SCHLUMBERGER ASIA SERVICES LTD. Vs OIL & NATURAL GAS CORP.LTD.
Bench: SURINDER SINGH NIJJAR
Case number: ARBIT.CASE(C) No.-000006-000006 / 2013
Diary number: 25301 / 2012
Advocates: Vs
GAURAV AGRAWAL
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 1
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION NO.6 OF 2013
Schlumberger Asia Services Ltd. ...Petitioner
VERSUS
Oil & Natural Gas Corporation Ltd. …
Respondent
J U D G M E N T
SURINDER SINGH NIJJAR,J.
1. This petition is filed under Section 11(6) of the
Arbitration and Conciliation Act, 1996 seeks a direction
from this Court for appointment of the nominee Arbitrator
on behalf of the respondent and also appointment of third
Arbitrator (Presiding Arbitrator) in the Arbitral Tribunal to
adjudicate the disputes arises between the parties.
2. The petitioner is a Company incorporated and
registered under the law of Hong Kong having its project
office in India and one of the base offices at Mumbai. The
respondent is a Corporation registered under the
1
Page 2
Companies Act, 1956 having its registered office at Jivan
Bharti Tower-2, 124, Circus New Delhi.
3. In its counter-affidavit, the respondent has raised a
preliminary objection to the maintainability of the petition.
It is submitted by the respondent that the petitioner has
filed the present case only to bring unnecessary litigation.
The arbitration petition is an abuse of process of law and
the claims made are barred by a long period of time and
are, therefore, dead claims.
4. In order to decide the preliminary objection, it would
be necessary to take note of certain relevant events.
5. The petitioner and the respondent had entered into
and executed a contract dated 7th December, 2004
(effective from the date of issue of the firm order dated 6th
August, 2004). The contract under Clause 27 provides for
arbitration as the mechanism for resolution of any dispute
that may arise between the petitioner and the respondent.
The arbitration clause reads as under:
“27 ARBITRATION
27.1 Except as otherwise provided elsewhere in the CONTRACT if any dispute, difference, question or disagreement arises, at any time before or after completion or abandonment of work, between the parties hereto or their respective representatives or
2
Page 3
assignees, at any time in connection with construction, meaning, operation, effect, interpretation or out of the CONTRACT or breach thereof the same shall be decided by an Arbitral Tribunal consisting of three Arbitrators. Each party shall appoint one Arbitrator and the Arbitrators so appointed shall appoint the third Arbitrator who will act as Presiding Arbitrator.
The party desiring the settlement of dispute shall give notice of its intention to go for arbitration clearly stating all disputes to be decided by arbitral tribunal and appoint its own arbitrator and call upon the other party to appoint its own arbitrator within 30 days. In case a party fails to appoint an arbitrator within 30 days from the receipt of the request to do so by the other party or the two Arbitrators so appointed fail to agree on the appointment of third Arbitrator within 30 days from the date of their appointment, upon request of a party, the Chief Justice of India or any person or institution designated by him (in case of International Commercial Arbitration) shall appoint the Arbitrators/Presiding Arbitrator. In case of domestic Contracts, the Chief Justice of the High Court or any person or institution designated by him within whose jurisdiction the subject purchase order/CONTRACT has been placed/made, shall appoint the arbitrator/Presiding Arbitrator upon request of one of the parties.
If any of the Arbitrators so appointed dies, resigns, incapacitated or withdraws for any reason from the proceedings, if shall be lawful for the concerned party/arbitrators to appoint another person in his place in the same manner as aforesaid. Such person shall proceed with the reference from the stage where his predecessor had left if both parties consent for the same; otherwise, he shall proceed de novo.
It is a term of the CONTRACT that the party invoking arbitration shall specify all disputes to
3
Page 4
be referred to arbitration at the time of invocation of arbitration and not thereafter.
It is also a term of the CONTRACT that neither party to the CONTRACT shall be entitled for any ante-lite (pre-reference) or pendent-lite interest on the amount of the award.
The Arbitral Tribunal shall give reasoned award and the same shall be final, conclusive and binding on the parties.
The venue of the arbitration shall be at Mumbai, India.
It is a term of the CONTRACT that the cost of the arbitration will be borne by the parties in equal shares.
Subject to as aforesaid the provisions of the Arbitration and Conciliation Act, 1996 and any statutory modifications or re-enactment in lieu thereof shall apply to the arbitration proceedings under this clause.”
Clause 26 of the Contract further provides as under:
“26 JURISDICTION AND APPLICABLE LAW:
This agreement including all matter connected with this Agreement, shall be governed by the laws of India (both substantive and procedural) for the time being in force and shall be subject to exclusive jurisdiction of the Indian Court at Mumbai. Foreign Companies, operating in Indian or entering into Joint ventures in India, shall have to obey the law of the Land and there shall be no compromise or excuse for the ignorance of the Indian legal system in any way.”
4
Page 5
6. The petitioner together with its affiliates is a leading
oilfield service provider. It is trusted to deliver superior
results and improved E&P performance for oil and gas
companies around the world, including India. Through its
well site operations, research and engineering facilities, it
is working to develop products, services and solutions that
optimize customer performance in a safe and
environmentally sound manner. It employs over 113,000
people of more than 140 nationalities working
in 85 countries, including India.
7. The respondent was desirous of hiring four sets of
Measurement While Drilling (MWD) and one set of Gyro
Equipment & Services (Gyro) collectively referred to as
“Equipments” for carrying out its operation. Accordingly,
the respondent issued a tender No.MR/DS/MAT/CT/MWD/
142(390) 2003-04/P46KC04002. The petitioner had the
necessary experience of carrying out operation as stated
in the tender and submitted a bid on 8th June, 2004 under
offer No.SASL/D&M/ONGC 4002/2002-02 for providing the
required services against the respondent’s tender in
accordance with the terms and conditions set-forth
therein. The respondent accepted the bid of the petitioner
5
Page 6
and placed a firm order dated 6th August, 2004 under
No.MR/DS/MAT/CT/MWD/142(390)2003-04/DY8DF0301/
9010002261. Accordingly, on 7th December, 2004, the
parties entered into and duly executed a contract
effective from the date of issue of the firm order i.e. 6 th
August, 2004. The petitioner agreed to perform a work
defined in Appendix-III of the Contract. The respondent in
consideration thereto promised to pay the amounts set
out in Appendix-IV of the Contract at the time and in the
manner prescribed in the contract. The duration of the
contract was initially for a period of 2 years from the date
of receipt of “Equipments” at Nhava base. The
respondent had the option of extending the contract by
one more year in two equal installments of six months
each at the same rate, terms and conditions. The contract
was automatically extendable for completion of jobs in
ongoing wells, at the same rates, terms and conditions.
The petitioner claims that as it was providing excellent
services to the respondent, the contract was extended
from 16th October, 2006 to 15th April, 2007 for the
first installment of six months. Thereafter, it was
extended from 16th April, 2007 to 15th October,
6
Page 7
2007 for the second installment of six months on the
same rates, terms and conditions as contained in Clause
2.0 of the Special Terms and Conditions of the Contract.
8. The petitioner further claims that it performed the
work in terms of the contract and raised invoices for the
work performed from time to time. However, invoices
amounting to USD 481,252.65 and INR 9,565,616 were
either short paid or not paid despite the work under the
contract was satisfactorily performed by the petitioner.
The details of the invoices raised by the petitioner are as
under:
Invoice No. Period Amount (USD)
800001820 March 2006 128,630.00 800001821 March 2006 89,149.00 800001828B March 2006 31,053.00 800001829B March 2006 41,406.00 800002119 September 2006 192,169.00 800002120B September 2006 63,729.00 800002860 September 2007 71,304.00 800002861B September 2007 96.00 800002862B September 2007 49,487.00
Total 667,023.00
9. The petitioner further claims that the respondent has
refused to make payment against the aforesaid invoices.
The respondent totally rejected the various Lost in Hole
(LIH) claims of the petitioner. According to the petitioner,
7
Page 8
in the event of “Equipments” are lost, destroyed or
damaged in the site well, the respondent is liable to pay
the depreciated replacement value of the “Equipments”
stuck/lost in the hole subject to a limit of 50% calculated
from the date of first use of such “Equipments” in India.
Furthermore, in terms of the Clause 17 of the Contract,
the respondent was under an obligation to make an
attempt to recover or retrieve the said tools but the
respondent failed to discharge this obligation also.
10. Since no payment had been received, the petitioner
sent a letter to the respondent on 11th July, 2008
demanding the payment of the outstanding amount.
However, there was no response to the aforesaid
communication. The petitioner, therefore, issued a legal
notice dated 14th November, 2008 invoking arbitration
under Clause 27 of the Contract. In the aforesaid notice,
the petitioner detailed the disputes that have arisen
between the parties. In the same notice, the petitioner
informed the respondent that it has nominated the
Arbitrator and called upon the respondent to nominate
their Arbitrator within 30 days from the date of receipt of
the notice, failing which the petitioner shall be constrained
8
Page 9
to initiate legal steps for appointment of Arbitrator on
behalf of the respondent. According to the petitioner, the
aforesaid notice was duly served upon the respondent but
no steps were taken by them for appointment of
Arbitrator. Thereafter, the petitioner sent a reminder
letter on 21st May, 2009 calling upon the respondent to
nominate an Arbitrator within 30 days from the date of
receipt of the notice. The petitioner reiterated that in
case the respondent still failed to nominate the Arbitrator,
the petitioner shall initiate proceedings for appointment of
Arbitrator on behalf of the respondent. Another reminder
was issued by the petitioner on 11th August, 2010 in the
same terms as the earlier notices and the reminders. Still
there was no response from the respondent, which led the
petitioner to send another notice on 9th January, 2012.
Finally, on 29th February, 2012, the respondent sent a
reply to the petitioner denying that any amount as
claimed by the petitioner was due.
11. At this stage, the petitioner finally accepted that
disputes have arisen between the parties and filed the
present petition under Section 11(6) of the Arbitration and
Conciliation Act, 1996 seeking appointment of the
9
Page 10
nominee Arbitrator on behalf of the respondent as well as
the third Arbitrator (Presiding Arbitrator).
12. I have heard the learned counsel for the parties.
Mr. Siddharth Luthra, learned senior counsel has
submitted that: (1) the petitioner had accepted the
payment without demur in 2007. The claims are,
therefore, already settled.; (2) The contract had come to
an end long time ago upon the petitioner accepting
payment in 2007.; (3) The cause of action, if any, arose in
2007, while the arbitration petition is filed in January,
2013.; (4) According to Mr. Luthra, even on pleadings of
the petitioner, the cause of action arose to the petitioner
for filing petition under Section 11(6) of the Arbitration
and Conciliation Act from 14th December, 2008 i.e. on
expiry of 30 days from the first notice
dated 14th November, 2008 invoking arbitration. Learned
senior counsel submitted that the present petition ought
to have been filed within a maximum period of 3 years
from the said date, i.e., on or before 14th December, 2011
while the present petition has been filed on 11th January,
2013. Learned senior counsel emphasized that this Court
would not entertain the present petition as it raises dead
10
Page 11
claims. The contract expired after the de-hiring of last
unit on 21st October, 2007. The respondent had received
the entire amount in the years 2006-07. Pointing out to
the averments made in the counter-affidavit, Mr. Luthra
submits that the letter dated 14th November, 2008, 21st
May, 2009 and 11th August, 2010, which were written to
ONGC, were not received in the concerned section of
ONGC. The address in the contract for correspondence
was given as ONGC Limited, Drilling Services, Mumbai
Region, 3B, Vasundhara Bhavan, Bandra-East, Mumbai-51.
This was changed to ONGC Limited, Drilling Services,
Directional Drilling Section, Mumbai Region, 2nd Floor, 11-
High, ONGC, Sion (W), Mumbai-400017 in October, 2005.
This was known to the petitioner as it had submitted the
invoices to ONGC at new address. However, notices dated
21st May, 2009 and 11th August, 2010 were still sent to the
earlier address. In any event, notice dated 14th
November, 2008 was never received by the respondent.
Mr. Luthra submits that mere sending of subsequent show
cause notice/letters would not extend the limitation as the
date of cause of action was fixed on the expiry of 30 days
from the first notice dated 14th November, 2008. Mr.
11
Page 12
Luthra points out that Section 43 of the Arbitration and
Conciliation Act, 1996 provides that the Limitation Act,
1963 shall apply to arbitrations as it applies to
proceedings in Court. Relying on Section 43(2) read with
Section 21 of the aforesaid Act, the learned counsel
submitted that the arbitration shall be deemed to have
commenced on the date on which a request for that
dispute referred to arbitration is received by the
respondent. The petitioner having sent the first notice
on 14th November, 2008, the arbitration petition ought to
have been filed after the expiry of 30 days therefrom.
Learned counsel relies on the Constitution Bench of this
Court in SBP & Co. Vs. Patel Engineering Ltd. & Anr.
(2005) 8 SCC 618, in support of the submission that the
present petition is barred by limitation. He relies on para
39 of the judgment, which reads as under:
“39. It is necessary to define what exactly the Chief Justice, approached with an application under Section 11 of the Act, is to decide at that stage. Obviously, he has to decide his own jurisdiction in the sense whether the party making the motion has approached the right High Court. He has to decide whether there is an arbitration agreement, as defined in the Act and whether the person who has made the request before him, is a party to such an agreement. It is necessary to indicate that he can also decide the question whether the claim was a dead one;
12
Page 13
or a long-barred claim that was sought to be resurrected and whether the parties have concluded the transaction by recording satisfaction of their mutual rights and obligations or by receiving the final payment without objection. It may not be possible at that stage, to decide whether a live claim made, is one which comes within the purview of the arbitration clause. It will be appropriate to leave that question to be decided by the Arbitral Tribunal on taking evidence, along with the merits of the claims involved in the arbitration. The Chief Justice has to decide whether the applicant has satisfied the conditions for appointing an arbitrator under Section 11(6) of the Act. For the purpose of taking a decision on these aspects, the Chief Justice can either proceed on the basis of affidavits and the documents produced or take such evidence or get such evidence recorded, as may be necessary. We think that adoption of this procedure in the context of the Act would best serve the purpose sought to be achieved by the Act of expediting the process of arbitration, without too many approaches to the court at various stages of the proceedings before the Arbitral Tribunal.”
13. Relying on the aforesaid observations, the learned
senior counsel has submitted that this Court would have
to decide as to whether the petition is liable to be
dismissed on the ground of limitation as it raises dead
claims. It would not be necessary for this Court to leave
the matter to be decided by the Arbitral Tribunal.
13
Page 14
14. On the other hand, Mr. Sanjiv Puri, learned senior
counsel appearing for the petitioner submits that the
limitation stops running from the date mentioned in the
notice invoking arbitration and in the present case, the
notice invoking arbitration was sent on 14th November,
2008. Learned counsel also relied on Section 3 of the
Arbitration and Conciliation Act, 1996 in support of the
submission that the notice is deemed to have been
received by respondent as it was delivered to the
addresses mentioned in the contract. In any event, the
learned counsel submitted that the petitioner had sent the
final notice on 9th January, 2012 and the respondent had
denied the claim through its letter dated 29th February,
2012. The disputes clearly arose only w.e.f. 29th February,
2012. Therefore, the preliminary objection raised by the
respondent deserves to be rejected.
15. In any event, learned senior counsel submitted that
this Court in the case of Indian Oil Corporation Ltd. Vs.
SPS Engineering Ltd. (2011) 3 SCC 507 has
considered and explained the observations made by the
Constitution Bench in SBP & Company’s case (supra).
It is submitted that on the question of limitation, this Court
14
Page 15
had categorically held that the matter will be left to the
decision of the Tribunal to decide whether the claim made
is barred by limitation or not.
16. I have considered the submissions made by the
learned counsel for the parties. A bare perusal of the
observations made by this Court in paragraph 39 of the
judgment in SBP & Co. (supra) makes it clear that the
Chief Justice or the designated Judge can also decide
whether the claim was dead one or a long-barred claim.
But it is not imperative for the Chief Justice or his
designate to decide the questions at the threshold. It can
be left to be decided by the Arbitral Tribunal. The
observations made in SBP & Co. (supra) were explained
by this Court in Indian Oil Co. Ltd. (supra), which are as
under:
“14. To find out whether a claim is barred by res judicata, or whether a claim is “mala fide”, it will be necessary to examine the facts and relevant documents. What is to be decided in an application under Section 11 of the Act is whether there is an arbitration agreement between the parties. The Chief Justice or his designate is not expected to go into the merits of the claim or examine the tenability of the claim, in an application under Section 11 of the Act. The Chief Justice or his designate may however choose to decide whether the claim is
15
Page 16
a dead (long-barred) claim or whether the parties have, by recording satisfaction, exhausted all rights, obligations and remedies under the contract, so that neither the contract nor the arbitration agreement survived. When it is said that the Chief Justice or his designate may choose to decide whether the claim is a dead claim, it is implied that he will do so only when the claim is evidently and patently a long time-barred claim and there is no need for any detailed consideration of evidence. We may elucidate by an illustration: if the contractor makes a claim a decade or so after completion of the work without referring to any acknowledgment of a liability or other factors that kept the claim alive in law, and the claim is patently long time-barred, the Chief Justice or his designate will examine whether the claim is a dead claim (that is, a long time-barred claim). On the other hand, if the contractor makes a claim for payment, beyond three years of completing of the work but say within five years of completion of work, and alleges that the final bill was drawn up and payments were made within three years before the claim, the Court will not enter into a disputed question whether the claim was barred by limitation or not. The Court will leave the matter to the decision of the Tribunal. If the distinction between apparent and obvious dead claims, and claims involving disputed issues of limitation is not kept in view, the Chief Justice or his designate will end up deciding the question of limitation in all applications under Section 11 of the Act.
These observations make it clear that it is optional
for the Chief Justice or his designate to decide whether the
claim is dead (long-barred). It is also made clear by this
Court that the Chief Justice or his designate would do so
16
Page 17
only when the claim is evidently and patently a long time-
barred claim. The claim could be said to be patently long
time-barred, if the contractor makes it a decade or so
after completion of the work without referring to any
acknowledgment of a liability or other factors that kept
the claim alive in law. On the other hand, if the contractor
makes a claim, which is slightly beyond the period of three
years of completing the work say within five years of
completion, the Court will not enter into disputed
questions of fact as to whether the claim was barred by
limitation or not. The judgment further makes it clear that
there is no need for any detailed consideration of
evidence.
17. In the present case, there is a dispute as to whether
the repeated notices sent by the petitioner to the
respondents were ever received. There are further
disputes (even if the notices were received by ONGC) as
to whether they were actually received in the correct
section of ONGC. These are matters of evidence which
are normally best left to be decided by the Arbitral
Tribunal.
17
Page 18
18. In my opinion, it would be appropriate for this Court
to constitute the entire Arbitral Tribunal in exercise of my
powers under Section 11(6) of the Arbitration and
Conciliation Act, 1996. In exercise of the aforesaid
powers, I nominate Justice V.N. Khare, Former Chief
Justice of India as the Chairman and Justice D.P. Wadhwa
and Justice S.N. Variava, former Judges of this Court as
Arbitrators to adjudicate the disputes that have arisen
between the parties. The arbitrators shall fix their own
remuneration in consultation with the parties.
19. The Registry is directed to communicate this order to
the Chairman of the Arbitral Tribunal, as well as to the
other Arbitrators, so that they can enter upon reference,
as soon as possible.
20. With these observations, the Arbitration Petition is
allowed with no order as to costs.
.……..…………………..J. [Surinder Singh
Nijjar] New Delhi; May 09, 2013.
18