M/S. SONELL CLOCKS AND GIFTS LTD. Vs THE NEW INDIA ASSURANCE CO. LTD.
Bench: HON'BLE THE CHIEF JUSTICE, HON'BLE MR. JUSTICE A.M. KHANWILKAR, HON'BLE DR. JUSTICE D.Y. CHANDRACHUD
Judgment by: HON'BLE MR. JUSTICE A.M. KHANWILKAR
Case number: C.A. No.-001217-001218 / 2017
Diary number: 40963 / 2016
Advocates: AJIT SHARMA Vs
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.1217-1218 OF 2017
M/s. Sonell Clocks and Gifts Ltd. ....Appellant(s)
:Versus:
The New India Assurance Co. Ltd. ....Respondent(s)
J U D G M E N T
A.M. Khanwilkar, J.
1. The appellant filed a complaint before the National
Consumer Disputes Redressal Commission, New Delhi being
Consumer Complaint No.20 of 2006, asserting that it had
taken an Insurance Policy from the respondent (Insurance
Company) for a period of one year from 19th July, 2004 to 18th
July, 2005, in respect of its building, plant and machinery at
plot No.70/3, B.K. Textile Compound, Dan Udyog Sangh Ltd.,
Piparia, Silvassa, Dadra Nagar, Haveli, for a sum assured of
2
Rs.2,87,00,000/- (Two Crore Eighty Seven Lakh Only) on
reinstatement value basis. Due to torrential rains and floods in
the entire area, the water gushed into the factory premises
causing damage to the machinery as well as raw material lying
therein. This event occurred on 4th August, 2004. Intimation of
the loss was given to the respondent after a gap of 3 months
25 days, on 30th November, 2004. Thereafter, the respondent
appointed a surveyor to assess the loss caused due to the
flooding of the factory premises. The surveyor after causing
inspection submitted its report to the respondent inter alia
stating that the claim was not payable on account of the
failure of the complainant to comply with the mandate of
Clause 6 of the general conditions of the policy. Acting upon
the said report, the respondent vide letter dated 18th February,
2005 conveyed rejection of the claim to the appellant on the
ground that neither the intimation of the loss had been given
to it immediately nor were the requisite particulars of the loss
conveyed within stipulated period. Thus, there was breach of
terms and conditions of Clause 6 of the general conditions of
the policy.
3
2. As a sequel, the appellant approached the Commission
for a declaration that the respondent was guilty of deficiency
in service as well as unfair trade practices. Additionally, to
direct the respondent to sanction the genuine claim of the
appellant and reimburse the loss caused to it due to the floods
to the tune of Rs.2,66,05,000/-(Two Crore Sixty Six Lakh Five
Thousand Only) with interest at the rate of 21% per annum
from the date of incident till realization of the same. The
appellant also prayed for compensation amount of
Rs.5,00,000/- (Five Lakh Only) towards mental agony and cost
and further an amount of Rs.1,00,000/- (One Lakh Only)
towards incidental expenses.
3. The complaint was opposed by the respondent on the
ground that there was gross violation of the terms and
conditions of the policy as no intimation muchless immediate
information about the loss was given to the Insurance
Company nor was a claim lodged with the requisite particulars
within the time stipulated in the policy.
4
4. This objection commended to the Commission as a result
of which, the complaint filed by the appellant came to be
dismissed by the judgment and order dated 10th December,
2015 on the following terms:
“5. It would thus be seen that as per the terms and
conditions of the policy taken by it, there were three obligations on the complainant/insured. The first obligation
was to give notice of the loss to the insurer, immediately on the said loss taking place. The second obligation on the complainant was to submit a claim for the loss or damage,
giving all necessary particulars of the loss, within a period of 15 days or such other time as the insurer might allow. The third obligation on the insured was to intimate the insurer,
within six months of the date of the loss, that it intended to replace or reinstate the property which had been destroyed
or damaged. 6. It is not in dispute that the alleged loss despite having occurred on 04.08.2004 was reported to the Insurance
Company only on 30.11.2004. Thus neither immediate intimation of the loss was given to the Insurance Company
nor was a claim lodged with the requisite particulars within the time stipulated in the policy. The complainant Company, therefore, contravened clause 6 of the insurance policy taken
by it on account of the above referred two defaults. 7. It is contended by the learned counsel for the complainant that the requirement of intimating the insurer
and submitting a claim within 15 days of the loss stands superseded by clause 4(3) applicable to reinstatement value
policies, which required the requisite intimation to be given within six months of the date of loss. I, however, find no merit in the contention. The obligation of the insured under
clause 4(3) applicable to reinstatement value policies was independent of the obligation placed upon it under clause 3
of the said policy. Under clause 3 of the policy, the insurer was to be informed immediately on happening of the loss followed by lodging of the claim with necessary particulars
within 15 days of the loss or within such further time as
5
should be extended by the insurer, whereas under clause 4(3), which was applicable to reinstatement value policies, it
has to express its intention to replace or reinstate the property which had been destroyed or damaged. There is no
question of any supersession of clause 6 of the policy by clause 4(3), applicable to reinstatement value policies, the reinstatement of these clauses being distinct and separate
from each other. 8. For the reasons stated hereinabove, I have no hesitation in holding that the complainant committed breach
of clause 6 of the insurance policy, and therefore as stipulated in the said clause, no claim under the policy is
payable. The complaint is, therefore, dismissed with no order as to costs.”
5. The aforementioned decision was assailed before this
Court by way of Civil Appeal No……..(D.No.6048 of 2016).
This Court vide order dated 26th February, 2016, relegated the
parties before the Commission by giving liberty to the
appellant to file a review petition before the Commission on
the singular contention of waiver of condition stipulated in
Clause No.6 by the respondent. The order reads thus:
“O R D E R Delay condoned.
Heard Mr. Jitendra Mohan Sharma, learned senior counsel for the appellant. It is submitted by the learned
counsel that the insurer has waived the condition relating to delay in intimation by appointing a surveyor. On a perusal of the order passed by the National
Consumer Disputes Redressal Commission (N.C.D.R.C.),
6
New Delhi, we do not find that the said issue was raised before the N.C.D.R.C.
In view of the aforesaid, we permit the appellant to file an application for review and put forth the issue of waiver
before the N.C.D.R.C. within a period of four weeks hence. The N.C.D.R.C. will entertain the application for review singularly on this score.
With the aforesaid observation, the appeal is disposed of.”
(emphasis supplied)
It is noticed that no liberty was given to the appellant to
challenge the judgment and order dated 10th December, 2015
passed by the Commission, in the event the review petition
was decided against the appellant.
6. Be that as it may, as per the liberty given by this Court
the appellant preferred a review petition before the
Commission bearing Review Petition No.662 of 2016. The
singular issue as to whether the respondent (insurer) had
waived the condition relating to delay in intimation by
appointing a surveyor was considered by the Commission. The
Commission adverted to the decision of this Court in Oriental
Insurance Co. Ltd. Versus Parvesh Chander Chadha1. It
then noticed the decision of the Commission in New India
1 MANU/SC/1343/2010 Civil Appeal No.6739 of 2010 dated 17th August, 2010
7
Assurance Company Ltd Versus Trilochan Jane2.
Additionally, the Commission adverted to the decision in State
of Punjab Versus Davinder Pal Singh Bhullar and Others3
and on analysing the factual matrix concluded that there was
nothing to indicate an intentional and conscious
relinquishment by the respondent (insurer) of its right to reject
the claim on account of the delayed intimation of the loss, by
appointing a surveyor to assess the loss claimed by the
insured (appellant). The Commission distinguished the
decision of this Court in Galada Power and
Telecommunication Ltd. Versus United India Insurance
Co. Ltd. and Another,4 which was profusely relied upon by
the appellant as not applicable to the facts of the present case.
At the end, the Commission also relied on the observation in
Reliance General Insurance Company Ltd. Versus Harleen
Kaur5.
2 First Appeal No.321 of 2005 dated 9th December, 2009 3 (2011) 14 SCC 770 4 (2016) 14 SCC 161 5 In Revision Petition No.2850 of 2015
8
7. The review petition filed by the appellant was accordingly
dismissed vide judgment and order dated 25th October, 2016.
Both the decisions of the Commission dated 25th October,
2016 in Review Application No.77 of 2016 and dated 10th
December, 2015 in Consumer Complaint No.20 of 2006 have
been assailed in the present appeals.
8. The appellant would contend that the issue is no more
res integra. For, this Court in Galada Power and
Telecommunication Ltd. (supra), while considering similar
contention has held that the insurer having appointed a
surveyor despite stipulation such as in Clause 6, waives its
right to advance the plea that the claim was not entertainable
because of the condition enumerated in duration clause was
not satisfied.
9. Per contra, the respondent would contend that the
dictum in the said decision is contextual and in the backdrop
of the factual matrix of that case. In other words, the issue of
waiver by the insurer has been answered against the insurer
not merely because of appointing a surveyor despite the
9
stipulation in the policy, but the Court at more than one place
while analysing the facts noted the additional circumstance
that the letter of repudiation sent by the insurer merely stated
that, the claim lodged by the insured was not falling under the
purview of the transit loss. The Court opined that the
appointment of a surveyor despite the stipulation in Clause 5
therein was a positive action taken by the insurer reinforcing
the finding of waiver of its right to advance the plea that the
claim was not entertainable because the condition enumerated
in duration clause was not satisfied.
10. We have heard Mr. Jitendra Mohan Sharma, learned
senior counsel for the appellant and Mr. Joy Basu, learned
senior counsel for the respondent.
11. The singular question involved in these appeals is
whether the respondent (insurer) had waived the condition
relating to delay in intimation, by appointing a surveyor.
12. It is well established position that waiver is an intentional
relinquishment of a right. It must involve conscious
10
abandonment of an existing legal right, advantage, benefit,
claim or privilege, which except for such a waiver, a party
could have enjoyed. It is an agreement not to assert a right.
To invoke the principle of waiver, the person who is said to
have waived must be fully informed as to his rights and with
full knowledge about the same, he intentionally abandons
them. [See para 41 of State of Punjab (supra)]. There must
be a specific plea of waiver, much less of abandonment of a
right by the opposite party.
13. We shall, therefore, first traverse through the pleadings
of the parties. The appellant has asserted that it was pointed
out to the respondent that the act of appointing surveyor by
the respondent was an implied consent of condoning the
delay. In case the respondent wanted to repudiate the
appellant‟s claim only on the technical ground of 15 days‟
delay, it should have done at the first instance and there was
no need to have appointed a surveyor thereafter.
14. The respondent while refuting the said assertion of the
appellant stated in the written version filed before the
11
Commission that the appellant was negligent in dealing with
its affairs, including in the matter of informing the respondent
forthwith about the claim after the loss or damage caused on
account of flooding as was essential as per condition No.6 of
the policy. Condition No.6 of the policy reads thus:
“6. (i) On the happening of any loss or damage the insured shall forthwith give notice thereof to the Company and shall
within 15 days after the loss or damage, or such further time as the Company may in writing allow in that behalf, deliver to the Company
…………………………….. No Claim under this policy shall be payable unless the terms
of this condition have been complied with.”
The respondent also urged that after the receipt of the claim
intimation from the Bank, it immediately appointed M/s.
Saran Engineers & Consultants to survey and assess the loss.
The surveyor after visiting the premises gave a detailed report
dated 29th December, 2004 including its recommendation that
the loss is not payable as per the policy (B) General
Conditions, Para 6. On the basis of that report and keeping in
mind the terms and conditions of the policy, the respondent
repudiated the claim in terms of policy condition No.6 and
intimated the repudiation of the claim to the appellant vide
12
letter dated 18th February, 2005. The respondent also asserted
that the true import of the letter of repudiation is a matter of
interpretation. In any case, the appointment of the surveyor
was necessary, otherwise the appellant would have
complained about the non-appointment of the surveyor. The
respondent urged that the appellant was in breach of the
policy condition.
15. The Commission considered the pleadings of the parties
and including condition No.6 of the Insurance Policy, the
repudiation letter dated 18th February, 2005 and the
Surveyor‟s Report which had recommended that the loss as
such is not payable as per the Policy. The Commission then
went on to distinguish the decision in Galada Power and
Telecommunication’s case, (supra).
16. In the said case, the issue of waiver was decided on the
facts of that case as is evinced from the dictum in paragraphs
18-20 of the said decision. The same reads thus:
13
“18. In the instant case, the insurer was in custody of the policy. It had prescribed the clause relating to
duration. It was very much aware about the stipulation made in Clauses 5(3) to 5(5), but despite the stipulations
therein, it appointed a surveyor. Additionally, as has been stated earlier, in the letter of repudiation, it only stated that the claim lodged by the insured was not
falling under the purview of transit loss. Thus, by positive action, the insurer has waived its right to advance the plea that the claim was not entertainable
because conditions enumerated in duration clause were not satisfied. In our considered opinion, the National
Commission could not have placed reliance on the said terms to come to the conclusion that there was no policy cover in existence and that the risks stood not covered after
delivery of goods to the consignee.
19. Coming to the merits of the claim, we find that the surveyor had given a report that there was a loss. He had
also quantified it. The State Commission after elaborate discussion has held as follows:
„The surveyor also confirmed in their reports, the shortage/loss of AAAC due to pilferage during transit and
estimated the loss as per Ext. A-12. This shortage was also confirmed by Katigorah Police as per Ext. A-13 and as
reiterated earlier by the Takeover Certificate, Ext. A-19. Taking into consideration that the surveyors appointed by the insurance company have completed their investigation
and submitted their reports and thereafter an investigator was appointed on 16-4-1998 without any valid reasons. It is held by the National Commission in Gammon India Ltd. v. New India Assurance Co. Ltd. that: (CPJ p. 10)
„… Report of first Surveyor not accepted, second Surveyor appointed — Appointment of second Surveyor not explained
— Deficiency in service proved — Report of first Surveyor upheld.…‟
and the investigator in the instant case submitted his report on 28-12-1998 i.e. almost 8 months after his appointment. Taking into consideration all the above submissions, we are of the considered opinion that the appellant complainant
was able to establish that there was shortage/damage to the consignment which was given to the second respondent for
transportation.‟
14
20. Though the said aspect has not been gone into by the National Commission, yet we find, the findings recorded by
the State Commission are absolutely justified and tenable in law being based on materials brought on record, in such a
situation we do not think it appropriate that an exercise of remit should be carried out asking the National Commission to have a further look at it. In any case, the
exercise of revisional jurisdiction by the National Commission is a limited one. We may hasten to add that to satisfy ourselves, we have perused the surveyor’s report
and scrutinised the judgment and order passed by the State Commission in this regard and we are completely
satisfied that the determination made by it is absolutely impeccable.”
(emphasis supplied)
17. In the present case, it is common ground that the letter
of repudiation dated 18th February, 2005 elucidates that the
claim of the appellant was rejected on the ground that neither
the intimation of the loss had been given to it immediately
after the loss nor were the requisite particulars of the loss
conveyed within stipulated period and there was breach of
terms and conditions of Clause 6 of the general conditions of
the policy. Additionally, the surveyor report predicates that it
was very difficult to estimate the damages for the reasons
mentioned therein and that the claim of the appellant was not
payable on account of breach of Clause 6 of the general
conditions of the policy. That recommendation commended to
15
the respondent. It has been so incorporated in the letter of
repudiation dated 18th February, 2005.
18. The respondent has rightly pointed out the other
distinguishing features in the present case. To wit, in that case
[Galada (supra)], the Court had considered Clause 5 of a
Marine Insurance Policy wherein the issue was whether the
insurance cover itself had extinguished by efflux of time and
that the intimation given by the insured to the insurer was not
made within 7 days of arrival of the vehicle at the destination
mentioned in the policy. According to the insurer, on expiry of
7 days from delivery the insurance cover stood perished and
no cover would subsist beyond the said 7 days period. It is in
that context, the Court noted that appointment of the surveyor
by the insurer beyond the said period can be construed as an
act of waiver by the insurer of the position that the policy
stands extinguished. In other words, appointment of a
surveyor by the insurer was interpreted as a manifestation of
the stand of the insurer that the insurance cover still subsists.
This is evident from the dictum in paragraph 13 of the
16
reported decision as the Court noted that once a surveyor was
nominated to verify the loss, the insurer could not be allowed
to take a stand that the claim is hit by the clause pertaining to
duration and moreso because of absence of any mention in the
letter of repudiation. Thus, it went on to hold that from the
positive conduct of the insurer in unequivocally appointing a
surveyor, the insurer had waived the right which was in its
favour under the duration clause.
19. The expression “duration” is of some significance which
is reflective of the existence or otherwise of the policy itself. In
the present case, there is no dispute about the subsistence of
the policy but is one of violation of condition No.6 of the policy.
Furthermore, in the present case the controversy will have to
be answered on the basis of Standard Fire and Special Perils
Policy relatable to condition No.6 obligating the insured to give
forthwith intimation of the loss to the insurer. The two clauses
are materially different and relate to two different and distinct
insurance policies. In other words, Clause 5 of the Marine
17
Insurance Policy and Clause 6 of the present policy are
incomparable being qualitatively different.
20. To put it differently, Galada’s case (supra) was not a case
which considered repudiation based on a premise or a reason
similar to condition No.6 of the present policy and a specific
plea taken by the insurer in that behalf in the repudiation
letter itself. Notably, Clause 5 of the Marine Insurance Policy
which was the subject matter in Galada’s case (supra) did not
have a negative covenant as in this case in the proviso to
condition No.6 of the subject policy. The fulfillment of the
stipulation in Clause 6 of the general conditions of the policy
is the sine qua non to maintain a valid claim under the policy.
21. We, therefore, agree with the respondent that the dictum
in Galada’s case (supra) is in the context of the facts of that
case and does not lay down that on the appointment of a
surveyor, per se, the insurer is estopped from raising a plea of
violation of the condition warranting a repudiation of the
claim. The factum of waiver has to be gathered from the
totality of the obtaining circumstances.
18
22. Suffice it to observe that Galada’s case (supra) will be of
no avail to the facts and circumstances of the present case. In
that, the event occurred on 4th August, 2004 but intimation
was given to the insurer only on 30th November, 2004 after a
gap of around 3 months 25 days. No explanation was offered
for such a long gap muchless plausible and satisfactory
explanation. The stipulation in condition No.6 of the policy to
forthwith give notice to the insurer is to facilitate the insurer
to make a meaningful investigation into the cause of damage
and nature of loss, if any. This Court in Parvesh Chander
Chadha (supra) has held that it is the duty of insured to
inform the loss forthwith after the incident.
23. The respondent has also invited our attention to the fact
that in Galada’s case (supra), this Court has had no occasion
to consider the efficacy of Insurance Surveyors and Loss
Assessors (Licensing, Professional Requirements and Code of
Conduct) Regulations, 2000, which came into effect from 14th
November, 2000. For, the claim in Galada’s case (supra) arose
in 1998 and the repudiation took place in 1999. By virtue of
19
the regulations, it is mandatory to appoint a surveyor on
receipt of intimation about the loss; and the surveyor so
appointed has to discharge his responsibilities and duties
specified in the regulations while submitting its report.
24. Thus, the appointment of a surveyor by the respondent
after receipt of intimation of the loss from the appellant, in the
context of the present insurance policy, coupled with the 2000
Regulations and in particular an express stand taken in the
repudiation letter dated 18th February, 2005 sent by the
respondent to the appellant after consideration of the
surveyor‟s report, it cannot be construed to be a case of waiver
on the part of the respondent.
25. The appellant would then contend that the respondent
did not take a plea that the surveyor was appointed because of
statutory obligation. Such a plea is raised for the first time
before this Court. Even this submission does not commend us.
For, that plea has been taken as an additional factor to
distinguish the decision in Galada’s case (supra). The party is
not expected to state the provisions of law in its pleading. The
20
fact that such obligation flows from the regulation, in that
sense, is a mixed question of fact and law. The fact remains
that the respondent had appointed a surveyor to enquire into
the entire matter and submit its report. The surveyor expressly
recommended that the claim was not payable on account of
the infringement of Clause 6 of the general conditions of the
policy.
26. We also find no merit in the grievance made by the
appellant that the Commission did not consider the issue of
waiver for which the appellant was granted liberty to file
review petition by this Court. We say so because we find that
the Commission considered the said issue as the singular
issue and after analysing relevant aspects concluded that
there was nothing to indicate that the respondent insurer had
intentionally or consciously relinquished or waived its right to
reject the claim on delayed intimation of loss, by appointing a
surveyor to assess the loss claimed by the insured. For the
above reasons, the argument that the Commission has not
21
analysed the said issue, as has been done by us, will make no
difference to the conclusion recorded by it.
27. The appellant has also placed reliance on the decision in
Om Prakash Versus Reliance General Insurance and
Another,6 to contend that the genuine claim of the appellant
ought not to be rejected on technical ground, keeping in mind
that the Consumer Protection Act is a beneficial legislation
warranting liberal construction. That contention cannot be
taken forward at the instance of the appellant who has failed
to fulfill the threshold stipulation contained in Clause 6 of the
general conditions of the policy and for which reason must
suffer the consequence. It is not a technical matter but sine
qua non for a valid claim to be pursued by the insured, as
agreed upon between the parties.
28. In view of the above, we uphold the conclusion of the
Commission that the respondent (insurer) had not waived the
condition relating to delay stipulated in Clause 6 of the general
6 (2017) 9 SCC 724
22
conditions of the policy, by appointing a surveyor. Accordingly,
these appeals must fail.
29. The appeals are dismissed with no order as to costs.
.………………………….CJI.
(Dipak Misra)
…………………………..….J. (A.M. Khanwilkar)
…………………………..….J. (Dr. D.Y. Chandrachud)
New Delhi;
August 21, 2018.