. F. NARIMAN, J.
Leave granted.
The present appeals relate to whether a notice under
Section 80 of the Code of Civil Procedure (CPC) has been
given to the State of Tamil Nadu in terms of the Section or
in substantial compliance thereof.
The appellant is a Government Contractor who has
executed various works in the National Highways, P.W.D. and
Electricity Board. On 15.10.1997, the appellant and
respondent No.2 entered into an agreement for strengthening
the existing two-lane pavement of NH7 from a particular
kilometer point from Madurai to Kanyakumari. As per the
agreement, the work ought to have been completed in 18
months. The site was handed over to the appellant on
20.10.1997, but, in the course of the progress of work, the
appellant stated that due to delay caused by the
1
CIVIL APPEAL NOS.4495-4496 OF 2019
respondents, he was not able to progress and complete the
work in time. The immediate reason why the appellant had to
knock at the doors of the High Court was an order dated
16.12.1999 passed by the Superintending Engineer partially
terminating the contract on the ground that the plaintiff-
appellant has not shown sufficient progress in the execution
of the said work. The plaintiff-appellant first filed a
Writ Petition before the Madras High Court, which, by a
judgment dated 24.12.1999, rejected the Writ Petition,
stating that an adequate alternative remedy existed in terms
of filing of a Civil Suit. This was appealed against by the
appellant, which appeal substantially met the same fate by
the order dated 10.07.2000, by which the Writ Appeal was
dismissed, and it was stated that an adequate alternative
remedy existed by way of arbitration.
In between the learned Single Judge’s judgment and the
Division Bench judgment dismissing the Writ Appeal, the
appellant sent a legal notice dated 14.01.2000 in which the
appellant made it clear that he had completed the work to
the extent of Rs.1,25,00,000/- in spite of delay in
approving the pre-level work and fitness of the plant. He
also mentioned that the original period of 18 months was
extended up to 30.03.2000 for the reason that there was
delay on the part of the Department. Despite this, an order
of 16.12.1999 was made even before the said extension came
2
CIVIL APPEAL NOS.4495-4496 OF 2019
to an end, by which the contract was partially terminated.
It was for this reason that he stated that it was necessary
for him to have gone to the High Court by way of a Writ
Petition. It is further stated that the Writ Petition was
dismissed on 24.12.1999 and that the appellant had decided
to file a Writ Appeal against the said order. Despite this,
however, the appellant made it clear that the part-
termination, even before the expiry of the extended time, is
arbitrary and equally arbitrary is the fresh tender that had
been called for without issuing any notice to the appellant
for which he would take “appropriate legal actions” as
available in law, holding the State liable for all costs and
consequences. This legal notice was followed by two other
letters, one dated 25.01.2000, and the other dated
29.01.2000. The letter dated 29.01.2000 went on to state
that he is challenging the partial termination of the
contract and enclosing a list of payments due for the work,
which, at that point of time, amounted to a sum of Rs.88.06
lakhs.
Since the Writ Appeal had also been dismissed and
since the remedy of arbitration could not be availed of as
claims of above Rs.2 lakhs were not arbitrable, but ought to
be decided in a Civil Suit, the appellant filed O.S. No.
2/2002 on 12.09.2002 in the Court of the Special Judge at
Virudhunagar. After setting out the fact that the partial
3
CIVIL APPEAL NOS.4495-4496 OF 2019
termination was bad in law, the appellant prayed for a
declaration that the partial termination order dated
16.12.1999 is illegal and void and that a sum of Rs.3.30
crores with interest of 15 per cent per annum be granted to
him as these were the amounts owing to him by the State.
The learned Additional District Judge by his judgment
dated 29.06.2007 found that there was substantial compliance
of section 80 CPC, given the fact that the notice dated
14.01.2000 was clearly sent to the three authorities in
question and served on them. Further, the cause of action
and reliefs claimed were also substantially set out both in
the notice as well as in the letter dated 29.01.2000 already
referred to hereinabove.
After citing case law, the learned Additional District
Judge found that there was a substantial compliance with the
provisions of section 80 CPC. On merits, ultimately, the
appellant was awarded a sum of Rs.87,01,200/- together with
interest at the rate of 6 per cent per annum.
Being dissatisfied with the judgment of the learned
Additional District Judge, both the appellant as well as the
State filed appeals. These appeals were disposed of by the
High Court in which the High Court found that the provision
of Section 80 CPC was mandatory and that “full particulars”
as mentioned by the said provision was not given in the so-
4
CIVIL APPEAL NOS.4495-4496 OF 2019
called notices that were sent under section 80, and,
therefore, allowed the appeal of the State on the
preliminary ground itself and stated that the Suit as filed
would not be maintainable as it was filed without complying
with the provisions of section 80 CPC.
Learned counsel appearing on behalf of the appellant
has submitted, based on the legal notice together with the
letters sent by the appellant, that substantial compliance
with section 80 CPC has been made in the present case as was
correctly found by the learned Additional District Judge.
The High Court went in error in not adverting to substantial
compliance of Section 80 but acted as if section 80 was a
rigid provision which, like the Laws of the Medes and
Persians, could not be bent at all. He cited certain
judgments to show that, by the 1976 amendment to the Code of
Civil Procedure, section 80(3) was added making it clear
that so long as the State was put on notice and properly
served, and so long as the cause of action and the prayer in
the Suit was substantially communicated, this must be held
to be sufficient compliance with the provision.
On the other hand, learned counsel appearing on behalf
of the State has argued before us that it is clear that
there was no notice at all issued under Section 80 CPC for
the reason that none of the three notices/letters relied
upon by the appellant had stated that they were under
5
CIVIL APPEAL NOS.4495-4496 OF 2019
Section 80 CPC. He has also argued that these notices were
issued prior to the disposal of the Writ Appeal which was
still pending, as a result of which, the object of giving a
notice, that is for the Government to settle the claim,
could not have taken place as it is well-known that the
Government can never settle claims which are sub-judice. He
has also argued that none of the notices were issued after
the Writ Appeal was dismissed, which alone could have
qualified as notices, if at all, before filing the present
Suit. He has also buttressed his submissions with reference
to certain decisions of this Court.
Section 80 CPC is set out as follows:
“80.Notice.-
(1) Save as otherwise provided in sub-section (2), no suits shall be instituted against the Government(including the Government of the State of Jammu & Kashmir) or against a public officer in respect of any act purporting to be done by such officer in his official capacity, until the expiration of two months next after notice in writing has been delivered to, or left at the office of-
(a) in the case of a suit against the Central Government, except where it relates to a railway, a Secretary to that Government;
(b) in the case of a suit against the Central Government where it relates to railway, the General Manager of that railway;
(bb) in the case of a suit against the Government of the State of Jammu and Kashmir the Chief Secretary to that Government or any other officer authorised by that Government in this behalf;
(c) in the case of a suit against any other State Government, a Secretary to that Government or the Collector of the district;
6
CIVIL APPEAL NOS.4495-4496 OF 2019
and, in the case of a public officer, delivered to him or left at this office, stating the cause of action, the name, description and place of residence of the plaintiff and the relief which he claims; and the plaint shall contain a statement that such notice has been so delivered or left.”
(2) A suit to obtain an urgent or immediate relief agianst the Government (including the Government of the State of Jammu & Kashmir) or any public officer in respect of any act purporting to be done by such public officer in his official capacity, may be instituted, with the leave of the Court, without serving any notice as required by sub-section (1); but the Court shall not grant relief in the suit, whether interim or otherwise, except after giving to the Government or public officer, as the caes may be, a resaonable opportunity of showing cause in respect of the relief prayed for in the suit:
Provided that the Court shall, if it is satisfied, after heairng the parties, that no urgent or immediate relief need be granted in the suit, return the plaint for presentation to it after complying with the requirements of sub-section (1).
(3) No suit instituted agianst the Government or against a public officer in respect of any act purporting to be done by such public officer in his official capacity shall be dismissed merely by reason of any error or defect in the notice referred to in sub-section (1), if in such notice-
(a) the name, description and the residence of the plaintiff had been so given as to enable the appropriate authority or the public officer to identify the person serving the notice and such notice had been delivered or left at the office of the appropriate authority specified in sub-section (1), and
(b) the cause of action and the relief claimed by the plaintiff had been substantially indicated.”
Even at a time when Section 80(3) was not available,
this Court in Dhian Singh Sobha Singh & Another v. Union of
India, (1958) SCR 781 made it clear that Section 80, which
must be strictly complied with, cannot be construed in a
7
CIVIL APPEAL NOS.4495-4496 OF 2019
pedantic manner completely divorced from common sense.
“We are constrained to observe that the approach of the High Court to this question was not well founded. The Privy Council no doubt laid down in Bhagchand Dagadusa v. Secretary of State [(1927) L.R.54 I.A. 338] that the terms of this section should be strictly complied with. That does not however mean that the terms of the notice should be scrutinized in a pedantic manner or in a manner completely divorced from common sense. As was stated by Pollock C. B. in Jones v. Nicholls [(1844) 13 M.&W. 361, 363; 153 E.R. 149, 150] "We must import a little common sense into notices of this kind." Beaumont C.J. also observed in Chandu Lal Vadilal v. Government of Bombay [I.L.R. [1943] Bom.128] : "One must construe section 80 with some regard to common sense and to the object with which it appears to have been passed..........." If the terms of the notice in question be scrutinized in this manner it is abundantly clear that the relief claimed by the appellant was the re-delivery of the said two trucks or in the alternative payment of Rs.3,500 being the value thereof. The value which was placed by the appellants on the trucks was the then value according to them - a value as on August 1, 1942, the date on which the delivery of the trucks ought to have been given by the respondent to the appellants. The appellants could only have demanded that sum as on the date of that notice. They could not sensibly enough have demanded any other sum. If the respondent had complied with the terms of that notice then and there and re-delivered the trucks to the appellant, nothing further needed to be done. If on the other hand instead of re-delivering the trucks it paid to the appellant the value thereof then also it need not have paid anything more than Rs.3,500 to the appellant, on that alternative. If, however, the respondent failed and neglected to comply with the requisitions contained in that notice the appellants would certainly be entitled to recover from the respondent the value of the said trucks in the alternative on the failure of the respondent to re-deliver the same to the appellants in accordance with the terms of the decree ultimately passed by the Court in their favour. That date could certainly not be foreseen by the appellants and it is contrary to all reason and common sense to expect the appellants to have made a claim for the alternative value of the said two trucks as of that date. The respondent was and ought
8
CIVIL APPEAL NOS.4495-4496 OF 2019
to have been well aware of the situation as it would develop as a result of its non-compliance with the terms of that notice and if on January 8, 1943, the appellants in the suit which they filed for wrongful detention of the said trucks claimed re-delivery of the said trucks or in the alternative Rs.3,500 as their value and reserved their right to claim the further appreciation in the value of the trucks by reason of the rise in prices thereof up to the date of the decree by paying additional court-fee in that behalf, it could not be laid at their door that they had not made the specific demand in their notice to the respondent under s.80 of the Code of Civil Procedure and that therefore their claim to recover anything beyond Rs.3,500 was barred under that section. A common sense reading of the notice under s.80 would lead any Court to the conclusion that the strict requirements of that section had been complied with and that there was no defect in the same such as to disentitle the appellants from recovering from the respondent the appreciated value of the said two trucks as at the date of the judgment. It is relevant to note that neither was this point taken by the respondent in the written statement which it filed in answer to the appellants' claim nor was any issue framed in that behalf by the Trial Court and this may justify the inference that the objection under s.80 had been waived. The point appears to have been taken for the first time before the High Court which negatived the claim of the appellants for the appreciated value of the said trucks.”
In Vithalbhai (P) Ltd. v. Union Bank of India, (2005)
4 SCC 315, this Court, in paragraph 10, cited certain
judgments which made it clear that the object of the said
Section is the advancement of justice and the securing of
public good by avoidance of unnecessary litigation.
“10.Under Section 80 CPC no suit shall be instituted against the Government or a public officer until the expiration of two months next after service of notice in writing in the manner set out in the provision and if filed before the expiry of said period, the suit is not maintainable because there is clearly a public purpose underlying the provision. “The object of the
9
CIVIL APPEAL NOS.4495-4496 OF 2019
section is the advancement of justice and the securing of public good by avoidance of unnecessary litigation” (See Bihari Chowdhary v. State of Bihar (1984) 2 SCC 627). In Butchiraju (Vaddadi) v. Doddi Seetharamayya (AIR 1926 Mad 377) the suit was for a sum of money which had not become payable on the date of the suit but became payable since. Viswanatha Sastri, J. (as His Lordship then was) held that the Court could pass a decree for the recovery of money. Reliance was placed on a Full Bench decision in A.T. Raghava Chariar v. O.M. Srinivasa Raghava Chariar (ILR (1917) 40 Mad 308) and a few other cases. Here, in all fairness, it may be mentioned that in Rangayya Naidu (Mylavarapu) v. Basana Simon (AIR 1926 Mad 594), Spencer, J. has held that if a suit is premature at the date of institution, though not at the date of decision, a decree cannot be granted and the only course in such cases is to dismiss the suit with liberty to bring a fresh suit upon a proper cause of action. It is pertinent to note that Butchiraju case was decided on 5-10-1925 while Rangayya Naidu case was decided on 7-10-1925 but the former decision though of a prior date was not brought to the notice of the Court deciding the latter case.”
In Ghanshyam Dass and Others v. Dominion of India and
Others, (1984) 3 SCC 46, this Court went into the amendment
made by the Law Commission and stated:
“17. Section 80 of the Code is but a part of the Procedure Code passed to provide the regulation and machinery, by means of which the courts may do justice between the parties. It is therefore merely a part of the adjective law and deals with procedure alone and must be interpreted in a manner so as to subserve and advance the cause of justice rather than to defeat it. In Sangram Singh v. Election Tribunal, Kotah (1955) 2 SCR 1 Vivian Bose, J. in his illuminating language dealing with the Code of Civil Procedure said :
It is procedure, something designed to facilitate justice and further its ends: not a penal enactment for punishment and penalties; not a thing designed to trip people up. Too technical a construction of sections that leaves no room for reasonable elasticity of interpretation should therefore be guarded
10
CIVIL APPEAL NOS.4495-4496 OF 2019
against (provided always that justice is done to both sides) lest the very means designed for the furtherance of justice be used to frustrate it.
18. Our laws of procedure are based on the principle that “as far as possible, no proceeding in a court of law should be allowed to be defeated on mere technicalities”. Here, all the requirements of Section 80 of the Code were fulfilled. Before the suit was brought, the Dominion of India received a notice of claim from Seth Lachman Dass. The whole object of serving a notice under Section 80 is to give the Government sufficient warning of the case which is going to be instituted against it (sic so) that the Government, if it so wished, (sic can) settle the claim without litigation or afford restitution without recourse to a court of law. That requirement of Section 80 was clearly fulfilled in the facts and circumstances of the present case.
19. It is a matter of common experience that in a large majority of cases the Government or the public officer concerned make no use of the opportunity afforded by the section. In most cases the notice given under Section 80 remains unanswered till the expiration of two months provided by the section. It is also clear that in a large number of cases, as here, the Government or the public officer utilised the section merely to raise technical defences contending either that no notice had been given or that the notice actually given did not comply with the requirements of the section. It is unfortunate that the defendants came forward with a technical plea that the suit was not maintainable at the instance of the plaintiffs, the legal heirs of Seth Lachman Dass, on the ground that no fresh notice had been given by them. This was obviously a technical plea calculated to defeat the just claim. Unfortunately, the technical plea so raised prevailed with the High Court with the result that the plaintiffs have been deprived of their legitimate dues for the last 35 years.
20. The Law Commission in the Fourteenth Report, Volume 1 on the Code of Civil Procedure, 1908 at p. 475 made a recommendation that Section 80 of the Code should be deleted. It was stated as follows:
The evidence disclosed that in a large majority of cases, the Government or the public officer made no use of the opportunity afforded
11
CIVIL APPEAL NOS.4495-4496 OF 2019
by the section. In most cases the notice given under Section 80 remained unanswered till the expiry of the period of two months provided by the section. It was also clear that in a large number of cases, governments and public offices utilised the section merely to raise technical defences contending either that no notice had been given or that the notice actually given did not comply with the requirements of the section. These technical defences appeared to have succeeded in a number of cases defeating the just claims of the citizens.
21. The Law Commission in the Twenty-Seventh Report on the Code at pp.21-22 reiterated its earlier recommendation for deletion of Section 80 and in the Fifty-Fourth Report at p.56 fully concurred with the recommendation made earlier. In conformity with the recommendation of the Law Commission, Section 80 has undergone substantial changes. By Section 27 of the Code of Civil Procedure (Amendment) Act, 1976 which was brought into effect from February 1, 1977, the existing Section 80 has been renumbered as Section 80(1) and sub-sections(2) and (3) have been inserted. Sub-section (2) as inserted has been designed to give an urgent and immediate relief against the Government or the public officer with the leave of the court. But the court shall not grant relief in the suit, whether interim or otherwise, except after giving to the Government or public officer, as the case may be, a reasonable opportunity of showing cause in respect of the relief prayed for in the suit. Proviso to sub-section (2) enjoins that the court shall, if it is satisfied, after hearing the parties that no urgent or immediate relief need be granted in the suit, return the plaint for presentation to it after complying with the requirements of sub-section (1).
xxx xxx xxx
23. By sub-section (3), Parliament has brought in the rule of substantial compliance. The present suit would be directly covered by sub-section (3) of Section 80 so introduced if the suit had been brought after February 1, 1977. Unfortunately for the plaintiffs, Section 97 of the Amendment Act provides that the amendment shall not apply to pending suits and the suits pending on February 1, 1977 have to be dealt with as if such amendment had not been made. Nevertheless the courts must have due regard to the change in law brought about by sub-section (3) of
12
CIVIL APPEAL NOS.4495-4496 OF 2019
Section 80 of the Code introduced by the Amendment Act w.e.f. February 1, 1977. Such a change has a legislative acceptance of the rule of substantial compliance laid down by this Court in Dhian Singh Sobha Singh (1958) SCR 781 and Raghunath Dass (1969) 1 SCR 450. As observed in Dhian Singh Sobha Singh case, one must construe Section 80 with some regard to common sense and to the object with which it appears to have been enacted. The decision in S.N. Dutt v. Union of India case (1962) 1 SCR 560, does not accord with the view expressed by us and is therefore overruled.”
In another recent judgment in State of A.P. and Others
v. Pioneer Builders, A.P., (2006) 12 SCC 119, this Court
again referred to the Law Commission Report and held as
follows:
“14. From a bare reading of sub-section (1) of Section 80, it is plain that subject to what is provided in sub-section (2) thereof, no suit can be filed against the Government or a public officer unless requisite notice under the said provision has been served on such Government or public officer, as the case may be. It is well-settled that before the amendment of Section 80 the provisions of unamended Section 80 admitted of no implications and exceptions whatsoever and are express, explicit and mandatory. The Section imposes a statutory and unqualified obligation upon the Court and in the absence of compliance with Section 80, the suit is not maintainable. (See: Bhagchand Dagadusa v. Secretary of State for India in Council AIR 1927 P.C. 176; Sawai Singhai Nirmal Chand v. Union of India (1966) 1 SCR 986 and Bihari Chowdhary v. State of Bihar (1984) 2 SCC 627). The service of notice under Section 80 is, thus, a condition precedent for the institution of a suit against the Government or a public officer. The legislative intent of the Section is to give the Government sufficient notice of the suit, which is proposed to be filed against it so that it may reconsider the decision and decide for itself whether the claim made could be accepted or not. As observed in Bihari Chowdhary, the object of the Section is the advancement of justice and the securing of public good by avoidance of unnecessary litigation.
15. It seems that the provision did not achieve the
13
CIVIL APPEAL NOS.4495-4496 OF 2019
desired results inasmuch as it is a matter of common experience that hardly any matter is settled by the Government or the public officer concerned by making use of the opportunity afforded by said provisions. In most of the cases, notice given under Section 80 remains unanswered. In its 14th report (reiterated in the 27th and 54th Reports), the Law Commission, while noting that the provisions of this section had worked a great hardship in a large number of cases where immediate relief by way of injunction against the Government or a public officer was necessary in the interests of justice, had recommended omission of the Section. However, the Joint Committee of Parliament, to which the Amendment Bill 1974 was referred, did not agree with the Law Commission and recommended retention of Section 80 with necessary modifications/relaxations.
16. Thus, in conformity therewith, by the Code of Civil Procedure (Amendment) Act, 1976 the existing Section 80 was renumbered as Section 80(1) and sub- sections (2) and (3) were inserted with effect from 1-2-1977. Sub-section (2) carved out an exception to the mandatory rule that no suit can be filed against the Government or a public officer unless two months' notice has been served on such Government or public officer. The provision mitigates the rigours of sub- section (1) and empowers the Court to allow a person to institute a suit without serving any notice under sub-section (1) in case it finds that the suit is for the purpose of obtaining an urgent and immediate relief against the Government or a public officer. But, the Court cannot grant relief under the sub- section unless a reasonable opportunity is given to the Government or public officer to show cause in respect of the relief prayed for. The proviso to the said sub-section enjoins that in case the Court is of the opinion that no urgent and immediate relief should be granted, it shall return the plaint for presentation to it after complying with the requirements of sub-section (1). Sub-section (3), though not relevant for the present case, seeks to bring in the rule of substantial compliance and tends to relax the rigour of sub-section (1).”
On a perusal of the notice dated 14.01.2000, it is
clear that this is a legal notice sent by a lawyer of the
appellant to the authorities concerned. It is not disputed
14
CIVIL APPEAL NOS.4495-4496 OF 2019
that it was by registered A.D. and served upon the
authorities. There is also no dispute that the cause of
action is sufficiently set out in the said notice, which is
the illegality of the partial termination of the contract on
16.12.1999. It was also made clear that though a Writ
Appeal at that point of time was going to be filed against
the Writ Petition dismissal, yet this would be a notice to
take “appropriate legal action” against the State. There is
no doubt, whatsoever, that more than two months have elapsed
from the date of this notice, after which the Suit has been
filed. In fact, the Suit was filed long after, on
12.09.2002. Quite apart from this, on 29.01.2000 also, the
letter of the appellant made it clear to the Divisional
Engineer that not only is the partial termination bad in law
but that the payments due for work would have to be made.
It is clear, therefore, that there is sufficient
compliance with the provisions of Section 80 CPC as has been
introduced by the Amendment Act introducing section 80(3)
into the Statute book. The respondents’ argument that
section 80 is not expressly referred to and that the legal
notice and letters were written prior to the disposal of the
Writ Appeal have no legs to stand on. This is for the
reason that a notice does not have to state the section
under which it is made so long as the ingredients of sub-
section (3) of section 80 are met. It is admitted that
15
CIVIL APPEAL NOS.4495-4496 OF 2019
there was no need for any legal notice before filing the
Writ Appeal. The notice, therefore, that was sent on
14.01.2000, was only under Section 80 CPC in the event the
Writ Appeal failed and a Suit would have to be filed.
We are, therefore, of the view that the learned
Additional District Judge’s judgment was correct. In this
view of the matter, we set aside the impugned judgment of
the High Court and remit the matter to the High Court to
dispose of the two appeals on merits. Further, considering
this is a Suit of the year 2002, we request the High Court
to take up these appeals and dispose of the same at the
earliest.
The appeals stand disposed of accordingly.
……………………………………………………………., J. [ ROHINTON FALI NARIMAN ]
……………………………………………………………., J. [ VINEET SARAN ]
New Delhi; April 30, 2019.
16