25 April 2014
Supreme Court
Download

M/S. SESA STERLITE LTD. Vs ORISSA ELECTRICITY REGULATORY COMM

Bench: SURINDER SINGH NIJJAR,A.K. SIKRI
Case number: C.A. No.-005479-005479 / 2013
Diary number: 19087 / 2013
Advocates: DIVYA ROY Vs


1

Page 1

Civil Appeal No.5479 of 2013

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 5479 of 2013

M/s. Sesa Sterlite Ltd.         ….Appellant(s)

Vs.

Orissa Electricity Regulatory  Comm. & Ors.            …

Respondent(s)

J U D G M E N T  

A.K. SIKRI, J.

1. Instant  is  a  statutory  Appeal  which  is  filed  by  the  

Appellant  under  Section  125  of  the  Electricity  Act,  2003  

(hereinafter referred to as ‘the Act’).  This Appeal arises out  

of the judgment and order dated 3rd May, 2013 passed by  

Appellate Tribunal for Electricity.

2. By the aforesaid judgment, the Appellate Tribunal has  

affirmed  the  orders  of  the  Odisha  Electricity  Regulatory  

Commission  (hereinafter  referred  to  as  the  ‘State  

Commission’).   The essence of  these orders  is  that  even  

1

2

Page 2

Civil Appeal No.5479 of 2013

when the Appellant is a “Deemed Distribution Licensee” for  

the purpose of Electricity Act, it is still liable to pay Cross  

Subsidy  Surcharge  (CSS)  to  the  Respondent  No.8  viz.  

WESCO  which  is  a  Distribution  Licensee  for  the  area  in  

question.

3. To put it in nutshell, the case of the Appellant is that it  

has  its  unit  in  Special  Economic  Zone  (SEZ)  and  it  is  a  

Developer in the said SEZ area.  It is not drawing or utilizing  

any electricity from the Distribution Licensee viz. WESCO for  

its  unit  namely  VALE-SEZ.   In  fact,  the  Appellant  had  

entered into a Power Purchase Agreement (PPA) dated 18th  

August, 2011 with M/s. Sterlite Energy Ltd.  The Appellant  

had filed application for getting approval of the said PPA.  

However the Odisha State Commission, instead of granting  

the  approval,  rejected  the  said  PPA  and  directed  the  

Appellant to pay CSS to WESCO holding the Appellant to be  

a ‘Consumer’.   

4. As  per  the  Appellant,  as  it  is  a  deemed  distribution  

licensee  for  the  purpose  of  Electricity  Act  by  virtue  of  it  

2

3

Page 3

Civil Appeal No.5479 of 2013

being a ‘Developer’ because of the reason that its unit is in  

SEZ area and such a recognition is given to the Appellant  

statutorily under the provisions of Special  Economic Zone  

Act, 2005 (hereinafter referred to as SEZ Act).  Therefore,  

the question of payment of CSS to the Distribution Licensee  

does not arise.  It is also the case of the Appellant that, in  

any case, since no electricity is being drawn from the open  

access network of WESCO, there is no question of making  

payment  of  cross  subsidy  surcharge.   This  is  the  brief  

description of  the dispute raised by the Appellant  and in  

order to understand the gravamen of this dispute, we take a  

tour of the factual roadmap.

The Facts:

5. These  facts  are  in  narrow  compass  and  have  been  

narrated succinctly by the Appellate Tribunal in its order.  As  

there is no dispute about the correctness of these facts, we  

intend  to  traverse  the  same  therefrom.  The  Appellant  is  

engaged  in  the  business  of  production  and  export  of  

aluminium.  The Appellant has set up a 1.25 MTPA capacity  

3

4

Page 4

Civil Appeal No.5479 of 2013

aluminium  smelter  project  in  a  sector  specific  Special  

Economic Zone.  After getting all  necessary approvals for  

the  development  of  SEZ  for  manufacture  of  export  of  

aluminium the appellant set up the aforesaid plant.  These  

approvals include the approval with captive power plant as  

well.   It  is  also a matter of record that on 27th February,  

2009 the Ministry of Commerce and Industry, Government  

of  India  issued  a  notification  declaring  the  unit  of  the  

Appellant to be SEZ.  It was followed by Notification dated  

3rd March, 2010 under Section 49(1) of the SEZ Act.  By the  

said notification, the Central Government of promoting the  

objects of Special Economic Zone and in terms of powers  

delegated under the Special Economic Zone Act, introduced  

a proviso to the provisions of Section 14(b) of the Electricity  

Act, 2003.  By the said introduction, a developer of a Special  

Economic  Zone  was  declared  as  a  deemed  licensee  

authorized  to  distribute  electricity  within  the  Special  

Economic zone area.  The effect of the aforesaid Notification  

under  section  14(b)  of  the  Electricity  Act  is  that  the  

Appellant became a deemed Distribution Licensee.   

4

5

Page 5

Civil Appeal No.5479 of 2013

6. It would be pertinent to mention at this stage that the  

units of the Appellant are divided into two broad areas.  One  

is Domestic Tariff Area (DTA) where it has established one  

of  its  unit.   Other  unit  is  VAL-SEZ  which  is  in  SEZ  

(hereinafter referred to as VAL-SEZ Unit).   In so far as its  

unit in DTA is concerned, it draws power from open access  

and duly phased pays cross subsidy surcharge for this area.  

There is no dispute to this extent.  In the present Appeal, we  

are concerned with VAL-SEZ which is in SEZ Area where the  

Appellant is stated as deemed Distribution Licensee for the  

purpose  of  Electricity  Act  by  virtue  of  Notification  under  

Section 14(b) of the Electricity Act.   

7. For supply of energy to this unit in SEZ Area (VAL-2),  

the Appellant entered into a PPA on 18th August, 2011 with  

Sterlite Energy Ltd. which was arrayed as Respondent No.4  

in the Appeal.  However during the pendency of the Appeal  

under the scheme of merger approved by the High Court,  

Sterlite stood merged with the Appellant itself and because  

of this reason the Respondent No.4 (hereinafter referred to  

5

6

Page 6

Civil Appeal No.5479 of 2013

as ‘Sterlite’) has been deleted from the array of parties at  

the instance of the Appellant.   

8. Since the supply of power by a Generating Company to  

Distribution Company is regulated under the provisions of  

Electricity  Act,  2003,  the  Appellant  on  30th August,  2011  

filed a petition before the State Commission for approval of  

the said PPA.  Subsequently, the State Commission at the  

preliminary hearing sought some clarifications with regard  

to the factual aspects.  The Appellant, thereafter filed two  

amendment petitions.  One was on 8th November, 2011 and  

another was on 27th March, 2012 seeking for the additional  

prayer requesting the State Commission to grant deemed  

distribution  licence  in  favour  of  the  Appellant  on  the  

strength  of  the  Government  of  India  notification  issued  

dated 3rd March, 2010 with effect from the date of the said  

notification.

9. As  already pointed  out  above,  the  State Commission  

rejected  this  application  for  grant  of  deemed Distribution  

Licensee  and  subsequently  rejected  the  prayer  of  the  

6

7

Page 7

Civil Appeal No.5479 of 2013

Appellant for approval of PPA also.  The State Commission,  

while doing so held as under:

“a.  Since the Application for grant of Distribution  License  was  rejected,  State  Commission  did  not  consider it necessary to go into the issues relating  to the PPA. b.   Consequent  upon  the  rejection  of  the  Application for grant of Distribution License, State  Commission held that VAL is  to be treated as a  consumer of WESCO. c.   As  a  result,  VAL  has  to  pay  cross  subsidy  surcharge  to  WESCO for  open  access  drawal  of  power from SEL.”

10. This Order of the State Commission has been upheld by  

the Appellate Tribunal in Appeal filed by the Appellant.

Question of Law:

11. In  the  present  Appeal,  the  Appellant  has  raised  

following  question  of  law  which  the  Appellant  recall  this  

Court to determine an answer:

“Whether  a  developer  of  a  notified  Special  Economic Zone, who has been deemed by law to  be  a  licensee  for  distribution  of  electricity,  is  required  to,  once  again,  apply  to  Electricity  Regulatory  Commission  under  the  Electricity  Act  for grant of a licence or the deeming fiction carved  out  in  Section  14  of  the  Electricity  Act  

7

8

Page 8

Civil Appeal No.5479 of 2013

automatically dispenses with this requirement and  ipso facto makes such SEZ developer a distribution  licensee.”

The Arguments: Appellant

12. Mr.  Shyam Diwan,  Learned Senior  Counsel  appearing  

for  the  Appellant,  with  full  of  passion  and  vehemence  

argued that all the three findings of the State Commission,  

which  are upheld  by the  Appellate  Tribunal,  are  ex facie  

untenable in law.  Questioning the first aspect of the order  

of the authorities below refusing to register the said PPA, his  

plea was that since the PPA is a contract between the two  

parties,  the  State  Commission  could  not  have refused  to  

consider the same.  Such outright refusal amounts to failure  

to discharge the function enjoined by the Parliament on the  

State Commission under Section 86(b) of the Act.   Under  

this  provision,  the  State  Commission  has  to  regulate  

electricity purchase and procurement process of distribution  

licensee  including  the  price  at  which  electricity  shall  be  

procured from the generating company.  Thus it was duty  

bound to approve a PPA subject to the terms and conditions  

8

9

Page 9

Civil Appeal No.5479 of 2013

which it deems fit in law and only when the parties fail to  

comply with those terms of the license that such license can  

be revoked.  The failure to not look into a PPA altogether  

amounts to non exercise of jurisdiction.

13.  In so far as the opinion of the Appellate Authority that  

the Appellant is to be treated as a consumer of WESCO is  

concerned, Mr. Diwan placed heavy reliance on the proviso  

to Section 14(b) of the Act as per which developer of the  

notified SEZ itself becomes deemed Licensee from the date  

of such notification.  He thus argued that when there was a  

specific  notification  under  that  proviso  declaring  the  

Appellant  as  a  developer,  the  Appellant  was  a  deemed  

Licensee  and  therefore  there  could  not  have  any  

requirement for the Appellant to obtain the license under  

the Electricity Act.  As a fortiorari,  such a developer cannot  

be  treated  as  a  ‘consumer’.   Therefore,  the  authorities  

below could not, in law, hold the Appellant to be a consumer  

of WESCO.   

9

10

Page 10

Civil Appeal No.5479 of 2013

In the alternative, it was argued that in any case, the  

Appellant was purchasing the electricity from Sterlite under  

the PPA and, therefore, by no stretch of imagination, it could  

be  treated  as  consumer  of  WESCO.   To  buttress  this  

submission, Mr. Diwan referred to the provisions of Section  

2(15)  of  the  Electricity  Act  which  defines  the  term  

“consumer”  and  submitted  that  in  order  to  treat  the  

Appellant as a consumer, it was necessary to establish that  

it is supplied with the electricity by such “Licensee” or the  

“government” or “any other person engaged in the business  

of supplying electricity to the public”.

14. In so far as the third finding holding the Appellant liable  

to pay CSS to WESCO for open access drawal of power from  

SEZ is  concerned,  the  submission  of  Mr.  Diwan was  that  

there was no occasion for the State Commission (or for that  

matter Appellate Tribunal) to go into the aspect of CSS in an  

application filed by the Appellant initially for approval of PPA  

only which was later amended on the directions of the State  

Commission  to  include  a  prayer  to  the  extent  that  the  

Appellant should be recognized as a Distribution Licensee  10

11

Page 11

Civil Appeal No.5479 of 2013

under Section 14(b) of the Electricity Act.  It was submitted  

that even in the amended application there was no issue of  

CSS and the authorities below exceeded their jurisdiction in  

going into this issue and giving such a direction.   

Without  prejudice  to  the  aforesaid  preliminary  

submission, Mr. Diwan argued that even on merits that such  

a decision was palpably contrary to law.  In this behalf his  

submission  was  that  since  under  Section  42  of  the  

Electricity Act, 2003, cross subsidy surcharge is payable to  

the Distribution Licensee of the area of supply only when  

the  “distribution  system”  of  such  Distribution  Licensee  is  

“used” for supply of electricity.  Therefore, without a clear  

finding of fact on appreciation of evidence, that the supply-

line of SEL-VAL is connected to WESCO and that WESCO’s  

“distribution  system”  is  “used”  for  supply  of  electricity,  

State Commission could not have held that VAL has to pay  

cross subsidy surcharge to WESCO for open access drawal  

of power from SEL.

11

12

Page 12

Civil Appeal No.5479 of 2013

In this context, the attention of the Court was drawn to  

the National Tariff Policy dated 6th January, 2014, Clause 8.5,  

Orissa  Electricity  Regulatory  Commission  (Terms  and  

Conditions  for  Open  access  Charges)  Regulations,  2005  

(Clause  13(1)(ii)]  and  to  Orissa  Electricity  Regulatory  

Commission  (Determination  of  Open  access  Charges)  

Regulations, 2006 [Clause 2(j).  It was submitted that from a  

bare perusal of the relevant Clauses of these Regulations, it  

is clear that CSS can be levied on “open access customers”  

i.e. “a consumer who has availed of or intends to avail  of  

open access”.

In addition to the aforesaid submission, questioning the  

correctness  of  the  each  of  the  findings  of  the  State  

Commission  and  the  Appellate  Tribunal,  Mr.  Diwan  

emphasized that it is to be kept in mind in deciding the issue  

that VAL SEZ is a Deemed Distribution Licensee by operation  

of law and it need not be a Distribution Licensee within the  

meaning of Section 2(17) of the Electricity Act,  2003.  He  

admitted that a contention of the Respondents that VAL SEZ  

does  not  qualify  as  a  Distribution  Licensee  within  the  12

13

Page 13

Civil Appeal No.5479 of 2013

meaning  of  Section  2(17)  of  the  Electricity  Act,  2003  is  

misplaced since accepting such contention would defeat the  

very purpose of the deeming fiction created by the statute.  

The deeming fiction would have no relevance if the reality  

which the statute creates by way of fiction already existed.  

He argued that none of the five provisos to Section 14 of the  

Electricity  Act,  2003  require  the  deemed  distribution  

licensees mentioned therein to obtain a license under the  

Electricity Act.  The Developer of a notified SEZ is a special  

entity  under  a  special  legislation  and  the  definition  of  

“consumer” or “distribution licensee” etc. as defined under  

the Electricity Act, 2003 cannot be made applicable.   

It  is  crucial  point  that  the  SEZ  Act  conceptually  

envisages “Developer” of an SEZ distinct from the “Zone”  

itself as also distinct from “Unit”.  Developer is defined under  

Section 2(g) of the SEZ Act whereas Special Economic Zone  

is  defined  under  Section  (za)  of  the  SEZ  Act  and  Unit  is  

defined  under  Section  2(zc)  of  the  SEZ  Act.   Thus  the  

Appellant in its capacity as the Developer of the SEZ has the  

duty to develop, operate and maintain the Zone.  Failing the  13

14

Page 14

Civil Appeal No.5479 of 2013

reconciliation between the provisions of the Electricity Act,  

2003 and the SEZ Act, the provisions, objects and purpose of  

the SEZ Act will  prevail  (Section 51 of the SEZ Act).   The  

object and purpose of the SEZ Act, inter alia, is to provide an  

internationally for export production, expeditious and single  

window approval mechanism and a package of incentives to  

attract  foreign  and  domestic  investments  for  promoting  

export-led growth.

The Arguments: Respondents

15. Mr. R.K. Mehta, Learned Counsel appearing on behalf of  

GRIDCO Ltd. refuted the aforesaid submissions of Mr. Diwan.  

His main argument was that even though the Appellant was  

possessed  of  notification  issued  under  Proviso  to  Section  

14(b) of the Electricity Act, which treats the Appellant as of  

Deemed Distribution Licensee,  the concept of  Distribution  

Licensee  under  the  Electricity  Act  pre-supposes  

supply/distribution of  power.   An entity  which utilizes  the  

entire quantum of electricity for its own consumption and  

does not have any other consumers cannot be deemed to  

14

15

Page 15

Civil Appeal No.5479 of 2013

be  a  Distribution  Licensee,  even  by  a  legal  fiction.   In  

support of this submission, the Learned Counsel referred to  

the definitions of “consumer” in Section 2(15), “Distribution  

Licensee”  as  contained  in  Section  2(17)  and  “supply”  in  

relation to electricity to the consumers in Section 2(70).  He  

also referred to Section 42 of the Act which spells out the  

duties  of  Distribution  Licensee  and  open  access.   His  

submission,  thus,  was  that  by  virtue  of  the  legal  fiction  

created by the Notification dated 3rd March, 2010, a person  

who  distributes  Electricity  can  be  deemed  to  be  a  

distribution  licensee  even  though  he  does  not  have  a  

distribution license – But the legal fiction cannot go further  

and make a person who does not distribute electricity as a  

distribution licensee.

16. He  also  argued  that  if  a  ‘Distribution  Licensee’  is  

equated with  ‘Consumer’  the provisions  of  Section 2(15),  

2(17),  42  and  43  of  the  Electricity  Act,  2003  would  be  

rendered otiose and nugatory.  The mandate of Section 42  

and 43 of the Electricity Act, 2003 cannot be negated by  

exercise of power under Section 49(1)(b) of the SEZ Act.  It  15

16

Page 16

Civil Appeal No.5479 of 2013

was further submitted that only a proviso has been added to  

Section 14(b) by Notification dated 3rd March, 2010 qua the  

Appellant.  There  is  no  stipulation  in  the  Notification  that  

other provisions of the Electricity Act will not apply to the  

Developer of a SEZ.

17. Mr.  Mehta  called  for  harmonious  construction  of  the  

provisions  of  SEZ  and  the  Electricity  Act  to  support  his  

submission  that  the  legal  fiction  of  deemed  Distribution  

Licensee cannot be taken to the level of absurdity and made  

applicable even when it does not involve distribution/supply  

of  power  at  all.   He  further  pointed  out  the  object  and  

scheme of SEZ Act envisages several units being set up in a  

SEZ.  This is evident from a collective reading of the various  

provisions of the SEZ Act viz. Section 2(g)(j)(za)(zc), Section  

3, 4, 11, 12, 13 and 15.  There can be a Sector Specific SEZ  

with Several Units i.e. for IT, Mineral Based Industries etc.  

but instances of single unit SEZ like in the present case of  

the appellant may be rare.  The Notification dated 3rd March,  

2010  providing  for  the   “Developer”  of  an  SEZ  being  

deemed as a “Distribution Licensee” was issued keeping in  16

17

Page 17

Civil Appeal No.5479 of 2013

view the concept of Multi Unit SEZs and will apply only to  

such cases in which the Developer is supplying the power to  

multiple  Units  in  the  SEZ.   The  said  Notification  will  not  

apply to a Developer like the Appellant who has established  

the SEZ only for itself.   

18. Mr. Parag P. Tripathi, Learned Senior Counsel appeared  

with Mr.  Shiv Kumar Suri,  Advocate on behalf  of  WESCO.  

His submission was that in the facts of present case WESCO  

was  entitled  to  CSS  on  the  electricity  purchase  by  the  

Appellant  from  Sterlite  which  was  consumed  wholly  and  

completely by the Appellant itself.  It was pointed out that  

surcharge  was  meant  to  compensate  a  Distribution  

Licensing from the loss of cross subsidy surcharge that such  

distribution licensee would suffer by reason of the consumer  

taking supply  from someone other  than such Distribution  

Licensee,  the  moment  it  is  found  that  the  Appellant  is  

covered by the Definition of a consumer within the meaning  

of  Section  2(15)  of  the  Act.   He  argued  that  in  such  a  

situation the mere fact that the Appellants claims to be a  

deemed Distribution Licensee is  of no consequence at  all  17

18

Page 18

Civil Appeal No.5479 of 2013

since the entire power purchase by the Appellant is for its  

own  use  or  consumer  and  not  for  the  purpose  of  

Distribution.  The Appellant, therefore, could be categorized  

as a consumer as regards its own consumption even if it is a  

deemed  Licensee.   On  merits,  it  was  submitted  that  

Transmission  line  between  the  Generating  Company  

(Sterlite) and the Appellant is not a Dedicated Transmission  

Line,  with  an  attempt  to  justify  it  giving  various  reasons  

which we shall advert to all a later stage.

19. It  was  also  argued that  as  per  Regulation  27 of  the  

OERC  (Conditions  of  supply  Code)  Regulations  2004,  the  

“service line” shall  be the property of the licensee unless  

otherwise specified in writing.  Hence the line between the  

grid  sub-station  and  the  Appellant’s  SEZ  qualify  as  the  

property of WESCO and therefore any use of such line could  

only be by Open Access under the EA and in any event CSS  

would be payable.  Reference was also made to the Rule 4  

of the Electricity Rules,  2005, as per which aforesaid line  

would  be  deemed  as  part  of  the  Distribution  System  of  

WESCO.  On that basis submission of Mr. Tripathi was that  18

19

Page 19

Civil Appeal No.5479 of 2013

from any angle the matter is to be looked into the orders of  

the Appellate Tribunal was perfectly justified.

Our Analysis:

20. From  the  aforesaid  narration  of  events  as  well  as  

arguments  of  the  counsel  for  the  parties,  it  has  become  

manifest the primary dispute relates to the CSS which the  

Appellant  is  called  upon  to  pay  to  WESCO.   As  per  the  

Appellant no such CSS is payable and the PPA which was  

submitted  by  the  Appellant  to  the  State  Commission  for  

approval, should have been accorded due approval by the  

State Commission.   

(1) Special Feature of the 2003 Act

21. Before adverting to this central issue, it would be apt to  

understand conceptually the rationale of payment of such  

CSS to the Distribution Company, under the scheme of the  

Electricity  Act.   The  first  enactment  to  govern  electricity  

supply  in  India  was  passed  in  the  year  1910  viz.  the  

Electricity  Act,  1910.   This  Act  envisaged  growth  of  

electricity industry through private licences.  It created the  

19

20

Page 20

Civil Appeal No.5479 of 2013

legal framework for laying down of wires and other works  

relating  to  the  supply  of  electricity.   Thereafter,  the  

Electricity (Supply)  Act,  1948 mandated the creation of a  

State  Electricity  Board.   The  Board  assigned  the  

responsibility  of  arranging the supply  of  electricity  in  the  

State.  It  was experienced that over a period of time the  

performance of State Electricity Boards had deteriorated on  

account of various factors.  Main failure on the part of these  

Electricity  Boards  was  to  take  decision  on  tariffs  in  

independent  manner  and  cross  subsidies  had  reached  

untenable levels.  To address this issue and also to distance  

governance  from  determination  of  tariffs,  the  Electricity  

Regulation Commission Act was enacted in the year 1998.  

This Act created regulatory mechanism.  Within few years, it  

was felt that the three Acts of 1910, 1948 and 1998 which  

were operating in the field needed to be brought in a new  

self contained comprehensive legislation with the policy of  

encouraging  private  sector  participation  in  generation,  

transmission  and  distribution  and  also  the  objectives  of  

distancing  the  regulatory  responsibilities  from  the  

20

21

Page 21

Civil Appeal No.5479 of 2013

Government and giving it to the Regulatory Commissions.  

With these objectives in mind the Electricity Act, 2003 has  

been  enacted.   Significant  addition  is  the  provisions  for  

newer concepts like power trading and open access. Various  

features of the 2003 Act which are outlined in the statement  

of objects and reasons to this Act.  Notably, generation is  

being  delicensed  and  captive  generation  is  being  freely  

permitted.  The Act makes provision for private transmission  

licensees.  It now provides open access in transmission from  

the outset.

(2)  Open Access and CSS

22. Open access  implies  freedom to  procure  power  from  

any source.  Open access in transmission means freedom to  

the  licensees  to  procure  power  from  any  source.   The  

expression “open access” has been defined in  the Act to  

mean  “the  non-discriminatory  provision  for  the  use  of  

transmission  lines  or  distribution  system  or  associated  

facilities  with  such  lines  or  system  by  any  licensee  or  

consumer or a person engaged in generation in accordance  

21

22

Page 22

Civil Appeal No.5479 of 2013

with  the  regulations  specified  by  the  Appropriate  

Commission”.  The Act mandates that it shall be duty of the  

transmission  utility/licensee  to  provide  non-discriminatory  

open access to its  transmission system to every licensee  

and generating company.  Open access in transmission thus  

enables  the  licensees  (distribution  licensees  and  traders)  

and generating companies the right to use the transmission  

systems without any discrimination.   This  would facilitate  

sale  of  electricity  directly  to  the  distribution  companies.  

This would generate competition amongst the sellers and  

help reduce, gradually, the cost of generation/procurement.

23. While open access in transmission implies freedom to  

the licensee to procure power from any source of his choice,  

open  access  in  distribution  with  which  we  are  concerned  

here, means freedom to the consumer to get supply from  

any source of his choice.  The provision of open access to  

consumers, ensures right of the consumer to get supply from  

a person other than the distribution licensee of his area of  

supply by using the distribution system of such distribution  

licensee.  Unlike in transmission, open access in distribution  22

23

Page 23

Civil Appeal No.5479 of 2013

has not been allowed from the outset primarily because of  

considerations  of  cross-subsidies.   The  law  provides  that  

open access in distribution would be allowed by the State  

Commissions  in  phases.   For  this  purpose,  the  State  

Commissions  are  required  to  specify  the  phases  and  

conditions of introduction of open access.

24. However open access can be allowed on payment of a  

surcharge,  to  be determined by the State Commission,  to  

take  care  of  the  requirements  of  current  level  of  cross-

subsidy  and  the  fixed  cost  arising  out  of  the  licensee’s  

obligation to supply.  Consequent to the enactment of the  

Electricity  (Amendment)  Act,  2003,  it  has  been mandated  

that the State Commission shall within five years necessarily  

allow open access to consumers having demand exceeding  

one megawatt.

(3)  CSS: Its Rationale

25. The issue of open access surcharge is very crucial and  

implementation of the provision of open access depends on  

judicious  determination  of  surcharge  by  the  State  

23

24

Page 24

Civil Appeal No.5479 of 2013

Commissions.   There  are  two  aspects  to  the  concept  of  

surcharge  –  one,  the  cross-subsidy  surcharge  i.e.  the  

surcharge meant to take care of the requirements of current  

levels  of  cross-subsidy,  and  the  other,  the  additional  

surcharge to meet the fixed cost of the distribution licensee  

arising  out  of  his  obligation  to  supply.   The presumption,  

normally is that generally the bulk consumers would avail of  

open access,  who also  pay at  relatively  higher  rates.   As  

such, their exit would necessarily have adverse effect on the  

finances of the existing licensee, primarily on two counts –  

one, on its ability to cross-subsidise the vulnerable sections  

of society and the other, in terms of recovery of the fixed  

cost  such  licensee  might  have  incurred  as  part  of  his  

obligation to supply electricity to that consumer on demand  

(stranded costs).  The mechanism of surcharge is meant to  

compensate the licensee for both these aspects.

26. Through  this  provision  of  open  access,  the  law  thus  

balances the right of the consumers to procure power from a  

source of his choice and the legitimate claims/interests of  

the existing licensees. Apart from ensuring freedom to the  24

25

Page 25

Civil Appeal No.5479 of 2013

consumers,  the  provision  of  open  access  is  expected  to  

encourage competition  amongst  the  suppliers  and also  to  

put  pressure  on  the  existing  utilities  to  improve  their  

performance in terms of quality and price of supply so as to  

ensure that the consumers do not go out of their fold to get  

supply from some other source.

27. With this open access policy, the consumer is given a  

choice  to  take  electricity  from any  Distribution  Licensee.  

However,  at  the  same  time  the  Act  makes  provision  of  

surcharge for taking care of current level of cross subsidy.  

Thus,  the  State  Electricity  Regulatory  Commissions  are  

authorized to frame open access in distribution in phases  

with surcharge for:

(a)   Current  level  of  cross  subsidy  to  be  gradually  phased out along with cross subsidies; and  (b)  obligation to supply.

28. Therefore, in the aforesaid circumstances though CSS is  

payable by the Consumer to the Distribution Licensee of the  

area in question when it  decides not to take supply from  

that  company  but  to  avail  it  from  another  distribution  

25

26

Page 26

Civil Appeal No.5479 of 2013

licensee.   In  nutshell,  CSS  is  a  compensation  to  the  

distribution licensee irrespective of the fact whether its line  

is  used or not,  in view of the fact that,  but for  the open  

access the consumer would pay tariff applicable for supply  

which would include an element of cross subsidy surcharge  

on  certain  other  categories  of  consumers.   What  is  

important is that a consumer situated in an area is bound to  

contribute to subsidizing a low and consumer if he falls in  

the category of subsidizing consumer.  Once a cross subsidy  

surcharge is fixed for an area it is liable to be paid and such  

payment will be used for meeting the current levels of cross  

subsidy within the area.  A fortiorari, even a licensee which  

purchases electricity for its own consumption either through  

a “dedicated transmission line” or through “open access”  

would be liable to pay Cross Subsidy Surcharge under the  

Act.   Thus, Cross Subsidy Surcharge, broadly speaking,  is  

the charge payable by a consumer who opt to avail power  

supply through open access from someone other than such  

Distribution  licensee  in  whose  area  it  is  situated.   Such  

surcharge  is  meant  to  compensate  such  Distribution  

26

27

Page 27

Civil Appeal No.5479 of 2013

licensee from the loss of cross subsidy that such Distribution  

licensee  would  suffer  by  reason  of  the  consumer  taking  

supply from someone other than such Distribution licensee.  

(4)  Application of the CSS Principle  

29. In the present case,  admittedly,  the Appellant (which  

happens to be the operator of an SEZ) is situate within the  

area of supply of WESCO.  It is seeking to procure its entire  

requirement  of  electricity  from  Sterlite  (an  Independent  

Power Producer (“IPP”) (which at the relevant time was a  

sister concern under the same management) and thereby is  

seeking to denude WESCO of the Cross Subsidy that WESCO  

would otherwise have got from it if WESCO were to supply  

electricity to the Appellant.  In order to be liable to pay cross  

subsidy surcharge to a distribution licensee, it is necessary  

that  such  distribution  licensee  must  be  a  distribution  

licensee  in  respect  of  the  area  where  the  consumer  is  

situated and it is not necessary that such consumer should  

be connected only to such distribution licensee but it would  

suffice if it is a “consumer” within the aforesaid definition.

27

28

Page 28

Civil Appeal No.5479 of 2013

30. Having  regard  to  the  aforesaid  scheme,  in  normal  

course when the Appellant has entered to PPA with Sterlite,  

another Electricity Generating Company and is purchasing  

electricity from the said Company it is liable to pay CSS to  

the  WESCO.   Admittedly  under  the  PPA,  the  Appellant  is  

purchasing his electricity from the said generating station  

and  it  is  consumed  by  the  single  integrated  unit  of  the  

Appellant.   The  Appellant  therefore,  qualifies  to  be  a  

“consumer” under Section 2(15) of the Electricity Act.  It is  

also not in dispute that the unit of the Appellant is in the  

area which is covered by the licenses granted to WESCO as  

distribution licenses.

31. Notwithstanding the above, because of the reason that  

the area where the unit of Val-SEZ unit of the Appellant is  

situate  is  a  SEZ  area  and  the  Appellant  is  declared  as  

developer  for  that  area  under  the  SEZ  Act,  it  is  the  

contention of the Appellant that in such a scenario it is not  

liable to pay any CSS to the WESCO.  This submission flows  

from the fact that there is a notification issued in this behalf  

under  proviso  to  Section  49  of  the  SEZ  Act  and  the  28

29

Page 29

Civil Appeal No.5479 of 2013

Appellant itself is treated as a deemed Distribution Licensee  

as per the provisions of Section 14 of the Electricity Act.  On  

that basis, detailed submissions are made by the Appellant  

with  an  attempt  to  show  that  it  cannot  be  treated  as  a  

“consumer”  under  the  Electricity  Act  when  the  Appellant  

itself is deemed to be a licensee.  It is further argued that  

since the supply line of VAL-SEZ is not connected to WESCO  

and it is getting the electricity directly from Sterlite under  

the PPA, there is no question of payment of CSS to WESCO  

at all.  Argument of the WESCO that the lines owned by the  

VAL-SEZ are only “Transmission Lines” under Section 2 of  

the Electricity Act and not “dedicated Transmission Lines”  

because of  the reason that  the duty  of  the Generator  to  

establish  and  maintain  dedicated  transmission  lines,  is  

sought to be refuted by arguing that even as per Section  

2(72)  of  the  Act  Transmission  Lines  are  part  of  the  

Distribution System of Licensing”.  It is argued that it is not  

even the case of WESCO that the supply line of SEL-VAL is a  

part of WESCO Distribution System.

29

30

Page 30

Civil Appeal No.5479 of 2013

(5)  Factual Aspect of the Electricity Supply to the  Appellant:

32. In  order  to  appreciate  these  arguments,  it  would  

appropriate  to  first  advert  to  the  factual  aspect  of  the  

supply of electricity by Sterlite to the Appellant under the  

PPA.   No  doubt  the  Appellant  is  getting  direct  supply  of  

electricity from Sterlite.  However, question is as to whether,  

in the process,  it  is  using dedicated transmission lines of  

WESCO.   We  may  point  out  at  the  outset  that  such  an  

argument was not even raised before the two authorities  

below.   Primarily  it  was argued that  having acquired the  

status of deemed distribution licensee under the Electricity  

Act,  it  cannot  be  treated  as  a  “consumer”  of  other  

distribution licensee, viz. the WESCO.  Even the question of  

law which is proposed and framed in the grounds of appeal  

and is already reproduced, does not raise this issue, which  

is  even  otherwise  factual.   Notwithstanding,  the  Learned  

Counsel  for  the WESCO has argued that the transmission  

line  between  the  Sterlite  and  the  Appellant  is  not  a  

dedicated transmission line for the following reasons:

30

31

Page 31

Civil Appeal No.5479 of 2013

(a)   Under  Section  2(16)  of  the  Electricity  Act,  2003,  a  

“Dedicated Transmission Line” is an electric supply line for  

“point  to  point”  transmission,  which  are  required  for  the  

purpose  of  connecting  electric  line  or  electric  plan  of  a  

generating  station  to  “any  transmission  line”,  or  “sub-

station” or “generating station” or the “load centre”, “as the  

case may be”.

(b)  The Transmission Line in question commences from the  

Generator (Sterlite) and connects to the 400 KV Sub-Station  

at Sterlite end at Jharsuguda.  It does not connect directly to  

the “Load Centre” which is the Appellant.

(c)  The 400 KV Busbar at the Generator (Sterlite) end is  

connected to a 200 KV Busbnar at VAL-CGP caters to the  

VAL -  Smelter 1 in the Domestic Tariff Area.

(d)  The said 400/200 KV sub-station is also connected to  

the OPTCL Grid (State Transmission Utility)  at  Budhipadar  

through 220 KV Bus at VAL – CGP end for the purpose of  

evacuation of Sterlite power to GRIDCO as well as drawal of  

power by VAL – Smelter – 1.

31

32

Page 32

Civil Appeal No.5479 of 2013

(e)  The said 400/220 kv sub-station is also connected to  

Power Grid Corporation of India (PGCIL) line from which 2  

nos  of  400  KV  Lines  emanate  for  Interstate  sale  of  its  

Sterlite power through PGCIL Grid.

(f)   The  said  400/220  kv  sub-station  which  is  connected  

through 5 Km of 220 KV line to the 220 KV Bus of switching  

station  at  VAL  –  CGP  end.   There  are  4  no’s  of  200  KV  

transmission  lines  branching  out  from  the  said  220  KV  

switching station to carry power to VAL Smelter-1 Unit of the  

Appellant  which  is  within  the  area  of  the  Distribution  

Licensee (WESCO).

(g)  The said 400/220 kv sub-station also has 2 nos of 33 KV  

Tertiary transmission lines from 100/220/33 KV Transformer  

supplying electricity to Vedanta Township.

(h)  Three such 400 KV Transmission lines emanating from  

the 400 KV Busbar at the Sterlite-IPP (Generator end) also  

happens  to  Supply  power  from  the  sub-station  to  the  

Appellant’s load centre (VAL-Smelter-2) in the SEZ area.

32

33

Page 33

Civil Appeal No.5479 of 2013

(i)   Hence,  the  only  part  of  the  “dedicated”  transmission  

line, if at all, is from the Generating Station 9Sterlite – IPP)  

to such 400 KV Busbar of the 400/220 KV Grid Sub-station.

(j)  The transmission line that connects the sub-station to  

the load centre of the Appellant is only a “transmission line”  

under Section 2(72) of the EP 2003.

33. Following diagram is placed by WESCO to demonstrate  

this:

33

34

Page 34

Civil Appeal No.5479 of 2013

34

35

Page 35

Civil Appeal No.5479 of 2013

34.  Though  the  Appellant  endeavoured  to  counter  this  

position and has given its own diagram that does not lodge  

the  aforesaid  factual  aspect.   Therefore,  prima  facie  we  

accept the position as explained by the WESCO. Thus we  

feel  that  notwithstanding  that  supply  line  of  SEL-VAL  is  

transmission  line,  but  not  “dedicated  transmission  line”.  

The Appellant  cannot  run  away from the fact  that  under  

Section  2(10)  of  the  Electricity  Act,  it  is  the  duty  of  the  

Generating Company (i.e. WESCO) in this case to establish,  

operate and maintain dedicated transmission lines.  Since it  

is  duty  bound  to  establish,  operate  and  maintain  these  

dedicated lines by making huge investment, in order to get  

into  the  consumption  in  the  area  in  question  the  very  

necessity  of  payment  of  CSS  arises  by  the  consumer  of  

Electricity  covered by the  definition of  “consumer”  under  

Section 2(15) of the Act but is not getting supply of that  

Generator and someone else.  We have also to keep in mind  

the provision of Regulation 27 of OERC (Conditions of Supply  

Code) Regulation 2004.  As per this Regulation the “service  

35

36

Page 36

Civil Appeal No.5479 of 2013

line” shall be the property of the licensee unless otherwise  

specified in writing.  This clause reads as under:

“27.  The entire service line, notwithstanding that  whole or portion thereof has been paid for by the  consumer,  shall  be  the  property  of  the  licensee  and shall be maintained by the licensee who shall  always have the right to use it for the supply of  energy  to  any  other  person  unless  the  line  has  been  provided  for  the  exclusive  use  of  the  consumer through any arrangement agreed to in  writing.”

35.  Further as per Rule 4 of the Electricity Rule, 2005 the  

aforesaid line would be deemed to be part  of Distribution  

System of WESCO:

“4.  Distribution System – The distribution system  of a distribution licensee in terms of sub-section  (19)  of  section  2  of  the  Act  shall  also  include  electric line,  sub-station and electrical plant that  are  primarily  maintained  for  the  purpose  of  distributing electricity in the area of supply of such  distribution  licensee  notwithstanding  that  such  line,  sub-station  or  electrical  plant  are  high  pressure  cables  or  overhead  lines  or  associated  with such high pressure cables or overhead lines;  or  used  incidentally  for  the  purposes  of  transmitting electricity for others.” “Distribution system” is defined in Section 2(19) of  the Act to mean:- “(19) “distribution system” means the system of  wires  and  associated  facilities  between  the  

36

37

Page 37

Civil Appeal No.5479 of 2013

delivery  points  on  the  transmission  lines  or  the  generating  station  connection  and  the  point  of  connection to the installation of the consumers:” “Transmission Line” is defined in Section 2(72) to  mean:- (72) “transmission lines” means all high pressure  cables and overhead lines (not being an essential  part  of  the  distribution  system  of  a  licensee)  transmitting electricity from a generating station  to  another  generating  station  or  a  sub-station,  together  with  any  step-up  and  step-down  transformers, switch-gear and other works….”

(6)  Appellant deemed distribution Licensee: Its  effect

36. It  is  now to be seen as to whether the fact that the  

Appellant  is  a  Developer  in  SEZ,  armed  with  Notification  

dated 3rd March, 2010 issued under Proviso to Section 49 of  

the  SEZ  Act  and  it  deemed  distribution  licensee  as  per  

Section 14 of the Electricity Act, this would take away the  

Appellant from the clutches of CSS liability?

37. In order to appreciate this argument let us first refer to  

the certain statutory provisions:  

Section 49 of the Special Economic Zone Act  provides as under:

37

38

Page 38

Civil Appeal No.5479 of 2013

“Power  to  modify  provisions  of  this  Act  or  other enactments in relation to Special Economic  Zones.

(1)   the  Central  Government  may,  by  notification, direct that any of the provision of this  Act (other than Section 54 and 56) or any other  Central  Act  or  any  rules  or  regulations  made  thereunder or any notification or Order issued or  direction  given  thereunder  (other  than  the  provisions  relating  to  making  of  the  rules  or  regulations) specified in the notification-

(a) shall not apply to a Special Economic Zone  or a class of Special Economic Zones or all Special  Economic Zones: or

(b) shall apply to a Special Economic Zone or  a class of Special Economic Zones or all Specials  Economic  Zones  only  with  such  exceptions,  modifications and adaptation, as may be specified  in the notifications.”

38. Likewise Section 14 of the Electricity Act reads as under:  

“14.  Grant of License The Appropriate Commission may, on application  made  to  it  under  section  15,  grant  any  person  licence to any person –  (a)   To  transmit  electricity  as  a  transmission  licensee: or (b)   To  distribute  electricity  as  a  distribution  licensee: or  (c)   To  undertake  trading  in  electricity  as  an  electricity  trader,  in  any  area  which  may  be  specified in the licence:

38

39

Page 39

Civil Appeal No.5479 of 2013

Provided that any person engaged in the business  of transmission or supply or electricity under the  provisions  of  the  repealed  laws  or  any  Act  specified  in  the  Schedule  on  or  before  the  appointed date shall be deemed to be a licensee  under this Act for such period as may be stipulated  in  the  licence,  clearance or  approval  granted to  him under the repealed laws or such Act specified  in the Schedule, and the provisions of the repealed  laws  or  such  Act  specified  in  the  Schedule  in  respect of such licence shall apply for a period of  one year from the date of commencement of this  Act or such earlier period as may be specified, at  the  request  of  the  licensee,  by  the  Appropriate  Commission and thereafter the provisions of this  Act shall apply to such business: Provided  further  that  the  Central  transmission  Utility  or  the  State  Transmission  Utility  shall  be  deemed to be a transmission licensee under this  Act: Provided  also  that  in  case  an  Appropriate  Government  transmits  electricity  or  distributes  electricity  or  undertakes  trading  in  electricity,  whether before or after the commencement of this  Act,  such Government  shall  be deemed to  be a  licensee under this Act, but shall not be required  to obtain a licence under this Act: Provided  also  that  the  Damodar  Valley  Corporation,  established  under  sub-section(1)  of  section 3 of the Damodar Valley Corporation Act,  1948, shall be deemed to be a licensee under this  Act but shall  not be required to obtain a licence  under this Act and the provisions of the Damodar  Valley Corporation Act, 1948, in so far as they are  not  inconsistent  with  the  provisions  of  this  Act,  shall continue to apply to that Corporation:

39

40

Page 40

Civil Appeal No.5479 of 2013

Provided also  that  the  Government  Company or  the  Company  referred  to  in  sub-section  (2)  of  section  131  of  this  Act  and  the  company  or  companies  created  in  pursuance  of  the  Acts  specified in the Schedule, shall be deemed to be a  licensee under this Act. Provided  also  that  the  Appropriate  Commission  may grant a licence to two or more persons for  distribution  of  electricity  through  their  own  distribution system within the same area, subject  to  the conditions  that  the applicant  for  grant  of  licence  within  the  same  area,  subject  to  the  conditions that the applicant for grant of licence  within  the same area shall,  without prejudice to  the  other  conditions  or  requirements  under  this  Act,  comply  with  the  additional  requirements  (including the capital adequacy, credit worthiness,  or code of conduct) as may be prescribed by the  Central  Government,  and no such applicant who  complies  with  all  the  requirements  for  grant  of  licence,  shall  be refused grant of licence on the  ground that there already exists a licensee in the  same are for the same purpose: Provided also that in a case where a distribution  licensee  proposes  to  undertake  distribution  of  electricity for  a specified area within his area of  supply through another person, that person shall  not  be  required  to  obtain  any  separate  licence  from the concerned State  Commission and such  distribution  licensee  shall  be  responsible  for  distribution of electricity in his area of supply:   Provided  also  that  where  a  person  intends  to  generate and distribute electricity in a rural area  to  be  notified  by  the  State  Government,  such  person  shall  not  require  any  licence  for  such  generation  and distribution  of  electricity,  but  he  

40

41

Page 41

Civil Appeal No.5479 of 2013

shall  comply  with  the  measures  which  may  be  specified by the Authority under section 53: Provided also that a distribution licensee shall not  require  a  licence  to  undertake  trading  in  electricity.”

39. We would also like to take note of Notification dated 3 rd  

March, 2010 issued in the case of Appellant.  It makes the  

following reading:

“NOTIFICATION

S.O.  No.528(E).  In  exercise  of  the  powers  conferred  by  clause(b)  of  sub-section  (1)  of  section  49  of  the  Special  Economic  zones  Act,  2005  (28  of  2005),  the  Central  Government hereby notifies that the provisions of clause (b)  of section 14 of the Electricity Act, 2003 (36 of 2003), shall  apply  to  all  Special  Economic  Zones  notified  under  sub- section (1) of section 4 of the Special Economic Zones Act,  2005, subject to the following modification, namely:-

In clause (b) of section 14 of the Electricity Act, 2003  

(36  of  2003),  the  following  proviso  shall  be  inserted,  

namely:-

“  Provided  that  the  Developer  of  a  Special    Economic Zone notified under sub section (1) of  section 4 of the Special Economic Zones Act, 2005  shall be deemed to be a licensee for the purpose  of  this  clause,  with  effect  from  the  date  of  notification of such Special Economic Zone.”

41

42

Page 42

Civil Appeal No.5479 of 2013

40. The reading of Section 49 of SEZ Act would reveal that  

the Central Government has got the authority to direct that  

any  of  the  provisions  of  a  Central  Act  and  rules  and  

regulations made thereunder would not apply or to declare  

that some of the provisions of the Central Acts shall apply  

with exceptions, modifications and adaptation to the Special  

Economic Zone.  So, under the scheme of Special Economic  

Zone Act, Central Government has to first notify as to what  

extent  the  provision  of  the  other  Acts  are  to  be  made  

applicable or applicable with modification or not applicable  

for  the  Special  Economic  Zone  area.   It  is  in  furtherance  

thereto, the Government of India, Ministry of Commerce and  

Industry through its notification dated 21st March, 2012, with  

regard to power generation in Special Economic Zone, has  

declared that all the provisions of the Electricity Act, 2003  

and  Electricity  Rule,  2005  shall  be  applicable  to  the  

generation, transmission and distribution of power, whether  

stand alone or captive power.  This notification would clarify  

that  there  is  no  inconsistency  between  Special  Economic  

Zone Act, 2005 and Electricity Act, 2003.

42

43

Page 43

Civil Appeal No.5479 of 2013

41. No  doubt  vide  Notification  dated  3rd March,  2010  

Central  Government  has  added  an  additional  proviso  to  

Clause  (b)  of  Section  14  of  the  Electricity  Act  viz.  the  

Appellant shall be deemed to be licensee for the purpose of  

the said clause w.e.f. the date of notification of such SEZ.  It  

is on this basis, the argument of the Appellant is that as it is  

already a deemed Distribution Licensee it need not apply for  

this license to the said Commission before entering into the  

PPA  and  the  State  Government  is  bound  to  grant  the  

License.   This  contention  is  negated  by  the  Appellate  

Tribunal on two grounds which are as follows:

(i)  There has to be a harmonious construction of SEZ Act  

and Electricity Act to give effect to the provisions of both  

the acts so long as they are not consistent with each other  

in the opinion of the Tribunal.  The provisions of Section 51  

of  SEZ  Act,  2005  are  to  be  considered  along  with  the  

provisions of Section 49 of the said Act.  Accordingly, in view  

of  the  provision  of  the  SEZ  Act,  2005  and  consequent  

notification by the Ministry of Commerce and Industry, the  

deemed  distribution  licensee  status  as  claimed  by  the  43

44

Page 44

Civil Appeal No.5479 of 2013

Appellant should also be tested through other provisions of  

the  Electricity  Act,  2003  and  Electricity  Rules,  2005,  for  

certifying  its  validity  and  converting  it  into  a  formal  

distribution licensee.  In fact, the Appellant has submitted to  

the jurisdiction of the State Commission, by filing a petition  

before the  State  Commission  seeking for  approval  of  the  

PPA and also for grant of distribution licence. The Appellate  

Tribunal, thus queried as to how could the Appellant now  

question the jurisdiction?  

(ii)  The Appellate Tribunal pointed out that there are none  

provisos to Section 14(b) of the Electricity Act and another  

is added in respect of the Appellant vide Notification dated  

3rd March, 2010.  A reading of these provisos would indicate  

that  some  of  them  confer  status  of  deemed  distribution  

licensee on certain specified entities who are not required to  

take separate licence from the State Commission under this  

Act whereas some other provisos merely declare the party  

as  deemed licensee  and nothing  specified  as  to  whether  

they are required to  obtain the licence or  not.   However  

when it is specially provided in proviso 4 and proviso 8 and  44

45

Page 45

Civil Appeal No.5479 of 2013

2  that  the  Damodar  Valley  Corporation  and  State  

Government are not required to obtain licence, and other  

provisos  do  not  confer  such  privilege,  they  would  be  

required to obtain licence.   

42. Further  discussion  on  this  aspect  by  the  Appellate  

Tribunal is as under:

“42.  Keeping this in mind, the statute makers by  the notification dated 3.03.2010 have inserted the  additional  proviso  to  Section  14(b)  of  the  Electricity Act.  Admittedly, the development and  operation  of  the  SEZ  are  two  distinct  activities.  Thus, the jurisdiction of the State Commission to  scruitinise  the  deemed distribution status  of  the  Appellant is well established in view of the Section  49(1) of SEZ, Act, 2005 and the notification of the  Central Government dated 21.03.2012.  Therefore,  the  contention  of  the  Appellant  that  the  State  Commission dealt with the matter relating to the  grant of  distribution licence by going beyond its  jurisdiction is misplaced. 43.  It  is  noticed that the Ministry of Commerce  and  Industry  (Department  of  SEZ  Section)  has  accorded  SEZ  status  to  the  Appellant  for  development  and  operation  and  maintenance  of  sector  specific  Special  Economic  Zone  for  manufacture  and  export  of  aluminium  on  the  condition  that  the  Appellant  should  establish  captive  generating  plant  as  stipulated  in  the  approval  letter  of  Ministry  of  Commerce  and  Industry but it is pointed out the still the plant has  not  been  established  for  various  reasons.   If  

45

46

Page 46

Civil Appeal No.5479 of 2013

Captive  generating  plant  of  1215  MW had been  established  as  per  the  condition  inside  the  SEZ  area, the question of power purchase from Sterlite  Energy  Limited  under  the  pretext  of  distribution  licensee status would not have arisen.  That apart,  the  State  Commission  has  framed  Orissa  Electricity  Regulatory  Commission  (conduct  of  business)  Regulation,  2004  under  the  powers  conferred under Section 181 of the Electricity Act,  2003.   The  distribution  of  electricity  Licence  (Additional  requirement  of  Capital  Adequacy,  Credit  Worthiness  and  Code  of  Conduct)  Rules,  2005  framed  by  the  Central  Government  also  would  apply  to  the  Appellant  for  distribution  licence  in  addition  to  the  requirements  of  State  Commission’s Regulations. 45.  Section 174 of the Electricity Act provides that  the provisions of the Electricity Act shall have to  overriding  effect  notwithstanding  anything  inconsistent with any other law for the time being  in  force  or  in  any  instrument  having  effect  by  virtue of any law other than Electricity Act.  That  apart,  Section  175  also  provides  that  the  provisions of the Electricity Act are in addition to  and not in derogation of any other law for the time  being in force. 47.   The  perusal  of  the  notification  dated  03.03.2010  would  make  it  evident  that  the  legislation’s intention for declaring the developer  in  SEZ  area  as  deemed  distribution  licence,  is  confined  only  to  clause-b  of  Section  14  of  Electricity  Act,  which  deals  with  the  grant  of  license  by  the  appropriate  State  Commission  to  any person for distribution of electricity.  The said  notification has not  curtailed the power of  State  Commission  so  far  as  the  applicability  of  other  provisions  is  concerned.   The  interpretation  of  various  relevant  terms  was  necessary  prior  to  

46

47

Page 47

Civil Appeal No.5479 of 2013

grant of deemed distribution licence by the State  Commission.   Therefore,  the  State  Commission  rightly acted upon those provisions.  As a matter  of  fact,  by  the  said  amendment  by  inserting  another proviso to Section 14(b), the context has  not been changed as claimed by the Appellant. 49.   As  correctly  indicated  by  the  State  Commission,  the  definition  of  term  “distribution  licensee” as  enumerated under  Section  2(17)  of  Electricity  Act,  2003,  emphasizes  upon  the  distribution  licensee  to  operate  and  maintain  a  distribution  system  and  supply  of  power  to  the  consumers.  Considering the definition of ‘supply’  in  Section 2(70),  the supply here means sale  of  electricity  to  consumers.   By  merely  being  authorized to operate and maintain a distribution  system as a  deemed licensee,  would  not  confer  the status of distribution licensee to any person.  The purpose of such establishment is for supply of  power to consumers.  Mere fact that the Appellant  claims to be a deemed distribution licensee is of  no consequence at all since admittedly, the entire  power purchased by the Appellant is  for  its own  use and consumption and not for the purpose of  distribution and supply/sale to consumers. 50.  An entity which utilizes the entire quantum of  electricity for its own consumption and does not  have  any  other  consumers,  cannot,  by  such  a  notification, be deemed to be distribution licensee,  even  by  a  legal  fiction.   By  virtue  of  the  legal  fiction created by the notification dated 3.03.2010,  the Developer of SEZ notified under the SEZ Act,  who distributes electricity can be deemed to be a  distribution  licensee.   Thus,  this  legal  fiction  cannot go further and make a person who does  not  distribute electricity  to  the  consumers  as  to  distribution licensee.  Therefore there is no merit  in the contention of the Appellant.

47

48

Page 48

Civil Appeal No.5479 of 2013

43. We are in agreement with the aforesaid rationale in the  

impugned order of the Appellate Tribunal as that is the only  

manner  in  which  the  two  Acts  can  be  harmoniously  

construed.   To recapitulate briefly,  in the present case no  

doubt by virtue of the status of a developer in the SEZ area,  

the  Appellant  is  also  treated  as  deemed  Distribution  

Licensee.  However with this,  it  only gets exemption from  

specifically applying for licence under Section 14 of the Act.  

In order to avail further benefits under the Act, the Appellant  

is also required to show that it is in fact having distribution  

system  and  has  number  of  consumers  to  whom  it  is  

supplying the electricity.  That is not the case here.  For its  

own plant only, it is getting the electricity from Sterlite Ltd.  

for which it has entered into PPA.  We have to keep in mind  

the object and scheme of SEZ Act which envisages several  

units being set  up in  a SEZ area.   This is  evident from a  

collective reading of the various provisions of the SEZ Act  

viz. Section 2(g)(j)(za)(zc), Section 3, 4, 11, 12, 13 and 15.  

There can be a Sector Specific SEZ with Several Units i.e. for  

IT, Mineral Based Industries etc. but instances of single unit  

48

49

Page 49

Civil Appeal No.5479 of 2013

SEZ like in the present case of the Appellant may be rare.  

The  Notification  dated  03.03.2010  providing  for  the  

“Developer”  of  SEZ  being  deemed  as  a  “Distribution  

Licensee” was issued keeping in view the concept of Multi  

Unit  SEZs and will  apply  only to  such cases in  which the  

Developer  is  supplying the power  to  multiple Units  in  the  

SEZ.  The said Notification will not apply to a Developer like  

the Appellant who has established the SEZ only for itself.   

44.  Having regard to the aforesaid factual and legal aspects  

and keeping in mind the purpose for which CSS is payable,  

as explained in detail in the earlier part of this judgment, we  

are of the view that on the facts of this case it is not possible  

for the Appellant to avoid payment of CSS to WESCO.  We,  

therefore,  do  not  find  any  merit  in  this  Appeal  which  is  

accordingly dismissed.

…………………………….………J.         [Surinder Singh Nijjar]

 …………………………………….J.

49

50

Page 50

Civil Appeal No.5479 of 2013

     [A.K. Sikri]

                                   

 New Delhi     April 25, 2014  

50