TEHRI HYDRO DEV. CORPN LTD. Vs JAI PRAKASH ASSO. LTD.
Bench: R.M. LODHA,ANIL R. DAVE,RANJAN GOGOI
Case number: C.A. No.-003682-003682 / 2007
Diary number: 27222 / 2006
Advocates: SHAIL KUMAR DWIVEDI Vs
SHARMILA UPADHYAY
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELATE JURISDICTION
CIVIL APPEAL No. 3682 OF 2007
Tehri Hydro Dev. Corpn. Ltd.& Anr. … Appellants
Versus
Jai Prakash Asso. Ltd. … Respondent
J U D G M E N T
RANJAN GOGOI, J
This appeal is directed against the judgment and order
dated 20th July, 2006 passed by the High Court of
Uttaranchal at Nainital whereby the decree passed by the
learned trial court under the Arbitration Act, 1940
(hereinafter referred to as ‘the Act’) has been modified. The
1
Page 2
terms of award as passed by the learned Arbitrator and the
decree passed by the learned trial court as well as the
modification thereof by the High Court will now have to be
noticed :
2. The appellants and the respondent herein had entered
into a contract for execution of certain works in connection
with the Tehri Hydro Dam Project. The agreement between
the parties was executed on 29th March, 1978 and the works
in question were completed on 31st December, 1985. The
completion certificate was issued by the competent
authority of the appellant-Corporation on 27th April, 1986.
As the final bill of the respondent-contractor had not been
prepared and security money, furnished by way of bank
guarantee was not released, the parties went to arbitration
in accordance with the Arbitration clause under the
contract/agreement. In the course of the aforesaid
Arbitration proceeding the appellant-Corporation submitted
a final bill which according to the respondent-Contractor
2
Page 3
entitled it to receive a sum of Rs.10,17,461.09 on account of
work done besides a sum of Rs. 12..50 lakhs that was lying
in deposit with the Corporation. As the amounts due.
according to the respondent-contractor, had become
crystallized, another arbitration proceeding between the
parties for the aforesaid specific claims commenced in
accordance with the arbitration clause of the agreement.
3. The award in the aforesaid arbitration proceeding was
passed on 29th January, 1996 holding the respondent –
contractor to be entitled to the sum of Rs. 10,17,461/- with
the interest at the rate of 6% per annum from the date of
invocation of the claim till the date of the award and at the
rate of 12% per annum from the date of the award till
payment or till the award is made Rule of court, whichever
is earlier. Insofar as the claim of the respondent –
contractor to the sum of Rs. 12.50 lakhs lying in deposit
with the Corporation, the Arbitrators held the said amount
to be beyond the scope of the dispute raised in the
3
Page 4
arbitration proceeding. Accordingly, the respondent –
contractor was left with the option of settling the said claim
in an amicable manner or by resorting to a civil suit for
recovery of the same.
4. Objections against the specific parts of the award by
which the respective parties felt aggrieved were filed before
the learned District Judge, Tehri, Garhwal. The learned
District Judge by his order dated 15th October, 1997 upheld
the claim of the respondent – contractor to the sum of
Rs.10,17,461/- lakhs as awarded. In so far as the claim of
Rs.12.50 lakhs is concerned, the learned trial court,
notwithstanding the fact that the arbitrator did not decide
the said claim, went into the issue and held the respondent
– contractor to be entitled to the said amount also.
Thereafter, a decree was passed in respect of the two
amounts alongwith interest thereon at the rate of 12%
pendente lite and 6% for the post award period. Aggrieved
by the aforesaid order passed by the learned District Judge,
4
Page 5
Tehri Garhwal, the appellant moved the High Court of
Uttaranchal by filing an appeal under the provisions of the
Act. The High Court by its order dated 20th July, 2006
allowed the appeal in part. While the claim of
Rs.10,17,461/- awarded in favour of the respondent-
contractor was maintained in so far as the claim of Rs. 12.50
lakhs is concerned, the High Court took the view that the
aforesaid amount could not have been awarded by the
learned trial court as the said entitlement was not gone into
by the learned Arbitrators. Accordingly, the High Court
remanded the aforesaid claim to be settled by an Arbitrator
appointed by it. Insofar as the question of interest is
concerned, the High Court did not deal with the said aspect
of the matter at all. Aggrieved, the Corporation is before this
court challenging the judgment and order dated 20th July,
2006 passed by the High Court of Uttaranchal.
5
Page 6
5. We have heard Mr. Puneet Taneja, learned counsel for
the appellants and Mr. S.B. Upadhyay, learned senior
counsel for the respondent.
6. Learned counsel for the appellants has contended that
the claims of the respondent - contractor for the unpaid
amounts under the final bill as well as for return/refund of
security deposit, including amounts furnished by way of
bank guarantee, was the subject matter of an earlier
arbitration between the parties. In the course of the said
arbitration the final bill was placed before the arbitrators by
the Corporation. On scrutiny of the aforesaid final bill the
respondent-contractor claimed the two specific amounts in
question and resorted to another process of arbitration
without seeking leave in the first arbitration proceeding to
have recourse to a second round of arbitration. The
arbitration proceeding leading to the award is, therefore,
without any authority of law. Specifically, insofar as the
amount of Rs.12.50 lakhs is concerned, according to the
learned counsel for the appellants, the said amount was not
6
Page 7
adjudicated upon by the Arbitrators and the same was to be
recovered by an amicable process or by resorting to a civil
suit. In such a situation it was clearly beyond the power of
the learned trial court to hold the said claim in favour of the
respondent-contractor. Though the High Court was justified
in setting aside the said claim of Rs.12.50 lakhs for the
aforesaid reason, it could not have directed adjudication of
the said issue by an Arbitrator nominated by it as has been
done by the impugned order of the High Court. According to
the learned counsel, the adjudication of the said claim of the
respondent – contractor, if at all, should have been directed
by a process contemplated by the specific provisions of the
Arbitration agreement between the parties.
Insofar as the grant of interest is concerned, learned
counsel for the appellants has relied on Clauses 1.2.14 and
1.2.15 of Part II of the contract agreement between the
parties to contend that under the aforesaid clauses of the
agreement governing the parties there was a specific bar to
7
Page 8
grant of interest. Relying on several judgments of this
court, details of which will be noticed in the discussions that
will follow, learned counsel has contended that the award of
interest in favour of the respondent-contractor being clearly
contrary to the terms of the agreement between the parties
is wholly untenable and therefore needs to be interfered
with by this court.
7. Controverting the submissions advanced on behalf of
the appellants, learned counsel for the respondent –
contractor has contended that the appellants had actively
participated in the proceeding before the Arbitrators and
therefore, cannot, at this stage, question the jurisdiction of
the Arbitrators to make the award in question. It is
contended that the claim of the respondent to the amount of
Rs.10,17,461/- having been held in its favour all along, the
same does not disclose any basis for interference. In so far
as the amount of Rs.12.50 lakhs is concerned the only issue
that will require deterimination is the manner in which the
de novo adjudication is required to be carried out. So far as
8
Page 9
the question of interest is concerned, learned counsel has
placed before the court the UP Civil Laws (Reforms and
Amendment) Act, 1976 by which certain provisions of the
Arbitration Act of 1940 have been amended in its application
to the State of UP. The attention of the court has been
drawn to Paragraph 7A which has been added after Para 7
of the First Schedule to the Act. According to the learned
counsel, Paragraph 7A authorized and empowered the
arbitrator as well as the courts below to grant interest.
Learned counsel has also relied on the decisions of this court
in Indian oil Corporation Ltd. vs. Amritsar Gas service and
others 1 , State of Orissa vs. B.N. Agarwalla 2 and Asian Techs
Limited vs . Union of India and others 3 2009 10 SCC 354
(para 21) in support of the contentions advanced.
1 [(1991) 1 SCC 533 2 [(1997) 2 SCC 469] 3 2009 10 SCC 354 (para 21).
9
Page 10
8. Para 7A of the U.P. Civil Laws (Reforms and
Amendment) Act, 1976 referred to above may now be
reproduced :
“7A. Where and in so far as an award is for the payment of money, the arbitrators of the umpire may, in the award, order interest at such rate as the arbitrators or umpire may deem reasonable to be paid on the principal sum awarded, from the date of the commencement of the arbitration as defined in sub-section (3) of section 37, to the date of award, in addition to any interest awarded on such principal sum for any period prior to such commencement, with further interest at such rate not exceeding six per cent per annum as the arbitrators or umpire may deem reasonable on such principal sum from the date of the award to the date of payment or to such earlier date as the arbitrators or umpire may think fit, but in no case beyond the date of the decree to be passed on the award.”
9. Insofar as the jurisdiction of the Arbitrator to
adjudicate on the two claims of Rs.10,17,461/- and
Rs.12.50 lakhs are concerned, the dispute is capable of
resolution within a short compass. The entitlement of the
respondent – contractor to the aforesaid two amounts was
not the subject matter of the earlier proceeding before the
Arbitrators which arose out of the grievance of the
10
Page 11
respondent – contractor that though the execution of the
work had been completed, the final bill had not been
prepared and further that certain amounts lying in deposit
as security had not been refunded. Once the final bill was
prepared and placed before the Arbitrators the claim of the
respondent-contractor got crystallized. It is these specific
claims, after quantification, that had been referred to the
Arbitrators in the proceeding in which the award has been
passed. It will, therefore, not be correct to say that the
arbitration proceeding in respect of the specific claims of the
contractor stood barred in view of the earlier arbitration
proceeding between the parties. That apart, from an order
passed by the Arbitrators on 15th January, 1994, which is
available on record as an enclosure to the counter affidavit
of the respondent, it appears that the arbitrators in the
aforesaid order dated 15th January, 1994 had clearly
recorded that the “. . . .both the parties agree that we
should adjudicate both the disputes relating to refund of
11
Page 12
deposit of Rs.12.5 lakhs and payment of final bill to the
tune of Rs.10.00 lakhs and odd . . . .”
In these circumstances, the award insofar as the claim
of Rs.10,17,461/- made by the learned Arbitrator and
affirmed by the learned courts below will not require any
further scrutiny by us.
10. Insofar as the claim in respect of the sum of Rs.12.50
lakhs is concerned, it has already been noticed that the
entitlement of the respondent – contractor to the said
amount had not been adjudicated upon by the Arbitrators on
the ground that the said issue was not an arbitrable issue
and the same ought be resolved either by an amicable
process or by way of a suit for recovery. If the aforesaid
claim was not adjudicated upon by the Arbitrators the
learned trial court was patently wrong in decreeing the said
claim. Therefore, the High Court was perfectly justified in
reversing the said part of the decree. However, we do not
12
Page 13
find any reasonable basis for the view taken by the High
Court that the entitlement of the respondent-contractor to
the said amount should now be determined by the Arbitrator
nominated by it. Rather, according to us, the aforesaid
issue should have been left for determination in accordance
with the procedure agreed upon by the parties, if the parties
are, at all, inclined to go into a further round of adjudication
at this stage. We, therefore, interfere with the aforesaid
part of the order of the High Court and, subject to our
observations above, we leave the parties to work out their
remedies as may be considered best and most appropriate
in the facts and circumstances of the case.
11. This will lead the court to a consideration of what is the
principal bone of contention between the parties in the
present case, namely, the issue with regard to payment of
interest. Clauses 1.2.14 and 1.2.15 on which much
arguments have been advanced by learned counsel for both
sides may now be extracted below :
13
Page 14
“ PART – II
CONDITIONS OF CONTRACT
1 11111 NO CLAIM FOR DELAYED PAYMENT DUE TO DISPUTE ETC.
The contractor agrees that no claim for interest of damages will be entertained or payable by the Government in respect of any money or balances which may be lying with Government owing to any disputes, differences or misunderstandings between the parties or in respect of any delay or omission on the part of the Engineer-in- charge in making immediate or final payments or in any other respect whatsoever.
1 11111 INTEREST ON MONEY DUE TO THE CONTRACTOR :
No omission on the part of the Engineer-in- charge to pay the amount due upon measurement or otherwise shall vitiate or make void the contract, nor shall the contractor be entitled to interest upon any guarantee or payments in arrears nor upon any balance which may on the final settlement of his accounts be due to him.”
12. A reading of the aforesaid two Clauses of the contract
agreement between the parties clearly reveal that despite
14
Page 15
some overlapping of the circumstances contemplated by the
two Clauses, no interest is payable to the contractor for
delay in payment, either, interim or final, for the works done
or on any amount lying in deposit by way of guarantee. The
aforesaid contemplated consequence would be applicable
both to a situation where withholding of payment is on
account of some dispute or difference between the parties or
even otherwise.
13. Of the several decisions of this Court referred to by the
learned counsel for the appellant the judgments of the
Constitution Bench of this Court in Secretary, Irrigation
Department, Government of Orissa and others vs. G.C. Roy
and anr. 4 and Executive Engineer, Dhenkalal Minor
Irrigation Division, Orissa and others vs. N.C. Budhraj
(deceased) By lrs. And others 5 will require specific notice.
The true ratio laid down in the aforesaid two judgments
have been elaborately considered in a more recent
4 (1992) 1 SCC 508 5 (2001) 2 SCC 721
15
Page 16
pronouncement of this court in the case of Union of India vs
Krafters Engineers and Leasing Private Limited 6 . In Krafters
Engineers’s case (supra) the ratio of the decision in G.C.
Roy’s case (supra) was identified to mean that if the
agreement between the parties does not prohibit grant of
interest and the claim of a party to interest is referred to
the arbitrator, the arbitrator would have the power to award
the interest. This is on the basis that in such a case of
silence (where the agreement is silent) it must be
presumed that interest was an implied term of the
agreement and, therefore, whether such a claim is tenable
can be examined by the arbitrator in the reference made to
him. The aforesaid view, specifically, is with regard to
pendente lite interest. In the subsequent decision of the
Constitution Bench in N.C. Budhraj’s case (supra) a
similar view has been taken with regard to interest for the
pre reference period.
6 (2011) 7 SCC 279
16
Page 17
14. In Krafters Engineers’ case (supra) the somewhat
discordant note struck by the decisions of this court in
Board of Trustees for the Port of Calcutta vs. Engineers-De-
Space-Age 7 and Madnani Construction Corporation Private
Limited vs. Union of India and others 8 were also taken note
of. Thereafter, it was also noticed that the decision in
Engineers-De-Space-Age’s case (supra) was considered in
Sayeed Ahmed & Co. vs. State of Uttar Pradesh & Ors. 9 and
the decision in Madnani Construction case (supra) was
considered in Sree Kamatchi Amman Constructions vs.
Divisional, Railway manager (Works), Palghat and others 10.
In Sayeed Ahmed’s case (supra) (para 24) it was held that
in the light of the decision of the Constitution bench in GC
Roy’s case and NC Budhraj’s case it is doubtful whether the
observations in Engineers-de-Space-Age’s case (supra) to
the effect that the Arbitrator could award interest pendente
lite, ignoring the express bar in the contract, is good law. In
7 (1996) 1 SCC 516 8 (2010) 1 SCC 549 9 (2009) 12 SCC 26 10 (2010) 8 SCC 767.
17
Page 18
Sree Kamatchi Amman Constructions’s case(Supra) while
considering Madnani’s case (supra) this court noted that the
decision in Madnani’s case follows the decision in Engineers-
de-Space-Age’s case (supra).
15. From the above discussions, it is crystal clear that
insofar as pendente lite interest is concerned, the
observations contained in Para 43 and 44 of the judgment in
GC Roy’s case (supra) will hold the field. Though the gist of
the said principle has been noticed earlier it would still be
appropriate to set out para 44 of the judgment in G.C.
Roy’s case (supra) which is in the following terms :
“ 44. Having regard to the above consideration, we think that the following is the correct principle which should be followed in this behalf.
Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendent elite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes – or refer
18
Page 19
the dispute as to interest as such – to the arbitrator, he shall have the power to award interest. This does not mean that in every case the arbitrator should necessarily award interest pendent elite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.”
16. The provisions of the UP Civil (Reforms and
Amendment) Act amending the First Schedule to the
Arbitration Act, 1940 does not assist the respondent -
contractor in any manner to sustain the claim of award of
interest pendente lite, inasmuch, as paragraph 7A to the
First Schedule, as amended, is only an enabling provision
which will have no application to a situation where there is
an express bar to the entertainment or payment of interest
on the delayed payment either of an amount due for the
work done or of an amount lying in deposit as security. The
decision in BN Agarwalla’s case (supra) on which reliance
has been placed by the learned counsel for the respondent,
once again, does not assist the claim of the respondent to
interest pendente lite inasmuch as in BN Agarwalla’s case
19
Page 20
(supra) the views of the Constitution Bench in GC Roy’s case
(supra) with regard to interest pendente lite could not have
been and, infact, were not even remotely doubted. The
observation of the bench in B.N. Agarwalla’s case that in
G.C.Roy’s case (supra) the decision in Executive Eningeer
(Irrigation), Balimela and others vs . Abhaduta Jena and
others 11 was not overruled was only in the context of the
issue of award of interest for the pre reference period. The
decision in Asian Techs Limited case (supra) also relied on
by the respondent takes note of the decision in Engineers-
De-Space-Age case (supra) to come to the conclusion the
prohibition on payment of interest contained in clause 11 of
the agreement between the parties was qua the department
and did not bar the Arbitrator from entertaining the claim.
It has already been noticed that the correctness of the
propositions laid down in Engineers-De-Space-Age case
(supra) have been doubted in the subsequent decisions of
this court, reference to which has already been made.
11 (1988) 1 SCC 418
20
Page 21
17. Clauses 1.2.14 and 1.2.15, already extracted and
analysed, imposed a clear bar on either entertainment or
payment of interest in any situation of non payment or
delayed payment of either the amounts due for work done
or lying in security deposit. On the basis of the discussions
that have preceded we, therefore, take the view that the
grant of pendente lite interest on the claim of
Rs.10,17,461/- is not justified. The award as well as the
orders of the courts below are accordingly modified to the
aforesaid extent.
18. However, the grant of interest for the post-award
period would stand on a somewhat different footing. This
very issue has been elaborately considered by this Court in
B.N. Agarwalla (supra) in the light of the provisions of
Section 29 of the Arbitration Act, 1940. Eventually this Court
took the view that in a situation where the award passed by
the arbitrator granting interest from the date of the award
21
Page 22
till the date of payment is not modified by the Court “.....the
effect would be as if the Court itself had granted interest
from the date of the decree till the date of payment...” In
view of the above, the grant of interest on the amount of
Rs.10,17,461/-from the date of the award till the date of the
decree or date of payment, whichever is earlier, is upheld.
In the facts of the case we are of the view that the rate of
interest should be 12% per annum as determined in the
arbitration proceeding between the parties.
19. In view of the foregoing discussions we allow this
appeal in part
and modify the order of the High Court dated 20th July,
2006 as indicated above.
...……………………J. [R.M.LODHA]
22
Page 23
............................J. [ANIL R. DAVE]
………………………J. [RANJAN GOGOI]
New Delhi, September 25, 2012.
23
Page 24
2