02 April 2013
Supreme Court
Download

STERLITE INDUSTRIES (I) LTD. ETC. ETC. Vs UNION OF INDIA AND ORS. ETC. ETC.

Bench: A.K. PATNAIK,H.L. GOKHALE
Case number: C.A. No.-002776-002783 / 2013
Diary number: 31123 / 2010
Advocates: E. C. AGRAWALA Vs RESPONDENT-IN-PERSON


1

Page 1

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL Nos.  2776-2783  OF 2013  (Arising out of SLP (C) Nos. 28116-28123 of 2010)

  Sterlite Industries (India) Ltd. Etc. Etc.            … Appellants

Versus

Union of India & Ors. Etc. Etc.                     … Respondents

J U D G M E N T

A. K. PATNAIK, J.

Leave granted.

FACTS:

2. The relevant facts very briefly are that the appellant-  

company applied and obtained ‘No Objection Certificate’ on  

01.08.1994 from the Tamil Nadu Pollution Control Board (for

2

Page 2

short ‘the TNPCB’) for setting up a copper smelter plant (for  

short  ‘the  plant’)  in  Melavittan  village,  Tuticorin.   On  

16.01.1995,  the  Ministry  of  Environment  and  Forests,  

Government  of  India,  granted  environmental  clearance  to  

the  setting  up  of  the  plant  of  the  appellants  at  Tuticorin  

subject to certain conditions including those laid down by the  

TNPCB and the Government of Tamil Nadu.  On 17.05.1995,  

the Government of Tamil Nadu granted clearance subject to  

certain conditions and requested the TNPCB to issue consent  

to  the  proposed  plant  of  the  appellants.   Accordingly,  on  

22.05.1995, the TNPCB granted its consent under Section 21  

of the Air (Prevention and Control of Pollution) Act, 1981 (for  

short  ‘the  Air  Act’)  and  under  Section  25  of  the  Water  

(Prevention and Control of Pollution) Act, 1974 (for short ‘the  

Water Act’)  to the appellants to establish the plant in the  

SIPCOT  Industrial  Complex,  Melavittan  village,  Tuticorin  

Taluk.

3. The environmental clearance granted by the Ministry of  

Environment  and  Forests,  Government  of  India,  and  the  

consent orders under the Air Act and the Water Act granted  

2

3

Page 3

by the TNPCB were challenged before the Madras High Court  

in W.P. Nos.15501, 15502 and 15503 of 1996 by the National  

Trust for Clean Environment.  While these writ petitions were  

pending,  the appellants set  up the plant  and commenced  

production on 01.01.1997.   Writ  Petition No.5769 of  1997  

was then filed by V. Gopalsamy, General Secretary, MDMK  

Political Party, Thayagam, praying for inter alia a direction to  

the appellants to stop forthwith the operation of the plant.  

Writ  Petition No.  16861 of  1991 was also  filed by Shri  K.  

Kanagaraj,  Secretary,  CITU  District  Committee,  District  

Thoothukudi,  for  directions  to  the  State  of  Tamil  Nadu,  

TNPCB and the Union of India to take suitable action against  

the appellant-company for its failure to take safety measures  

due to which there were pollution and industrial accidents in  

the plant.   A Division Bench of the High Court heard Writ  

Petition Nos. 15501 to 15503 of 1996, Writ Petition No.5769  

of  1997  and  Writ  Petition  No.16861  of  1998  and  by  the  

common judgment dated 28.09.2010, allowed and disposed  

of  the  writ  petitions  with  the  direction  to  the  appellant-

company  to  close  down  its  plant  at  Tuticorin.   By  the  

3

4

Page 4

common judgment,  the High Court  also  declared that  the  

employees of  the appellant-company would be entitled to  

compensation under Section 25FFF of the Industrial Disputes  

Act,  1947 and directed the District  Collector,  Tuticorin,  to  

take  all  necessary  and  immediate  steps  for  the  re-

employment of the workforce of the appellant-company in  

some  other  companies/factories/organizations  so  as  to  

protect their livelihood and to the extent possible take into  

consideration their  educational  and technical  qualifications  

and  also  the  experience  in  the  field.   Aggrieved,  the  

appellant  has  filed  these  appeals  against  the  common  

judgment dated 28.09.2010 of the Division Bench of Madras  

High Court and on 01.10.2010, this Court passed an interim  

order staying the impugned judgment of the High Court.

    

CONTENTIONS ON BEHALF OF THE APPELLANTS:

4. Mr.  C.A.  Sundaram,  learned senior  counsel  appearing  

for the appellants, submitted that one of the grounds stated  

in the impugned judgment of the High Court  for  directing  

closure of the plant of the appellants was that the TNPCB  

4

5

Page 5

had stipulated in the Consent Order dated 22.05.1995 that  

the appellant-company has to ensure that the location of the  

unit should be 25 kms. away from the ecologically sensitive  

area and as per the report of NEERI (National Environmental  

Engineering and Research Institute) of 1998 submitted to the  

High Court, the plant is situated within 25 kms. from four of  

the  twenty  one  islands  in  the  Gulf  of  Munnar,  namely,  

Vanthivu, Kasuwar, Karaichalli and Villanguchalli, which are  

at distances of 6 k.m., 7 k.m. and 15 k.m. respectively from  

Tuticorin where the plant is located.  He submitted that there  

is no notification issued by the Central Government under  

Rule  5(1)  of  the  Environment  (Protection)  Act,  1986  

prohibiting  or  restricting  the  location  of  an  industry  in  

Tuticorin area.  He submitted that the Government of Tamil  

Nadu, however, had issued a notification dated 10.09.1986  

notifying  its  intention  under  Section  35(1)  of  the  Wildlife  

(Protection) Act, 1972 to declare the twenty one islands of  

the  Gulf  of  Munnar  as  a  Marine  National  Park,  but  no  

notification has yet been issued by the Government of Tamil  

Nadu under Section 35(4) of the aforesaid Act declaring the  

5

6

Page 6

twenty one islands of the Gulf of Munnar as a National Park.  

He explained that prior to the Environment (Protection) Act,  

1986 and the Environment (Protection) Rules,  1986,  some  

environmental guidelines had been issued by the Ministry of  

Environment  and  Forests,  Department  of  Environment,  

Government  of  India,  in  August,  1985  and  one  of  the  

guidelines  therein  was  that  industries  must  be  located at  

least 25 kms. away from the ecologically sensitive areas and  

it  is  on account of  these guidelines that  the TNPCB in its  

Consent Order dated 22.05.1995 under the Water Act had  

stipulated that the plant of the appellants should be situated  

25  kms.  away  from  ecologically  sensitive  areas.   He  

submitted  that  this  stipulation  was  made  in  the  Consent  

Order under the Water Act because the plant was likely to  

discharge effluent  which  could  directly  or  indirectly  affect  

the ecological sensitive areas within 25 kms. of the industry,  

but in the Consent Order issued on 14.10.1996 to operate  

the industry, this stipulation was removed and instead it was  

stipulated in clause (20) that the unit shall re-use the entire  

quantity of treated effluent in the process and ensure that  

6

7

Page 7

no treated effluent is discharged into inland surface water or  

on  land  or  sewer  or  sea  as  proposed  by  the  unit.   He  

submitted that  in  any case the consent  for  establishment  

issued under the Water Act by the TNPCB would show that  

the appellant-company was given the consent to establish its  

copper  smelter  project  in  SIPCOT  Industrial  Complex  

irrespective of the distance at which the SIPCOT Industrial  

Complex was located from any ecological sensitive area and  

in  the  SIPCOT  Industrial  Complex,  many  other  chemical  

industries are located and the High Court appears to have  

lost sight of this aspect of the consent given by the TNPCB to  

establish the plant.

5. Mr. Sundaram submitted that the second ground given  

by the High Court for directing closure of the plant of the  

appellants was that this being a project exceeding Rs.50/-  

crores, environmental clearance was required to be obtained  

from the Ministry of Environment and Forests, Government  

of  India,  after  a  public  hearing  which  was  a  mandatory  

requirement but no materials were produced before the High  

Court  to  show  that  there  was  any  such  public  hearing  

7

8

Page 8

conducted  before  the  commencement  of  the  plant  of  the  

appellant-company.   He  submitted  that  when  the  

environmental  clearance  was  granted  to  the  appellant-

company the  Environmental  Impact  Assessment  (for  short  

‘EIA’)  notification  dated  27.01.1994  was  in  force  and  this  

notification did not make public hearing mandatory and only  

stated that comments of the public may be solicited if  so  

recommended by the Impact Assessment Agency within 30  

days of the receipt of the proposal.  He submitted that the  

High Court, therefore, was not correct in taking a view that a  

public  hearing  was  mandatory  during  EIA  before  

environmental  clearance  was  given  by  the  Ministry  of  

Environment and Forests, Government of India.  He clarified  

that by a subsequent notification dated 10.04.1997, a public  

hearing  was  made  compulsory  but  by  the  time  this  

notification  came  into  force  environmental  clearance  had  

already  been  granted  to  the  plant  of  the  appellants  on  

16.01.1995.

6. Mr. Sundaram submitted that the High Court also took  

the  view  in  the  impugned  judgment  on  the  basis  of  the  

8

9

Page 9

report of the NEERI of 1998 that there was undue haste on  

the  part  of  the  governmental  authorities  in  granting  

permissions  and  consents  to  the  appellant-company.   He  

submitted that in an Explanatory Note to the EIA notification  

dated 27.01.1994 the Central Government has clarified that  

Rapid EIA could also be conducted for obtaining environment  

clearance  for  any  new  project/activity  and  therefore  the  

State Government while granting No Objection Certificate by  

its letter dated 01.08.1994 asked the appellants to conduct  

Rapid  EIA  based  on  one  season  data  and  the  appellants  

carried out Rapid EIA study based on the data collected by  

the M/s. Tata Consultancy Service (TCS).  He relied on the  

affidavit dated 01.12.1998 filed on behalf of the Ministry of  

Environment  and  Forests,  Government  of  India  to  submit  

that Rapid EIA before granting clearance to the plant of the  

appellant was conducted in accordance with the guidelines.

7. Mr. Sundaram submitted that the third ground on which  

the High Court directed closure of the plant of the appellants  

was that the TNPCB stipulated a condition in clause No.20 of  

the No Objection Certificate that the appellants will develop  

9

10

Page 10

a green belt of 250 meters width around the battery limit of  

the  industry  as  contemplated  under  the  Environmental  

Management Plan but subsequently the appellant-company  

submitted a representation to TNPCB requesting TNPCB to  

reduce the requirement of green belt from 250 meters to the  

width of 10-15 meters as development of the green belt of  

250 meters width requires a land of around 150 acres and  

TNPCB  in  its  meeting  held  on  18.08.1994  relaxed  this  

condition  and  stipulated  that  the  appellant-company  will  

develop a green belt of minimum width of 25 meters.  He  

submitted  that  the  land  allocated  by  SIPCOT  to  the  

appellants was not sufficient to provide a green belt of 250  

meters  width  around  the  plant  and  hence  this  was  an  

impossible  condition  laid  down  in  the  No  Objection  

Certificate and for this reason the appellants approached the  

TNPCB to modify this condition and the TNPCB reduced the  

width of the green belt to 25 meters.  He further submitted  

that generally, the TNPCB and the Ministry of Environment  

and Forests, Government of India, have been insisting on a  

green belt of 25% of the plant area and the appellants could  

10

11

Page 11

not be asked to provide a green belt of more than 25% of  

the plant area.   

8. Mr. Sundaram submitted that the last ground, on which  

the High Court directed closure of the plant of the appellants  

is  that  the  plant  of  the  appellants  has  caused  severe  

pollution in the area as has been recorded by NEERI in its  

report  of  2005  submitted  to  the  High  Court  and  the  

groundwater samples taken from the area indicate that the  

copper, chrome, lead cadmium and arsenic and the chloride  

and fluoride content is too high when compared to Indian  

drinking  water  standards.   He  referred  to  the  reports  of  

NEERI of 1998, 1999, 2003 and 2005 submitted to the High  

Court  and the report  of  NEERI  of  2011 and also the joint  

inspection  report  of  TNPCB and CPCB of  September  2012  

submitted to this Court, to show that the finding of the High  

Court  that  the  plant  of  the appellants  had caused severe  

pollution  in  the  area  was  not  correct.   He  vehemently  

submitted  that  though  there  were  no  deficiencies  in  the  

plant  of  the  appellants,  the  TNPCB  in  its  affidavit  has  

referred  to  its  recommendations  as  if  there  were  

11

12

Page 12

deficiencies.  He submitted that the recommendations made  

by the TNPCB were only to provide the best of checks in the  

plant against environmental pollution with a view to ensure  

that the plant of the appellants becomes a model plant from  

the point of view of the environment, but that does not mean  

that the plant of the appellants had deficiencies which need  

to be corrected.   He submitted that the reports of NEERI of  

2005  and  2011  referred  to  accumulation  of  gypsum  and  

phospho  gypsum,  which  come  out  from  the  plant  of  the  

appellants as part of the slag but the opinion of CPCB in its  

letter  dated 17.11.2003 to the TNPCB is that such slag is  

non-hazardous  and can  be  used  in  cement  industries,  for  

filling up lower level area and as building/road construction  

material, etc. and has no adverse environmental effects.

9. Mr. Sundaram finally submitted that since none of the  

grounds given by the High Court in the impugned judgment  

for directing closure of the plant of the appellants are well-

founded, it is a fit case in which this Court should set aside  

the  impugned  judgment  of  the  High  Court  and  allow  the  

appeals.   He  submitted  that  the  plant  of  the  appellants  

12

13

Page 13

produces 2,02,000 metric tones of copper which constitute  

39% of the total of 5,14,000 metric tones of copper produced  

in India and that 50% of the copper produced by the plant of  

the appellants is consumed in the domestic market and the  

balance 50% is exported abroad.  He also submitted that the  

plant provides direct and indirect employment to about 3000  

people and yields a huge revenue to both the Central and  

State Governments.  He submitted that closure of the plant  

of the appellants, therefore, would also not be in the public  

interest.

CONTENTIONS ON BEHALF OF THE WRIT PETITIONERS- RESPONDENTS:

10. Mr. V. Gopalsamy, who was the writ petitioner in Writ  

Petition No.5769 of 1997 before the High Court, appeared in-

person and supported the impugned judgment of the High  

Court.   He  submitted  that  the  TNPCB in  its  No  Objection  

Certificate dated 01.08.1994 as well as in its Consent Order  

dated 22.05.1995 under the Water Act clearly stipulated that  

the appellant-company shall ensure that the location of its  

unit should be 25 kms. away from ecological sensitive area  

13

14

Page 14

and the Government of Tamil Nadu in their affidavit dated  

27.10.2012 have stated that all the 21 islands including the  

four  near  Tuticorin  in  the  Gulf  of  Munnar  Marine  National  

Park  are  ecologically  sensitive  areas.   He  submitted  that  

NEERI  in its  report  of  1998 has observed that four  out  of  

twenty one islands, namely, Vanthivu, Kasuwar, Karaichalli  

and Villanguchalli, are at distances of 6 kms., 7 kms. and 15  

kms. respectively from Tuticorin.  He further submitted that  

merely because a condition has been subsequently imposed  

on the appellant-company by TNPCB not to discharge any  

effluent  to  the  sea,  the  restriction  of  minimum  25  kms.  

distance from ecological sensitive area from location of the  

unit of the appellants cannot be lifted particularly when the  

Government  of  Tamil  Nadu  as  well  as  the  Central  

Government  are  treating  the  Gulf  of  Munnar  as  a  Marine  

National  Park  and  extending  financial  assistance  for  the  

development of its ecology.  He submitted that the proposal  

for  issuance  of  a  declaration  under  Section  35(4)  of  the  

Wildlife (Protection) Act, 1972 is pending for concurrence of  

the  Central  Government  and,  therefore,  the  ecological  

14

15

Page 15

balance in the area of Gulf of Munnar would be disturbed if  

the plant  of  the appellants continues at  Tuticorin and the  

High Court was right in directing closure of the plant of the  

appellants located at Tuticorin.   

11. Mr.  V.  Gopalsamy submitted that the High Court was  

similarly  right  in  directing  closure  of  the  plant  of  the  

appellants on the ground that the appellants did not develop  

a  green  belt  of  250  metres  width  around  their  plant  as  

stipulated in the No Objection Certificate dated 01.08.1994  

of the TNPCB and instead represented to the TNPCB and got  

the  green  belt  reduced  to  only  25  metres  width.   He  

submitted that considering the grave adverse impact on the  

environment by the plant of the appellants,  a 250 metres  

width of green belt was absolutely a must but the TNPCB  

very casually reduced the green belt from 250 metres width  

to 25 metres.  He submitted that it will  be seen from the  

joint report of TNPCB and CPCB filed pursuant to the order  

dated 27.08.2012 of  this  Court  that  as a  condition of  the  

renewal  of  the  consent  order,  the  appellant-company  has  

been asked to develop a green belt to an extent of 25% of  

15

16

Page 16

the total area of 172.17 hectares which works out to 43.04  

hectares and yet the TNPCB has found development of green  

belt of 26 hectares as sufficient compliance.  He submitted  

that the appellants would, therefore, be required to develop  

a green belt of 17.04 hectares more for compliance of the  

condition for renewal of consent stipulated by the TNPCB.

12. Mr.  V.  Gopalsamy submitted  that  for  their  plant,  the  

appellants  have  been  importing  copper  concentrate  from  

Australian  mines  which  are  highly  radioactive  and  

contaminated and contain high levels of arsenic,  uranium,  

bismuth,  fluorine  and  experts  of  environment  like  Mark  

Chernaik have given a report on the adverse impacts of the  

plant of the appellants at Tuticorin on the environment.  In  

this context, he also submitted that an American company,  

namely, the Asarco producing copper had to be closed down  

on  account  of  such  adverse  environmental  effects.   He  

submitted that the claim of the appellants that their plant  

has no deficiencies and that it does not have any impact on  

the environment is not correct and different reports of the  

NEERI  would  show  that  the  plant  of  the  appellants  is  

16

17

Page 17

continuing to pollute the air and has also affected the ground  

water of the area by discharging effluent and the High Court,  

therefore,  rightly  directed  the  closure  of  the  plant.   He  

submitted  that  the  appellants  had  initially  proposed  to  

establish  the  plant  in  Gujarat  but  this  was  opposed  

vehemently  and  the  appellants  decided  to  shift  the  

establishment of the plant to Goa but because of opposition  

the plant could not be established in Goa.  He submitted that  

the  appellants  thereafter  intended  to  set  up  the  plant  at  

Ratnagiri  in  Maharashtra  and  invested  Rs.200  crores  in  

construction  activities  after  obtaining  environmental  

clearance but because of the opposition of the farmers of  

Ratnagiri,  the Maharashtra Government had to revoke the  

licence granted to the appellants.   He submitted that  the  

appellants have been able to set up the plant at Tuticorin in  

Tamil Nadu by somehow obtaining environmental clearance  

from the Ministry of Environment and Forests, Government  

of India, without a public hearing and the consents under the  

Water  Act  and the  Air  Act  from the TNPCB and the  High  

17

18

Page 18

Court rightly allowed the writ petitions and directed closure  

of the plant of the appellants.

13. Mr. V. Prakash, learned senior counsel appearing for the  

writ petitioner, National Trust For Clean Environment, in Writ  

Petition Nos. 15501 to 15503 of 1996 before the High Court,  

submitted that the appellants had made a false statement in  

the synopsis at page (B) of the Special Leave Petition that it  

has been consistently operating for more than a decade with  

all necessary consents and approvals from all the statutory  

authorities  without  any  complaint.   He  submitted  that  

similarly in ground no. IV at page 45 of the Special Leave  

Petitions  the  appellants  have  falsely  stated  that  the  High  

Court has erred in not appreciating that the appellants had  

got  all  the  statutory  approvals/consent  orders  from  the  

authorities concerned as also the Central Government and  

the  State  Government.   He  submitted  that  the  report  of  

NEERI of 2011 would show that the appellants did not have  

valid  consent  during  various  periods  including  the  period  

when it filed the Special Leave Petitions.  He submitted that  

the appellants did not also inform this Court that when they  

18

19

Page 19

moved this Court on 01.10.2010 to stay the operation of the  

impugned  order  of  the  High  Court,  the  plant  of  the  

appellants  had already  stopped operation.  He  vehemently  

argued that due to misrepresentation of the material facts  

by the appellants in the Special Leave Petitions as well as  

suppression of the material facts, this Court was persuaded  

to pass the stay order dated 01.10.2010.  He argued that on  

this ground alone this Court should refuse to grant relief to  

the appellants in exercise of its discretion under Article 136  

of the Constitution.  He relied on the decisions of this Court  

in  Hari  Narain  v.  Badri  Das [AIR  1963  SC  1558],  G.  

Narayanaswamy Reddy (dead) by LRs. & Anr. v. Government   

of Karnataka & Anr. [(1991) 3 SCC 261] and Dalip Singh v.   

State  of  Uttar  Pradesh  &  Ors.  [(2010)  2  SCC  114]  and  

Abhyudya Sanstha v. Union of India [(2011) 6 SCC 145] for  

the proposition that this Court can refuse relief under Article  

136  of  the  Constitution  where  the  appellants  have  not  

approached  this  Court  with  clean  hands  and  have  made  

patently false statements in the special leave petition.  

19

20

Page 20

14. Mr. Prakash next submitted that the main ground that  

was  taken  in  the  writ  petitions  before  the  High  Court  by  

National Trust For Clean Environment was that the Ministry  

of Environment and Forests, Government of India,  and the  

TNPCB  had  not  applied  their  mind  to  the  nature  of  the  

industry as well as the pollution fall out of the industry of the  

appellants and the capacity of the unit of the appellants to  

handle  the  waste  without  causing  adverse  impact  on  the  

environment as well as on the people living in the vicinity of  

the plant.  He submitted that this Court has already held that  

a  right  to  clean  environment  is  part  of  the  right  to  life  

guaranteed  under  Article  21  of  the  Constitution  and  has  

explained the  precautionary  principle  and  the  principle  of  

sustainable development in  Vellore Citizens Welfare Forum  

v. Union of India & Ors. [(1996) 5 SCC 647], Tirupur Dyeing  

Factory  Owners’  Association  v.  Noyyal  River  Ayacutdars   

Protection Association [(2009) 9 SCC 737] and M.C. Mehta v.   

Union of India Ors. [(2009) 6 SCC 142].  He submitted that  

these principles, therefore, have to be borne in mind by the  

authorities  while  granting  environmental  clearance  and  

20

21

Page 21

consent under the Water Act or the Air Act, but unfortunately  

both the Ministry of Environment and Forests, Government  

of India, and the TNPCB have ignored these principles and  

have  gone  ahead  and  hastily  granted  environmental  

clearance and the consent under the two Acts.  He submitted  

that, in the present case, the appellants have relied on the  

Rapid EIA done by Tata Consultancy Service, but this Rapid  

EIA was based on the data which is less than the month’s  

particulars and is inadequate for making a proper EIA which  

must address the issue of the nature of the manufacturing  

process, the capacity of the manufacturing facility and the  

quantum  of  production,  the  quantum  and  nature  of  

pollutants, air, liquid and solid and handling of the waste.

15. Mr.  Prakash  referred  to  the  report  of  NEERI  of  1998  

submitted  to  the  High  Court  to  show  that  the  inspection  

team of NEERI collected waste water samples from the plant  

of the appellants and an analysis of the waste water samples  

indicate  that  the  treatment  plant  of  the  appellants  was  

operating inefficiently as the levels of arsenic, selenium and  

lead in the treated effluent as also the effluent stored in the  

21

22

Page 22

surge ponds were higher than the standards stipulated by  

the  TNPCB.   He  also  referred  to  the  report  of  NEERI  of  

February 1999 in which NEERI has stated that the treated  

effluent quality did not conform to the standards stipulated  

by the TNPCB.   

16. Mr. Prakash further submitted that the counter affidavit  

of  the Union of  India filed on 01.12.1998 before the High  

Court also does not disclose whether, apart from the Rapid  

EIA of Tata Consultancy Services, there was any independent  

evaluation  of  the  Rapid  EIA  by  the  environmental  impact  

assessment authority, namely, the Ministry of Environment  

and  Forests.   He  submitted  that  the  TNPCB  in  its  No  

Objection  Certificate  dated  01.08.1994   has  stipulated  in  

Clause 18 that the appellants have to carry out Rapid EIA  

(for  one  season  other  than  monsoon)  as  per  the  EIA  

notification  dated  27.01.1994   issued  by  the  Ministry  of  

Environment and Forests, Government of India, and furnish a  

copy to the TNPCB and this clause itself  would show that  

TNPCB had not applied its mind as to whether there was a  

sufficient  rational  analysis  of  the  nature  of  the  industry,  

22

23

Page 23

nature  of  pollutants,  quantum of  fall  out  and the  plan  or  

method for  handling  the waste.   He submitted that  since  

there was no application of mind by either the Ministry of  

Environment  and  Forests,  Government  of  India,  before  

granting  the  environmental  clearance  or  by  the  TNPCB  

before granting the consents under the Water Act and the  

Air Act, the environmental clearance and the consent orders  

are liable to be quashed.   

17. In support of his submissions,  Mr.  Prakash cited  East  

Coast Railway & Anr. v. Mahadev Appa Rao & Ors. [(2010) 7  

SCC 678], for the proposition that for a valid order there has  

to  be  application  of  mind  by  the  authority,  and  in  the  

absence of  such application of mind by the authority,  the  

order is arbitrary and is liable to be quashed.  He cited the  

decision  of  the  Lords  of  the  Judicial  Committee  of  Privy  

Council in Belize Alliance of Conservation Non-governmental   

Organizations v.  The Department  of  the Environment  and  

Belize Electric Company Limited [(2004) 64 WIR 68 para 69]  

in which it  has been observed that EIA is  expected to be  

comprehensive in treatment of the subject, objective in its  

23

24

Page 24

approach and must meet the requirement that it alerts the  

decision  maker  to  the  effect  of  the  activity  on  the  

environment and the consequences to the community.  He  

also  relied  on  the  judgment  of  the  Supreme  Court  of  

Judicature of Jamaica in The Northern Jamaica Conservation  

Association v. The Natural Resources Conservation Authority  

[Claim No. HCV 3022 of 2005] to argue that a public hearing  

was  a  must  for  grant  of  environmental  clearance  and  

submitted that as there was no public hearing in this case  

and  there  was  inadequate  EIA  before  the  grant  of  the  

environmental clearance for the plant of the appellants, the  

High Court has rightly directed closure of the plant of the  

appellants.

18. Finally,  Mr.  Prakash submitted that the finding of the  

High  Court  that  the  plant  of  the  appellants  continues  to  

pollute  the  environment  has  been  substantiated  by  the  

inspection report which has been filed in this Court by the  

NEERI as well as the TNPCB from time to time.  In particular,  

he referred to the joint inspection report of the TNPCB and  

CPCB to show that the directions issued by the TNPCB to  

24

25

Page 25

improve solid  waste disposal  has not  been complied with.  

He submitted that one of the conditions of the consent order  

of  the  TNPCB  was  that  no  slag  was  to  be  stored  in  the  

premises of the plant but huge quantity of slag has been  

stored  in  the  premises  of  the  plant  and  the  direction  to  

dispose  at  least  50%  more  than  the  monthly  generation  

quantities of both slag and gypsum has not been complied  

with.  He vehemently argued that unless the plant is shut  

down,  the  appellants  will  not  be  able  to  clear  the  huge  

quantity of slag and gypsum lying in the plant premises.  He  

submitted that it  is not correct as has been submitted on  

behalf  of  the  appellants  that  the  slag  is  not  a  hazardous  

waste  containing  arsenic  and  will  certainly  jeopardize  the  

environment.  He argued that there was therefore no other  

option for the High Court but to direct closure of the plant of  

the appellants to ensure clean environment in the area.

CONTENTIONS ON BEHALF OF THE AUTHORITIES:

19. Mr. S. Guru Krishna Kumar, learned counsel appearing  

for the TNPCB as well as the State of Tamil Nadu, relying on  

25

26

Page 26

the affidavit filed on behalf of the State of Tamil Nadu on  

29.10.2012 submitted that the Gulf of Munnar consisting of  

21 islands in 4 groups was notified under Section 35(1) of  

the Wildlife (Protection) Act, 1972 on 10th September 1986  

as  this  group  of  islands  consisted  of  territorial  waters  

between them and the proposal to declare Gulf of Munnar as  

a Marine National Park under Section 35(4) of the said Act  

was  sent  by  the  Chief  Wild  Life  Warden  to  the  State  

Government for approval on 30.04.2003 but the declaration  

under  Section  35(4)  of  the  said  Act  has  not  been  finally  

made.  He further submitted that all the 21 islands including  

the 4 islands in the Gulf of Munnar are therefore ecological  

sensitive areas.  He submitted that notwithstanding the fact  

that four of the islands were near Tuticorin, the TNPCB gave  

the consent under the Water Act to the appellants to set up  

the plant at Tuticorin because the plant has a zero effluent  

discharge.  He also referred to the compliance affidavit of  

the TNPCB filed on 08.10.2012 to show that the TNPCB is  

monitoring the emissions from the plant of the appellants to  

26

27

Page 27

ensure that the National Ambient Air Quality Standards are  

maintained.

20. Mr. Vijay Panjwani, learned counsel appearing for CPCB,  

made a reference to Sections 3, 16 and 18 of the Water Act  

which relate to the CPCB and submitted that it was not for  

the CPCB but for the TNPCB to issue No Objection Certificate  

and consent in respect of the plant set up in the State of  

Tamil  Nadu.   He  submitted  that  under  Rule  19  of  the  

Manufacture,  Storage  and  Import  of  Hazardous  Chemical  

Rules,  1989, however,  improvement notices can be issued  

by the CPCB to any person to remedy the contravention of  

the Rules.

CONTENTIONS ON BEHALF OF THE INTERVENER:  

21. Mr.  Raj  Panjwani,  learned counsel  for  the  intervener,  

submitted that a marine biosphere is an ecological sensitive  

area and if in the consent order a condition was stipulated  

that the plant of the appellants has to be situated beyond 25  

kms. from ecological sensitive area, this condition has to be  

complied with.  He further submitted that in any case the  

27

28

Page 28

appellants are liable to compensate for having damaged the  

environment.

FINDINGS OF THE COURT:

22. Writ Petition No.15501 of 1996, Writ Petition No.15503  

of 1996 and Writ Petition No.5769 of 1997 had been filed for  

quashing  the  environmental  clearances  dated  16.01.1995  

and 17.05.1995 granted by the Ministry of Environment and  

Forests, Government of India, to the appellants for setting up  

the plant at Tuticorin and by the impugned judgment, the  

High Court has not quashed the environmental clearance but  

has  allowed  the  three  writ  petitions.   Hence,  the  first  

question which we will have to decide is whether the High  

Court  could  have  interfered  with  the  environmental  

clearances  granted  by  the  Ministry  of  Environment  and  

Forests, Government of India, and the Government of Tamil  

Nadu, Department of Environment.   

23.   The environmental clearance for setting up the plant  

was  granted  to  the  appellants  under  the  Environment  

(Protection) Act, 1986.  Sub-section (1) of Section 3 of the  

28

29

Page 29

Environment (Protection) Act, 1986 provides that subject to  

the provisions of the Act, the Central Government shall have  

the power to take all such measures as it deems necessary  

or expedient for the purpose of protecting and improving the  

quality of the environment and preventing, controlling and  

abating environmental pollution.   Sub-section (2) of Section  

3 further provides that in particular, and without prejudice to  

the  generality  of  the  provisions  of  sub-section  (1),  such  

measures may include measures with respect to all or any of  

the matters specified therein.  One such matter specified in  

clause (v) of sub-section (2) is restriction of areas in which  

any industries, operations or processes or class of industries,  

operations or processes shall not be carried out or shall be  

carried out subject to certain safeguards.  Rule 5(3) of the  

Environment (Protection) Rules, 1986 accordingly empowers  

the  Central  Government  to  impose  prohibitions  or  

restrictions on the location of an industry or the carrying on  

processes and operations in an area, by notification in the  

Official Gazette.  In exercise of these powers under Section  

3(2)(v) of the Environment (Protection) Act, 1986 and Rule  

29

30

Page 30

5(3) of the Environment (Protection) Rules, 1986, the Central  

Government  has  issued  a  notification  dated  27.01.1994  

imposing restrictions and prohibitions on the expansion and  

modernization  of  any  activity  or  new  projects  being  

undertaken  in  any  part  of  India  unless  environmental  

clearance has been accorded by the Central Government or  

the  State  Government  in  accordance  with  the  procedure  

specified in the said notification.   

24. Para 2 of the notification dated 27.01.1994 lays down  

the requirements and procedure for seeking environmental  

clearance of projects, and clause (c) of Para 2 provides that  

the Impact Assessment Agency could solicit comments of the  

public  within  thirty  days  of  receipt  of  proposal,  in  public  

hearings, arranged for the purpose, after giving thirty days  

notice of such hearings in at least two newspapers, and after  

completion  of  public  hearing,  where  required,  convey  its  

decision.  The language of this notification did not lay down  

that the public hearing was a must.  The Impact Assessment  

was  done  by  Tata  Consultancy  Services  as  per  the  

requirements then existing and the Government of India has  

30

31

Page 31

granted the Environmental Clearance on 16.01.1995.  The  

notification  dated  27.01.1994,  however,  was  amended  by  

notification dated 10.04.1997 and it was provided in clause  

(c) of Para 2 of the notification that the Impact Assessment  

Agency shall conduct a public hearing and the procedure for  

public hearing was detailed in Schedule IV to the notification  

by  the  amendment  notification  dated  10.04.1997.  

Admittedly,  in  this  case,  the environmental  clearance was  

granted  by  the  Ministry  of  Environment,  Government  of  

India, on 16.01.1995 in accordance with the procedure laid  

down  by  notification  dated  27.01.1994  well  before  the  

notification dated 10.04.1997 providing for mandatory public  

hearing  in  accordance  with  the  procedure  laid  down  in  

Schedule IV.  As there was no mandatory requirement in the  

procedure laid down under the Environment (Protection) Act,  

1986 and the Environment (Protection) Rules, 1986 and the  

notifications dated 27.01.1994 as amended by notification  

dated 04.05.1994 that a public hearing has to be conducted  

before  grant  of  environmental  clearance,   the  High  Court  

could  not  have  allowed  the  writ  petitions  challenging  the  

31

32

Page 32

environmental  clearances  on  the  ground  that  no  public  

hearing was conducted before grant of  the environmental  

clearances.

25. An  Explanatory  Note  regarding  the  EIA  notification  

dated  27.01.1994  was  also  issued  by  the  Central  

Government  and  Para  5  of  the  Explanatory  Note  clarified  

that project proponents could furnish Rapid EIA report to the  

Impact Assessment Agency based on one season data, for  

examination  of  the  project  and Comprehensive  EIA  report  

may  be  submitted  later,  if  so  asked  for  by  the  Impact  

Assessment  Agency  and  this  was  permitted  where  

Comprehensive EIA report would take at least one year for  

its preparation.  In Para 5 of the affidavit filed by the Union  

of India before the High Court in Writ Petition Nos.15501 to  

15503 of 1996, the allegation of the writ petitioner that the  

Ministry  of  Environment  and  Forests  have  accorded  

environmental  clearance  without  applying  its  mind  and  

without making any analysis of the adverse impacts on the  

marine ecological system has been denied and it has been  

further  stated  that  after  detailed  examination  of  Rapid  

32

33

Page 33

EIA/EMP, filled in Questionnaire for industrial projects, NOC  

from State  Pollution  Control  Board  and  Risk  Analysis,  the  

project was examined as per the procedure laid down in the  

EIA  notification  dated  27.01.1994  (as  amended  on  

04.05.1994)  and  the  project  was  accorded  approval  on  

16.01.1995 subject to specific conditions.  As the procedure  

laid down under the Environment (Protection) Act, 1986 and  

the  Environment  (Protection)  Rules,  1986  and  the  

notifications dated 27.01.1994 as amended by notification  

dated 04.05.1994 and as explained by the Explanatory Note  

issued by the Government of India permitted Rapid EIA in  

certain  circumstances,  the  High  Court  could  not  have  

allowed the writ petitions on the ground that environmental  

clearance was issued to the appellant-company on the basis  

of inadequate Rapid EIA, particularly when the Union of India  

in  its  affidavit  had clearly  averred that  the environmental  

clearance was granted after detailed examination of Rapid  

EIA/EMP, filled in Questionnaire for industrial projects, NOC  

from  State  Pollution  Control  Board  and  Risk  Analysis  in  

33

34

Page 34

accordance with the procedure laid down in EIA notification  

dated 27.01.1994 (as amended on 04.05.1994).

26. The High Court has noticed some decisions of this Court  

on  Sustainable  Development,  Precautionary  and  Polluter  

Pays Principles and Public Trust Doctrine, but has failed to  

appreciate that the decision of the Central Government to  

grant environmental clearance to the plant of the appellants  

could  only  be  tested  on  the  anvil  of  well  recognized  

principles  of  judicial  review as  has  been  held  by  a  three  

Judge Bench of this Court in  Lafarge Umiam Mining (P) Ltd.   

v. Union of India & Others [(2011) 7 SCC 338 at 380].  To  

quote Environmental Law edited by David Woolley QC, John  

Pugh-Smith,  Richard  Langham  and  William  Upton,  Oxford  

University Press:

“The  specific  grounds  upon  which  a  public  authority  can  be  challenged  by  way  of  judicial  review are the same for environmental law as for  any other branch of judicial review, namely on the  grounds of illegality,  irrationality,  and procedural  impropriety.”

Thus,  if  the  environmental  clearance  granted  by  the  

competent authority is clearly outside the powers given to it  

34

35

Page 35

by the Environment (Protection) Act, 1986, the Environment  

(Protection)  Rules,  1986  or  the  notifications  issued  

thereunder, the High Court could quash the environmental  

clearance on the ground of illegality.  If the environmental  

clearance is based on a conclusion so unreasonable that no  

reasonable authority could ever have come to the decision,  

the environmental clearance would suffer from Wednesbury  

unreasonableness and the High Court could interfere on the  

ground of irrationality.  And, if the environmental clearance  

is  granted in  breach of  proper  procedure,  the  High  Court  

could review the decision of the authority on the ground of  

procedural impropriety.

27. Where,  however,  the  challenge  to  the  environmental  

clearance is  on the ground of  procedural  impropriety,  the  

High Court could quash the environmental clearance only if  

it  is  satisfied  that  the  breach  was  of  a  mandatory  

requirement in the procedure.  As stated in Environmental  

Law edited by David Woolley QC, John Pugh-Smith, Richard  

Langham and William Upton, Oxford University Press:

35

36

Page 36

“It will  often not be enough to show that there  has  been  a  procedural  breach.    Most  of  the  procedural  requirements  are  found  in  the  regulations  made  under  primary  legislation.  There has been much debate in the courts about  whether a breach of regulations is mandatory or  directory, but in the end the crucial point which  has to be considered in any given case is what  the  particular  provision  was  designed  to  achieve.”

As  we  have  noticed,  when  the  plant  of  the  appellant-

company  was  granted  environmental  clearance,  the  

notification dated 27.01.1994 did not provide for mandatory  

public hearing.  The Explanatory Note issued by the Central  

Government on the notification dated 27.01.1994 also made  

it  clear that  the project proponents may furnish rapid EIA  

report  to  the  IAA  based  on  one  season  data  (other  than  

monsoon), for examination of the project Comprehensive EIA  

report  was not  a  must.    In  the absence of  a  mandatory  

requirement in the procedure laid down under the scheme  

under the Environment (Protection) Act, 1986 at the relevant  

time requiring a mandatory public hearing and a mandatory  

comprehensive  EIA  report,  the  High Court  could  not  have  

interfered  with  the  decision  of  the  Central  Government  

36

37

Page 37

granting  environmental  clearance  on  the  ground  of  

procedural impropriety.

28. Coming now to  the  ground of  irrationality  argued so  

vehemently  by  Mr.  V.  Prakash,  we  find  that  no  materials  

have  been  produced  before  us  to  take  a  view  that  the  

decision  of  the  Central  Government  to  grant  the  

environmental clearance to the plant of the appellants was  

so  unreasonable  that  no  reasonable  authority  could  ever  

have taken the decision.   As  we have already noticed,  in  

Para 5 of the affidavit filed by the Union of India before the  

High Court in Writ Petition Nos.15501 to 15503 of 1996, it  

has been stated that the Ministry of Environment and Forests  

have  accorded  environmental  clearance  after  detailed  

examination  of  rapid  EIA/EMP,  filled  in  Questionnaire  for  

industrial projects,  NOC from State Pollution Control Board  

and Risk Analysis, and that the project was examined as per  

the  procedure  laid  down  in  the  EIA  notification  dated  

27.01.1994 (as amended on 04.05.1994) and only thereafter  

the  project  was  accorded  approval  on  16.01.1995.   No  

material has been placed before us to show that the decision  

37

38

Page 38

of  the  Ministry  of  Environment  and  Forests  to  accord  

environmental  clearance to  the  plant  of  the  appellants  at  

Tuticorin  was  wholly  irrational  and  frustrated  the  very  

purpose of EIA.

29. In  Belize  Alliance  of  Conservation  Non-governmental   

Organizations v.  The Department  of  the Environment  and  

Belize  Electric  Company  Limited (supra)  cited  by  Mr.  

Prakash,  the  Lords  of  the  Judicial  Committee  of  the  Privy  

Council  have quoted with approval  the following words of  

Linden JA with reference to the Canadian legislation in  Bow  

Valley Naturalists Society v.  Minister of Canadian Heritage   

[2001] 2 FC 461 at 494:

“The Court must ensure that the steps in the Act  are followed, but it must defer to the responsible  authorities in their substantive determinations as  to  the  scope  of  the  project,  the  extent  of  the  screening and the assessment of the cumulative  effects  in  the  light  of  the  mitigating  factors  proposed.  It is not for the judges to decide what  projects are to be authorized but, as long as they  follow  the  statutory  process,  it  is  for  the  responsible authorities.”

The aforesaid passage will  make it  clear  that  it  is  for  the  

authorities  under  the  Environment  (Protection)  Act,  1986,  

38

39

Page 39

the  Environment  (Protection)  Rules,  1986  and  the  

notifications issued thereunder to determine the scope of the  

project, the extent of the screening and the assessment of  

the cumulative effects and so long as the statutory process  

is followed and the EIA made by the authorities is not found  

to be irrational so as to frustrate the very purpose of EIA, the  

Court will not interfere with the decision of the authorities in  

exercise of its powers of judicial review.

30. The next question that we have to decide is whether  

the High Court was right in directing closure of the plant of  

the appellants on the ground that the plant of the appellants  

is located at Tuticorin within 25 kms. of four of the twenty  

one  islands  in  the  Gulf  of  Munnar,  namely,  Vanthivu,  

Kasuwar, Karaichalli and Villanguchalli.  The reason given by  

the High Court in coming to this conclusion is that the TNPCB  

had stipulated in the Consent Order dated 22.05.1995 that  

the appellant-company has to ensure that the location of the  

unit should be 25 kms. away from ecologically sensitive area  

and as per the report of NEERI, the plant of the appellants  

was situated at a distance of 6 kms. of Vanthivu, 7 kms. of  

39

40

Page 40

Kasuwar and 15 kms. of Karaichalli  and Villanguchalli  and  

these four villages are part of the twenty one islands in the  

Gulf of Munnar.  Hence, the High Court directed closure of  

the plant because the appellant-company has violated the  

condition of the Consent Order dated 22.05.1995 issued by  

the TNPCB under the Water Act.   

31. The  Consent  Order  dated  22.05.1995  issued  by  the  

TNPCB under Section 25 of the Water Act states as follows:

“Consent to establish or take steps to establish is  hereby  granted  under  Section  25  of  the  Water  (Prevention and Control of Pollution) Act, 1974 as  amended in 1988) (hereinafter referred to as ‘The  Act’) and the rules and orders made thereunder to

The Chief Project Manager, M/s  Sterlite  Industries  (India)  Limited  (Copper Smelter Project)

SIPCOT Industrial Complex, Meelavittam Village, Tuticorin Taluk, V.O. Chidambaraner District

(hereinafter  referred  to  as  ‘The  applicant’)  authorizing  him/her/them  to  establish  or  take  steps  to  establish  the  industry  in  the  site  mentioned below:

SIPCOT Industrial Complex, Meelavittam Village, Tuticorin Taluk, V.O. Chidambaraner District.”

40

41

Page 41

The  aforesaid  extract  from  the  Consent  Order  dated  

22.05.1995 of the TNPCB issued under the Water Act makes  

it  clear  that  the  appellant-company was  given  consent  to  

establish  its  plant  in  the  SIPCOT  Industrial  Complex,  

Melavittan Village, Tuticorin Taluk.  Along with the Consent  

Order under the Water Act, special conditions were annexed  

and clause 20 of the special conditions reads as follows:

“20. (i)       1 km away from the water resources                  specified in G.O.Ms. No.213 E&P Dept Dt.                  30.3.89

(i) 25 km away from ecological/sensitive            areas.

(ii) 500 metres away from high tide line.”

32. On the one hand, therefore, the appellants were given  

consent  to  establish  their  plant  in  the  SIPCOT  Industrial  

Complex, which as per the NEERI report is within 25 kms. of  

four of the twenty one islands in the Gulf of Munnar.  On the  

other hand, a condition was stipulated in the consent order  

that the appellants have to ensure that the location of the  

unit is 25 kms. away from ecological sensitive area.  It thus  

41

42

Page 42

appears that the TNPCB while granting the consent under  

the  Water  Act  for  establishment  of  the  plant  of  the  

appellants  in  the  SIPCOT  Industrial  Complex  added  the  

above requirement without noting that the SIPCOT Industrial  

Complex was within 25 kms. from ecological sensitive area.  

Since,  however,  the  Consent  Order  was  granted  to  the  

appellant-company  to  establish  its  plant  in  the  SIPCOT  

Industrial Complex and the plant has in fact been established  

in the SIPCOT Industrial Complex, the High Court could not  

have  come to  the  conclusion  that  the  appellant-company  

had violated the Consent Order and directed closure of the  

plant on this ground.

33. This is not to say that in case it becomes necessary for  

preservation of ecology of the aforesaid four islands which  

form part of the Gulf of Munnar, the plant of the appellants  

cannot be directed to be shifted in future.  We find from the  

affidavit  filed  on  behalf  of  the  State  of  Tamil  Nadu  on  

29.10.2012 that the Gulf of Munnar consisting of 21 islands  

including the aforesaid four islands have been notified under  

Section 35(1) of the Wildlife (Protection) Act, 1972 on 10th  

42

43

Page 43

September 1986 and a declaration may also be made under  

Section 35(4) of the said Act declaring the Gulf of Munnar as  

a Marine National Park.  We have, therefore, no doubt that  

the Gulf of Munnar is an ecological sensitive area and the  

Central  Government  may  in  exercise  of  its  powers  under  

clause (v) of sub-section (1) of Rule 5 of the Environment  

(Protection) Rules,  1986 prohibit  or restrict  the location of  

industries  and  carrying  on  processes  and  operations  to  

preserve the biological diversity of the Gulf of Munnar.  As  

and when  the  Central  Government  issues  an  order  under  

Rule  5  of  the  Environment  (Protection)  Rules,  1986  

prohibiting or restricting the location of industries within and  

around  the  Gulf  of  Munnar  Marine  National  Park,  then  

appropriate steps may have to be taken by all concerned for  

shifting  the  industry  of  the  appellants  from  the  SIPCOT  

Industrial Complex depending upon the content of the order  

or notification issued by the Central Government under the  

aforesaid  Rule  5  of  the  Environment  (Protection)  Rules,  

1986, subject to the legal challenge by the industries.

43

44

Page 44

34. The  next  question  with  which  we  have  to  deal  is  

whether the High Court could have directed the closure of  

the  plant  of  the  appellants  on  the  ground  that  though  

originally  the  TNPCB  stipulated  a  condition  in  the  ‘No  

Objection  Certificate’  that  the   appellant-company  has  to  

develop a green belt of 250 meters width around the battery  

limit of the plant, the appellants made representation to the  

TNPCB  for  reducing  the  width  of  the  green  belt  and  the  

TNPCB  in  its  meeting  held  on  18.08.1994  relaxed  this  

condition and required the appellants to develop the green  

belt  with  a  minimum width  of  25  meters.   We find  on  a  

reading of the No Objection Certificate issued by the TNPCB  

that various conditions have been imposed on the industry  

of  the  appellants  to  ensure  that  air  pollution  control  

measures are installed for the control of emission generated  

from the plant and that the emission from the plant satisfies  

the ambient area quality standards prescribed by the TNPCB  

and  development  of  green  belt  contemplated  under  the  

environmental management plan around the battery limit of  

the industry of  the appellants was an additional  condition  

44

45

Page 45

that  was  imposed  by  the  TNPCB  in  the  No  Objection  

Certificate.   If  the  TNPCB  after  considering  the  

representation of the appellants has reduced the width of  

the green belt from a minimum of 250 meters to a minimum  

of 25 meters around the battery limit of the industry of the  

appellants  and it  is  not  shown that  this  power  which has  

been  exercised  was  vitiated  by  procedural  breach  or  

irrationality,  the  High  Court  in  exercise  of  its  powers  of  

judicial review could not have interfered with the exercise of  

such power by the State Pollution Control Board. The High  

Court  in  the  impugned  judgment  has  not  recorded  any  

finding that  there has been any breach of  the mandatory  

provisions  of  the  Air  Act  or  the  Rules  thereunder  by  the  

TNPCB by reducing the green belt to 25 meters.   Nor has  

the High Court  recorded any finding that  by reducing the  

width  of  the  green  belt  around  the  battery  limit  of  the  

industry of the appellants from 250 meters to 25 meters, it  

will  not  be  possible  to  mitigate  the  effects  of  fugitive  

emissions from the plant.  The High Court has merely held  

that  the  TNPCB  should  not  have  taken  such  a  generous  

45

46

Page 46

attitude and should not have in a casual way dealt with the  

issue permitting the appellant-company to reduce the green  

belt particularly when there have been ugly repercussions in  

the area on account of the incidents which took place on  

05.07.1997  onwards.   It  was  for  the  TNPCB  to  take  the  

decision in that behalf and considering that the appellant’s  

plant  was  within  a  pre-existing  industrial  estate,  the  

appellant could not have been singled out to require such a  

huge green belt.  

35. This takes us to the argument of Mr. Prakash that had  

the  Ministry  of  Environment  and  Forests,  Government  of  

India, applied its mind fully before granting the environment  

clearance and had the TNPCB applied its mind fully to the  

consents under the Air Act and the Water Act and considered  

all  possible  environmental  repercussions  that  the  plant  

proposed to be set  up by the appellants would have,  the  

environmental  problems  now  created  by  the  plant  of  the  

appellants would have been prevented.  As we have already  

held,  it  is  for  the  administrative  and  statutory  authorities  

empowered  under  the  law  to  consider  and  grant  

46

47

Page 47

environmental clearance and the consents to the appellants  

for setting up the plant and where no ground for interference  

with  the  decisions  of  the  authorities  on  well  recognized  

principles of judicial review is made out, the High Court could  

not interfere with  the decisions of the authorities to grant  

the environmental clearance or the consents on the ground  

that  had  the  authorities  made  a  proper  environmental  

assessment of the plant, the adverse environmental effects  

of  the  industry  could  have  been  prevented.   If,  however,  

after  the  environmental  clearance  under  the  Environment  

(Protection) Act, 1986, and the Rules and the notifications  

issued thereunder and after the consents granted under the  

Air Act and the Water Act, the industry continues to pollute  

the environment  so as to effect the fundamental right to life  

under Article 21 of the Constitution, the High Court could still  

direct  the  closure  of  the  industry  by  virtue  of  its  powers  

under  Article  21  of  the  Constitution  if  it  came  to  the  

conclusion that there were no other remedial measures to  

ensure that the industry maintains the standards of emission  

and effluent as laid down by law for safe environment (see  

47

48

Page 48

M.C. Mehta v. Union of India and others [(1987) 4 SCC 463]  

in which this Court directed closure of tanneries polluting the  

waters of Ganga river).   

36. We  have,  therefore,  to  examine  whether  there  were  

materials before the High Court to show that the plant of the  

appellants did not maintain the standards of emission and  

effluent as laid down by the TNPCB and whether there were  

no remedial measures other than the closure of the industry  

of the appellants to protect the environment.  We find on a  

reading of the impugned judgment of the High Court that it  

has relied on the report of NEERI of 2005 to hold that the  

plant site itself is severely polluted and the ground samples  

level  of  arsenic  justified  classifying  the  whole  site  of  the  

plant  of  the  appellant  as  hazardous  waste.   We  extract  

hereinbelow the relevant observations of NEERI in its report  

of 2005 relating to air,  water and soil  environment in the  

Executive Summary:  

“Air Environment:  

 The emission factors of SO2 from sulphuric acid  plant – I  (SAP-I)  and sulphuric acid plant – II  

48

49

Page 49

(SAP-II)  were  0.55  kg/MT  of  H2SO4  manufactured which is well within the TNPCB  stipulated  limit  of  2kg/MT  of  H2SO4  manufactured.  

 The acid mist  concentration of  SAP-I  was 85  mg/Nm3, which exceeds the TNPCB limit of 50  mg/Nm3.   The  acid  mist  concentration  from  SAP-II was 42 mg/Nm3, which is well within the  TNPCB  limit.   In  view  of  the  exceedance  of  TNPCB limit for acid mist, it is recommended  that the performance of acid mist eliminators  may be intermittently  checked.   It  is  further  recommended to  install  a  tail  gas  treatment  plant to take care of occasional upsets.  

 Out of the seven D.G. sets, one (6.3 MW) was  monitored  for  particulate  matter  (PM)  emissions.  The level of PM was 115 mg/Nm3  (0.84  gm/kWh)  which  is  within  the  TNPCB  stipulated  limit  of  150  mg/Nm3 for  thermal  power plants of 200 MW and higher capacity  (165 mg/Nm3) but higher than that stipulated  for  diesel  engines  /  Gen  sets  up  to  800 KW  capacity (0.3 gm/kWh).  Therefore TNPCB may  decide whether the present PM emissions from  the DG sets of 6.3 MW capacity is within the  limit or otherwise.  

 The fugitive emissions were monitored at four  sites  to  assess  the status  of  air  quality  with  respect of SO2,  NO2 and SPM.  The results of  analysis  at  all  fugitive  emission  monitoring  sites  indicate  that  the  levels  of  gaseous  pollutants  SO2 and  NO2,  were  below  the  respective  NIOSH/OSHA  standards  for  work  place  environment.   The levels  of  SPM were  also within the stipulated TNPCB standards for  industrial areas.  

49

50

Page 50

 Impact  of  stack  and  fugitive  emissions  on  surrounding air  quality was also assessed by  monitoring  SO2,  NO2 and  SPM  levels  at  five  monitoring locations.  The levels of SPM, SO2  and NO2 at all the five sites were far below the  TNPCB  standards  of  120  μg/Nm3 for  SO2 as  well  as  NO2 and  500  μg/Nm3  for  SPM  for  industrial zone.    Water Environment  

 Surface  water  samples  were  collected  and  analyzed  for  physico-chemical,  nutrient  demand  parameters.  The  physico-chemical  characteristics  and  nutrient  demand  parameters,  i.e.  with special  reference to pH  (7.9-8.0),  TDS  (120-160  mg/L),  COD  (11-18  mg/L) and levels of heavy metals viz. Cd, Cr,  Cu,  Pb,  Fe,  Mn,  Zn and As in  surface water,  were  found  within  the  prescribed  limits  of  drinking water standards (IS: 10500-1995).  

 Total  eight  groundwater  samples  were  collected  (seven  from  hand  pumps  and  one  from  dug  well)  to  assess  the  groundwater  quality  in  the  study  area.   The  analysis  on  physico-chemical  characteristics  of  groundwater  samples  collected  from  various  locations  showed  high  mineral  contents  in  terms  of  dissolved  solids  (395-3020mg/L),  alkalinity (63-210 mg/L), total hardness (225- 2434 mg/L), chloride (109-950 mg/L), sulphate  (29-1124 mg/L) and sodium (57-677 mg/L) as  compared  to  the  drinking  water  standards  (IS:10500-1995).   Thus, it could be concluded  that water in some of the wells investigated is  unfit  for  drinking.   The  concentrations  of  nutrient  demand  parameters  revealed  that  phosphate was in the range 0.1-0.3 mg/L while  nitrate  was  in  the  range  1-7.5  mg/L  at  all  

50

51

Page 51

sampling  locations  which  is  within  the  limits  stipulated  under  drinking  water  standards  (IS:10500-1995).  Levels of Chromium, Copper  and  lead  were  found  to  be  higher  in  comparison  to  the  parameters  stipulated  under  drinking  water  standards  (IS:10500- 1995), other heady metal concentrations, viz.  iron, manganese, zinc and arsenic were found  in  the  range  0.01-0.05  mg/L,  ND-0.01  mg/L  and  ND-0.08  mg/L  respectively  which  are  within the drinking water standards (IS:10500- 1995).  

 To assess the impact on groundwater quality  due to secured and fill  sites and other waste  disposal facilities, five samples were collected  from  monitoring  wells  (shallow  bore  wells  located around the waste disposal sites).  The  Physico-Chemical characteristics of well water  around secured land fill site and gypsum pond  showed  mineral  contents  higher  then  the  levels stipulated in IS: 10500-1995 in terms of  dissolved  solids  (400-3245  mg/L),  alkalinity  (57-137  mg/L),  hardness  (290-1280  mg/L),  chloride  (46-1390  mg/L),  sulphate  (177-649  mg/L) and sodium (9-271 mg/L).  The results of  nutrient  demand  parameters  showed  phosphate  in  the  range  0.1-0.5  mg/L  while  nitrate was in the range 0.8-11.7 mg/L at all  sampling locations, which are within the levels  stipulated in IS:10500-1995, whereas level of  arsenic  was  found  in  the  range  of  ND-0.08  mg/L  as  against  the  stipulated  limit  of  0.05  mg/L  under  drinking  water  standards  (IS:10500-1995).   Levels  of  cadmium,  chromium, copper and lead were also found to  exceed the drinking water standards in some  of the wells.   

51

52

Page 52

 The  hourly  composite  wastewater  samples  were  collected  at  six  locations.   During  the  sample  collection,  flow  monitoring  was  also  carried out at the inlet and final outlet of the  effluent  treatment  plant  (ETP).   The  concentrations  of  total  dissolved  solid  (TDS)  and sulphate exceed the limit stipulated by the  TNPCB  for  treated  effluent.   All  the  other  parameters are within the consent conditions  prescribed by TNPCB.  The treated effluent is  being recycled back in the process to achieve  zero discharge.  

Soil Environment  

 Soil  samples  were  also  analyzed for  level  of  heavy metals.  The soil  samples at the plant  site  showed presence  of  As  (132.5  to  163.0  mg/kg), Cu (8.6 to 163.5 mg/kg), Mn (283 to  521.0 mg/kg) and Fe (929.6 to 1764.6 mg/kg).  Though there is no prescribed limit for heavy  metal contents in soil, the occurrence of these  heavy metals in the soil may be attributed to  fugitive emission, solid waste dumps, etc.”

It  will  be  clear  from  the  extracts  from  the  Executive  

Summary of NEERI in its report of 2005, that while some of  

the emissions from the plant of the appellants were within  

the limits stipulated by the TNPCB, some of the emissions  

did not conform to the standards stipulated by TNPCB.  It will  

also be clear from the extracts from the Executive Summary  

52

53

Page 53

relating  to  water  environment  that  the  surface  water  

samples  were  found  to  be  within  the  prescribed  limits  of  

drinking  water  (IS:10500-1995)  whereas  ground  water  

samples showed high mineral contents in terms of dissolved  

solids  as  compared  to  the  drinking  water  standards,  but  

concentrations of nutrient demand parameters revealed that  

the phosphate and nitrate contents were within the limits  

stipulated  under  drinking  water  standards  and  levels  of  

chromium,  copper  and  lead  were  found  to  be  higher  in  

comparison  to  the  parameters  stipulated  under  drinking  

water standards, whereas the heavy metal concentrations,  

namely, iron, manganese, zinc and arsenic were within the  

drinking water standards.  Soil samples also revealed heavy  

metals.  Regarding the solid waste out of slag in the plant  

site, the CPCB has taken a view in its communication dated  

17.11.2003 to TNPCB that the slag is non-hazardous.  Thus,  

the NEERI  report of 2005 did show that the emission and  

effluent discharge affected the environment but the report  

read as whole does not warrant a conclusion that the plant  

of the appellants could not possibly take remedial steps to  

53

54

Page 54

improve  the  environment  and  that  the  only  remedy  to  

protect the environment was to direct closure of the plant of  

the appellants.   

37. In  fact,  this  Court  passed  orders  on  25.02.2011  

directing a joint inspection by NEERI (National Engineering  

and  Research  Institute)  with  the  officials  of  the  Central  

Pollution Control Board (for short ‘the CPCB’) as well as the  

TNPCB.  Accordingly, an inspection was carried out during 6th  

April to 8th April, 2011 and 19th April to 22nd April, 2011 and a  

report  was  submitted  by  NEERI  to  this  Court.   On  

18.07.2011, this Court directed the Tamil Nadu Government  

and the TNPCB to submit their comments with reference to  

the NEERI report.  On 25.08.2011, this Court directed TNPCB  

to file a synopsis specifying the deficiencies with reference  

to  the  NEERI  report  and  suggest  control  measures  that  

should  be taken by  the  appellants  so  that  this  Court  can  

consider the direction to be issued for  remedial  measures  

which can be monitored by the TNPCB.   Accordingly,  the  

TNPCB filed  an  affidavit  dated  30.08.2011  along  with  the  

chart  of  deficiencies and measures to be implemented by  

54

55

Page 55

the appellants and on 11.10.2011,  this  Court  directed the  

TNPCB to issue directions, in exercise of its powers under the  

Air Act and the Water Act to the appellants to carry out the  

measures and remove the deficiencies indicated in the chart.  

Pursuant to the order dated 11.10.2011, the TNPCB issued  

directions  to  the  appellants  and  on  17.01.2012,  the  

appellants claimed before the Court that they have removed  

the  deficiencies  pointed  out  by  the  TNPCB  and  on  

27.08.2012,  this  Court  directed  that  a  joint  inspection  be  

carried  out  by  TNPCB  and  CPCB  and  completed  by  14th  

September,  2012  and  a  joint  report  be  submitted  to  this  

Court.   

38.  The conclusion in the joint inspection report of CPCB and  

TNPCB is extracted hereinbelow:

“Out of the 30 Directions issued by the Tamil  Nadu  Pollution  Control  Board,  the  industry  has  complied  with  29  Directions.   The  remaining Direction No.1(3) under the Air Act  on installation of bag filter to converter is at  the final stage of erection, which will require  further  15 working  days  to  fully  comply  as  per the industry’s revised schedule.”

55

56

Page 56

From the aforesaid conclusion of the joint inspection report,  

it is clear that out of the 30 directions issued by the TNPCB,  

the appellant-company has complied with 29 directions and  

only one more direction under the Air Act was to be complied  

with.  As the deficiencies in the plant of the appellants which  

affected the environment as pointed out by NEERI have now  

been  removed,  the  impugned  order  of  the  High  Court  

directing closure of the plant of the appellants is liable to be  

set aside.

39. We may now consider the contention on behalf of the  

interveners  that  the  appellants  were  liable  to  pay  

compensation for  the damage caused by the plant  to  the  

environment.  The NEERI reports of 1998, 1999, 2003 and  

2005 show that the plant of the appellant did pollute the  

environment through emissions which did not conform to the  

standards laid  down by the TNPCB under  the Air  Act  and  

through discharge of effluent which did not conform to the  

standards laid down by the TNPCB under the Water Act.  As  

pointed  out  by  Mr.  V.  Gopalsamy  and  Mr.  Prakash,  on  

account of some of these deficiencies, TNPCB also did not  

56

57

Page 57

renew the consent to operate for some periods and yet the  

appellants  continued  to  operate  its  plant  without  such  

renewal.  This is evident from the following extracts from the  

NEERI report of 2011:

“Further, renewal of the Consent to Operate was  issued  vide  the  following  Proceedings  Nos.  and  validity period:

TNPCB Proceeding Validity  Upto

No.T7/TNPCB/F.22276/RL/TTN/W/2007  dated 07.05.2007 No.T7/TNPCB/F.22276/RL/TTN/A/2006  dated 07.05.2007

30-09-2007

No.T7/TNPCB/F.22276/URL/TTN/W/20 08 dated 19.01.2009 No.T7/TNPCB/F.22276/URL/TTN/A/200 8 dated 19.01.2009

31-03-2009

No.T7/TNPCB/F.22276/URL/TTN/W/20 09 dated 14.08.2009 No.T7/TNPCB/F.22276/URL/TTN/A/200 9 dated 14.08.2009

31-12-2009

Thereafter, the TNPCB did not renew the Consents  due to non-compliance of the following conditions:

Under Water Act, 1974

i. The unit shall take expedite action to achieve the  time bound target for disposal of slag, submitted  to  the  Board,  including  BIS  clearance  before  arriving at disposal to cement industries,  marine  impact study before arriving at disposal for landfill  in abandoned quarries.

57

58

Page 58

ii. The unit shall take expedite action to dispose the  entire stock of the solid waste of gypsum.

Under Air Act, 1981

i. The  unit  shall  improve  the  fugitive  control  measure  to  ensure  that  no  secondary  fugitive  emission is discharged at any stage, including at  the  points  of  material  handing  and  vehicle  movement area.”

For such damages caused to the environment from 1997 to  

2012 and for operating the plant without a valid renewal for  

a  fairly  long  period,  the  appellant-company  obviously  is  

liable to compensate by paying damages.  In M.C. Mehta and  

Another vs. Union of India and Others [(1987) 1 SCC 395], a  

Constitution Bench of this Court held:

“The  enterprise  must  be  held  to  be  under an obligation to provide that the  hazardous  or  inherently  dangerous  activity in which it is engaged must be  conducted with the highest standards of  safety  and  if  any  harm  results  on  account of such activity, the enterprise  must be absolutely liable to compensate  for  such  harm  and  it  should  be  no  answer to the enterprise to say that it  had taken all reasonable care and that  

58

59

Page 59

the  harm  occurred  without  any  negligence on its part.”

The  Constitution  Bench  in  the  aforesaid  case  further  

observed that  the  quantum of  compensation must  be co-

related  to  the  magnitude  and  capacity  of  the  enterprise  

because such compensation  must  have a  deterrent  effect  

and  the  larger  and  more  prosperous  the  enterprise,  the  

greater must be the amount of compensation payable by it.  

In  the  Annual  Report  2011  of  the  appellant-company,  at  

pages 20 and 21, the performance of its copper project is  

given.  We extract hereinbelow the paragraph titled Financial  

Performance:

“PBDIT  for  the  financial  year  2010-11  was  Rs.1,043  Crore,  40%  higher  than  the  PBDIT  of  Rs.744  Crore  for  the  financial  year  2009-10.   This  was  primarily due to higher LME prices and  lower unit costs at Copper India and with  the improved by-product realization.”

Considering the magnitude, capacity and prosperity of the  

appellant-company, we are of the view that the appellant-

company should be held liable for a compensation of Rs. 100  

crores for having polluted the environment in the vicinity of  

59

60

Page 60

its plant and for having operated the plant without a renewal  

of the consents by the TNPCB for a fairly long period and  

according  to  us,  any  less  amount,  would  not  have  the  

desired  deterrent  effect  on  the  appellant-company.   The  

aforesaid  amount  will  be  deposited  with  the  Collector  of  

Thoothukudi  District,  who will  invest  it  in  a  Fixed Deposit  

with  a  Nationalized  Bank for  a  period  of  five  years.   The  

interest  therefrom  will  be  spent  for  improving  the  

environment, including water and soil, of the vicinity of the  

plant  after  consultation  with  TNPCB  and  approval  of  the  

Secretary, Environment, Government of Tamil Nadu.

40. We now come to the submission of Mr. Prakash that we  

should  not  grant  relief  to  the  appellants  because  of  

misrepresentation and suppression of material facts made in  

the special  leave petition that the appellants have always  

been  running  their  plant  with  statutory  consents  and  

approvals  and  misrepresentation  and  suppression  of  

material  facts  made in the special  leave petition that  the  

plant was closed at the time the special leave petition was  

moved and a stay order was obtained from this  Court  on  

60

61

Page 61

01.10.2010.   There  is  no  doubt  that  there  has  been  

misrepresentation and suppression of material facts made in  

the  special  leave  petition  but  to  decline  relief  to  the  

appellants in this case would mean closure of the plant of  

the  appellants.   The  plant  of  the  appellants  contributes  

substantially to the copper production in India and copper is  

used  in  defence,  electricity,  automobile,  construction  and  

infrastructure  etc.   The plant  of  the  appellants  has about  

1300 employees and it also provides employment to large  

number  of  people  through  contractors.   A  number  of  

ancillary  industries  are  also  dependent  on  the  plant.  

Through its various transactions, the plant generates a huge  

revenue  to  Central  and  State  Governments  in  terms  of  

excise,  custom  duties,  income  tax  and  VAT.   It  also  

contributes  to  10% of  the total  cargo volume of  Tuticorin  

port.  For these considerations of public interest, we do not  

think  it  will  be  a  proper  exercise  of  our  discretion  under  

Article 136 of the Constitution to refuse relief on the grounds  

of misrepresentation and suppression of material facts in the  

special leave petition.  

61

62

Page 62

41. Before we part with this case, we would like to put on  

record our  appreciation for  the writ  petitioners before the  

High Court and the intervener before this Court for having  

taken up the cause of the environment both before the High  

Court and this Court and for having assisted this Court on all  

dates of  hearing with utmost sincerity and hard work.   In  

Indian Council for Enviro-Legal Action and Others vs.  Union  

of India and Others [(1996) 3 SCC 211], this Court observed  

that  voluntary  bodies  deserve  encouragement  wherever  

their actions are found to be in furtherance of public interest.  

Very  few  would  venture  to  litigate  for  the  cause  of  

environment,  particularly  against  the  mighty  and  the  

resourceful,  but the writ  petitioners before the High Court  

and the intervener before this Court not only ventured but  

also put in their best for the cause of the general public.  

42. In the result, the appeals are allowed and the impugned  

common  judgment  of  the  High  Court  is  set  aside.   The  

appellants,  however,  are  directed  to  deposit  within  three  

62

63

Page 63

months from today a compensation of Rs.100 crores with the  

Collector of Thoothukudi District, which will be kept in a fixed  

deposit in a Nationalized Bank for a minimum of five years,  

renewable  as  and  when  it  expires,  and  the  interest  

therefrom  will  be  spent  on  suitable  measures  for  

improvement of the environment, including water and soil, of  

the vicinity of the plant of the appellants after consultation  

with  TNPCB  and  approval  of  the  Secretary,  Environment,  

Government  of  Tamil  Nadu.   In  case  the  Collector  of  

Thoothukudi District, after consultation with TNPCB, finds the  

interest amount inadequate, he may also utilize the principal  

amount  or  part  thereof  for  the  aforesaid  purpose  after  

approval  from the Secretary,  Environment,  Government  of  

Tamil Nadu.  By this judgment, we have only set aside the  

directions  of  the  High  Court  in  the  impugned  common  

judgment and we make it clear that this judgment will not  

stand  in  the  way  of  the  TNPCB  issuing  directions  to  the  

appellant-company, including a direction for closure of the  

plant, for the protection of environment in accordance with  

law.

63

64

Page 64

43.    We also make it clear that the award of damages  

of  Rs. 100 Crores by this judgment against the appellant-

Company for the period from 1997 to 2012 will not stand in  

the way of any claim for damages for the aforesaid period or  

any  other  period  in  a  civil  court  or  any  other  forum  in  

accordance with law.

.……………………….J.                                                            (A. K. Patnaik)

………………………..J.                                                            (H. L. Gokhale) New Delhi, April 2, 2013.  

64