M/S SHINHAN APEX CORPORATION Vs M/S EURO APEX B.V
Bench: FAKKIR MOHAMED IBRAHIM KALIFULLA,S.A. BOBDE
Case number: C.A. No.-004359-004360 / 2016
Diary number: 3025 / 2015
Advocates: LIZ MATHEW Vs
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 1
REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 4359-4360 OF 2016 [arising out of SLP(C) Nos.3134-3135 of 2015]
M/S. SHINHAN APEX CORPORATION …APPELLANT VERSUS
M/S. EURO APEX B.V. …RESPONDENT
J U D G M E N T
Fakkir Mohamed Ibrahim Kalifulla, J.
Leave granted.
1. These appeals are directed against the order
dated 29.9.2014 in Execution Application No.643 of
2013 in Award dated 23.12.2011 with Chamber
Summons No.832 of 2014.
2. To briefly note the facts, there was a Licence
Agreement between the appellant and the respondent
dated 22.2.1993 which provided for settlement of
disputes by way of arbitration in accordance with
1
Page 2
the Rules of the Dutch Arbitration Institute. The
said agreement was sought to be terminated by a
notice by the respondent on 12.3.2007. The
termination was to take effect from 23.02.2008.
The dispute went before the Arbitral Tribunal. On
11.6.2008, the appellant filed an application for
registration of Patent Nos.10-0865115 and
100909490 in the United States as well as in
India. In the arbitral proceedings, a Partial
Final Award (for short, PFA) came to be passed by
the Arbitral Trinunal on 23.12.2011. We are
presently concerned with the Indian Patents in
which the appellant's rights and interest were
involved, namely, Patent Nos. 2143/MUM/2008 and
2144/MUM/2008. The relevant part of the award
(viz) paragraphs 7 and 9, of the PFA reads as
under:-
“7. Respondent to, within 30 days following the notification of the arbitration award, unconditionally and irrevocably, fully transfer all rights
2
Page 3
and interests of Indian Patent No.2143/MUM/2008 and 2144/MUM/2008 to Claimant, or a company designated by Claimant, and sign/execute and submit, at the first request of Claimant, and within 3 days following such request, all the documents that are required to effect such patent rights and interests transfer in accordance with the requirements of the Indian Patent Act and applicable Indian laws; and to simultaneously provide copies of all the relevant correspondence relating to such transfer to the attorney of Claimant by fax and registered post (fax: +31-20-6513001, HIL International Lawyers & Advisers, PO Box 22678, 1100 DD Amsterdam, the Netherlands);
8. xxx xxx xxx 9. Respondent to pay a direct enforcement penalty in the amount of Euro 50,000 for each case in which Respondent infringes the arbitral orders sub 7 and 8 above, and Euro 5,000 for each day the infringement continues;”
3
Page 4
3. The Award dated 23.12.2011 was communicated to
the parties by the Arbitral Tribunal on
27.12.2011. Therefore, the period of thirty days,
fixed in paragraph 7, was to start from
27.12.2011.
4. Closely followed by that, the respondent
forwarded its request dated 19.1.2012 in the form
of a letter communicated by the Advocate of the
respondent to the appellant by enclosing the
required documents to be executed by the appellant
for the purpose of transfer of the patents. In
the opening paragraph of the draft transfer deed a
reference was made to PFA rendered on 23.12.2011
of CASE NAI 3625, in order to ascertain the
obligation of the appellant to execute the
transfer of the patents. It is not in dispute that
subsequent to the said letter dated 19.1.2012 and
the enclosures, discussions were held between
January and March, 2012 among the advocates of the
4
Page 5
appellant and the respondent to finalize the draft
deed of transfer.
5. Thereafter, again at the instance of the
respondent through a communication dated 3.4.2012
of the respondent's lawyers addressed to the
appellant a re-draft of the deed of transfer was
enclosed, which was dated 4.4.2012. In the opening
part of the said Deed, the reference to PFA, which
was mentioned in the earlier draft transfer deed,
was omitted. In other respects, the draft remained
the same which contained a clause under the
caption 'Consideration' to the effect, “Pursuant
to the above, the Parties agree that the
consideration for the sale and transfer of the
patent and the patent rights shall be US$ 1
(United States Dollar One), receipt of which is
hereby acknowledged”.
6. That apart, in clause 5.5 of the re-draft it
was mentioned that arbitration of the dispute
arising out of or in connection with the deed
5
Page 6
should be initially settled under the Rules of
Singapore International Arbitration Centre by a
Sole Arbitrator appointed in accordance with the
said Rules and the proceedings should be in
English and the seat of arbitration should be
Singapore. Insofar as the said clause was
concerned, the same was different than the one
which was contained in the earlier draft, as per
which the arbitration was to be carried out with
the Rules and provisions by Netherlands
Arbitration Institute and the venue of the
arbitration as Hague, The Netherlands and
governing law was also mentioned as the laws in
force in the Netherlands and the Courts at
Netherlands to have jurisdiction. In the draft
dated 4.4.2012 the governing law was to be the
laws in force in India.
7. The appellant received the re-draft by way of
e-mail on 3.4.2012 with a direction to the
appellant to sign the document, get it legalized
6
Page 7
by the Indian Embassy in Seoul and dispatch the
same to the respondent's lawyers in Amsterdam.
The appellant executed the deed of transfer dated
4.4.2012 and thereby transferred all its rights
and interests in the Indian Patents in favour of
the respondent. The appellant's lawyers sent an
electronic copy of the said document to the
respondent duly notarized with an assurance that
the original would be promptly couriered to the
respondent upon confirmation. In response to the
same, the lawyers of the respondent in their e-
mail dated 11.4.2012 intimated that the signature
part of the deed was correctly executed by the
appellant and also wanted the original deed to be
sent by courier to their Amsterdam Office for
carrying out other additional formalities for
effecting the transfer. Simultaneously, their
lawyers also on the same day informed the
respondent confirming the forwarding of the
transfer deed for effecting the transfer of the
7
Page 8
patent applications duly signed by the appellant.
The original document was also forwarded to the
lawyers of the respondent on 12.4.2012.
8. However, it appears that the respondent had
its own issue with its lawyers as regards the
draft as well as the final deed executed by the
appellant in favour of the respondent which came
to light when the present proceedings before the
High Court was launched by the respondent. The
same was reflected in the communication dated
12.4.2012 addressed by the representative of the
respondent to its lawyers. Thereafter, the next
communication was dated 3.12.2012 by the
respondent's lawyer addressed by way of an e-mail
to the appellant's lawyer suggesting that the
transaction can be by way of trade sale of the
appellant's business. On behalf of the appellant,
its lawyer sent a reply dated 11.12.2012 taking
the definite stand that after the execution of the
transfer deed dated 4.4.2012 the requirement of
8
Page 9
the obligation to be fulfilled by the appellant
was duly complied with as per the PFA dated
23.12.2011. Thereafter, by another communication
dated 15.3.2013, the respondent's lawyers sent a
fresh e-mail to the appellant's lawyers informing
that fresh steps are required to be taken to
arrive at a final settlement of disputes. The
said e-mail was also replied on behalf of the
appellant on 20.3.2013 wherein the respondent was
reminded as to the confirmation of the steps taken
based on the transfer deed executed by them. For
the first time, on 8.6.2013, by way of e-mail at
the instance of the respondent's lawyers it was
intimated that respondent was not willing to
accept the transfer of Indian Patents based on the
language used in the draft deed as signed by the
appellant. The said e-mail was also duly replied
on behalf of the appellant on 15.6.2013 pointing
out that the deed was executed as per the draft
forwarded to the respondent by their lawyers and
9
Page 10
consequently the appellant was not in any way
liable for either any delay or for the terms
contained in the transfer deed.
9. It was in the above-stated background the
present application came to be filed by the
respondent on 8.7.2013 before the High Court of
Bombay for the enforcement of paragraph 7 of the
PFA dated 23.12.2011. By the impugned order, the
learned Single Judge held that there was a
material alteration in the draft deed forwarded by
the respondent to the appellant when the final
deed was executed in the deed dated 4.4.2012 and
consequently, the appellant is bound to execute a
transfer deed of assignment as per the draft sent
by the award holder, namely, the respondent as was
originally forwarded to the appellant.
10. With that view, the learned Judge directed the
appellant to execute the deed of transfer and
assignment of Patent Nos. 2143/MUM/2008 and
2144/MUM/2008 in favour of the award holder in
10
Page 11
terms of Annexure P6 to the Execution Application
incorporating therein the complete recital 'B' and
the Arbitration Clause 5.5 showing the future
arbitration in Netherlands within two weeks from
the date of the order. Aggrieved by the impugned
order, the appellant is before us.
11. We heard Mr. K.V. Vishwanathan, learned senior
counsel appearing for the appellant and Mr. Manoj
K. Singh, learned counsel appearing for the
respondent.
12. Having drawn our attention to the above
factual details which emanated after the passing
of PFA dated 23.12.2011, Mr. Vishwanathan, learned
senior counsel, contended that when the
application was initially moved, the respondent
failed to bring to the notice of the Court about
the extensive correspondence which took place
between 19.1.2012 and 15.6.2013, that after the
appellant in its Chamber Summons brought to the
notice of the Court the relevant information,
11
Page 12
namely, the re-draft sent by the respondent on
3.4.2012 which contained the variation in para 'B'
as between the one contained in the earlier draft
of 19.1.2012 and 3.4.2012 as well as the
arbitration clause and the governing law contained
in paragraphs 5.5 and 5.6, the respondent for the
first time in their rejoinder referred to those
documents. The learned senior counsel pointed out
that learned Judge completely omitted to take note
of such relevant factors and proceeded to hold as
though the draft sent by the respondent on
19.1.2012 alone was material and that the changes
found in the final deed dated 4.4.2012 was at the
instance of the appellant which unfortunately led
to the passing of the impugned order.
13. In reply, Mr. Singh, learned counsel appearing
for the respondent, was not able to controvert the
factual position, namely, that the first request
of the respondent after the PFA dated 23.12.2011
was 19.1.2012, that along with the said
12
Page 13
communication the draft deed of transfer to be
executed by the appellant was forwarded to it,
that after detailed discussions between January
and March, 2012, the re-draft was forwarded by the
respondent on 3.4.2012 wherein the reference to
PFA in the opening paragraph of the earlier draft
was omitted and that the paragraphs relating to
consideration was specified apart from the change
about the venue and the applicable Rules of the
Arbitral Tribunal was noted as Singapore instead
of Netherlands and the governing law applicable
was also changed from Netherlands to India.
Learned counsel was also not able to controvert
any of the other subsequent correspondence
exchanged between the appellant and the respondent
between 11.4.2012 and 15.6.2013.
14. Having regard to the said development which
had taken place after the PFA dated 23.12.2011
which discloses that the appellant did not commit
any default in complying with the direction of the
13
Page 14
said Award and, therefore, the present direction
of the learned Judge in the impugned order was
wholly unwarranted. If the respondent failed to
act based on the final transfer deed executed by
the appellant on 4.4.4012, which was in tune with
the draft forwarded by the respondent themselves,
the appellant cannot be in any way blamed for the
misfeasance committed by the respondent.
15. In the above-stated background, when we
consider the prayer of the respondent as claimed
in the application, the prayer was for a direction
to the appellant to execute the deed of transfer
and assignment of Patent Nos. 2143/MUM/2008 and
2144/MUM/2008 in favour of the respondent in terms
of the draft deed in Annexure P6, which was dated
4.4.2012. In fact the learned Judge, as rightly
pointed out by Mr. Vishwanathan, learned senior
counsel for the appellant, completely missed to
note that based on the correspondence exchanged
between the respondent and the appellant between
14
Page 15
19.1.2012 and 3.4.2012 Annexure P6 which was dated
4.4.2012 was the ultimate transfer deed which the
appellant was obliged to execute, that the
appellant duly executed the said document by
signing the same on 4.4.2012 and forwarded to the
respondent's lawyers on 9.4.2012 and the due
execution of which was also confirmed on behalf of
the respondent by their lawyers on 11.4.2012. A
further confirmation was made by the respondent's
counsel to the respondent themselves on the same
day, i.e. 11.4.2012 as to the execution of the
transfer deed dated 4.4.2012. The original
documents were also forwarded by the appellant on
12.4.2012. After the above referred sequence of
events as regards Annexure P6 dated 4.4.2012 are
noted, it must be held that the direction
contained in paragraph 7 of the PFA of the
Arbitral Tribunal was duly carried out by the
appellant based on the first request of the
respondent themselves as made on 19.1.2012 and as
15
Page 16
per the modified request dated 3.4.2012. If that
was the real fact situation in regard to the
execution of the transfer deed, which was
completely omitted to be noted by the learned
Single Judge, it must be held that there was no
occasion for the respondent to have any grievance
in regard to the execution of the transfer deed as
directed in paragraph 7 of the PFA of the Arbitral
Tribunal dated 23.12.2011. The failure on the part
of the learned Judge in having noted the fact that
the transfer deed dated 4.4.2012 was as per the
re-draft forwarded by the respondent themselves
which was duly executed and sent back by the
appellant by 9.4.2012 and the original by
12.4.2012 unfortunately resulted in the passing of
the impugned order. In the light of the said
patent illegality in the impugned order, the same
is liable to be set aside.
16
Page 17
16. In the said circumstances, the impugned order
of the learned Judge cannot be sustained, the same
is set aside and the appeals stand allowed.
................................J. [Fakkir Mohamed Ibrahim Kalifulla]
................................J. [S.A. Bobde]
New Delhi; April 22, 2016
17