07 January 2020
Supreme Court
Download

UNION OF INDIA Vs RELIANCE COMMUNICATION LIMITED

Bench: HON'BLE MR. JUSTICE ROHINTON FALI NARIMAN, HON'BLE MR. JUSTICE S. RAVINDRA BHAT
Judgment by: HON'BLE MR. JUSTICE ROHINTON FALI NARIMAN
Case number: C.A. No.-000032-000032 / 2020
Diary number: 15656 / 2019
Advocates: GURMEET SINGH MAKKER Vs


1

1

REPORTABLE

 IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL No.    32            OF 2020 (ARISING OUT OF SPECIAL LEAVE PETITION (C) NO. 15972 OF 2019)

UNION OF INDIA                 ...APPELLANT(S)

VERSUS

RELIANCE COMMUNICATION LIMITED & ANR.                                   ...RESPONDENT(S)

J U D G M E N T

S. RAVINDRA BHAT, J.

1. Leave granted. With the consent of the learned counsel for the parties, the appeal

was heard finally. The appellant/Union of India (hereafter referred to as “the Union”) is

aggrieved by a direction of the Telecom Disputes Settlement and Appellate Tribunal

(hereafter referred to as “TDSAT” or the “Tribunal”) to return  104.34 crores lying₹

unadjusted, to the respondents (collectively hereafter referred to as “RCL/RTL”).

2. The facts  necessary for  this  judgment  are  that  the Union had,  on 30.01.2013,

published a notice inviting bids (hereafter referred to as “NIA 2013”), for the auction of

spectrum. Sistema Shyam Teleservices Ltd. (hereafter referred to as “Sistema”) was the

successful applicant in respect of the 800 MHz band spectrum for eight circles/regions.

By orders of the court, a Scheme for Amalgamation under the erstwhile Companies Act,

1956 was approved, by virtue of which Sistema merged with RCL. Resultantly, its assets

2

2

and liabilities, including the spectrum license it had successfully bid for – to NIA 2013

devolved on RCL. The Union approved this transfer on 20.10.2017.  

3. The Union invited bids for auction of further spectrum bandwidth in 2015; the

bids of RCL and the second appellant (hereafter “RTL”) were successful in respect of

three kinds of spectrum in several regions/circles; licenses were issued to them. In terms

of NIA 2013, the third instalment of deferred spectrum charges of  281.45 crores fell₹

due from RCL, which could not be paid by it. This led to the encashment on 11.05.2018,

of bank guarantees furnished, to the extent of  281.45 crores. The total extent of bank₹

guarantee furnished was  390.41 crores.  Contemporaneously,  the deferred spectrum₹

liability under the NIA 2015 @  492.79 crores became payable on 09.04.2018. The₹

respondents (RCL and RTL) could not pay these charges. Consequently, the Union en-

cashed  492.79 crores out of the bank guarantees furnished.₹

4. RCL and RTL apparently along with several other telecom service providers faced

acute economic problems which led to the Union revisiting certain issues and modifying

the payment periods/terms towards deferred spectrum charges, in regard to subsisting

spectrum licenses. Accordingly, letters containing such modified terms were issued on

19.03.2018.  These  facts,  coupled  with  the  other  financial  problems  faced  by  the

respondents, leading to their adopting a strategic debt restructuring scheme with their

lender banks in accordance with the guidelines issued by the RBI were mentioned by

them; Formation of a joint-lenders forum (JLFs) with the objective of realizing dues

payable by RCL and RTL, (to the tune of  45,000 crores) are cited by the respondents₹

as reasons for default in fulfilling the commitments under the licenses. It is also stated

that  these  two  respondents  eventually  decided  to  exit  from  the  strategic  debt

restructuring  framework  and  monetize  their  assets,  including  the  spectrum licenses.

These  circumstances  led  the  respondents  (RCL  and  RTL)  to  approach  TDSAT

complaining of acute financial crunch as well as interim orders made in the course of

litigation with lenders, to seek relief by way of extension of time towards payment of

3

3

deferred spectrum charges, (under the licenses acquired under the NIA 2013 and NIA

2015). The reliefs claimed in TP 56/2018 and TP 58/2018 were declined by TDSAT.

Consequently, Civil Appeal No.4432-4433/2018 was preferred to this court which was

disposed of  by granting time to the respondent  licensees till  12.05.2018 for  making

payments towards deferred spectrum instalment charges.

5. As  narrated  previously,  these  deferred  instalment  charges  could  not  be  made

within the time granted; consequently, the Union encashed bank guarantees to the tune

of  908.91 crores as against the actual amount of  774.25 crores due and payable by₹ ₹

the respondent licensees. On 13.08.2018, the respondent licensees submitted fresh bank

guarantees for  the sum of   774.25 crores towards the next instalments  of  deferred₹

spectrum liability. They also urged to release the excess of  134.66 crores encashment₹

(i.e. the difference between the amount of  908.91 crores against admitted dues of ₹ ₹

774.25 crores). The Union had accepted fresh bank guarantees towards the subsequent

spectrum liability  (  774.25 crores).  The Union however,  did not  refund the excess₹

sums.  As  a  consequence,  the  respondents  approached  the  TDSAT  in  execution

proceedings and sought a direction for the return of  134.66 crores, i.e.  the excess₹

amounts and also the release of the bank guarantee amounting to  108.95 crores.₹

6. The Union disputed its liability before the TDSAT and relied upon Para 4.5b(x) of

the NIA 2015 and also alleged that default interest was payable and furthermore, that

RCL had defaulted in payment of spectrum instalment to the tune of  795.77 crores in₹

March-April 2019.

7. The TDSAT, by its impugned order, partly allowed the respondent’s application

after noting the Union’s reservations and objections. The TDSAT observed as follows:

“In our considered view the request of the respondent would amount to a demand for  enhanced  bank  guarantee  for  other  purposes.  This  cannot  be achieved through the method of encashment of bank guarantees furnished for deferred Spectrum Charges.

4

4

The existing charges against the petitioner have already been taken note of and an amount of Rs.30.33 crores approx. has been adjusted out of the encashed amount of Rs.908 crores. The remaining amount of Rs.104.34 crores is lying and unadjusted amount should be returned to the petitioner without prejudice to the rights of either of the parties for any other charges which the petitioner  may  be  found  to  be  liable  to  pay.  Since  the  petitioner  has reservations against the adjusted amount of Rs.30.33 crores, it may file its reply by way of rejoinder within three weeks.  

Post the matter under the same head on 29.1.2019.”

8. The Union contends that TDSAT’s impugned order is contrary to clause 4.5b(ix)

of NIA 2013 under the corresponding provision, i.e. Clause 4.5b(x) of NIA 2015 as well

as other conditions such as clauses 13.1 and 13.2 of the license agreement. It further

contends that the respondents could not have been granted relief given the fact that they

went into liquidation and were continuously defaulting in spectrum deferred payments;

the Union also cites the default to the extent of  21.53 crores – with overdue interest₹

amount working out to  27.63 crores as on 03.03.2019. It, therefore, contended that the₹

question of refund of excess amounts retained could not arise. It was lastly contended

that in any case, these issues could not have been gone in execution proceedings but

were properly the subject matter of substantive proceedings.

9. The respondents argue that the Union’s refusal to refund the money amounts to its

unjust enrichment at their cost. The Union has no right over the excess money directed

to be refunded by the Tribunal. It is submitted that despite the directions of the TDSAT,

the Union has refused to refund the money. It is further submitted that encashment of the

bank  guarantees  in  respect  of  the  subsequent  default  of  the  deferred  spectrum

instalments  for  the  year  2019 was stayed by the  NCLAT (National  Company Law

Appellate Tribunal). Thereafter, the moratorium was revived qua the Respondents and

therefore, the appropriate remedy available to the Union was under the IBC (Insolvency

5

5

and Bankruptcy Code). The Union, it is stated, has already filed its claim before the

resolution professional  for  the said deferred spectrum instalments  for  the year 2019.

Therefore,  it  cannot  be  permitted  to  claim  adjustment  of  the  unlawfully  encashed

amount towards subsequent deferred spectrum liabilities. The respondents also urge that  

a subsequent default of the deferred spectrum instalment for the year 2019, is a separate

cause of action and the Union has remedies in law to recover those so called dues. It

cannot arbitrarily and illegally withhold return of excess amount, despite there being a

judicial order to the effect.

10. The  facts  narrated  above  show  that  the  respondent-licencees  faced  financial

constraints; apparently telecom service providers as a class also faced some financial

stress, which triggered the Union to revisit its policy and ultimately modify the terms of

payment  of  deferred  payment  charges  and  consequently,  the  letter  of  19.03.2018.

Despite these, the respondent licensees could not fulfil the conditions of the licenses

held by them (i.e.  NIA 2013 and NIA 2015) vis-à-vis payment of deferred spectrum

charges; they approached the TDSAT, but without success. Their appeals to this court

fared better; the time for making payment was extended somewhat. Upon default (in

payment of the charges), the Union invoked guarantees under the sets of licenses. The

respondent licencees pointed out to the Union repeatedly, that despite the furnishing of

requisite guarantees (to the extent of  774.25 crores) later (on 19₹ th August, 2018) the

excess amounts i.e. amount after adjusting the invoked guarantees towards the deferred

charges  had  to  be  refunded.  The  Union  did  not  do  so;  consequently  RCL/RTL

approached TDSAT for a direction in execution proceedings. Their claim was accepted

inasmuch as the impugned direction was issued.  

11. On a recapitulation of all circumstances, and the various terms of NIA 2013 and

NIA 2015, this court is of the opinion that the order of the TDSAT does not call for any

interference. The Union nowhere disputes that the respondent licensees’ liability toward

payment of deferred spectrum charges, in May, 2018, was to the tune of  774.25 crores.₹

6

6

The total amount realized upon encashment of the bank guarantees furnished by the

respondents, however, was to the extent of    908.91 crores. It is also a matter of record₹

that the respondents furnished another bank guarantee to the tune of  774.25 crores.₹

There is consequently logic and merit  in the contention of RCL/RTL that the Union

unreasonably refused to refund the excess amounts. The Union’s argument that there

were subsequent defaults or short payments in respect of liability towards later periods,

or its objection that the impugned directions could not have been issued in execution

proceedings,  are  insubstantial.  As  noticed  earlier,  the  bank  guarantees  for  the  later

periods were furnished by the respondents (to the extent of  774.25 crores). In these₹

circumstances, there is no  rationale for the Union to resist  the demand for refund of

excess amounts. The TDSAT, in the opinion of this court, exercised its discretion, with

respect,  circumspectly,  because the entire amount of   134.66 crores claimed in the₹

application was not allowed; rather the direction issued was in respect  of  104. 34₹

crores.  

12. In view of the foregoing discussion, it is held that there is no merit in the present

appeal, which is dismissed without costs.

.…....................…….....................J.                                                            [R. F. NARIMAN]     

………….......................................J.                                                        [S. RAVINDRA BHAT]

New Delhi, January 7, 2020.