SAJAN Vs THE STATE OF MAHARASHTRA
Bench: HON'BLE MRS. JUSTICE R. BANUMATHI, HON'BLE MR. JUSTICE A.S. BOPANNA
Judgment by: HON'BLE MRS. JUSTICE R. BANUMATHI
Case number: C.A. No.-002170-002171 / 2020
Diary number: 15467 / 2018
Advocates: SHIRISH K. DESHPANDE Vs
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 2170-2171 OF 2020 (Arising out of SLP(C) Nos.16945-46 of 2018)
SAJAN …..Appellant
VERSUS
STATE OF MAHARASHTRA AND OTHERS …..Respondents
WITH
CIVIL APPEAL NOS. 2172-2173 OF 2020 (Arising out of SLP(C) Nos.6393-6394 of 2020
@ SLP(C) Diary No.24459 of 2019)
J U D G M E N T R. BANUMATHI, J.
Leave granted.
2. These appeals have been filed by the appellants assailing the
impugned judgment and final order dated 21.08.2017 passed by the
High Court of Judicature at Bombay Bench at Aurangabad in First
Appeal No.601 of 1997 along with Cross Objection St. No.22145 of
1997 in the First Appeal in and by which the High Court partly
allowed the appeal and inter-alia reduced the compensation for the
land by giving 40% deduction towards development cost.
3. The facts giving rise to these appeals are that land in Gat
No.85 at village Mhasekota, Tehsil Soyegaon, District Aurangabad
1
admeasuring 6 acres (2.40 hectares) owned by the partnership firm
of the appellant and respondents No.2 and 3 was proposed for
acquisition for the purpose of construction of Hiwra Dam project by
the office of the Executive Engineer, Jalgaon Medium Project
Division. Accordingly, on 29.03.1982, the Special Land Acquisition
Officer issued notification under Section 4 of the Land Acquisition
Act, 1984 (for short, “Land Acquisition Act”) and on 03.11.1983,
notification under Section 6 was published. Out of this acquired
land, land admeasuring 0.80 hectares was non-agricultural land
used for running the Sugar Mill by the partnership firm and the
remaining was cultivable land.
4. The Special Land Acquisition Officer, Aurangabad passed an
award dated 01.09.1986 under Section 11 of the Land Acquisition
Act awarding compensation considering valuation of land @
Rs.29,712/- (Rs.20,000/- per hectare for 0.80 hectares non-
agricultural land, Rs.9500/- per hectare in respect of 1.44 hectare
cultivable land and Rs.200 per hectare in respect of 0.16 hectare
Potkharaba land). Apart from the costs of the land, the S.L.A.O.
has also fixed the valuation of structure under three heads i.e. (i)
Civil part/Building valuation Rs.3,67,100/-; (ii) Electrical installation
(now to be demolished) Rs.1,06,000/-; and (iii) Mechanical
2
machinery (dismantling and transportation) Rs.1,05,000/-, total
Rs.5,78,100/-. To this compensation amount, statutory entitlement
of 30% solatium and 12% enhancement of compensation value
w.e.f. notification under Section 4 was added. The net amount
payable was calculated at Rs.36,00,385.50/-.
5. Aggrieved, the appellant and also respondents No.2 and 3
filed reference application (Land Acquisition Reference No.299/94)
under Section 18 of Land Acquisition Act on the ground that market
value has not been properly determined. The appellant and
respondents No.2 and 3 further claimed damages and loss of
business @ Rs.5,00,000/- per year since 1981 till 1986
to the tune of Rs.30,00,000/-. The appellants claimed market value
@ Rs.10 per sq.ft and claimed total compensation at
Rs.1,69,45,111/- along with other statutory benefits.
6. The Reference Court-Civil Judge, Senior Division,
Aurangabad, vide judgment and award dated 24.04.1996 awarded
compensation at the enhanced rate of Rs.6/- per sq. ft. for the entire
acquired land by treating the entire land as land meant for
non-agricultural use and deducted 10% towards development costs,
Rs.3,86,867/- towards demolishing and dismantling charges of
electrical, mechanical and machinery installation, Rs.5,00,000/- was
3
awarded for loss of earning for the period from 1981 to 1986,
Rs.91,000/- towards damages and dismantling charges and
Rs.15,000/- towards transportation, loading and unloading along
with the statutory benefits. Thus, total additional claim of the
appellant to the extent of Rs.23,73,011/- was allowed.
7. Respondent-State filed First Appeal No.601 of 1997 assailing
the aforesaid order and the appellant and respondents No.2 and 3
also filed Cross Objection bearing St. No.22145 of 1997. Initially this
cross-objection was dismissed by the High Court for non-removal of
objections. Restoration application was also dismissed on account
of inordinate delay and the appeal filed by the respondents was
partly allowed. Against this dismissal, the appellant and respondents
No.2 and 3 filed appeal No.2432 of 2005 before the Supreme Court
which was allowed vide judgment dated 20.04.2011 and the matter
was remitted back to the High Court for fresh disposal taking into
consideration the law laid down by this court in recent judgments.
8. Thereafter, by impugned Judgment dated 21.08.2017, the
High Court partly allowed the appeal as well as cross-objections
and passed the following award:-
i. Cost of the land @ Rs.6/- per sq.ft. (Deduction at 10%)
…. Rs.9,40,896/-
ii. Dismantling and damage …. Rs.4,26,890/-
4
of Civil work costs iii. Replacement of
electrical installation …. Rs.2,39,000/-
iv. Depreciated value of machineries
…. Rs.6,62,000/-
v. Loss of business …. Rs.5,00,000/-
Total …. Rs.21,60,974/-
9. Mr. Gopal Balwant Sathe, learned counsel for the appellant
assailed the impugned judgment contending that the High Court
failed to consider the valuation certificate (Exh.-21) duly proved by
PW-2-Mukund Dharashivkar-Empanelled Government Valuer
whose evidence remained unrebutted by the State Government.
Further, it has been submitted that Exh.-21 proves that the civil work
comes to the tune of Rs.9,55,000/-, electrical installation
Rs.3,21,000/- and mechanical installation Rs.10,69,000/- which
totally comes to Rs.23,45,000/- and the depreciation value comes to
Rs.14,28,000/-. Totally, the valuation of the civil, mechanical and
electrical structure comes to Rs.63,80,000/- and the valuation done
by PW-21-Valuer has not been considered by the High Court. It was
further submitted that the High Court has completely ignored the
fact that the respondents had not adduced any documentary
evidence to show that the valuation certificate (Exh.-21) issued by
PW-2 is not proper and lacks precision. It was further submitted that
computation of loss of business @ Rs.1,00,000/- per year is
5
completely erroneous. It was submitted that the High Court erred in
not taking into consideration that the appellant had to close the
sugar factory and face financial crisis suffering decree of civil court
for recovery of loan amount as the appellant had raised loan from
the bank. It was further submitted that the High Court erred in
making deduction of 40% though the lands were acquired for
irrigation project which does not require development charges like
providing basic amenities like roads, water etc. and the Reference
Court rightly made deduction of 10% which is a reasonable
deduction and the High Court erred in reducing the compensation
amount.
10. On the other hand, Mr. Aaditya A. Pande, learned counsel
appearing for the State of Maharashtra has submitted that the
Reference Court has committed an error by considering the market
value of fully developed plot and comparing the same with
undeveloped land. It was submitted that village Mhasekota is a very
small village having a population of one thousand, situated in a
remote area without any development potentials and there was no
potential value of the acquired land as non-agricultural land. It was
further contended that no purchaser will come forward to purchase
the large area of land admeasuring 1.44 hectares on square feet
6
basis and without considering this aspect, the Reference Court had
enhanced the compensation @ Rs. 6.90 per sq.ft. Drawing our
attention to the evidence of the State witness Dilip Gudwe,
Sub-Divisional Officer, it was submitted that SDO had visited the
site and factory premises and submitted a report (Exh.-54)
mentioning that the factory was not in operation and the machinery
was lying idle and considering the same, the High Court has
recorded a finding that the claimants had closed the sugar factory.
The learned counsel urged that the High Court rightly reduced the
compensation awarded by the First Appellate Court and there is no
ground warranting interference with the impugned judgment.
11. We have heard Mr. Shirish K. Deshpande and Mr. Sagar N.
Pahune Patil, learned counsel appearing on behalf of the appellants
and Mr. Rahul Chitnis, learned counsel appearing on behalf of the
respondent-State. We have carefully considered the contentions
and perused the impugned judgment and materials on record.
12. The land Gat No.85 admeasuring 6 acres, situated at
Mhasekota in Soygaon Tahsil of Aurangabad district, owned by the
appellants-claimants came to be acquired by the Government for
construction of Hiwra medium project. The land Gat No.85
admeasuring 2 hectares 40 R came to be acquired including 0.16
7
hectare Potkharaba land. Out of this area, land admeasuring 0.80
hectare has been converted into non-agriculture (N.A) purpose for
installation of Khandsari factory (sugar factory). Rest of the area
admeasuring 1.44 hectare is appellants claim that they have been
using for non-agricultural purpose. Though the claimants had asked
for non-agricultural permission for the land admeasuing 1.44
hectare out of the land Gat No.85, the same was not granted by the
concerned authority. The S.L.A.O. on 29.03.1982 has published the
notification under Section 4 of the Land Acquisition Act and on
01.09.1986 awarded the compensation for the acquired land
admeasuring 0.80 R, since converted into the non-agriculture land,
at the rate of Rs.2.00 per sq. meter i.e. Rs.20,000/- per hectare. The
S.L.A.O. has awarded the compensation to the agricultural land
admeasuring 1.44 R at the rate of Rs.9500/- per hectare. So far as
Potkharaba land, which is 0.16 hectare is concerned, the S.L.A.O.
has awarded the compensation at the rate of Rs.200/- per hectare.
The S.L.A.O. has awarded total compensation at Rs.29,712/- as the
costs of the land, as stated above.
13. So far as the use of the entire land for non-agricultural
purpose is concerned, the High Court found that the Reference
Court is justified in treating the entire land having the potential for
8
non-agricultural purpose of the remaining area – 1.44 hectare.
Referring to the Project report – Exh.42 - scheme of the factory
approved by the Small Scale industries, Aurangabad, the High
Court found that the main raw material required for the sugar factory
is sugarcane and part of the building is used for keeping the raw
materials. The High Court further found that besides flow sheet,
certain part of the land would be utilised for office building,
workshop, staff quarters, etc. and also used for parking and various
other purposes. The High Court also pointed out that the State has
not adduced any evidence to the effect that the land admeasuring 1
hectare 44 R out of the acquired land was mainly used for
agricultural purpose and not for the non-agricultural purpose. In
view of the concurrent findings by the Reference Court and by the
High Court that apart from 0.80 hectare, the land measuring 1
hectare 44 R be taken as having the potential for non-agricultural
purpose, we do not find any reason to take a different view.
Market value and deduction for development
14. The High Court has taken Exh.23 dated 03.06.1976 as
exemplar which is the sale deed for plot admeasuring 30x32 ft.
9
(960 sq.ft.) for Rs.3,000/- i.e. at the rate of Rs.3.12 per sq.ft. The
appellants have also placed further reliance on the sale deed dated
03.02.1982 Exh.35 wherein, the plot of admeasuring 5023 sq.ft.
was sold for Rs.35,000/- i.e. Rs.6.90 per sq.ft. The High Court has
taken Exh.23 sale deed dated 03.06.1976 and had taken 10%
increase for every year and arrived at the value at Rs.6 per sq.ft.
Even going by Exh.35 sale deed (03.02.1982) under which Rs.5023
sq.ft. was sold for Rs.35,000/- i.e. Rs.6.90 per sq.ft., Exh.35 sale
deed (03.02.1982) is after possession of the land was taken by the
State Government (21.11.1981) and Section 4 Notification dated
10.02.1982. Since Exh.35 sale deed dated 03.02.1982 is between
two dates - date of taking possession of the land and the date of
Section 4 Notification, it is necessary to adopt a reasonable
valuation. Considering Exh.23 and Exh.35, the value adopted by the
Reference Court at Rs.6.90 per sq.ft., in our view, fixation of
valuation at Rs.6.90 per sq.ft., the value adopted is fair and
reasonable and the same is affirmed.
15. Taking the value at Rs.6.90 per sq.ft, the High Court deducted
40% towards the development cost and calculated the value of the
land at Rs.2,61,300 sq.ft. at Rs.9,40,896.00. While determining the
market value of the acquired land, normally one-third deduction i.e.
33 1/3% towards development charges is allowed. After referring to
10
number of judgments, in Major General Kapil Mehra and Others vs.
Union of India and Another (2015) 2 SCC 262, the Supreme Court
held as under:-
“36. While determining the market value of the acquired land, normally one-third deduction i.e. 33 1/3% towards development charges is allowed. One-third deduction towards development was allowed in Tehsildar (LA) v. A. Mangala Gowri (1991) 4 SCC 218, Gulzara Singh v. State of Punjab (1993) 4 SCC 245, Santosh Kumari v. State of Haryana (1996) 10 SCC 631, Revenue Divl. Officer and LAO v. Sk. Azam Saheb (2009) 4 SCC 395, A.P. Housing Board v. K. Manohar Reddy (2010) 12 SCC 707, Ashrafi v. State of Haryana (2013) 5 SCC 527 and Kashmir Singh v. State of Haryana (2014) 2 SCC 165.
37. Depending on the nature and location of the acquired land, extent of land required to be set apart and expenses involved for development, 30% to 50% deduction towards development was allowed in Haryana State Agricultural Market Board v. Krishan Kumar (2011) 15 SCC 297, Director, Land Acquisition v. Malla Atchinaid (2006) 12 SCC 87, Mummidi Apparao v. Nagarjuna Fertilizers & Chemicals Ltd. (2009) 4 SCC 402 and Lal Chand v. Union of India (2009) 15 SCC 769.”
16. Rule of one-third deduction towards development is the
general rule. But depending upon the purpose of acquisition and
taking note of well planned layouts, if any, the deduction for
development cost may vary from 20% to 75%. Observing that
deduction towards development can range from 20% to 75% of the
price of the plot, in Lal Chand vs. Union of India and Another (2009)
15 SCC 769, the Supreme Court held as under:-
“19. If the acquired land is in a semi-developed urban area, and not an undeveloped rural area, then the deduction for development may be as much less, that is, as little as 25% to 40%, as some basic infrastructure will already be available. (Note: The
11
percentages mentioned above are tentative standards and subject to proof to the contrary.)
…….
22. Some of the layouts formed by the statutory development authorities may have large areas earmarked for water/sewage treatment plants, water tanks, electrical substations, etc. in addition to the usual areas earmarked for roads, drains, parks, playgrounds and community/civic amenities. The purpose of the aforesaid examples is only to show that the “deduction for development” factor is a variable percentage and the range of percentage itself being very wide from 20% to 75%.”
17. In the present case, since the land was acquired for the
construction of Hiwra Dam project, much of the development like in
the case of a layout for housing colony is not required. In our view,
40% deduction made by the High Court appears to be on the higher
side. Considering the purpose of the acquisition and the facts and
circumstances of the case, 20% deduction for development cost
would be reasonable. Taking the entire land 2,61,300 sq.ft. as
non-agricultural and making 20% deduction for the development
cost, the value of the land is calculated at Rs.12,54,530/- as under:-
Value of the land 2,61,360 x 6.90 …. Rs.18,03,384.00 20% deduction …. Rs.3,60,67.68 Rounded to …. Rs.3,60,677/- Total …. Rs.14,42,707/-
Valuation of the construction/civil works
18. PW-2-Mukund Dharashivkar in his valuation report Exh.21 has
considered the valuation of the civil work and foundation under four
12
heads:- (i) reproduction costs; (ii) market value as on today;
(iii) dismantling costs and damages; and (iv) transportation costs of
good materials. The reproduction costs has been shown as
Rs.9,55,020/- whereas, the market value as on the date of report
has been shown at Rs.5,26,575/- and Rs.4,09,565/- has been
shown under the head of dismantling costs and damages and
further Rs.17,325/- has been shown as transportation costs of good
materials. PW-2-Mukund Dharashivkar has deposed that the
valuation of the civil work is Rs.5,26,575/- and that it includes the
valuation of foundation embedded in the earth. As referred to by the
High Court in its judgment in Para (28), PW-2-Mukund Dharashivkar
has considered the civil work and foundation with regard to power
house, office and workshop, staff quarter, water storage tank and
other infrastructure/constructions with size, specifications and the
number of items. Per contra, witness No.3 for the State,
Sub-Divisional Engineer, Mr. Dilip Gudwe has assessed the
valuation of civil work amounting to Rs.3,67,100/-. After extracting
the relevant portion of the judgment of the Reference Court as to
the valuation of the civil work, the evidence of PW-2 and witness
No.3 for the State- Sub-Divisional Engineer, the High Court
has assessed the valuation of the dismantling costs and damages
of civil work and foundation to the tune of Rs.4,09,565/- and
13
Rs.17,325/- for transportation costs of good materials and arrived at
the total amounting to Rs.4,26,890/-. We do not find any reason to
take a different view and we affirm the amount of Rs.4,26,890/-
towards damages of civil work and foundation and transportation of
good materials.
Electrical installation and re-installation
19. As against the amount of Rs.3,86,867/- awarded by the
Reference Court, the High Court has awarded Rs.2,39,000/-
towards depreciated market value of the electrical installation. As
per the project report that was initially prepared for the year 1976,
cost of factory installation was given at Rs.6,93,677/- and as per
award, it has been given Rs.5,78,100/-. Referring to Exh.21 report
and evidence of PW-2-Mukund Dharashivkar, the Reference Court
has awarded Rs.3,86,867/- towards dismantling charges in respect
of electrical, mechanical and re-installation. During the course of
dismantling and re-installation, there is every possibility of the
electrical installation being damaged. Considering the findings of the
Reference Court, in our view, the High Court was not justified in
reducing the amount of Rs.3,86,867/- to Rs.2,39,000/- on the
ground of depreciated market value of electrical installation.
Therefore, the amount of Rs.3,86,867/- awarded by the Reference
14
Court is affirmed. For the dismantling of the electrical installation
and re-installation of the same, the amount of Rs.2,39,000/-
awarded by the High Court is enhanced to Rs.3,86,867/- as
awarded by the Reference Court.
Replacement cost of machinery and mechanical installation
20. Based on the report Exh.21 and the evidence of PW-2, the
High Court has awarded depreciated market value of the machinery
and mechanical installation to the tune of Rs.6,62,000/- and the
same is affirmed.
Loss of business
21. A perusal of the evidence of PW-2-Mukund Dharashivkar
examined on behalf of the appellants shows that in the year 1978-
79, when the witness has visited the factory of the appellants, he
noticed that the production of the sugar was stopped. As pointed out
by the Reference Court as well as by the High Court, as regards
income, no statement of income had been produced. During the
period 1981 till 1986, the sugar mill was idle. The balance sheet for
the years 1975-76 as per Exh.33 shows that the factory was
running in loss initially during the year 1975-76. Though the
appellants have claimed that they were making profit of
Rs.2,00,000/- per year, as pointed out by the courts below, no
15
statement had been filed to show that the sugar factory was making
profit of Rs.2,00,000/-. The courts below have recorded the
concurrent findings for awarding the compensation of Rs.5,00,000/-
for loss of business from the year 1981, the time of taking
possession of the property and compensation paid in the year 1986.
The compensation amount of Rs.5,00,000/- paid towards the loss of
business is also affirmed.
22. The compensation awarded to the appellants under various
heads is modified as under:-
Sr. No.
Description of Items
By the High Court
By the Supreme Court
i. Land value Rs.9,40,896/- Rs.14,42,707/- ii. Civil work Rs.4,26,890/- Amount confirmed iii Replacement of
electrical installation Rs.2,39,000/- Rs.3,86,867/- as
awarded by the Reference Court
iv Depreciated value of the machinery and mechanical installation
Rs.6,62,000/- Amount confirmed
V Loss of business from the year 1981 to 1986
Rs.5,00,000/- Amount confirmed
In the counter affidavit filed by the respondent-State, it is stated that
the office of the Executive Engineer, Jalgaon Medium Project
Division-1 has deposited the decreetal amount of Rs.72,02,224/- by
way of a cheque deposited in the Civil court. Further the amount of
Rs.10,00,000/- has been paid to the appellant on 21.09.2018 by
way of cheque bearing No.000081 vide receipt No.0114362 and the
16
amount of Rs.5,00,000/- has been paid to the appellants on
02.11.2018 by way of the cheque bearing No.000094
(receipt No.0114663). It is stated that the appellant has also
executed the receipt of the above said amount and has also
executed an acknowledgement to the effect that, his entire claim
has been settled. As per the modified amount of compensation, the
appellants are entitled to the balance amount.
23. In the result, the impugned judgment and final order dated
21.08.2017 passed by the High Court of Judicature at Bombay
Bench at Aurangabad in First Appeal No.601 of 1997 along with
Cross Objection St. No.22145 of 1997 in the First Appeal, is
modified as stated above in Para (22) and these appeals are partly
allowed. The balance amount as per the modified amount of
compensation be paid to the appellants/claimants with all statutory
benefits as awarded by the Reference Court.
..…………………….J. [R. BANUMATHI]
..…………………….J. [A.S. BOPANNA]
New Delhi; March 17, 2020.
17