MANOHAR LAL SHARMA Vs THE PRINCIPLE SECRETARY & OTHERS
Bench: CHIEF JUSTICE,MADAN B. LOKUR,KURIAN JOSEPH
Case number: Writ Petition (crl.) 120 of 2012
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CRIMINAL/CIVIL ORIGINAL JURISDICTION
WRIT PETITION (CRL.) NO. 120 OF 2012
Manohar Lal Sharma ….Petitioner
Versus
The Principle Secretary & Ors. …Respondents
WITH
WRIT PETITION (CIVIL) NO. 463 OF 2012
WITH
WRIT PETITION (CIVIL) NO. 515 OF 2012
AND
WRIT PETITION (CIVIL) NO. 283 Of 2013
O R D E R
1. On 25th August, 2014 judgment was delivered in these
cases and it was held, inter alia, that the allotment of coal
blocks made by the Screening Committee of the
Government of India, as also the allotments made through
the Government dispensation route are arbitrary and
illegal. Since the conclusion arrived at would have
W.P. (Crl.) Nos.120 of 2012 etc. Page 1 of 27
Page 2
potentially had far-reaching consequences, on which
submissions were not made when the case was heard, the
question of what should be the consequences of the
declaration was left open for hearing.
2. The relevant paragraphs of the judgment dated 25th
August, 2014 read as follows:- “155. The allocation of coal blocks through Government dispensation route, however laudable the object may be, also is illegal since it is impermissible as per the scheme of the CMN Act. No State Government or public sector undertakings of the State Governments are eligible for mining coal for commercial use. Since allocation of coal is permissible only to those categories under Section 3(3) and (4), the joint venture arrangement with ineligible firms is also impermissible. Equally, there is also no question of any consortium/leader/association in allocation. Only an undertaking satisfying the eligibility criteria referred to in Section 3(3) of the CMN Act, viz., which has a unit engaged in the production of iron and steel and generation of power, washing of coal obtained from mine or production of cement, is entitled to the allocation in addition to Central Government, a Central Government company or a Central Government corporation.
156. In this context, it is worthwhile to note that the 1957 Act has been amended introducing Section 11-A w.e.f. 13.02.2012. As per the said amendment, the grant of reconnaissance permit or prospecting licence or mining lease in respect of an area containing coal or lignite can be made only through selection through auction by competitive bidding even among the eligible entities under Section 3(3)(a)(iii), referred to above. However, Government companies, Government corporations or companies or corporations, which have been awarded power projects on the basis of competitive bids for tariff (including Ultra Mega Power Projects) have been exempted of allocation in favour of them is not meant to be through the competitive bidding process.
157. As we have already found that the allocations made, both under the Screening Committee route and the
W.P. (Crl.) Nos.120 of 2012 etc. Page 2 of 27
Page 3
Government dispensation route, are arbitrary and illegal, what should be the consequences, is the issue which remains to be tackled. We are of the view that, to this limited extent, the matter requires further hearing.”
3. Accordingly, we heard several learned counsels
appearing for a very large number of interveners,
impleadment applicants and State Governments.
Substantive submissions were made, amongst others, by
the Coal Producers Association, the Independent Power
Producers Association of India and the Sponge Iron
Manufacturers Association. These associations had also
been heard on an earlier occasion well before judgment
was delivered on 25th August, 2014.
4. For the purposes of these “consequence proceedings”,
the Union of India filed an affidavit dated 8th September,
2014. It is stated in the affidavit that coal is actually being
mined from 40 coal blocks listed in Annexure I to the
affidavit. This list includes two coal blocks allotted to an
Ultra Mega Power Projects (Sasan Power Ltd. [UMPP]
allotted the coal blocks Moher and Moher Amroli
Extension). Coal blocks allotted to UMPPs have not been
disturbed in the judgment. The list of the 40 coal blocks is
attached to this order as Annexure 1.
5. In addition to the above 40 coal blocks, it is stated in
the affidavit that 6 more coal blocks are ready for
W.P. (Crl.) Nos.120 of 2012 etc. Page 3 of 27
Page 4
extraction of coal in 2014-15 and this list is Annexure II to
the affidavit. These 6 coal blocks have obtained the Mine
Opening Permission from the Coal Controller’s
Organization under Rule 9 of the Colliery Control Rules
20041 (framed under the Mines and Minerals
(Development and Regulation) Act, 1957). This permission
is granted subsequent to the execution of a mining lease.
The list of these 6 coal blocks is attached to this order as
Annexure 2.
6. Therefore, the affidavit is quite clear that 40 coal blocks
are already producing coal and 6 coal blocks are in a
position to produce coal virtually with immediate effect.
The question is whether the allotment of these coal blocks
should be cancelled or not.
7. It was submitted by the learned Attorney General that
after the declaration of law and the conclusion that the
allotment of coal blocks was arbitrary and illegal, only two
consequences flow from the judgment. The first is the
natural consequence, that is, the allotment of the coal
blocks (other than those mentioned in the judgment)
should be cancelled and the Central Government is fully 1 9. Requirement of prior permission to open a coal mine, seam or section of a seam.--
(1) No owner of a colliery shall open a coal mine, seam or a section of a seam without the prior permission in writing of the Central Government.
(2) No owner of a colliery shall also commence mining operations in a colliery or seam or a section of a seam, in which the mining operation has been discontinued for a period exceeding one hundred and eighty days, without the prior permission in writing of the Central Government.
W.P. (Crl.) Nos.120 of 2012 etc. Page 4 of 27
Page 5
prepared to take things forward. The second option is that
46 coal blocks (as above) be left undisturbed (subject to
conditions) and the allotment of the remaining coal blocks
should be cancelled.
8. Expounding on the alternative consequence, it was
submitted that Coal India Limited (CIL) a public sector
undertaking can take over and continue the extraction of
coal from these 44 coal blocks without adversely affecting
the rights of those employed therein. However, it was
submitted that CIL would require some time to take over
the coal blocks and manage its affairs for continuing the
mining process. Effectively therefore, it was submitted
that even if the allotment of these 44 coal blocks is
cancelled, the Central Government can ensure that coal
production will not stop.
9. Learned Attorney General submitted that all the
allottees of coal blocks should be directed to pay an
additional levy of Rs. 295/- per metric ton of coal extracted
from the date of extraction as per the Report of the
Comptroller and Auditor General (CAG) dealing with the
financial loss caused to the exchequer by the illegal and
arbitrary allotments. It was further submitted that in the
case of allottees supplying coal to the power sector, they
W.P. (Crl.) Nos.120 of 2012 etc. Page 5 of 27
Page 6
should be mandated to enter into Power Purchase
Agreements (PPAs) with the State utility or distribution
company (as the case may be) so that the benefit is
passed on to the consumers.
10. By way of abundant precaution, the learned
Attorney General pointed out that in respect of the
allotment of 6 coal blocks, a First Information Report has
been lodged by the Central Bureau of Investigation (CBI).
Therefore, investigations are in progress to ascertain
whether any criminal offence has been committed in
respect of the allotment of 6 coal blocks. In addition, it is
pointed out that the CBI has on 3rd September, 2014
informed that a final decision with regard to any alleged
criminality or otherwise in the allotment of 6 other coal
blocks is pending consideration. In other words, the
alleged criminality in the allotment of 12 out of the 46 coal
blocks identified by the learned Attorney General is under
scrutiny by the CBI.
11. To put the suggestions of the learned Attorney
General in perspective, they are summarized below:
(1) All coal block allotments (except those
mentioned in the judgment) may be cancelled.
(2) Alternatively,
W.P. (Crl.) Nos.120 of 2012 etc. Page 6 of 27
Page 7
(a) Extraction of coal from the 40 functional and 6
“ready” coal blocks may be permitted and the
remaining coal blocks be cancelled;
(b) The allottees of all 46 coal blocks be directed
to pay an additional levy of Rs.295/- per metric
ton of coal extracted from the date of
extraction; and
(c) The allottees of coal blocks for the power
sector be also directed to enter into PPAs with
the State utility or distribution company as the
case may be.
12. Learned Attorney General made two supplementary
submissions, not directly connected with the suggestions
made. It was submitted that though all the allotments
made by the Screening Committee and through the
Government dispensation route were held illegal and
arbitrary, the allotment of lignite blocks was not the
subject matter of discussion in the judgment delivered on
25th August, 2014. This is correct and it is made clear that
the judgment delivered on 25th August, 2014 does not
concern lignite blocks at all and their allotments are not
covered by the said judgment.
13. Secondly, the figure of Rs. 295/- per metric ton of
W.P. (Crl.) Nos.120 of 2012 etc. Page 7 of 27
Page 8
coal extracted as additional levy (based on the Report of
the Comptroller and Auditor General) has been calculated
on the basis of open cast mines and mixed mines, while
underground mines were not taken into calculation. Of the
coal blocks sought to be “saved” from cancellation, it has
not been pointed out by any learned counsel whether any
one of the 46 coal blocks contains an underground mine or
not. Therefore, there is no occasion to deal with a
hypothetical case.
14. In response to the submissions of the learned
Attorney General, Mr. K.K. Venugopal, Senior Advocate,
appearing on behalf of the Coal Producers Association
submitted that cancellation of all the coal blocks would
have very serious and far reaching consequences.
15. The consequences of cancellation of the coal blocks
were categorized by Mr. Venugopal under various heads
and these are detailed below.
(1)There would be a serious adverse impact on the
economy of the country: It was submitted that
Government companies are not in a position to supply the
required quantity of coal; in fact, a large number of
applications are pending with the Ministry of Coal for long
term coal linkages; power stations have a supply of less
W.P. (Crl.) Nos.120 of 2012 etc. Page 8 of 27
Page 9
than one week of coal and therefore there are possibilities
of power outages; as many as 10 power plants of the
National Thermal Power Corporation (NTPC) and the
Damodar Valley Corporation (DVC) have been shut down
because of shortage of coal supply by Coal India Ltd. (CIL);
there is an issue of poor quality of coal supplied by CIL;
huge investments up to about Rs. 2.87 lakh crores have
been made in 157 coal blocks as on December, 2012;
investments in end-use plants have been made to the
extent of about Rs. 4 lakh crores; the employment of
almost 10 lakh people is at stake; end-use plants have
been designed keeping in mind the specification of coal in
the allocated coal block and cancellation of the coal blocks
would result in the end-use plant becoming redundant;
loans to the extent of about Rs. 2.5 lakh crores given by
banks and financial institutions would become non-
performing assets; the State Bank of India may suffer a
loss of up to Rs. 78,263 crores which is almost 7.9% of its
net worth for the financial year 2013; other Public Sector
Banks such as the Punjab National Bank and the Union
Bank will receive a massive set back; Public Sector
Corporations like Rural Electricity Corporation and Power
Finance Corporation have an even higher exposure than
W.P. (Crl.) Nos.120 of 2012 etc. Page 9 of 27
Page 10
banks; there will be global ramifications of the de-
allotments such as a negative impact on investor
confidence; acute distress in some industries; the
country’s dependence on coal as a primary fuel source
with up to 60% for power generation may result in
inflationary trends; 28,000 MW of power capacity will be
affected due to de-allocation; closure of coal mines would
result in an estimated loss of Rs. 4.4 lakh crores in terms
of loss of royalty, cess, direct and indirect taxes; coal
imports (already very high) will go up even more in FY
2016-17 to the extent of Rs.1.44 lakh crores (without de-
allocation); and on the other hand, the production of coal
would substantially increase in case all coal blocks are
made operational after the grant of necessary permission.
(2)The cancellation of coal blocks would set back the
process (of extraction and effective utilization of coal) by
about 7 to 8 years: It was submitted that the auction of
coal blocks would take at least 1-2 years and from past
experience, it is unlikely that the auction would be
successful due to lack of bids or proper participation; it
would take at least 5-6 years for making the auctioned
coal blocks operational; in any event (based on the time
lines given by the Ministry of Coal in the allocation letters)
W.P. (Crl.) Nos.120 of 2012 etc. Page 10 of 27
Page 11
it would take 36-42 months to develop an open cast mine
and about 48-54 months to develop an underground mine;
and the commissioning of end-use plants after obtaining
various clearances would take a minimum of 3-4 years.
(3)If the coal blocks are not cancelled, the allottees could
continue their contribution towards corporate social
responsibility and socio-economic development of the
country: It was submitted on a positive note that the
allottees have invested in basic infrastructure like road,
rail links etc. since the coal blocks allotted to them were in
areas where CIL was not interested in making an
investment; the allottees have made huge investments in
setting up other infrastructure such as schools, hospitals,
facilities for clean and potable water, residential colonies,
community centers, playground etc. and in creation of job
opportunities; thousands of crores of rupees have already
been paid by the coal block allottees by way of direct and
indirect taxes and in the form of royalty, cess etc.; and if
the coal blocks are cancelled, the development activities
initiated by the allottees would come to a standstill.
(4)Many of the allottees have problems peculiar to them
which need to be examined along with ground realities: It
was submitted that the delay in development of coal
W.P. (Crl.) Nos.120 of 2012 etc. Page 11 of 27
Page 12
blocks is not attributable to the allottees who are actually
victims of the faults of the Screening Committee; delays
are attributable to various reasons such as administrative
delays on the part of the Ministry of Environment and
Forest and Ministry of Coal, the consent by the Pollution
Control Boards was not given on time, Court orders,
Naxalite issues in some areas, State Governments
directing that mining lease should not be executed,
introduction of go/no go areas or without statutory
permission etc.; this Court has tacitly acknowledged
administrative delays in grant of clearances in an order
passed on 1st September, 2014 in Samaj Parivartana
Samudaya v. State of Karnataka;2 the appropriate
course of action to adopt would be for this Court to
appoint a Committee to examine the peculiar facts of each
individual allotment.
(5) The additional levy of Rs. 295/- per metric ton of coal
extracted (described as a penalty) is unjustified: The
figure of loss of revenue to the exchequer to the extent of
Rs. 295/- per metric ton of coal extracted is borrowed from
the Report of the CAG which Report is contested by the
Government of India and is pending consideration before a
2 I.A. No.201 & 219, 223 in I.A. No.204 and I.A. Nos. 224 in I.A. No.215 in WP(C) No. 562/2009
W.P. (Crl.) Nos.120 of 2012 etc. Page 12 of 27
Page 13
Parliamentary Committee on Public Undertakings; the
Report itself suggested that only a part of the financial
gain could have accrued to the national exchequer; the
Government of India has not applied its mind while
suggesting the figure of Rs. 295/- per metric ton and it has
only considered the average price of coal as given by CIL
for the year 2010-11 (being Rs.1028/- per metric ton) and
that cannot be adopted for earlier financial years; the coal
extracted from the blocks allotted are of an inferior quality
and the sale price thereof is much lower than the average
sale price of CIL; the CAG has not taken into consideration
underground mines while calculating the alleged financial
loss; the cost of production of coal for CIL is less since CIL
has economically viable mines as compared to the mines
allocated to the private sector which lack infrastructure
and have several other problems; and penalty cannot be
imposed with retrospective effect since the coal extracted
by the allottees has already been utilized for production of
power, steel, cement etc.
16. Finally, Mr. Venugopal relied on Ashok Hurrah v.
Rupa Ashok Hurrah3 to contend that the allottees are
entitled to a hearing before the cancellation of their coal
3 (2002) 4 SCC 388
W.P. (Crl.) Nos.120 of 2012 etc. Page 13 of 27
Page 14
blocks in accordance with the well accepted principles of
natural justice since the cancellation adversely affects
their interests. Paragraph 51 of the Report was relied on
and this reads as follows: “Nevertheless, we think that a petitioner is entitled to relief ex debito justitiae if he establishes (1) violation of the principles of natural justice in that he was not a party to the lis but the judgment adversely affected his interests or, if he was a party to the lis, he was not served with notice of the proceedings and the matter proceeded as if he had notice, and (2) where in the proceedings a learned Judge failed to disclose his connection with the subject- matter or the parties giving scope for an apprehension of bias and the judgment adversely affects the petitioner.”
17. Mr. Harish Salve, Senior Advocate, appearing for the
Sponge Iron Manufacturers Association generally
supported the submissions made by Mr. Venugopal. He
emphasized that the more appropriate course for this
Court to adopt would be to appoint a Committee of three
persons, including experts, to examine each individual
allotment and consider the facts peculiar to each allottee
and report to this Court whether the coal block allotment
should be cancelled or not.
18. Learned counsel also emphasized the necessity of
granting a hearing to each allottee and referred to a
passage from National Textile Workers’ Union v. P. R.
Ramakrishna4 wherein the Constitution Bench
4 (1983) 1 SCC 228
W.P. (Crl.) Nos.120 of 2012 etc. Page 14 of 27
Page 15
emphasized the importance of natural justice in paragraph
16 of the Report. Particular emphasis was laid on the
following passage: “….It will surely be a travesty of justice to deny natural justice on the ground that courts know better. There is a peculiar and surprising misconception of natural justice, in some quarters, that it is, exclusively, a principle of administrative law. It is not. It is first a universal principle and, therefore, a rule of administrative law. It is that part of the judicial procedure which is imported into the administrative process because of its universality. “It is of the essence of most systems of justice – certainly of the Anglo-Saxon System – that in litigation both sides of a dispute musts be heard before decision. ‘Audi Alteram Partem’ was the aphorism of St. Augustine which was adopted by the courts at a time when Latin Maxims were fashionable”. “Audi Alteram Partem is as much a principle of African, as it is of English legal procedure : a popular Yoruba saying is “ ‘wicked and iniquitous is he who decides a case upon the testimony of only one party to it” (T.O. Elias : The Nature of African Customary Law). Courts even more than administrators must observe natural justice.”
19. Mr. Salve also referred to a passage from
Administrative Law5 to contend that the principle of legal
relativity should be borne in mind by the Court so that
“the law can be made to operate justly and reasonably in
cases where doctrine of ultra vires, rigidly applied, would
produce unacceptable results.”
20. Unfortunately, it is difficult to see relevance of the
passage cited by learned counsel since it deals with the
nullity and voidness of an Act or order which is ultra vires.
5 Administrative Law by Sir William Wade, 9th Edn.
W.P. (Crl.) Nos.120 of 2012 etc. Page 15 of 27
Page 16
The applicable principles are completely different and we
are not dealing with such a case. It would be more
apposite to refer to a passage from Sheela Barse v.
Union of India6 cited by Dr. A.M. Singhvi, Senior Advocate
(appearing for the Independent Power Producers
Association of India) wherein this Court observed the
future is important (and that is what we are looking at).
This Court said: “Again, the relief to be granted looks to the future and is, generally, corrective rather than compensatory which, sometimes, it also is. The pattern of relief need not necessarily be derived logically from the rights asserted or found. More importantly, the court is not merely a passive, disinterested umpire or onlooker, but has a more dynamic and positive role with the responsibility for the organization of the proceedings, moulding of the relief and – this is important – also supervising the implementation thereof. The court is entitled to, and often does, seek the assistance of expert panels, Commissioners, Advisory Committee, amici etc. This wide range of the responsibilities necessarily implies correspondingly higher measure of control over the parties, the subject matter and the procedure. Indeed as the relief is positive and implies affirmative action the decisions are not “one-shot” determinations but have ongoing implications. Remedy is both imposed, negotiated or quasi-negotiated.”
21. Dr. A.M. Singhvi also submitted a note which
essentially and substantially reiterates some of the
submissions made by Mr. Venugopal. It is not, therefore,
necessary to repeat those submissions. He also referred to
Onkar Lal Bajaj v. Union of India7 to submit that in the 6 (1988) 4 SCC 226 7 (2003) 2 SCC 673
W.P. (Crl.) Nos.120 of 2012 etc. Page 16 of 27
Page 17
case of apparently tainted allotment of dealerships for
petroleum products, this Court felt the necessity of
appointing a Committee and therefore we should also
appoint a Committee of retired judges to examine each
individual case of coal block allotment.
22. Dr. Rajeev Dhavan, Senior Advocate appearing for
one of the interveners referred to Chingleput Bottlers v.
Majestic Bottling Company8 to emphasize the necessity
of applying the principles of natural justice before
cancelling the allotments made in favour of the allottees.
23. Other learned counsels more or less repeated and
reiterated the submissions made, with slight variations
and emphasis depending upon the facts of the case of
their respective clients, including State Governments.
24. In response to the submissions made by various
learned counsels, it was submitted by the learned Attorney
General that all the aspects mentioned above including
the economic implications or fall-out of the cancellation of
coal block allotments and the possible adverse impact that
it may have on other socio-economic factors have been
taken into consideration and it is only thereafter that the
affidavit has been filed by the Union of India, which has
8 AIR 1984 SC 1030
W.P. (Crl.) Nos.120 of 2012 etc. Page 17 of 27
Page 18
been explained by him in his opening address. In other
words, the Union of India is fully prepared to face the
consequences of the cancellation of all coal blocks, if need
be, and is desirous of moving forward.
25. The learned Attorney General vehemently opposed
the setting up of any committee as proposed by learned
counsels. He categorically and emphatically stated that
the Central Government has no difficulty in taking matters
forward consequent upon the cancellation of the coal
blocks.
26. Learned counsels for the allottees have essentially
raised two contentions. Firstly, the principles of natural
justice require that they must be heard before their coal
block allotments are cancelled. Secondly, we should
appoint a committee to consider each individual case to
determine whether the coal block allotments should be
cancelled or not.
27. As far as the second contention is concerned, this is
strongly opposed by the learned Attorney General and we
think he is right in doing so. The judgment did not deal
with any individual case. It dealt only with the process of
allotment of coal blocks and found it to be illegal and
arbitrary. The process of allotment cannot be reopened
W.P. (Crl.) Nos.120 of 2012 etc. Page 18 of 27
Page 19
collaterally through the appointment of a committee. This
would virtually amount to nullifying the judgment. The
process is a continuous thread that runs through all the
allotments. Since it was fatally flawed, the beneficiaries of
the flawed process must suffer the consequences thereof
and the appointment of a committee would really amount
to permitting a body to examine the correctness of the
judgment. This is clearly impermissible.
28. It is true that this Court has taken the assistance of
one committee or the other in several cases but that was
where an inquiry was required to be conducted and this
Court was obviously not in a position to conduct any such
inquiry. This had happened, for example, in Onkar Lal
Bajaj. No such occasion or situation has arisen in the
present case to necessitate the appointment of a
committee. Therefore, the question of appointing a
committee simply does not arise.
29. The first contention relates to the applicability of the
principles of natural justice. As far as this is concerned, it
has specifically been recorded in the judgment (in
paragraph 11) to the following effect: “Three Associations, viz., Coal Producers Association, Sponge Iron Manufacturers Association and Independent Power Producers Association of India have made applications for their intervention stating that these associations represented large number of allottees who
W.P. (Crl.) Nos.120 of 2012 etc. Page 19 of 27
Page 20
have been allocated subject coal blocks. Accordingly, Mr. K.K. Venugopal, learned senior counsel was heard for Coal Producers Association and Mr. Harish N. Salve, learned senior counsel was heard on behalf of the Sponge Iron Manufacturers Association and Independent Power Producers Association of India. They commenced their arguments on 09.01.2014, which continued on 15.01.2014 and concluded on 16.01.2014.”
30. Therefore, it is incorrect to say that these
associations which represented the bulk (if not all) the
allottees or beneficiaries of coal blocks were not heard.
They presented their point of view, like any other party to
a lis and it was only then that judgment was delivered.
31. Similarly, several States were also heard as recorded
in paragraph 10 of the judgment. In this regard, it was
said: “The arguments re-commenced on 05.12.2013. On that day, arguments of the States of Jharkhand, Chhattisgarh and Odisha were concluded and matters were fixed for 08.01.2014. On 08.01.2014, the arguments on behalf of the States of Maharashtra, Andhra Pradesh, Madhya Pradesh and West Bengal were concluded and the matters were fixed for 09.01.2014. On that day, arguments of learned Attorney General were concluded.”
32. In effect, therefore, all parties likely to be adversely
affected were given a hearing. The principles of natural
justice, though universal, must be realistically and
pragmatically applied.
33. In Sheela Barse it was observed, and we endorse
that view, that the relief to be granted in a case always
W.P. (Crl.) Nos.120 of 2012 etc. Page 20 of 27
Page 21
looks to the future. It is generally corrective and in some
cases it is compensatory. The present case takes within its
fold all three elements mentioned in Sheela Barse. Our
judgment highlighted the illegality and arbitrariness in the
allotment of coal blocks and these “consequence
proceedings” are intended to correct the wrong done by
the Union of India; these proceedings look to the future in
that by highlighting the wrong, it is expected that the
Government will not deal with the natural resources that
belong to the country as if they belong to a few individuals
who can fritter them away at their sweet will; these
proceedings may also compensate the exchequer for the
loss caused to it, in the manner suggested by the learned
Attorney General, and which we now propose to consider.
34. There are two categories of coal block allotments:
the first category being allotments other than those
mentioned in Annexure 1 and Annexure 2; the second
category being the 46 coal blocks mentioned in Annexure
1 and Annexure 2 that could possibly be “saved” from
cancellation on certain terms and conditions, as submitted
by the learned Attorney General.
35. As far as the first category of coal block allotments
is concerned, they must be cancelled (except those
W.P. (Crl.) Nos.120 of 2012 etc. Page 21 of 27
Page 22
mentioned in the judgment). There is no reason to “save”
them from cancellation. The allocations are illegal and
arbitrary; the allottees have not yet entered into any
mining lease and they have not yet commenced
production. Whether they are 95% ready or 92% ready or
90% ready for production (as argued by some learned
counsel) is wholly irrelevant. Their allocation was illegal
and arbitrary, as already held, and therefore we quash all
these allotments.
36. Learned Attorney General identified 46 coal blocks
that could be “saved” from the guillotine, since all of them
have commenced production or are on the verge of
commencing production. As these allocations are also
illegal and arbitrary they are also liable to be cancelled.
However, the allotment of three coal blocks in Annexure 1
is not disturbed and they are Moher and Moher Amroli
Extension allocated to Sasan Power Ltd. (UMPP) and Tasra
(allotted to Steel Authority of India Ltd. (SAIL), a Central
Government public sector undertaking not having any
joint venture).
As far the 6 coal blocks mentioned in Annexure 2 are
concerned, the allocatees have not yet commenced
production. They do not stand on a different or better
W.P. (Crl.) Nos.120 of 2012 etc. Page 22 of 27
Page 23
footing as far the consequences are concerned. These
allotments are also liable to be cancelled. The allocation of
the Pakri Barwadih coal block (allotted to National Thermal
Power Corporation (NTPC), being a Central Government
public sector undertaking not having any joint venture) is
not liable to be cancelled.
37. Except the above two allocations made to the UMPP
and the two allocations made to the Central Government
public sector undertaking not having any joint venture
mentioned above, all other allocations mentioned in
Annexure 1 and Annexure 2 are cancelled.
38. It was submitted by the learned Attorney General
that on the cancellation of the coal block allotments, CIL
would require some breathing time to manage its affairs.
The Central Government is keen to move ahead but some
time would be required to manage the emerging situation.
Similarly, breathing time is also required to be given to the
allottees to manage their affairs on the cancellation of the
coal blocks.
39. In view of the submissions made, although we have
quashed the allotment of 42 out of these 46 coal blocks,
we make it clear that the cancellation will take effect only
after six months from today, which is with effect from 31st
W.P. (Crl.) Nos.120 of 2012 etc. Page 23 of 27
Page 24
March, 2015. This period of six months is being given
since the learned Attorney General submitted that the
Central Government and CIL would need some time to
adjust to the changed situation and move forward. This
period will also give adequate time to the coal block
allottees to adjust and manage their affairs. That the CIL is
inefficient and incapable of accepting the challenge, as
submitted by learned counsel, is not an issue at all. The
Central Government is confident, as submitted by the
learned Attorney General, that the CIL can fill the void and
take things forward.
40. In addition to the request for deferment of
cancellation, we also accept the submission of the learned
Attorney General that the allottees of the coal blocks other
than those covered by the judgment and the four coal
blocks covered by this order must pay an amount of Rs.
295/- per metric ton of coal extracted as an additional
levy. This compensatory amount is based on the
assessment made by the CAG. It may well be that the cost
of extraction of coal from an underground mine has not
been taken into consideration by the CAG, but in matters
of this nature it is difficult to arrive at any mathematically
acceptable figure quantifying the loss sustained. The
W.P. (Crl.) Nos.120 of 2012 etc. Page 24 of 27
Page 25
estimated loss of Rs. 295/- per metric ton of coal is,
therefore, accepted for the purposes of these cases. The
compensatory payment on this basis should be made
within a period of three months and in any case on or
before 31st December, 2014. The coal extracted hereafter
till 31st March, 2015 will also attract the additional levy of
Rs. 295/- per metric ton.
41. It is made clear that the scrutiny by the CBI in
respect of the allotment of 12 coal blocks out of 46
identified by the learned Attorney General (and for that
matter against any other allottee) will continue and be
taken to its logical conclusion. Needless to say, the
observations and findings in this order shall have no
bearing on the pending investigations. …......…………………….CJI. ( R.M. Lodha )
….…………………………..J. ( Madan B. Lokur )
…….………………………..J. ( Kurian Joseph )
New Delhi; September 24, 2014
W.P. (Crl.) Nos.120 of 2012 etc. Page 25 of 27
Page 26
Annexure 1 Details of 40 coal blocks which have come into production
Sl. No.
Name of Coal Block Name of Allocatee Company
1. Gare Palma IV/4 Jayaswal Neco Ltd. 2. Chotia Prakash Industries Ltd. 3. Namchik Namphuk Arunachal Pradesh Mining
Corp. 4-5. GarePalma IV/2&3 JSPL 6. Belgaon Sunflag Iron &Steel Ltd. 7-12. Baranj I-IV, Kiloni and
Manoradeep Karnataka Power Corp. Ltd.
13. Kathautia Usha Martin Ltd. 14. Parbatpur Electrosteel Castings Ltd. 15. Gare Palma IV/7 RAPL
(Now Sarda Energy Ltd.) 16. Barjore WBPDCL 17. Tara (East) WBSEB 18. Tara (West) WBPDCL 19. Gare Palma IV/1 Jindal Power Ltd. 20. Sarshatali CESC 21. Talabira-I Hindalco Industries Ltd. 22-23. Gotitoria (East & West) BLA Industries 24. Gare Palma IV/5 Monnet Ispat Ltd. 25. Pachwara Central Punjab State Electricity
Board 26. Tasra Steel Authority of India Ltd. 27. Barjora North DVC 28. Marki Mangli-I B.S. Ispat 29-30. Marki Mangli-III Shree Virangana Iron & Steel
Ltd. Marki Mangli-II
31. Trans Damodar WBMTCDL 32-33. Moher & Moher Amlori
Extension Sasan Power Ltd.
34. Ardhagram Sova Ispat Ltd. & Jai Balaji Industries Ltd.
35-36. Parsa (east) & Kanta Basan RRVUN Ltd. 37-38. Gangaramchak &
Gangaramchak Bhadulia WBPDCL
39. Amelia North MPSMDC Ltd. 40. Pachwara North WBPDCL
W.P. (Crl.) Nos.120 of 2012 etc. Page 26 of 27
Page 27
Annexure 2
Details of Coal Blocks which are likely come into production during 2014-15
Sl.No . of block
Company Name Name of Coal Block
1. GVK Power (Govindwal Sahib) Tokisud North 2. DVC Khagra Joydev 3. Prism Cement Sial Ghogri 4. Jaiprakash Associates Ltd. Mandla North 5. MPSMCL Bicharpur 6. NTPC Pakri Barwadih
W.P. (Crl.) Nos.120 of 2012 etc. Page 27 of 27