M/S.S.V.A.STEEL RE-ROLLING MILLS LTD&ORS Vs STATE OF KERALA .
Case number: C.A. No.-010103-010106 / 2010
Diary number: 5936 / 2005
Advocates: P. V. DINESH Vs
M. T. GEORGE
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs. 10103-10106 OF 2010
M/s S.V.A. Steel Re-rolling Mills Ltd. etc. etc. .....Appellants.
Versus
State of Kerala & Ors. etc. etc. …..Respondents.
WITH
C.A.NOS.10107-10108, 10110-10114, 10116-10121, 10123 OF 2010 AND C.A.NO.4035 OF 2007.
J U D G M E N T
ANIL R. DAVE, J.
1. Being aggrieved by the common Judgment dated 24th
February, 2005 delivered by the High Court of Kerala at
Ernakulam in W.P.(C) No.5795/2004, W.P.(C)
No.5877/2004, W.P.(C) No.5984/2004 and O.P.
No.9816/2001, the appellants, original petitioners before the
High Court have approached this Court by way of these
appeals.
1
Page 2
2. The facts giving rise to the present appeals, in a nut-shell, are
as under:
The appellants are businessmen having their manufacturing
units in the State of Kerala and they are manufacturing
different articles with the help of electricity, which is
generated/supplied by the Kerala State Electricity Board
(hereinafter referred to as ‘the Board’). The respondent-
Government was desirous of having industrial development in
the State of Kerala and therefore, it had framed certain
policies so as to encourage and invite businessmen for setting
up their manufacturing units in the State of Kerala. Due to
shortage of electricity supply in the State of Kerala, interested
entrepreneurs were not inclined to set up their units in the
State of Kerala. In view of the aforestated circumstances, the
State Government had laid down a policy whereby it declared
to give continuous electricity supply at a particular rate to
certain new manufacturing units.
3. So as to put the aforestated policy in practice, the respondent-
State had issued a Government Order dated 21st May, 1990
which read as under:
2
Page 3
“Government have been considering the question of giving
some incentives to new industries in the matter of power
connection. Taking into consideration the announcements
made by the Minister (Finance) in the current year’s
budget speech and after discussions with all concerned,
Government are now pleased to issue the following orders
in this context which will have effect from 1-4-1990.
1. Power connection will be given on completion of any project irrespective of whether a general power cut is in force or not. 2. New units commencing industrial production will be exempted from power cut for a period of 5 years from the date of commercial production. 3. Exemption from payment of electricity duty for a period of 5 years from the date of commencement of commercial production will be given to the new units. 4. In future the electricity duty will not be collected from the industries if they are eligible for exemption. 5. Service connection charges will not be levied if no extension is required or if the additional line to be provided is less than 500 meters in length.”
The aforestated State Government Order had been adopted by
the Board by its Order dated 19th June, 1990.
4. By virtue of the aforestated policy declared under the order
dated 21st May, 1990, the respondent-State had assured the
manufacturing units to be set up in the State of Kerala that
electricity connection would be given to the projects which
3
Page 4
might be set up and they would be exempted from power cut
for a period of 5 years from the date of commencement of
commercial production. Such new units were also given
certain exemption in relation to payment of electricity duty for
a period of five years.
5. It is not in dispute that in pursuance of the aforestated policy
the appellants had established their manufacturing units
(hereinafter referred to as ‘the new units’) in the respondent-
State. It is also not in dispute that the requisite conditions,
which had been imposed upon such new units, had been fully
complied with by the appellants and therefore, the appellants
were entitled to an uninterrupted electricity supply for a
period of 5 years from the date on which they had commenced
their commercial production.
6. The respondent-State had thereafter passed a further order on
6th February, 1992, whereby the new units were exempted for
5 years from the payment of enhanced power tariff on certain
conditions. According to the appellants, they were also
entitled to benefit under the aforestated G.O. dated 6th
February, 1992.
4
Page 5
7. In spite of the assurance given by the respondent-State to the
new units that they would not suffer any power cut, because
of certain difficulties faced by the Board with regard to supply
of electricity to new units, there used to be power cuts which
adversely affected the new units. In view of the said fact, to
alleviate the difficulties of the units set up under the
aforestated policy, the respondent-State passed further order
on 26th October, 1999, whereby it granted extension of period
of assured power supply to the new units, who were adversely
affected because of the power cut in certain circumstances.
Under the aforestated order, it was decided and declared to
extend the benefit which had been given under G.O. dated 25th
May, 1990 and 6th February, 1992 to the new units by number
of days during which supply of electricity to them had been
cut to the extent of 50% or more. The respondent-State also
decided to reimburse the Board with the amount of benefit
which was given to the new units on account of power cut
beyond 50%.
8. In the aforestated admitted facts and circumstances, the
respondent-State should have given the benefits which had
5
Page 6
been assured to the new units but for the reasons beyond
control of the State as well as the Board, the benefits assured
to the new units could not be given and therefore, along with
other industrial units, the present appellants had filed writ
petitions before the High Court of Kerala praying that the
benefits which had been assured to them should be given and
they should not be constrained to pay tariff at the enhanced
rate.
9. Thus, according to the appellants, in fact, they did not get real
benefit of the policy because their production was adversely
affected whenever there was power cut and the five years’
period of exemption from power cut was not extended by the
Government which was in violation of the promise given to
the appellants and other similarly situated new units.
10. All these grievances were ventilated before the High Court by
filing different petitions which were ultimately rejected by the
High Court by virtue of the impugned order.
11. The learned counsel appearing for the appellants had
vehemently submitted that it was unfair on the part of the
respondent -State not to adhere to the promise given to the
6
Page 7
appellants with regard to uninterrupted 100% electricity
supply. The appellants had set up their industries in the State
of Kerala because of the promise given by the respondent-
State that at least for a period of first 5 years from the date of
commencement of the commercial production, there would be
uninterrupted power supply and there would not be any
increase in the tariff and therefore, the respondent-State was
bound by the said policy. The principle of promissory
estoppel was also invoked by the appellants.
12. The learned counsel had further submitted that if for some
reason it was not possible for the respondent- State to give
uninterrupted 100% electricity supply to the appellants on a
particular day, the said period or the said day should have
been added to the period of 5 years for which the respondent-
State had promised uninterrupted 100% electricity supply to
the new units. According to the learned counsel, though, the
period had been extended, but not in a fair and reasonable
manner because the days during which there was cut of
electricity supply to the extent of 50% or more, were added to
the period of 5 years. According to the learned counsel,
7
Page 8
whenever there was any reduction in power supply, even if
the reduction or cut was 50% or less, the said period should
have been added to the period of 5 years, for the reason that in
case of continuing process industries, for proper functioning
of the manufacturing units, uninterrupted 100% supply of
electricity is a sine qua non.
13. The learned counsel had shown us some material whereby it
was shown that out of first 5 years during which the
appellants were to be given benefit, there was electricity cut
for 921 days and out of those 921 days there were 214 days
when the cut in electricity supply was for more than 50%. It
had been further submitted that the period during which even
the electricity cut was less than 50%, the new units could not
work at its optimum level, which had resulted into several
problems for the appellants.
14. He had further added that the respondent Board had accepted
the policy of the State with regard to giving benefit to the new
units for uninterrupted power supply on same tariff and
therefore, the Board could not have asked for additional tariff
8
Page 9
during the period of 5 years, as extended by the period during
which there was power cut.
15. The learned counsel had also alleged that the respondent-
State had given discriminatory treatment to the appellants by
not giving uninterrupted 100% electricity supply because the
State had given uninterrupted 100% electricity supply to
certain other manufacturing units like Malabar Cement and
the industries set up within the Export Processing Zone. It
had been asserted that if the above stated manufacturing units
could be given 100% uninterrupted electricity supply, there
was no reason for denying the same benefit to the appellants.
16. So as to substantiate the submission with regard to promissory
estoppel, the learned counsel had relied upon certain
judgments delivered by this Court.
17. On the other hand, the learned counsel appearing for the
respondent -State had submitted that the prayers made by the
appellants before the High Court were unjust and therefore,
their petitions and other petitions, praying for similar relief
had rightly been rejected by the impugned order of the High
Court.
9
Page 10
18. It had been also submitted that Section 22 B of the Indian
Electricity Act, 1910 (hereinafter referred to as ‘the Act’)
enables the respondent-State to impose control on distribution
and consumption of energy. Section 22 B of the Act reads as
under:
“Sector 22B. (1) Power to control the distribution and
consumption of energy:- If the State Government is of
opinion that it is necessary or expedient so to do, for
maintaining the supply and securing the equitable distribution
of energy, it may by order provide for regulating the supply,
distribution, consumption or use thereof.”
19. The aforestated provision, according to the learned counsel,
enables the respondent-State to regulate the supply,
distribution or consumption of electricity and as there was
shortage of electricity supply, the respondent-State had to
impose some electricity cut, so as to see that least problems
were created to the residents and industrial units set up in the
respondent-State. The Government authorities had to use
their discretion in the matter of supply of electricity. The
discretion which the respondent-State used was quite
reasonable as it was not possible to give 100% electricity
1
Page 11
supply to all the consumers of electricity in the State. In the
aforestated circumstances, the respondent-State had to
regulate the supply by imposing some power cut, and
unfortunately it resulted into some difficulties to the
appellants.
20. It had been further submitted by the learned counsel that, so as
to reduce the difficulties of the appellants, the Government
had issued an order whereby the days, during which electricity
supply was cut beyond 50%, had been added to the period of
5 years during which the appellants were entitled to the
concession declared by the State of Kerala. Thus, sufficient
efforts were made to see that the benefits assured to the
appellants were provided.
21. It had been further submitted that the appellants cannot expect
benefit of extension of period simply because there was
negligible cut in the supply for very less period. Therefore,
the respondent-State had decided that as and when the cut was
50% or more, the period for which such the cut had been
effected would be added to the period of 5 years and the said
decision was just and fair.
1
Page 12
22. The learned counsel had also submitted that all consumers of
electricity, including the appellants were informed well in
advance about the stoppage of electricity supply and thus, all
possible efforts were made to see that the appellants and other
similarly situated consumers were not put to much hardship.
23. The learned counsel had further submitted that looking at the
facts of the case, there would not be any promissory estoppel
as submitted by the learned counsel appearing for the
appellants. The learned counsel had relied upon the
judgments delivered in the case of State of Haryana & Ors.
v. Mahabir Vegetable Oils Pvt. Ltd., [2011 (3) SCC 778]
and State of Rajasthan & Anr. v. M/s Mahaveer Oil
Industries & Ors., [1999(4) SCC 357] to substantiate their
case to the effect that there could not be any promissory
estoppel in such cases.
24. We had heard the learned counsel at length and perused the
impugned judgment and the judgments referred to in the
course of hearing and the relevant material placed on record
of this Court. It is not in dispute that the appellants had set
up their new units in the State of Kerala only upon knowing
1
Page 13
the policy with regard to uninterrupted power supply and that
too at the same tariff for a period of 5 years from the date of
commercial production.
25. In the instant case, no case had been made out by the
respondent-State that the appellants had committed any
breach or were not entitled to any of the benefits or
concessions which had been offered to them by the
respondent-State. In the circumstances, the respondent-State
was bound to give the benefits which had been assured to the
appellants.
26. Though the respondent-State was bound to supply
uninterrupted 100% electricity required by the appellants, one
cannot lose sight of the fact that at times there would be
circumstances which would put the respondent-State and the
Board into such a difficulty that they would not be in a
position to fulfill the assurance given to the new units. It is
not in dispute that the State of Kerala is not generating enough
electricity to cater the needs of all its consumers in the State
of Kerala. The respondent-State is not having a magic wand
which would enable the State to generate more electricity.
1
Page 14
There might be several factors which might be adversely
affecting the respondents and as a result thereof, the
respondents might not be generating sufficient electricity so as
to fulfill the needs of the appellants and other residents of the
State.
27. The question, thus, arises as to how the adversely affected
persons who had been assured by a promise with regard to
continuous supply of electricity for five years can be fairly
compensated.
28. It is true that the respondent-State came out with
Government Order dated 26th October, 1999, whereby it had
decided that the period when there would be reduction or cut in
supply of power to the extent of 50% or more, such period of
power cut would be added to the period of 5 years, during which
the appellants and other similarly situated persons were to be
given continuous power supply.
29.The learned counsel appearing for the respondents could not
show us any justifiable reason for deciding as to why the
respondent-State decided to give the benefit of extended period
only when the power cut was 50% or more. It is pertinent to
1
Page 15
know that the cases where the consumer is having a continuous
process industry, even power cut below 50% would adversely
affect the manufacturing unit. It is a matter of common
knowledge that in several industries, the manufacturing process
can not be stopped abruptly. Many a times, restarting of the
machines or boilers take lot of time and energy, which results
into loss to the manufacturer. The said fact ought to have been
considered by the State while taking the aforestated decision.
The decision with regard to giving extension of time to such a
limited extent is not reasonable and in our opinion, that would
have surely affected the new units adversely.
30.It is true that Section 22B of the Act enables the State
Government to regulate the supply, distribution and
consumption of electricity for the purpose of maintenance and
supply of equitable distribution of energy but in our opinion,
provisions of the said section are not much relevant for the
reason that in the instant case, the respondent State had given
an assurance with regard to uninterrupted supply of electricity
and therefore, the respondents ought to have made provision for
uninterrupted supply of electricity to the appellants and other
1
Page 16
similarly situated persons by regulating electricity supply in a
proper manner.
31.Framing such policies and doing the needful for its
implementation are administrative functions of the respondent-
State and therefore, normally this Court would not like to
interfere with its policies but looking at the peculiar facts of the
case, where an assurance had been given for uninterrupted
supply of electricity, one would presume that the respondent-
State must have made necessary arrangements to provide 100%
uninterrupted supply of electricity for 5 years to the new units.
If for any reason it was not possible to supply electricity as
assured, the respondent-State ought to have extended the period
of 5 years by the period during which assured electricity was
not supplied. By doing so, the respondent-State could have
made an effort to fulfill its promise and satisfied the persons
who had acted on an assurance given by the State and set up
their manufacturing units in the State of Kerala.
32.Before laying down any policy which would give benefits to its
subjects, the State must think about pros and cons of the policy
and its capacity to give the benefits. Without proper
1
Page 17
appreciation of all the relevant factors, the State should not give
any assurance, not only because that would be in violation of
the principles of promissory estoppel but it would be unfair and
immoral on the part of the State not to act as per its promise.
33.In the instant case, the respondent-State was conscious about
the fact that there was a problem with regard to supply of
electricity in the State of Kerala and possibly for that reason
industries which depended much upon electricity as a source of
power were not inclined to establish new industries in the State
of Kerala. Before setting up an industry, the entrepreneur or the
industrialist considers several factors and thereupon takes
several decisions like place of business, capacity at which
production should be made, type of raw-material, etc. After
considering all these factors, a final decision is taken with
regard to setting up of an industry. For a new entrepreneur,
such a decision is of vital importance because if he fails in his
estimates or in consideration of all the relevant factors, there are
all chances that he would fail not only in his business but he
would completely ruin himself. Thus, one can very well
appreciate that the appellants must have thought about all
1
Page 18
relevant factors, including the incentives offered by the
respondent-State and might have decided to set up their
industries in the respondent-State. While deciding this case,
this Court would invariably keep in mind the circumstances in
which the appellants had set up their industries in the State of
Kerala.
34.In view of the incentives and assurances given to the appellants
along with others, who were desirous of setting up new
industries, the appellants set up their new units which were
much dependant upon continuous supply of electricity. One of
the appellants is a Steel Re-rolling Mill. In Steel industry, when
the industry is concerned with making of steel or re-rolling of
steel, it requires lot of power and energy, and electricity being
one of the important sources of power, the appellant was much
dependent on continuous supply of electricity, which had been
assured to it by the respondent-State.
35.If an assurance was given to the appellants and similarly
situated persons that they would be given 100% electricity
supply for five years, the respondents can not riggle out of their
liability by making a policy to the effect that the benefit by way
1
Page 19
of incentive would be extended only if the electricity supply
was reduced to less than 50% on a particular day. A steel
industry, for example, which cannot function without electricity
or power in any other form, would be put to enormous
inconvenience and loss if the power supply is not continuous.
So as to reactivate or to restart the machines or to start the
process afresh, the industry has to spend something more then
what it would have spent if the supply or power namely,
electricity was uninterrupted. Stoppage of manufacturing
process would mean losses under several heads. The labour
employed has to be paid even when the employer does not get
work from the labour force. Very often, so as to bring a
required temperature for the purpose of carrying on certain
processes, more fuel is to be injected so as to attain the
condition which was prevailing prior to electricity supply being
disconnected. Moreover, there would be several overhead
expenses which one has to incur even if there is no production
or stoppage of manufacturing process.
36.The judgments cited by the counsel appearing for the
respondents would not help them for the reason that in the cases
1
Page 20
referred to, the Government had to change the policy in public
interest. In the instant case, by compensating the aggrieved
appellants, no harm would be caused to the State of Kerala
except that it will have to compensate the appellants by
supplying assured electricity for some extended period at a
specified tariff.
37.For the aforestated reasons, in our opinion, the respondent-State
was not wholly fair when it extended benefit to the appellants
only for the period during which electricity supply was reduced
to less than 50% on certain days.
38.We, therefore, hold that the benefit extended by the respondent
State is not sufficient. The respondent-State ought to have
extended the period even for the days when supply of electricity
was more than 50% but not 100% as assured under G.O. dated
21.5.1990 and 6.2.1992. We, therefore, direct the respondents
to give the said benefit by extending the period of incentive.
39.We, therefore, allow the appeals by quashing and setting aside
the impugned order passed by the High Court and direct the
respondents to calculate the period during which 100%
electricity supply was not given to the appellants and extend the
2
Page 21
period of incentive accordingly. The calculation shall be made
and consequential orders shall be passed within two months
from today. The appeals are allowed with no order as to costs.
……………………….J. (ANIL R. DAVE)
……………………….J. (A.K. SIKRI)
New Delhi February 6, 2014.
2