07 March 2013
Supreme Court
Download

NTPC LTD. Vs BHASIN CONSTRUCTION P.LTD.

Bench: H.L. DATTU,DIPAK MISRA
Case number: C.A. No.-002675-002676 / 2013
Diary number: 4607 / 2009
Advocates: RACHANA JOSHI ISSAR Vs BINU TAMTA


1

Page 1

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS. 2675-2676  OF 2013 (@ SPECIAL LEAVE PETITION (CIVIL) NOS.4241-4242 OF 2009)

NTPC LTD.                                  APPELLANT VERSUS

BHASIN CONSTRUCTION P. LTD.               RESPONDENT

O R D E R

1. Leave granted.

2. These  appeals  are  directed  against  the  judgment and order passed by the High Court of Delhi in  FAO (OS) Nos. 116 and 118 of 1995, dated 04.12.2008,  whereby and whereunder, the learned Division Bench has  allowed FAO (OS) Nos. 116 of 1995 and has set aside the  judgment and order passed by the learned Single Judge  in Suit No. 1510-A of 1986, dated 02.12.1994 and while  disposing FAO (OS) No.118 of 1995, has directed the  appellant-corporation to pay to the respondent–company  a sum of Rs.95,394.10/- along with interest at the rate  of 9% per annum on the said amount from the date of the  

1

2

Page 2

award  i.e. 07.05.1986 till the date of payment. The  awards dated 15.05.1986 and 07.05.1986 passed by the  learned Arbitrator are modified to the above extent and  accordingly, are made rule of court by the Division  Bench.   

3. The brief facts of the case are:  The  appellant,  National  Thermal  Power  

Corporation Limited (for short ‘NTPC’) is a Government  Company  registered  under  the  provisions  of  the  Companies  Act,  1956.  It  is  engaged  in  construction/project  for  generation,  operation,  transmission  and  maintenance  of  super  thermal  power  projects in India.  

4. Some  time  in  the  year  1978,  the  NTPC  had  invited tenders for the work of construction of bridges  and  fly-overs  for  merry-go-round  (M.G.M.)  railway  system  and  sidings  for  the  Singrauli  Super  Thermal  Power Project. The said construction work was to be  carried  out  both  in  the  Mirzapur  District  of  Uttar  Pradesh  (approximately  80%  of  the  total  construction  

2

3

Page 3

work)  and  the  Sidhi  District  of  Madhya  Pradesh  (approximately 20% of the total construction work in  areas  adjoining  the  construction  sites  in  Uttar  Pradesh).  

5. The  respondent-Bhasin  Construction  Private  Ltd.  (for  brevity,  ‘the  Construction  Company')  had  participated in the said tender process.  In the bid  offered by the Construction Company, it had quoted the  'fair wages' payable to the skilled, unskilled or semi- skilled labourers on the date of the settlement of the  contract  at  Rs.2.70/-.  The  then  existing  rates  of  ‘minimum wages’ payable to the labourers as per the  governing  laws  in  the  States  of  Uttar  Pradesh  and  Madhya Pradesh were Rs.6/- and  Rs.2/- respectively.  

6. Since  the  bid  amount  quoted  by  the  Construction  Company  was  the  lowest  among  all  the  tenders received by the NTPC, the bid so offered by the  Construction  Company  was  accepted  by  the  NTPC.  Accordingly, the NTPC had issued a Letter of Intent  dated 13.10.1978 to the Construction Company awarding  

3

4

Page 4

the  work  of  aforesaid  construction.  The  Construction  Company had accepted the said Letter of Intent issued  by the NTPC, by their letter dated 18.11.1978. After a  series of communications, the parties had entered into  an  agreement  dated  20.02.1979.  The  tender  documents  comprising of Special Conditions of the Contract and  General Conditions of the Contract were annexed to the  said agreement. In toto, the construction contract was  valued at Rs.1,17,61,372/-.    

7. During the subsistence of the contract between  the parties, the rate of 'minimum wages' in respect of  employment  of  unskilled  workers  for  construction  and  maintenance was revised and had escalated to Rs.4/- per  day by the Government of State of Madhya Pradesh vide  the  Notification  No.342-I-4936-XVI,  dated  27.06.1979.  Since the  lis pertains to ‘minimum wages’ payable to  labourers in the State of Madhya Pradesh only, we would  not  saddle  the  judgment  by  noticing  the  co-lateral  changes effected in the State of Uttar Pradesh.

8. Consequently, the Construction Company, vide  

4

5

Page 5

its  letter  No.BCC/710/1093,  dated  07.03.1981,  made  a  claim of Rs.5,67,766.84/- towards labour escalation for  the work done in Sidhi District, Madhya Pradesh, for  the  period  from  01.02.1979  to  01.12.1980  and  Rs.36,83,475.72/- for the work done in the State of  Uttar Pradesh on the basis of the increase in the rate  of 'minimum wages' payable to the labourers. In the  said  escalation  bill,  the  Construction  Company  had  claimed escalation at the rate of Rs.3.00/- with effect  from  01.02.1979  and  Rs.4.00/-  with  effect  from  01.04.1979.  After  considering  the  escalation  bill  so  submitted,  the  NTPC  had  paid  a  total  sum  of  Rs.4,72,372.74/-  to  the  Construction  Company  for  the  work  carried  out  in  State  of  Madhya  Pradesh,  vide  cheques  dated  15.07.1981,  31.07.1981,  28.06.1982  and  22.07.1982, but denied their claim in respect of State  of  Uttar  Pradesh.  Thereafter,  a  series  of  communications  ensued  between  the  parties;  however,  their  respective  claims  could  not  be  settled.  Later  NTPC, having noticed that the Construction Company had  wrongly  claimed  a  sum  of  Rs.4,72,372.74/-,  requested  

5

6

Page 6

the Construction Company to refund the aforesaid sum,  by their letter dated 07.10.1983.

9. Since the parties had disputed the claim, in  terms of Clause 57 of the agreement, they had referred  the dispute for arbitration before the Sole Arbitrator.  The  parties  had  raised  two  separate  claims  for  adjudication and decision before the Sole Arbitrator.  The  Construction  Company  had  claimed  a  sum  of  Rs.37,78,869.82/-  [Rs.36,83,475.72/-  (for  Uttar  Pradesh) + Rs.5,67,766.84/- (for of Madhya Pradesh) –  Rs.4,72,372.74/- (amount of labour escalation already  paid)]  as  balance  due  from  NTPC  alongwith  interest  towards  the  increased  wages  paid  by  them  to  the  labourers, whereas the NTPC had denied the said claim  of  the  Construction  Company  and  further  claimed  a  refund of Rs.4,72,372.74/- with interest at the rate of  18% p.a. from the date of payment till the date of  refund of the amount.  

10. While  deciding  the  claim  made  by  the  Construction Company, the learned Arbitrator had raised  

6

7

Page 7

ten issues for his consideration and decision.  The  issues so framed were:-

“(1) What were the minimum wages for unskilled  labour  in  Madhya  Pradesh  during  the  relevant  period? (2) What were the minimum wages for unskilled  labour  in  Uttar  Pradesh  during  the  relevant  period? (3)  What  were  the  fair  wages  for  unskilled  workers  at  the  time  of  the  contract  at  the  places where works were to be executed? (4) What has been the effect of the increase in  minimum wages on fair wages? (5) Is the contract indivisible as claimed as  regards  the  payment  of  wages  to  unskilled  workers for the works executed at the place (s)  in M.P. and at different places of U.P. and if  so, to what result? (6) Is the work site No.10 located in M.P. or  both in M.P. and U.P.? (7)  Is  the  claimant  entitled  to  recover  escalation in wages for the whole of the No.10  and if so, to what extent? (8)  What  amount  was  actually  spent  by  the  claimant  Co.  on  the  payment  of  wages  to  unskilled  labour  on  account  of  escalation  in  minimum wages? (9) Is the Claimant Company entitled is more  payment, even if they did not pay more wages to  

7

8

Page 8

unskilled workers on account of such escalation  in wages? (10) Is the Claimant Company entitled to recover  any interest in this regard and, if so, to what  amount? (11) Relief.”

11. Since  the  question  before  us  is  limited  to  liability for payment of money for escalation in rates  of minimum wages in Madhya Pradesh, we would not notice  the  discussion  and  decision  made  by  the  learned  Arbitrator  in  respect  of  work  carried  out  in  Uttar  Pradesh.  The  learned  arbitrator  has  considered  issue  Nos.  1,  3,  5  and  9  collectively  and  recorded  his  findings that minimum wages (fair wages) for labour in  Sidhi  District,  Madhya  Pradesh  was  Rs.2.00/-  upto  26.06.1979 and pursuant to the notification was raised  to  Rs.4.00/-  and  further  that  the  contract  is  not  divisible and thereby wages payable in Uttar Pradesh  and Madhya Pradesh could not be calculated in isolation  with each other.     He has relied upon Clauses 7.1(a)  and 7.3 of the Special Conditions of the Contract and  Clause     53-A(b) of the General Conditions of the  

8

9

Page 9

Contract  and  has  concluded  that  the  claim  for  reimbursement on account of increase in ‘fair wages’  payable by the Construction Company would be admissible  under the contract only, when there has been escalation  in  ‘minimum  wages’  on  account  of  the  notification  issued by the appropriate State Government under the  payment  of  Minimum  Wages  Act,  however,  such  reimbursement would be subject to whether or not the  Construction  Company  has  paid  such  increased  ‘fair  wages’ on account of the said escalation.  In so far as  issue No.8, the learned Arbitrator has concluded that  for the works carried out at the sites/sides located in  Sidhi District, Madhya Pradesh the Construction Company  had to pay and has paid increased wages to unskilled  labourers  from  Rs.2.00/-  to  Rs.4.00/-  per  day  with  effect from 27.6.1979.  While considering issue No.6  and 7, the Sole Arbitrator has agreed with the claim  made  by  the  Construction  Company  in  respect  of  construction  work  of  Bridge  No.  10  situated  at  the  border of the two States that the minimum wages payable  for all labourers would be the same irrespective of  

9

10

Page 10

whether the work is carried out by them in the Madhya  Pradesh or Uttar Pradesh and consequently, directed the  NTPC to make the payment of the amounts for escalation  in minimum wages in Madhya Pradesh. In conclusion the  learned Arbitrator has thought it fit to direct the  NTPC to pay a sum of Rs.5,10,850/- to the Construction  Company.  

12. On the claim made by the NTPC, the learned  Arbitrator in his award dated 15.05.1986 has concluded  that the NTPC is required to reimburse the Construction  Company in accordance with the agreement between them  for payment of escalated ‘minimum wages’ from Rs.2.00/-  to Rs.4.00/- and rejected the claim of the NTPC for  refund of the monies already paid to the Construction  Company.  

13. Outcome  of  the  proceedings  of  the  learned  Arbitrator resulted in filing of two suits before the  High Court of Delhi by the parties. While the learned  Arbitrator had filed the Award, dated 07.05.1986, and  

1 0

11

Page 11

proceedings  before  the  High  Court  as  required  under  Section 14(2) of the Arbitration Act, 1940, the NTPC  has questioned the Award dated 7.5.1986 by filing its  objection under Section 30 and 33 of the Act in Suit  No.1496-A  of  1986.  The  other  connected  suit  (Suit  No.1510-A  of  1986)  arises  out  of  the  Award  dated  15.05.1986, wherein the claim made by NTPC for refund  of the monies paid to Construction Company was rejected  by the learned Arbitrator.   

14. The learned Single Judge of the High Court in  the  judgment  and  order  dated  02.12.1994  in  Suit  No.1496-A  of  1986,  has  observed  that  the  escalation  claim of the Construction Company in respect of the  work carried out in the State of Madhya Pradesh could  only be a sum of Rs.5,67,766.84/- and keeping in view  the  escalation  costs  already  paid  by  the  NTPC,  the  Construction Company would be entitled for payment of  Rs.95,394.10/- only. The learned Single Judge has also  come to the conclusion that the learned Arbitrator had  erroneously  awarded  a  sum  of  Rs.5,10,850/-  which  is  

1 1

12

Page 12

beyond the claim made by the Construction Company and,  accordingly, has set aside the Award, dated 07.05.1986.  By a separate order, dated 02.12.1994 in Suit No.1510-A  of 1986, has delved into the question of “basic wage”  considered under Clause 7.1(a) so as to carry out the  escalation calculations and concluded that the learned  Arbitrator  has  erroneously  considered  the  escalation  from Rs.2.00/- instead of Rs.2.70/-, which infact was  admittedly  paid  by  the  Construction  Company  as  fair  wages  to  the  labourers  in  Sidhi  District,  Madhya  Pradesh. Keeping the aforesaid fair wages paid by the  Construction Company as basic wages, the learned Single  Judge has calculated the difference payable at the rate  of Rs.1.03/-, considering escalated amount of Rs.2.97/-  after  10%  absorption  as  per  Clause  53-A(b)  of  the  General  Conditions  of  Contract.  Consequently,  the  learned  Single  Judge  has  modified  the  Award  dated  15.05.1986 and observed that the Construction Company  has paid a sum of Rs.2,09.376.74/- in excess of the  amounts due under the contract and accordingly directed  it to refund the said amount to NTPC with interest at  

1 2

13

Page 13

the rate of 12% per annum thereon from the date of  payment till realization.   

15. Being aggrieved by the aforesaid order passed  by the learned Single Judge, the Construction Company  had filed two appeals, one against the orders passed in  Suit No.1510-A of 1986 and the other against the order  passed  in  Suit  No.1496-A  of  1986.   The  appeals  are  numbered as FAO (OS) No.116 of 1985 and FAO (OS) No.118  of 1995. However, the NTPC being satisfied with the  aforesaid  judgment  and  orders  passed  by  the  learned  Single  Judge  had  not  carried  the  matter  in  further  appeal before the Division Bench.

16. The Division Bench, by the impugned judgment  and order dated 04.12.2008, has allowed the FAO (OS)  No.116 of 1985 and made the Award dated 15.05.1986 rule  of  Court.  However,  the  Division  Bench,  in  FAO  (OS)  No.118 of 1995, has modified the impugned judgment and  order of the learned Single Judge and directed the NTPC  to make payment of Rs.95,394.10/- to the Construction  Company  for  the  increase  in  minimum  wages  from  

1 3

14

Page 14

Rs.2.00/-  to  Rs.4.00/-.   It  is  the  correctness  or  otherwise of the said order which is the subject matter  of these appeals by special leave.

17. We have heard learned counsel for the parties  and carefully perused the documents on record. In our  view, to appreciate the contentions canvassed by the  learned counsel for the parties, the Clauses 7.1(a) and  7.3 of the Special Conditions and Clauses 16.2 and 53-A  (b) of the General Conditions of the Contract between  the parties are required to be noticed:  

“Special Conditions of Contract (SCC): Clause 7.1 For the purpose of calculation of  reimbursement/refund on variation in prices, if  there  be  any  (plus  or  minus),  the  basis  of  calculation shall be as under:-      Clause  7.3  The  price  variation  of  different  components under 7.1. a, b & c above shall be  subjected to the ceilings as stipulated under  clause 53-A “General Conditions of Contract” for  admissibility  of  reimbursement/refund  on  variation in prices.” General Conditions of Contract: Clause 16.2: “The  contractor  shall  pay  to  the  labourers  employed by him either directly or through sub-

1 4

15

Page 15

contractor wages not less than 'fair wages' as  defined in the contractors' labour regulations”. Clause 53 A (b): “Reimbursement/Refund on variation of price: (a) … (b) Labour: For the purpose of this contract the  minimum  wages  of  unskilled  labour  and  the  skilled labour and of semi-skilled labour on the  date of submission of the tender shall be taken  as  shown  in  Schedule-D  on  account  of  any  legislation,  notification,  labour  award,  the  minimum wages of unskilled labour, of skilled  labour and of semi-skilled labour are increased  at any time or times after the submission of the  tender  and  the  contractor  has  to  pay  any  increased  wages  then  the  corporation  shall  reimburse to the contractor the increase in the  cost  of  labour  not  exceeding  the  increase  permitted under the legislation, notification,  labour award or duly approved binding agreement  as aforesaid, subject to hereinafter provided-” (b)(i)..... (b)(ii) “Provided however no increase shall be  payable if the increase is not more than 10% of  the said wages and, if so, the increase shall be  payable only on the excess over 10% and provided  further  that  any  such  increase  shall  not  be  payable if such increase has become operative  after  the  contract  or  extended  date  of  completion  of  the  works  or  items  of  work  in  question....”

18. Clause  7.1(a)  of  the  Special  Conditions  of  Contract relates to refund on variation in prices of  various  components  of  works  contract;  one  such  component being ‘Labour’. It explains that basic index  

1 5

16

Page 16

for  calculation  there  would  be  the  minimum  wages  payable to the unskilled labour as per applicable rates  in  Sidhi  District,  Madhya  Pradesh  under  the  Minimum  Wages  Act.  Clause  7.3  speaks  of  price  variation  of  different components prescribed under 7.1 a, b and c  and  that  would  be  subjected  to  the  ceilings  as  stipulated under Clause 53-A of General Conditions of  the  Contract  for  the  purpose  of  admissibility  of  reimbursement/ refund on variation in prices.  

19. Clause  16  of  the  General  Conditions  of  the  Contract defines the meaning of the expression ‘fair  wages’.  It adopts the meaning as defined in Regulation  16 of the Contractors' Labour Regulations.  It means  “fair wages” to include wages for weekly day of rest  and other allowances, whether for time or piece work,  after taking into consideration, the prevalent market  rates for similar employment in the neighborhood, but  shall not be less than the market rates of the wages  fixed under the Payment of Minimum Wages Act, 1948.  

1 6

17

Page 17

20. Schedule ‘D’ to these General Conditions of  the Contract pertains to the minimum wages which are  contemplated as per ‘Payment of Minimum Wages Act’ as  notified by the appropriate State Government applicable  to the concerned project site.

21. Clause 53-A(b) of the General Conditions of  the Contract is in two parts.  The first part speaks of  payment of the minimum wages to unskilled labour and  the skilled labour and semi-skilled labourers on the  date of submission of the tenders and the same shall be  taken as shown in Schedule-D of the contract,  i.e.,  under the Payment of the Minimum Wages Act.  The second  part of the Clause speaks of the increase of wages on  account of a legislation, by issuance of a notification  or  by  passing  the  labour  award  in  respect  of  the  minimum wages of unskilled labour and of skilled labour  and of the semi-skilled labour at any time after the  submission of the tender.  The Construction Company,  after such increase, is required to pay the increased  wages  and  on  proof  of  such  payment  of  the  said  

1 7

18

Page 18

increased wages having been made, the NTPC is required  to reimburse the increased wages paid to its workers to  the contractor. The proviso appended to Clause 53-A(b)  provides that the increased wages need not be paid by  the NTPC, if the increase in wages is not more than 10%  of the said wages. The other part of the proviso speaks  of the payment of increased wages to the contractor, if  the  increase  is  in  excess  of  10%  and  again  such  a  payment need not be made by the Corporation, if such  increase has become operative after the completion of  the  contract  or  extended  date  of  completion  of  the  works or items of work in question.  

22. Having  noticed  the  relevant  clauses  in  the  contract  between  the  parties,  we  advert  to  the  reasoning  and  conclusions  drawn  in  the  two  Awards  passed by the learned Arbitrator, dated 07.05.1986 and  15.05.1986 and the judgment and order passed by the  learned Single Judge and the Division Bench of the High  Court of Delhi. 23. It is neither in dispute nor could be disputed  by the parties that the Construction Company at the  

1 8

19

Page 19

relevant  point  of  time  of  execution  of  20%  of  the  construction work in Sidhi District, Madhya Pradesh was  paying  Rs.2.70/-  as   the  ‘fair  wages’  to  the  unskilled/semi-skilled  labourers  on  the  date  of  submission  of  their  tender,  since  the  Construction  Company had specifically stated in the escalation bill  submitted to the NTPC that the amount paid as ‘fair  wages’ to labourers at Sidhi District, Madhya Pradesh  was Rs.2.70/-.

24. The learned Arbitrator, keeping in view the  possible construction that could be placed on Clauses  7,  16  and  53-A(b)  of  the  General  Conditions  of  the  Contract,  has  thought  it  fit  to  allow  only  the  increased  wages  paid  by  the  respondent-Company  from  Rs.2.70/- to Rs.4.00/-, i.e., from the ‘fair wages’ as  quoted in the escalation bill to the increased ‘minimum  wages’.  The  learned  Single  Judge  has  more  or  less  accepted this view of the learned Arbitrator and on the  basis of the said rates has rightly concluded that the  amount that requires to be paid by NTPC is only a sum  

1 9

20

Page 20

of  Rs.95,394.10/-.   He  has  arrived  at  this  figure  keeping in view Rs.1.03/- as the difference of amount  payable  as  per  the  contract.  However,  the  Division  Bench  of  the  High  Court,  while  modifying  the  conclusions  reached  by  the  learned  Single  Judge  has  thought it fit to direct the NTPC to pay the escalated  wages  by  taking  into  account  the  difference  of  the  minimum wages as payable on the date of submitting the  tender and the increased minimum wages, i.e., Rs.2.00/-  to Rs.4.00/-.  

25. The  learned  counsel  for  the  appellant,  Mrs.Rachana Joshi Issar has taken trouble to convince  us, that, what would be payable by the NTPC to the  Construction Company is only the difference between the  ‘fair wages’ paid by the contractor and the ‘minimum  wages’  fixed  by  way  of  legislation.  Therefore,  she  would submit that what is payable to the Construction  Company by the NTPC is only a sum of Rs.1.03/- after  making the calculations as provided under proviso to  Clause  53-A(b)  of  the  General  Conditions  of  the  

2 0

21

Page 21

Contract.  

26. Per Contra, Ms. Binu Tamta, learned counsel  for  the  Construction  Company  would  submit  that  the  Division  Bench  of  the  High  Court  is  justified  in  directing the NTPC to pay the difference of the minimum  wages that was fixed by the State of Madhya Pradesh at  the time of offering the tender and the increase of the  minimum  wages  by  way  of  notification  during  the  subsistence of the contract.

27. We  have  considered  the  rival  submissions  canvassed by the learned counsel for the parties.  We  are of the view that what is brought forth for our  consideration  and  decision  is,  whether  the  NTPC  is  required to make payment of escalated labour charges to  the  Construction  Company  from  the  amount  of  the  statutory ‘minimum wages’ as on the date of submission  of tender forms or ‘fair wages’ as quoted in the tender  form submitted by the Construction Company. Therefore,  the entire case of the parties would revolve only on  the mathematical calculation that requires to be done.

2 1

22

Page 22

28. Admittedly,  the  Construction  Company  while  offering  its  tender  forms  to  NTPC  had  specifically  stated that the ‘fair wages’ payable to their labourers  for  the  construction  work  at  Sidhi  District  in  the  State of Madhya Pradesh is Rs.2.70/- though, at the  relevant point of time the minimum wages prescribed for  the  said  work  was  only  Rs.2.00/-.  Subsequently,  the  minimum wages payable in the State of Madhya Pradesh  was  revised  by  the  State  Government  by  issuing  Notification dated 27.06.1979 to Rs.4.00/-.  If that is  so, in the light of Clause 7 of Special Conditions of  Contract  and  Clauses  16  and  53-A(b)  of  the  General  Conditions of Contract read with the tender documents  and  escalation  bill  submitted  by  the  Construction  Company, it is abundantly clear that what is required  to be paid to the Construction Company by the NTPC is  only  the  difference  between  Rs.4.00/-  and  Rs.2.70/-,  subject  to  other  calculations  as  provided  in  the  proviso to Clause 53-A of the General Conditions of  Contract.  

2 2

23

Page 23

29. In our considered opinion, the learned Single  Judge had rightly concluded that the difference shall  be  calculated  between  the  ‘fair  wages’  paid  by  the  Construction  Company  before  issuance  of  the  notification  and  the  increased  minimum  wages  after  issuance of the notification and if it is calculated in  that  manner,  what  requires  to  be  paid  is  Rs.1.03/-  after  making  necessary  adjustments  as  provided  under  second proviso to Clause 53-A(b). However, the learned  Division Bench had erroneously calculated the amounts  payable based on the difference of minimum wages at the  time of submission of tender forms and as increased by  the  Notification.  The  aforesaid  amount  shall  carry  interest at the rate of 9% per annum from the passing  of the Award, dated 07.05.1986, till the date of actual  payment.  

30. With these observations and directions, we set  aside the judgment and order passed by the Division  Bench  of  the  High  Court  in  part.  To  the  extent  indicated in the order, the appeals are partly allowed.  

2 3

24

Page 24

Parties to bear their own costs.

Ordered accordingly.

.......................J. (H.L. DATTU)

.......................J. (DIPAK MISRA)

NEW DELHI, MARCH 7, 2013.  

2 4