VENKATESH CONSTRN.CO. Vs KARNATAKA VIDYUT KARKHANE LTD.(KAVIKA)
Bench: T.S. THAKUR,A.K. SIKRI,R. BANUMATHI
Case number: C.A. No.-000461-000462 / 2016
Diary number: 31945 / 2010
Advocates: PARTHA SIL Vs
E. C. VIDYA SAGAR
Page 1
REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 461-462 OF 2016 (Arising out of SLP (C) Nos.29680-29681 of 2010)
VENKATESH CONSTRUCTION COMPANY ….Appellant
Versus
KARNATAKA VIDYUTH KARKHANE LIMITED (KAVIKA) ...Respondent
J U D G M E N T
R. BANUMATHI, J.
Leave granted.
2. These appeals assail the judgment dated 15.06.2010 in
R.F.A. Nos.1051 of 2003 and 1076 of 2003, by which the High Court
of Karnataka vide the common impugned judgment reversed the
judgment of the trial court and allowed the appeal of respondent-
defendant. While doing so, the High Court dismissed the cross-appeal
preferred by the appellant-plaintiff.
3. Briefly stated case of the appellant-plaintiff is that
appellant-company is engaged in construction of dams and other civil
works and registered as a civil contractor for the Government of 1
Page 2
Karnataka amongst others. The respondent-defendant invited tender
on 17.08.1991 “for constructing a compound wall along the boundary
line of Kavika and also for constructing underground sump, shed to
store useful laminations and also core assembly shop for these works”.
The appellant responded to the said tender and appellant’s tender was
accepted by the respondent. On 12.02.1992, a contract was executed
between the appellant and the respondent incorporating the terms
and conditions and the cost of work was estimated at Rs.10,86,200/-.
The appellant had quoted the rates on the premise that the earth work
for the foundation was to the depth of 1.5 metres and average width of
4.25 metres. However, after the work commenced, even while digging
earth to one foot depth, it was noticed that soil was caving in and
there was seepage of water from Vrushabhavathi river. The appellant
was instructed by the respondent’s engineers to dig earth up to four
metres depth until hard soil bed is reached. Accordingly, in order to
make a trench of four metres depth, appellant had to excavate earth
commencing from width of six metres at the ground level and the
entire nature of work changed and appellant had to incur additional
expenses on account of the changed plan. The changed measurements
were verified by the engineers nominated by the respondent and a
payment of Rs.4,50,000/- was made in two running bills. The
respondent then asked the appellant to stop the work till the new
2
Page 3
designs are given by the respondent which was not forthcoming. Vide
several letters appellant sought permission for continuation of the
work, but, there was no response from the respondent. Finally, after
issuing legal notice dated 15.03.1993, for which no reply was given by
the respondent. The appellant filed a civil suit being Original Suit
No.11037 of 1993 in the court of Additional City Civil Judge,
Bangalore, making a claim of rupees thirty lakhs under various heads,
interalia, on the work already completed, towards the extra earth
work, stocking of materials and also liquidated damages and others.
4. Admitting the execution of the contract dated 12.02.1992,
the respondent filed a written statement contending that the
construction of the compound wall was in accordance with the
estimate and the question of the respondent’s directing the appellant
to stop the ongoing work for want of fresh design did not arise.
Respondent averred that the appellant unilaterally stopped the work
and there is no question of defendant making further payment. It was
averred that no extra work was done by the appellant and the
respondent was not liable to pay any amount either towards the
damages or towards the alleged loss sustained by the appellant.
5. On the above pleadings, trial court framed seven issues.
To substantiate the claim, appellant-plaintiff examined four witnesses
and produced thirty three documents. On behalf of respondent-
3
Page 4
defendant, DW-1-Jagadeesh Kumar-Deputy Manager was examined
and five documents were produced. Upon consideration of evidence
adduced by the parties, the first three issues were answered in favour
of the appellant-plaintiff viz.: (i) appellant’s claim as to extra work;
(ii) respondent’s direction to stop the running work for want of revised
design and (iii) due to stoppage of work side embankment began to fall
in the trench due to the seepage of water and involving double work
for the appellant-plaintiff to remove the fallen loose earth. Taking
note of the fact that the respondent had paid only a sum of
Rs.4,36,575/- to the appellant out of the assessed value of
Rs.5,82,100/-, trial court calculated the balance of Rs.1,45,525/- as
the balance amount payable in respect of completed portion of the
work. On the value of building material stock, trial court awarded
Rs.1,00,000/- as against the appellant’s claim of Rs.6,00,000/-. Trial
court decreed the suit in respect of extra earth work, embankment
work and other heads and directed the defendant to pay in all a sum
of Rs.3,23,000/- to the appellant with proportionate cost and interest
on the said amount at 12% per annum from the date of the suit till
the date of realization.
6. Being aggrieved, respondent as well as the appellant
preferred appeals before the High Court and both the appeals were
heard together and disposed of by the impugned judgment. Referring
4
Page 5
to the contract, the High Court held that the written contract governs
the terms between the parties and any variation thereof ought to be in
terms of the provisions of clause 11 of the contract and the appellant
having not gone through the procedure envisaged under clause 11,
the appellant cannot putforth a claim for a higher payment on the
premise that it has executed some extra work over and above the
stipulated quantity of the work. The High Court reversed the judgment
of the trial court observing that the trial court acted more like an
arbitrator in examining the suit claim and that the trial court erred in
passing the decree in favour of the appellant-plaintiff for a sum of
Rs.3,23,000/- with interest and proportionate cost.
7. Learned counsel for the appellant Mr. Partha Sil has
contended that the High Court failed to appreciate that the change in
work which materially changed the nature of intended work
mentioned in the tender document which was admitted by DW-1-
Jagadeesh Kumar during trial. It was further submitted that the High
Court erred in ignoring the evidence adduced by the appellant which
clearly establish that the respondent directed the appellant to stop the
work resulting in double work due to soil caving in trenches causing
severe financial loss and hardship to the appellant. It was submitted
that upon appreciation of evidence when the trial court recorded
findings of fact, the High Court was not right in reversing the same.
5
Page 6
8. Per contra, learned Senior Counsel for the respondent
Mr. P. Vishwanatha Shetty submitted that appellant was appointed to
complete the given work as per the terms of the contract and it was
the duty of the appellant to collect the relevant information before
making an offer and the appellant was not justified in making an
exaggerated claim of rupees thirty lakhs which is thrice the estimated
cost of the work. It was submitted that the appellant failed to prove
that he had purchased material and they were brought to the site and
there is no acceptable evidence to show that the appellant had stored
large quantities of material in the site. It was submitted that the plea
of the appellant that he was orally asked to stop the work and to await
revised design is totally baseless and the High Court rightly reversed
the judgment of the trial court.
9. We have carefully considered the rival contention and
perused the impugned judgment and also the judgment of the trial
court and other material on record.
10. PW-1-Venkatesh, who is the proprietor of the appellant-
company stated that the alignment of compound wall to be
constructed is in line with the existing flow of water from the river and
that excavation for the compound wall was done in the river itself and
when the work commenced, water started collecting in the trenches
and the plaintiff had to dewater the same simultaneously. PW-1
6
Page 7
further stated that the appellant requested the respondent to consider
the matter and accord sanction for extra items namely, making
temporary drain, dewatering work and that the appellant had to do
extra work for removal of loose earth and this caused double work for
the appellant. PW-3-Hanumegowda, working as a supervisor under
the appellant corroborated the version of PW-1 and stated that while
doing the foundation work, seepage water from river flooded in and
collected in trenches and the appellant had to do extra work in
dewatering and removal of loose earth. PW-3 further stated that as per
the estimate, depth of the earth excavation for the foundation work
was only four feet and while digging the trenches it was found that the
soil was loose and that the engineers of the respondent told the
appellant to dig the earth to a further depth till hard soil bed is
reached and on this score also, the appellant had to do extra work.
The version of PWs 1 and 3 is fortified by letter dated 06.05.1992 (Ex.
P4) sent by the appellant to the respondent stating that there was
seepage of water in the trench and that embankment had fallen in the
trench and that the appellant has to do extra work in dewatering and
removing the loose soil. Inspite of repeated letters (Exs. P4 and P5),
there was no response from the respondent.
11. DW-1-Jagadeesh Kumar working as Deputy Manager with
the respondent had stated that the parties were not aware of the soil
7
Page 8
strength at the time of entrustment of the work to the appellant.
However during cross-examination, DW-1 admitted that before
commencement of work, both parties were unaware of nature of
different strata of soil. He also stated that in case soil testing had
been done before, the records would have been available with the
respondent. But no such record was produced by the respondent. Be
it noted that the defendant has not adduced any evidence to discredit
the testimony of PWs 1 and 3 that extra work was required to be done
on account of seepage of water and soil caving in and widening and
deepening the trench. On appreciation of evidence of PWs 1 and 3
and other documentary evidence, the trial court recorded the findings
of fact that the appellant had to do extra work incurring additional
expenditure.
12. In so far as the direction of the respondent to stop the
work, PW-1 stated that during the first week of April, 1992 officials of
the respondent had asked the appellant to stop the work for getting
the design from the architect on account of seepage of water. PW-2-
Raghavendra Rao working as Civil Engineer in the appellant company,
has also corroborated the version of PW-1 and stated that the
respondent asked the appellant to stop the work and that the work
could be resumed later. Though DW-1 stated that the defendant did
not issue any letter to the plaintiff complaining against the stopping of
8
Page 9
work, he also stated that the plaintiff was orally told about the same.
By perusal of various letters, it is seen that inspite of number of
letters by the appellant seeking permission to continue the work,
there was no response from the respondent. Absence of any response
on the part of the respondent, only indicates that the respondent was
aware of the change of nature of work.
13. PW4-Naresh Kumar-architect had stated about his visit to
the work site at the request of the respondent for preparing the design
after the masonry wall for the length of hundred metres was over and
that he gave the revised design and PW-4 estimated the cost of the
work as per the revised design at rupees twenty lakhs. PW-4 was
engaged to prepare the design suitable to the soil strength only
because of the change in the nature of the work. Otherwise the need
for engaging PW-4 for preparing new design would not have arisen if
the earlier design would have been suitable. On appreciation of
evidence, trial court rightly answered issue No.2 in favour of the
appellant that the respondent asked the appellant to stop the running
work for want of revised design.
14. The High Court took note of clause 11 of the contract
dated 12.02.1992 which states that the contractor is not authorized to
do any extra work or make any alteration without the previous
consent in writing of the respondent. High Court set aside the
9
Page 10
findings recorded by the trial court holding that the parties are
governed by the terms of the written contract and any variation with
the terms of the agreement was required to be done strictly adhering
to clause 11 of the contract. While saying so, the High Court brushed
aside the admission by DW-1 that extra work was done by the
appellant and the High Court was not right in ignoring the same to
hold that the admission of DW-1 cannot have the effect on the
contractual obligation of the parties. It is to be pointed out that the
respondent has not raised the plea relying upon clause 11 of the
contract. Further, by perusal of Ex.P2 dated 20.12.1991, a letter
addressed by the appellant to the respondent informing the
respondent about the extra work which needs to be done and the fact
that PW-4 was engaged by the respondent to prepare the new design
for the work, it is evident that the respondent was aware of the fact of
the change in the nature of work and that there is alteration in the
work done by the appellant. When the evidence and material clearly
depict the change of nature of work involved and when the extra work
to be done was also admitted by DW-1, parties cannot be expected to
go for a revised agreement/contract. Moreover, having regard to the
fact that the work was to be completed within a specified time-frame,
the parties cannot be expected to go for a second round of negotiation
and reframe the terms and conditions of the work. While so, the High
10
Page 11
Court was not right in placing reliance upon clause 11 of the contract
to reverse the findings of fact recorded by the trial court.
15. So far as the claim of the appellant that it suffered loss due
to loss of stock of material, PWs 1 and 3 have stated that they have
stocked the material of worth about rupees six lakhs at the work site.
The appellant also produced several letters (Exs. P5, P6 and P7) by
which the appellant has informed the respondent that there was no
progress in the work and that the building material are lying waste.
Apart from these letters, the appellant has also produced photographs
(Exs. P18 to P28) to substantiate their claim that the building material
like bricks, size stones and other materials were stocked at the work
site. Even though the appellant has claimed rupees six lakhs on
account of loss of the material stocked, as the appellant had not
produced any bill relating to purchase of material nor produced
authentic trip sheet, the trial court rightly awarded rupees one lakh
only on account of loss of building material. As noticed earlier, based
on the evidence of PWs 1 and 3 and other documents, the trial court
has awarded amount on various other heads viz., the amount payable
in respect of:- (i) extra earth work; (ii) embankment work; (iii) extra
soiling work; (iv) extra bed concrete work and (v) extra stone masonry
work. The amount so awarded by the trial court under various heads
is based on evidence and material on record.
11
Page 12
16. The Appellate Court may not interfere with the finding of
the trial court unless the finding recorded by the trial court is
erroneous or the trial court ignored the evidence on record. The High
Court reversed the decree passed by the trial court without discussing
oral and documentary evidence and several grounds raised before the
trial court. The High Court veered away from the main issue and
went on to elaborate on the law of arbitration and the mode of setting
aside the arbitral award under Section 34 of the Arbitration Act,
which in our view, was not warranted. Without considering the oral
and documentary evidence, the High Court erred in interfering with
the factual findings recorded by the trial court and the impugned
judgment is liable to be set aside.
17. Trial court directed the respondent to pay a sum of
Rs.3,23,000/- to the appellant with interest at the rate of 12% per
annum from the date of suit till the date of realization. To award
interest from the date of suit to date of decree and from the date of
decree till the date of realization is entirely discretionary. The terms of
the contract do not specify any rate of interest. In the facts and
circumstances of the case and having regard to the fact that the
matter is pending for over two decades and in the interest of justice, it
is appropriate that the interest of 12% per annum awarded by the trial
court is reduced to 6% per annum.
12
Page 13
18. In the result, the impugned judgment is set aside and the
appeals are allowed. The judgment and decree passed by the trial
court is restored with the modification of reduction of interest at 6%
per annum from the date of the suit till the date of realization. In the
facts and circumstances of the present case, no order as to costs in
these appeals.
…………………….…CJI. (T.S. THAKUR)
………………………….J. (A.K. SIKRI)
..………………………..J. (R. BANUMATHI) New Delhi; January 20, 2016
13