PRIYANKA ESTATES I'NATIONAL P.LTD. Vs STATE OF ASSAM .
Case number: C.A. No.-008026-008026 / 2009
Diary number: 21558 / 2006
Advocates: P. I. JOSE Vs
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.8026 OF 2009 [Arising out of SLP(C) No.14480 of 2006]
Priyanka Estates International Pvt. Ltd. & Ors. ....Appellants
Versus
State of Assam & Ors. ....Respondents
WITH
C.A.NO.8025 OF 2009 [Arising out of SLP(C) No.15546 of 2006]
C.A.NO.8027 OF 2009 [Arising out of SLP(C) No.15547 of 2006]
C.A.NO.8028 OF 2009 [Arising out of SLP(C) No.16898 of 2006]
AND C.A.NOS.8029-8032 OF 2009
[Arising out of SLP(C) Nos.28291-28294 of 2009]
J U D G M E N T
Deepak Verma, J.
1. Leave granted.
2. The principal question that emerges for consideration
in these appeals is whether to sustain the order of
demolition as passed by the Gauhati High Court vide
impugned judgment and order or to put an imprimatur
of this Court to the unauthorised constructions
raised by M/s. Priyanka Estates International (P)
Ltd. (Appellant No.1 herein) beyond 5½ floors. Facts
material for deciding the said appeals are mentioned
hereinbelow.
3. For the sake of convenience, the facts appearing in SLP (C)
No. 14480 of 2006 titled as M/s Priyanka Estates International
(P) Ltd. & Others Vs. State of Assam & Others are taken into
consideration. Appellant No.1 is a company of which Appellant
Nos.2 & 3 are Directors.
4. Appellant No.1 herein purchased an open piece of land
approximately admeasuring 4.62 Kathas from one Smt. Nandita
Banerjee on 9.8.1999 by registered deed of sale. Prior to
execution of sale, the vendor of Appellant No.1 applied to
Guwahati Metropolitan Development Authority (hereinafter
referred to as 'GMDA') for grant of ‘No Objection Certificate’
for sale of land. The said permission was accorded on
17.7.1999 mentioning therein that permission is granted for
“residential-cum-commercial use” of the said plot and that
proposed width of the road abutted by plot is approximately 50
feet.
5. Pursuant to the said permission, Sale Deed was executed in
favour of Appellant No.1, whereafter it applied to Guwahati
Municipal Corporation (hereinafter referred to as 'GMC') on
16.11.1999 for according permission for construction of
basement, ground, mezzanine, first, second, third, fourth
and half of 5th floors. The permission was accorded to M/s.
Priyanka Estates International (P) Ltd. on 03.02.2000 by the
GMC for construction of basement, ground floor, mezzanine upto
fourth floor and half on the 5th floor. For 1st floor to
fourth, the floor area permissible was 7283 sq. ft. but on 5th
floor, the permissible floor area was fixed at half of it,
i.e., 3817 sq. ft only. It was granted on certain conditions
as mentioned in the sanction dated 3.2.2000.
6. Thereafter, on 08.02.2000, Appellant No.1 applied for
grant of permission for construction of remaining part of 5th ,
6th, 7th and 8th floors. This permission was refused by GMC on
27.3.2000 on the following grounds.
“i) Maximum allowable height of building can be 76' and proposed height would be 93'.
ii) The margin on both sides and rear is less than required norms.
iii) FAR is exceeded than allowable 300.
iv) The structural certificate is not submitted.”
So, proposal for 5th (part) 6th, 7th and 8th floor building,
permission was rejected.
7. Feeling aggrieved by the said rejection by GMC,
appellants preferred an appeal under Section 438 of the
Guwahati Municipal Corporation Act, 1971 (hereinafter referred
to as 'the Act') before the Standing Appellate Committee (in
short 'SAC').
8. This came to be disposed of on 5.5.2000 with the
following directions:
“In view of the above discussion as well as observation, in our considered opinion, the appellant’s case deserve consideration. Accordingly, we hold that the appellant be accorded permission as sought for. We hereby set aside the impugned order, as aforesaid, passed by the Commissioner, GMC, the Respondent.
In the result, the appeal is allowed.”
9. Since, despite the fact that SAC had allowed the appeal of
Appellants with regard to construction of 5th (part), 6th, 7th
and 8th floors, no formal permission was still accorded by
Commissioner GMC to it, they moved further application on
28.8.2001 before Administrator-cum- Minister, Guwahati
Development Department, as it appears by that time, GMC had
been dissolved.
10. The said appeal was considered by Administrator-cum-
Minister and the appeal verdict was reviewed on 29.5.2002 with
certain conditions as mentioned hereinbelow :
“i) To obtain NOC from State Fire Department;
ii) Submit affidavit regarding the Structural Certificate;
iii) Compulsory covered parking and private service system like drainage, sewage, storm drain, water supply etc.;
iv) No further FAR beyond 487.00;
v) To submit completion certificate and obtain Occupancy Certificate from GMC;
vi) To pay a penal charge to the Corporation amounting to Rs.10,00,000.00 (ten lacs);
vii) Your building is liable for instant demolition at your own risk and cost in case of non-compliance of the above.”
11. However, it appears that without compliance of the
aforesaid conditions fully and without getting actual sanction
for construction of building beyond 5½ floors from the
Commissioner of G.M.C. Appellants continued with the
construction activities and tried to complete the same.
12. Guwahati Metropolitan Development Authority (As already
referred to as 'GMDA') now came into picture and issued notice
to Appellant No.2 on 02.02.2001 to show cause and to give
explanation as to without grant of proper sanction under GMDA
Act, how the construction work is progressing.
13. Another notice by GMDA was issued to the Appellant No.2
on 5.9.2001 asking to remove/demolish the
building/construction/ development or the portion erected by
them which is in violation of the provisions of Guwahati
Metropolitan Development Authority Act (for short 'the
Development Act'). No replies to the aforesaid two notices
were sent by the Appellants herein on the ground that the same
were not received.
14. Last and final notice in this regard was issued by GMDA
on 18.2.2002 mentioning therein with regard to earlier two
notices sent on 2.2.2001 and 5.9.2001 and finally asking the
Appellants to remove the construction within three days from
the receipt of this last notice failing which, necessary action
as per provision of the Development Act will be initiated
without giving further intimation.
15. Appellants replied to the said last notice on 18.2.2002
mentioning therein that they had not received the earlier two
letters but mentioned that permission has been granted by GMC
on 3.2.2000, and is still operative, which clarified the
position of construction of the building beyond 5½ floors also
but did not actually present any sanctioned or approved
plans/maps beyond 5½ floor.
16. Not being satisfied with the reply to the show cause
notice, submitted by the Appellants, the Respondents proceeded
to issue another notice to the Appellant No.2 on 3.5.2002, with
a categorical statement that construction over and above 6th
and 7th floor was wholly illegal, without due sanction and
therefore, the same be removed/demolished.
17. It appears that, thereafter, some correspondence
between the parties continued. Finally on 31.7.2002 by two
orders, the Commissioner, GMC informed the Appellant No.1 that
plans submitted by them are insufficient for the following
reasons and requested it to furnish the required materials as
under and to forthwith stop the construction :
“1. Affidavit for structural design as per format at the building bye laws.
2. NOC from State Fire Department.
3. Declaration in affidavit to maintain the FAR within 487.”
18. The Appellants, therefore, were constrained to move the
High Court challenging the said order dated 31.7.2002 by filing
W.P.(C) No.5018 of 2002 purportedly under Articles 226 and 227
of Constitution of India.
19. Further order of demolition came to be issued to the
Appellant No.2 by GMDA on 30.5.2006, clearly mentioning
therein that no sanction was obtained by the Appellants under
Section 24 & 25 of the Development Act and had actually
violated the provisions of Building Bye-laws of Guwahati
Municipal Corporation (for short, 'building bye-laws'), in the
following manner :
“1. FAR of the building is 490 which exceeds allowable FAR 300.
2. Maximum floor height 93’ exceeds allowable height 76’ in this road.
3. Since the building is mixed used with residential at top floors, setback required is 15’
side to 20’ rear, which is not maintained.
4. Balcony projection is allowed, maximum ¼ of the building length in any side, which is not maintained.
5. Two staircases and lift on opposite direction is required which is not available in the building as per building plan.
6. Construction of building is going on despite our order to stop construction.”
20. The said order further directed demolition of the
building beyond the sanctioned plan dated 3.2.2000. The
Appellants, therefore, challenged the said order dated
30.5.2006 issued by Chief Executive Officer GMDA by filing
another W.P.(C)No.2747 of 2006. In W.P.(C) No.5018 of 2002,
(earlier W.P. filed in the Gauhati High Court) an order of
status quo came to be passed on 12.8.2002 and it further
directed that Municipal Authority shall take no steps to pull
down the building and the operation of the letter dated
31.7.2002 was stayed.
21. It appears that pursuant to the said order, Appellants
continued with the construction activities presumably on the
ground that order of status quo is against the Respondents of
the Writ Petition and not against the Appellants. Thus,
Sanatan Dharam Sabha, Guwahati filed an application seeking
permission to be impleaded in the said petition and also
bringing to its notice that despite the order of maintenance of
status quo, Appellants are continuing with the construction.
Thus, another order clarifying the earlier order came to be
passed by the High Court on 20.9.2002 whereby a categorical
direction was issued that no further construction over the said
land shall be made and all construction activities should come
to a standstill immediately. It appears that only after
passing the said order, Appellants stopped the construction
work.
22. Sanatan Dharam Sabha alongwith three residents of
Panbazar locality of Guwahati city filed W.P.(C) No.5146 of
2002 in the Gauhati High Court against the action of GMC and
GMDA granting permission to the appellant, M/s. Priyanka
Estates for multi-storeyed building in question and prayed for
its demolition.
23. Thus, all the three petitions, i.e. W.P.(C)
No.5018/2002, W.P.(C) No.2747/2006 and W.P.(C) No.5146/2002
were consolidated for the purpose of analogous hearing and have
been disposed of by Division Bench of Gauhati High Court vide
impugned judgment and order dated 28.7.2006. Vide impugned
judgment, the Writ Petitions preferred by Appellants herein
numbered as 5018/02 and 2747/06 having been found devoid of
merit and substance were dismissed but W.P.(C) No. 5146/2002
filed by Sanatan Dharam Sabha has been allowed to the extent
indicated in the impugned order.
24. Feeling aggrieved and dissatisfied with the aforesaid
judgment and order, civil appeal arising out of
S.L.P.(C)No.14480/06 titled, 'M/s. Priyanka Estates
International (P) Ltd. & Ors. vs. State of Assam & Ors.' has
been filed by Builder and its Directors; civil appeals arising
out of S.L.P.(C) No.15546/06 titled, 'Vishal Saraf v. State of
Assam & Ors.' and civil appeal arising out of
S.L.P.(C)No.15547/06 titled, 'Suresh Kumar Harlalka v. State of
Assam & Ors.' have been filed by owners of flats on 7th floor
and civil appeal arising out of S.L.P.(C) No. 16898/06 titled,
'Sarla Devi Lahoty vs. State of Assam & Ors.' has been filed by
owner of one flat on 6th floor. Insofar as civil appeals
arising out of S.L.P.(C) Nos.28291-28294/2009 titled, 'Shyam
Sunder Agarwala vs. State of Assam & Ors.' are concerned, the
same have been filed by owner of one flat on 5th floor only.
Since the matters were common and identical challenging
primarily the order passed by Division Bench of the High Court
and pertained to the same building claiming identical reliefs,
these Appeals have been heard together. Perused the records.
25. Mr. Shekhar Naphade, leaned Senior Counsel, Mr. Mukul
Rohtagi, learned Senior Counsel with Mr. Shankar Divate, Mr.
Dhruv Mehta, Mr. Yashraj Singh Deora, Advocates, Mr. Vijay
Hansaria, learned Senior Counsel with Mr. P.I. Jose and Mr.
Kamal Mohan Gupta, Advocates appeared for the Appellants in the
aforesaid appeals. Mr. L. Nageshwar Rao, learned Senior Counsel
with Ms. Millie Hazarika and Mr. Manish Goswami appeared for
the Respondents.
26. Respondents have contended that for construction of any
building, permission from GMC is a condition precedent and
unless such permission is granted no construction can be
raised.
27. It has further been submitted that such construction
has to be as per the sanctioned plan approved by GMC and no
deviation from such approved plan can be made.
28. According to them, Appellant No.1 was admittedly
granted permission for construction of 5½ storeyed building,
apart from basement, ground and mezzanine floor vide order
dated 03.02.2000, thereafter, no further permission has been
granted for raising any construction on remaining part of 5th
floor and upwards. The order of the SAC dated 05.05.2000
setting aside the order of Commissioner, GMC dated 27.3.2000
rejecting the permission to raise construction on part of the
5th floor up to 8th floor was itself illegal, beyond the
jurisdiction and competence of SAC as it violated the building
bye-laws.
29. In view of the admitted position that the width of the
road is only 38 feet and under the building bye-laws, maximum
allowable height can be double the width of the road, i.e., 76
feet but in the instant case the SAC has allowed construction
upto 93 feet, which contravenes the building bye-laws,
therefore, such an order of SAC has no legal force and cannot
be basis for construction beyond 76 feet, allowable under
building bye-laws.
30. It has been submitted by them that the order of the SAC
dated 05.05.2000 lost its force and sanctity after the
communication dated 29.05.2002 was issued by GMC by which the
Appellants were asked to comply with certain conditions before
granting any permission for construction of a building for
remaining part of 5th floor and above.
31. It has also been contended that even though the order
passed in Appellants’ Writ Petition was to maintain status quo
but taking advantage thereof, they continued with the
construction and only on subsequent order being passed on
20.09.2002, the construction activities were stopped but by
that time Appellants had already raised construction upto 8th
floor, in flagrant violation of building bye-laws.
32. They have also contended that GMDA passed an order
under Section 88 of the Development Act for demolition of
construction for remaining part of the 5th floor and above and
that too after issuance of notices to Appellants and giving
reasonable opportunity to them to show cause. Appellants were
aware that construction beyond 5½ floor was without due
sanction and approval, thus, obviously illegal, yet they
continued with the same.
33. They further submitted that there was no violation of
principles of natural justice. It was contended that Appendix
III of the building bye-laws provides for compoundable and non-
compoundable items. It is evident therefrom that construction
of extra floor falls in the category of non-compoundable items
meaning thereby if extra floor is constructed without due
sanction/approval, then, it would be beyond the purview of
compoundable items. As regards violation of principles of
natural justice, they have contended that before passing the
order of demolition, notices were issued to the Appellants to
show cause, as required under Section 88 of Development Act but
they did not take any action thereon.
34. Whenever Respondents asked for sanctioned/approved
plans for construction beyond 5½ floors, Appellants only showed
them the plans which were sanctioned and/or approved for
construction of, only upto 5½ floors. It was also contended by
them that even upto that stage Appellants had failed to show
any approved sanctioned plans and maps allowing them to
construct beyond the permissible limit of 5½ floors. Thus, they
have contended that the building constructed beyond 5½ floors
is absolutely illegal, unauthorized and without any sanction
plans, thus liable to be demolished.
35. In order to understand the various provisions of the
Act, it is necessary to know the import of the relevant
sections of the Act material for deciding the appeals.
36. Section 327 of the Act prohibits any person from
erecting or re-erecting any building without written permission
from the Corporation. Section 328 provides for submission of an
application by a person interested to erect or re-erect a
building to the Corporation for approval of the site together
with site plan with land title document, elevation and sections
of the building, specification of the work and also containing
such particulars as may be required by bye-laws in that behalf.
Section 329 empowers the Commissioner of the GMC to refuse such
permission and to disapprove the site on the grounds formulated
in Section 330. Section 331 provides for the grounds on which
permission to erect or re-erect the building can be refused by
GMC. Section 332 empowers the Commissioner to direct
modification of the sanctioned plan. Section 333 stipulates the
period within which erection or re-erection is to be completed.
Section 337 empowers the Commissioner to require the removal or
alteration of the work which may not be in conformity with bye-
laws etc. Section 416 of the Act empowers the GMC to formulate
different bye-laws including the bye-laws relating to the
building. Section 438 of the Act provides for appeal from the
order passed by the Commissioner including the order refusing
to grant permission to construct or re-construct a building to
the SAC. Sub-section (3) of Section 438 of the Act empowers the
State Govt. to call for the records of any matter from the
Corporation and to pass such orders as may be deemed necessary
after examination of such records.
37. It is necessary to refer to Section 88 of the
Development Act which reads as under :
“88. Power of demolition of building.-(1) Where any development has been commenced or is being carried on or has been completed in contravention of the Master Plan or development scheme or without the permission, approval or sanction referred to in Section 25 and Section 30 of the Act or in contravention of any conditions subject to which such permission, approval or sanction has been granted, the authority may in addition to any prosecution that may be instituted under the Act, make an order directing that such development shall be removed by demolition, filling or otherwise by the owner, occupier, manager or by any person at whose instance the development has been commenced or is being carried out or has been completed within such period not being less than five days and more than thirty days from the date on which a copy of the order of removal with brief statement of the reasons thereof has been delivered to the owner, occupier and manager or the person at whose instance the development has been commenced or is being carried out or has been completed as may be specified in the order and on his failure to comply with the order, the authority may remove or cause to be removed the development and the expenses of such removal shall be recovered from the owner, occupier, manager or any person at whose instance the development was commenced or was being carried out or was completed as arrears of land revenue; provided
that no such order shall be made unless the owner, occupier, manager or the person concerned has been given a reasonable opportunity to show cause why the order shall not be made.
(2) The provisions of this section shall be in addition to and not in derogation of any other provision relating to demolition of buildings contained in any other law for the time being in force.
(3) No compensation shall be claimed by any person for any damage which he may sustain in consequence of the removal of any development under this section or the discontinuance of the development under Section 87 of this Act.”
38. Mr. Shekhar Naphade, learned Senior Counsel for
Appellants firstly strenuously contended before us that NOC
dated 17.7.1999 granted by GMDA clearly stipulated that the
plot purchased by Appellants would fall in the category of
“residential-cum-commercial use” and width of the road abutted
by the plot is proposed to be 50 feet. Thus, according to him,
the height of the building can be 100 feet, being the double of
the width of the road. Since the height of the building of the
Appellants even after construction upto 8th floors is only 93
feet, the part of the building beyond 5½ floors is not liable
to be demolished.
39. It was also contended by him that initial permission
was granted by GMC whereas notices of demolition have been
issued by GMDA which appears to be absolutely contrary and
against the provisions of law. It was also contended that
Respondents have failed to prove that any notices were sent to
them on 02.02.2001 or 05.09.2001 by GMDA as it has been
categorically mentioned by the Appellants pursuant to third
notice received by them and replied to.
40. It was also argued that in the light of specific order
passed by SAC, conscious decision has been taken by the
Government and denial of hearing itself would amount to
prejudice, consequently, violation of principles of natural
justice.
41. If Commissioner was dissatisfied with the modification
of his order by the SAC then as provided under sub-section (2)
of Section 438 of the Act, he was required to make a reference
to the Corporation within 60 days thereof which he failed to
do. He was, therefore, bound by the Appellate Order of SAC and
could not have super-imposed his own views or conditions.
42. Mr. Mukul Rohtagi, learned Senior Counsel appearing for
Shyam Sunder Agarwala submitted that he is owner of part of the
5th floor which has not been sanctioned.
43. According to Mr. Mukul Rohtagi half of the 5th floor has
already been sanctioned and even if the width of the road
abutted to the building is taken as 38 feet, the height allowed
would be 76 feet. Thus, it will have no height problem. At the
most, the only objection can be with regard to FAR which
objection can be waived as the same falls within compoundable
items.
44. Shri Shyam Sunder Agarwala had purchased the said flat
on 18.04.2005 for a total amount of Rs.9,43,850. It has also
been contended that after purchase of the said flat his name
has been mutated in the Corporation records. He is paying
property tax, water tax etc., which Corporation is accepting.
Thus, for this reason also it is not liable to be demolished.
45. He further contended that two parallel bodies, that is,
GMC and GMDA cannot take action for demolition of the building
as the permission was accorded by GMC whereas notices of
demolition have been issued by GMDA. Thus, according to him,
whole procedure is illegal and void, thus liable to be quashed.
46. In the light of this, it has been contended that
Section 88 of the Development Act could not be put into service
against the Appellants as the same amounts to violation of
principles of natural justice as no notice has been served on
the said Appellant.
47. Mr. Vijay Hansaria, learned Senior Counsel appearing
for other Appellants submitted that they are owners of flat
No.7A/7C and 7D having purchased on 14.06.2004 and 03.01.2005
for a sum of Rs.17,72,460 and 9,43,850 respectively. He has
reiterated that Section 88 of the Development Act has not been
complied with inasmuch as no opportunity to show cause has been
given to these Appellants, thus violation of principles of
natural justice is writ large from the record. Commissioner had
no other alternative but to abide by the Appellate Order of SAC
and in any case it should have been treated as deemed sanction.
48. Shri Kamal Mohan Gupta, learned counsel appearing for
Sarla Devi Lahoty, owner of a flat on 6th floor has also
reiterated the aforesaid arguments already advanced by M/s.
Shekhar Naphade, Vijay Hansaria and Mukul Rohtagi.
Additionally, he has submitted that Sarla Devi Lahoty purchased
a flat on 27.12.2004 for Rs. 8,63,010, after making due
inquiries with regard to sanction of building plans etc. Thus,
she would be a bonafide purchaser for value and for any acts of
omission or commission said to have been committed by builder
M/s. Priyanka Estates International Pvt. Ltd. this Appellant
cannot be put to any loss.
49. After having gone through the record carefully, the
crux of the matter is whether M/s. Priyanka Estates
International Pvt. Ltd. is in possession of any approved or
sanctioned plan beyond 5½ floors, i.e., for the remaining 3½
floors or not. If not, then what is the effect thereof?
50. It is clear from the record that the only plan approved
was on 03.02.2000 for 5½ floors by GMC. Order dated 05.05.2000
passed by SAC also does not give them blanket permission to
construct upto 8th floor.
51. It is also to be seen that respondents have come to the
conclusion and have fairly conceded before us that plan or
sanction approved by either of the two authorities, that is,
GMC or GMDA will hold good and permission from both the
authorities simultaneously would not be required for the same,
if it has already been accorded by any one of the authorities.
52. On the strength of this, we can safely proceed that if
no permission under Section 24 and 25 of the Development Act
was obtained by M/s. Priyanka Estates International Pvt. Ltd.
then it would not be detrimental to the interest of the
Appellants, provided there is sanction and approval of plans by
the Corporation for remaining 3½ floors i.e. beyond 5½ floors.
53. Here, it is pertinent to point out that Respondents had
also issued a public notice on 02.07.2002, published in local
newspaper in vernacular giving general warning and information
to all proposed purchasers of flats that unless builder is able
to show Completion Certificate and Occupancy Certificate duly
issued by authorities, no one should enter into agreement to
purchase flat/flats from the builder. It is, therefore, to be
construed that public notice will hold good even with regard to
adherence to the requirement of Section 88 of the Development
Act, if individual person had not been noticed by the
authorities.
54. Clause (a) of building bye-law 37 stipulates that for
the purpose of calculation of building height, existing width
of the road shall be taken into account and not the proposed
width. Even if the proposed width is 40 feet or 50 feet, it
will not make any difference because it clearly contemplates
that what is to be taken into consideration is the existing
width of the road. There is nothing on record to show that the
existing width of the road is more than 38 feet. Thus, at the
most, the construction could have been only upto the height of
76 feet, provided there was sanction granted by either of the
two Authorities.
55. Appendix III of building bye-laws deals with penalties
to be levied for violation of provisions of Master Plans,
Zoning Plans Regulations and Bye-laws. Certain items are
compoundable items but certain items fall in the category of
non-compoundable items. However, addition of extra floor falls
in the category of non-compoundable items. Thus, in any case
anything that has been constructed beyond 5th floor would be
non-compoundable and same cannot be compounded at all. In other
words, minor deviations from the sanctioned plan should be
confined only to the FAR permissible but should not extend to
the extra floor.
56. For better appreciation of the aforesaid provision the
same is reproduced hereinbelow :-
“Appendix III PENALTIES TO BE LEVIED FOR VIOLATIONS OF PROVISION OF MASTER PLAN/ZONING PLAN REGULATIONS AND BYE LAWS.
(i) All provisions of Bye-laws except items given below shall not be compounded/regularized and shall have to be rectified by alteration/demolition at the risk and cost of owner.
Compoundable items:
(1) Coverage - maximum of 15% (2) F.A.R. - maximum of 10% (3) Set Back - Upto 2’- 6” (4) Open Space - Maximum 10% reduction (5) Total Height of - 1.5% Building
Non Compoundable items:
(1)Use of building (2)Addition of extra floor (3)Parking Norms (4)Parking Norms (5)Projection/encroachment of public
land.”
Critical and analytical perusal of the same would show that
addition of extra floor falls within the ambit of non-
compoundable items.
57. The order of SAC cannot be construed as an order of
sanction as it is not a semblance of permission. It was not end
of the matter because necessary sanction or permission could
have been granted only by the Municipal Commissioner and not by
the Appellate Authority. Admittedly, even after passing of the
order by SAC in appeal, there was no further sanction by the
Municipal Commissioner or by Chief Executive Officer of the
Development Authority granting permission to raise the height
of the building upto 8th floor.
58. Thus, looking to the matter from all angles, we are of
the opinion that construction of the building beyond 5½ floors
was not only illegal, unauthorized and without any sanction or
approval of plans but was also against the spirit of Appellate
Order of SAC. Thus, except for directing the Respondent-
authorities to demolish 6th, 7th and 8th floor, we are left with
no alternative.
59. As regards construction of two flats on remaining half
of 5th floor, Mr. L. Nageshwar Rao, learned Senior Counsel for
Respondent-authorities fairly conceded that on suitable
representations being made by the occupants, their cases can be
considered afresh to find out if the same would fall within the
category of compoundable items or not. If the same are found
within the category of compoundable items then necessary order
by respondents in this regard would be passed otherwise order
of demolition would follow for them also. Thus, on the promise
of Sr. Advocate Mr. L. Nageshwar Rao, we hope and trust,
suitable orders would be passed by the Authorities as regards
two flats on 5th floor are concerned within two months from the
date of submission of the Representations.
60. Even though various authorities had been placed before
us by the learned counsel appearing for parties, it is not
required to deal with them in extenso. However, a cursory
reference to the same would meet the ends of justice.
61. Mr. Shekhar Naphade has placed reliance on Corporation
of Calcutta v. Mulchand Agarwala AIR 1956 SC 110 to contend
that it should be a last resort to direct demolition of a
building and if it falls within the compoundable limit then it
should not be directed to be demolished. To advance contentions
further in this regard, reliance has been placed on para 4 of
an order of this Court in the case of Syed Muzaffar Ali &
Others v. Municipal Corporation of Delhi 1995 Supp. (4) SCC 426
which is reproduced hereunder :
“4. However, it is to be pointed out that mere departure from the authorized plan or putting up a construction without sanction does not ipso facto and without more necessarily and inevitably justify demolition of the structure. There are cases and cases of such unauthorized constructions. Some are amenable to compounding and some may not be. There may be cases of grave and serious breaches of the licensing provisions or building regulations that may call for extreme stage of demolition.
62. Reliance has also been placed on yet another judgment
of this Court in the case of Muni Suvrat-Swamy Jain S.M.P.
Sangh v. Arun Nathuram Gaikwad & Others (2006) 8 SCC 590, which
dealt with Section 351 of the Bombay Municipal Corporation Act
to hold that if execution of work has commenced contrary to
provisions of the Act, then to give notice to the person
carrying on the construction work to show cause why it should
not be pulled down, is a must. The use of the word “shall”
would signify that it is mandatory to issue notice and then to
pass any order. Lastly, a recent judgment of this Court in the
case of Municipal Corporation, Ludhiana v. Inderjit Singh &
Anr. (2008) 13 SCC 506 has been pressed into service. This
also deals primarily with the requirement of issuance of show
cause notice to the person who had raised construction, so as
to enable the said party to show cause, if the construction has
been made in total violation of the sanctioned map or it falls
within the category of compoundable items.
63. Mr. Vijay Hansaria has placed reliance on the famous
off-quoted judgment of this Court in the case of Olga Tellis
and Others etc. v. Bombay Municipal Corporation & Others etc.
(1985) 3 SCC 545 which dealt with plight of the pavement
dwellers, who were in unauthorised possession and were sought
to be evicted. He sought to contend that the fundamental rule
of principles of natural justice should have been followed
before passing the order of demolition.
64. Further with regard to opportunity of hearing he has
placed reliance on a judgment of this Court in the case of S.L.
Kapoor v. Jagmohan and Others (1980) 4 SCC 379.
65. On the other hand, Mr. L. Nageshwar Rao has placed
reliance on various judgments of this Court, viz., M.I.
Builders Pvt. Ltd. v. Radhey Shyam Sahu and Others (1999) 6 SCC
464; Friends Colony Development Committee v. State of Orissa
and Others (2004) 8 SCC 733; Royal Paradise Hotel (P) Ltd. Vs.
State of Haryana and Others (2006) 7 SCC 597; and Mahendra
Buburao Mahadik and Others v. Subhash Krishna Kanitkar and
Others (2005) 4 SCC 99 to contend that where constructions have
been made in absolute and flagrant violation of the sanctioned
plan then the only alternative is to direct demolition of the
same.
66. It is not necessary to deal with the aforesaid
judgments of this Court in greater detail as the consistent
ratio decidendi of this Court is that if the constructions are
in absolute violation of sanctioned or approved plans and are
not likely to fall in the category of compoundable items, then
the necessary consequence is to order its demolition and seal
of approval for such illegal activities is not required to be
given by this Court.
67. It is pertinent to mention here that hearing of the
appeals had commenced on 22.10.2009 and had almost concluded on
28.10.2009. But on the said date, Mr. Anoop George Chaudhary
and Ms. June Chaudhary, learned Senior Counsel, appeared with
Mr. Kamal Mohan Gupta for Sarla Devi Lahoty and submitted that
they would be replying to the arguments advanced by learned
counsel for Respondents. Though not approved as a healthy
practice, yet we granted them permission.
68. It was submitted by them that if cases of two flat
owners on the 5th floor are to be considered so as to find out
whether the constructions raised by the builder in their cases
would fall within the compoundable items or not, then the case
of Sarla Devi Lahoty should also be directed to be considered
on a suitable representation being made by her, as her flat is
situated on the 6th floor. It was contended that even after
taking the height of 6th floor, it would not cross the maximum
height of 76 feet looking to the width of the existing road.
69. However, the said contention cannot be accepted as
construction of an extra floor does not fall within the
category of compoundable items which is manifest from Appendix
III of the building bye-laws of the Corporation reproduced
hereinabove.
70. However, with regard to two flats on 5th floor, a
direction can be given to the Respondents to consider their
cases if they submit their representations within a period of
30 days hereof. Respondents would examine whether their cases
fall within the compoundable items/limit or not. In case,
Respondents come to the conclusion that these two flats
constructed on 5th floor fall within the compoundable limit,
then necessary orders be passed in this regard, after charging
compounding fees as may be applicable to the facts of the case,
in accordance with law, otherwise, they would also face the
wrath of demolition.
71. Even a conjoint reading of the order dated
05.05.2000 passed by SAC and the order dated 29.05.2002 of the
Administrator-cum-Minister makes it clear as noon day that it
does not clothe the Appellants to continue with the
construction work beyond 5½ floors as these orders were passed
subject to fulfilling certain conditions contained therein.
72. It is obvious that what would ultimately constitute a
sanctioned and duly approved map would be the one approved by
the Commissioner as he alone has authority to do so. The
Appellants have failed to produce any such duly approved map.
73. It is a matter of common knowledge that illegal and
unauthorised constructions beyond the sanctioned plans are on
rise, may be due to paucity of land in big cities. Such
activities are required to be dealt with by firm hands
otherwise builders/colonisers would continue to build or
construct beyond the sanctioned and approved plans and would
still go scot-free. Ultimately, it is the flat owners who fall
prey to such activities as the ultimate desire of a common man
is to have a shelter of his own. Such unlawful constructions
are definitely against the public interest and hazardous to the
safety of occupiers and residents of multi-storeyed buildings.
To some extent both parties can be said to be equally
responsible for this. Still the greater loss would be of those
flat owners whose flats are to be demolished as compared to the
Builder.
74. Even though on earlier occasions also, under similar
circumstances, there have been judgments of this Court which
should have been a pointer to all the builders that raising
unauthorised construction never pays and is against the
interest of society at large, but, no heed to it has been given
by the builders. Rules, regulations and bye-laws are made by
Corporation or by Development Authorities, taking in view the
larger public interest of the society and it is a bounden duty
of the citizens to obey and follow such rules which are made
for their benefit. If unauthorised constructions are allowed
to stand or given a seal of approval by court then it is bound
to affect the public at large. An individual has a right,
including a fundamental right, within a reasonable limit, it
inroads the public rights leading to public inconvenience,
therefore, it is to be curtailed to that extent.
75. The jurisdiction and power of courts to indemnify a
citizen for injuries suffered due to such unauthorised or
illegal construction having been erected by builder/coloniser
is required to be compensated by them. An ordinary citizen or a
common man is hardly equipped to match the might and power of
the builders.
76. In the case in hand, it is noted that number of
occupiers were put in possession of the respective flats by the
builder/developer constructed unauthorisedly in violation of
the laws. Thus, looking to the matter from all angles it
cannot be disputed that ultimately the flat owners are going to
be the greater sufferers rather than builder who has already
pocketed the price of the flat.
77. It is a sound policy to punish the wrong-doer and it is
in that spirit that the courts have moulded the reliefs of
granting compensation to the victims in exercise of the powers
conferred on it. In doing so, the courts are required to take
into account not only the interest of the petitioners and the
respondents but also the interest of public as a whole with a
view that public bodies or officials or builders do not act
unlawfully and do perform their duties properly.
78. In the case in hand, admittedly, at no point of time
Appellant No.1- M/s. Priyanka Estates International Pvt. Ltd.
was able to show to its prospective purchasers the Occupancy
Certificate or Completion Certificate issued by the authorities
concerned. The same could not even be shown to us and without
it, Appellant No.1 could not have embarked into sale of flats
as it was mandatorily required.
79. The instant case is not a case of breach of contract.
It is a clear case of breach of the obligation undertaken to
erect the building in accordance with building regulations and
failure to truthfully inform the warranty of title and other
allied circumstances.
80. Even though at the first instance, we thought of
invoking this Court's jurisdiction conferred under Article 142
of the Constitution of India so as to do complete justice
between the parties and to direct awarding of
reasonable/suitable compensation/interest to the flat owners,
whose flats are ultimately going to be demolished, but, with a
very heart, we have restrained ourselves from doing so, for
variety of reasons and on account of various disputed questions
that may be posed in the matter. However, we grant liberty to
those, whose flats are ultimately going to be demolished, to
exhaust the remedy that may be available to them in accordance
with law.
81. We also feel it necessary and expedient to direct the
Respondent-authorities that if ultimately flat owners, whose
flats are going to be demolished shall be given at least three
months' time to vacate the same. This would enable them to
mitigate the losses that may be incurred by them. We
accordingly direct so.
82. In the light of the foregoing discussions, these
appeals are dismissed with the directions contained
hereinabove. Respondent-authorities shall be at liberty to
proceed with demolition of half of the 5th floor, if not
ultimately compounded; 6th, 7th and 8th floors as mentioned
hereinabove.
83. Counsel's fee Rs. 10,000/- each.
......................J. [V.S. SIRPURKAR]
......................J. [DEEPAK VERMA]
New Delhi. December 03, 2009.