M/S LANCO HILLS TECHNOLOGY PARK PVT LTD. Vs MANISHA BALKRISHNA KULKARNI
Bench: HON'BLE DR. JUSTICE D.Y. CHANDRACHUD, HON'BLE MR. JUSTICE HRISHIKESH ROY
Judgment by: HON'BLE DR. JUSTICE D.Y. CHANDRACHUD
Case number: C.A. No.-000155-000155 / 2015
Diary number: 39417 / 2014
Advocates: UMESH KUMAR KHAITAN Vs
1
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
Civil Appeal No 155 of 2015
M/s Lanco Hills Technology Park Pvt Ltd .... Appellant(s)
Versus
Manisha Balkrishna Kulkarni & Anr ....Respondent(s)
J U D G M E N T
Dr Dhananjaya Y Chandrachud, J
1 Admit.
2 This appeal arises from a judgment of the National Consumer
Disputes Redressal Commission1 dated 9 October 2014 in Consumer
Complaint No 112 of 2014.
3 An agreement to sell was executed between the appellant and the
respondents on 21 March 2011 under which the respondents agreed to
purchase an apartment in a complex which was developed by the
appellant in Hyderabad. The total consideration was Rs 1,55,50,826.
Subsequently, an amount of Rs 6,00,000 was paid towards an additional
parking space. Under Clause 5.1(iii) of the agreement, possession of the
1 NCDRC
2
apartment was to be handed over to the respondents by 28 March 2011,
with a grace period of three months. Clause 8 of the agreement
contemplated that the period of possession would be extended during the
operation of a force majeure event. The appellant received a no-objection
certificate from the State Disaster Response and Fire Services Department
on 4 July 2011. The final occupancy certificate for the residential tower in
which the apartment was situated was issued by the Andhra Pradesh
Industrial Infrastructure Corporation Limited on 22 August 2011.
4 Though the agreement contemplated that possession would be
handed over on 28 March 2011 with a grace period of three months, it
appears that on 28 March 2011 a restraining order was issued by the State
Waqf Tribunal as a result of a dispute in relation to a part of the land on
which the project was being developed. The order of the Waqf Tribunal
was upheld by the High Court on 3 April 2012. However, on 8 May 2012,
the order of injunction was vacated by this Court. On 15 October 2012, the
appellant informed the respondents that the apartment would be ready for
occupation on 3 November 2012 and followed this up with communications
dated 5 November 2012, 20 December 2012 and 7 February 2013. By the
communication dated 20 December 2012, the appellant recorded that all
the deficiencies which had been noticed by the respondents had been
cleared. Eventually, a sale deed was executed on 11 February 2013 and
the sale transaction was completed and registered. The total
consideration inclusive of the cost of the parking space was Rs
1,61,50,826. The respondents had paid 85% of the total agreed
consideration under the agreement to sell while the balance was paid,
3
together with the execution of the sale deed.
5 The dispute between the parties relates to the claim of the
respondents that despite the execution of the sale deed, possession was
not handed over. The respondents moved a consumer complaint before
the NCDRC seeking a direction for the handing over of physical
possession, together with interest and damages for delayed delivery.
6 During the pendency of the proceedings, possession of the apartment
was handed over to the respondents on 28 August 2014. A document
which is styled as “the Keys Hand Over Form” records that all three sets of
keys were handed over to the representative of the respondents.
7 The NCDRC disposed of the consumer complaint by its judgment and
order dated 8 October 2014. The NCDRC directed the appellant to pay
compensation at the rate of Rs 5 per sq ft for the delay of six months, at
the agreed contractual rate. There is a direction to pay compensation at
the rate of 18% per annum for the delay beyond six months for which no
specific provision was contained in the agreement between the parties.
8 Learned counsel appearing on behalf of the appellant placed reliance
on the provisions contained in the sale deed which was executed on 11
February 2013. Clause 3 of the sale deed contains a stipulation of
possession being handed over in the following terms:
4
“3. Possession
Simultaneously, upon the execution of this Sale Deed and the full receipt of the total consideration, the Vendor has and the Purchasers acknowledge that the Vendor has handed over the physical, vacant, lawful and peaceful possession of the Scheduled Property.”
Hence, it has been submitted that upon handing over of possession, the
appellant was not liable to pay compensation to the respondents.
9 On the other hand, it has been submitted on behalf of the
respondents that despite the above stipulation in the sale deed, the fact of
the matter is that there were numerous deficiencies in the apartment which
was agreed to be sold even at the stage when the sale deed was
executed. Hence, it has been submitted that it was only on 28 August
2014 that possession was handed over, as is evidenced by the document
which was executed between the parties.
10 The agreement to sell contained a stipulation in Clause 5.1(iii) to the
effect that the appellant would hand over the possession of the apartment
by 28 March 2011 and, in any event, within a grace period of three months
thereafter. The grace period expired on 28 June 2011. The agreement
contained a stipulation to the effect that:
“In the event of occurrence of a Force Majeure Event in terms of Clause 8 of this Agreement, the period of possession will be automatically extended for such period that the Force Majeure Event subsists. In the event of any delay beyond the time stated above the Developer shall pay the Purchaser an amount of Rs.5 (Rupees Five Only) per square foot of the Super built up area of the Residential Unit for every month of delay up to a maximum of 6 months”.
5
11 The record indicates that between 28 March 2011, when the
restraining order was passed by the Waqf Tribunal, and 8 May 2012, when
the injunction was vacated by this Court, the appellant was prohibited from
handing over of possession or alienating any part of the property. One of
the force majeure events stipulated in Clause 8 of the agreement is to the
following effect:
“(iv) any notice, order, rules, notification of the Government and/or other public or competent authority, including any prohibitory order of any court against development of property;”
Hence, in terms of the stipulation contained in Clause 5.1(iii), the period for
handing over of the possession stood extended during the prevalence of
the force majeure event. After the injunction was vacated by this Court on
8 May 2012, the appellant had, in terms of the grace period of three
months, time until 8 August 2012. Thereafter, for a period of six months
ending on 8 February 2013, the appellant was subject to the requirement
of paying compensation at Rs 5 per sq ft. The agreement stipulated that
this would be for a delay of up to a maximum of six months. The period of
six months ended on 8 February 2013. The agreement did not make any
specific provision for the period thereafter.
12 The respondents had paid 85% of the agreed consideration, together
with the agreement to sell, and even the balance at the time when the sale
deed was executed on 11 February 2013. Having paid the consideration,
it was evidently not in their interest to delay the receipt of possession.
6
Though the sale deed records that possession was handed over, it is clear
from the contemporaneous record that it was only on 28 August 2014 that
all the sets of keys of the apartment were handed over to the respondents.
Consequently, the appellant would be liable to pay reasonable
compensation to the respondents for the period between 9 February 2013
and 28 August 2014, in addition to the contractual payment due for the
period between 8 August 2012 and 8 February 2013.
13 However, we are of the view that the direction to pay interest at the
rate of 18% per annum is excessive and accordingly has to be scaled
down. Adopting a rate of 6% as a broad guideline, we have computed the
compensation at a lump sum of Rs 10 lakhs to obviate any dispute on
computation.
14 We accordingly issue the following directions:
(i) For the period between 8 February 2012 and 8 February 2013, the
appellant shall pay compensation in terms of Clause 5.1(iii) of the
agreement to sell at the rate of Rs 5 per sq ft;
(ii) For the period between 9 February 2013 and 28 August 2014, the
compensation which is payable by the appellant to the respondents is
computed at a lump sum of Rupees Ten Lakhs.
The aforesaid amount shall be paid within a period of one month from the
receipt of a certified copy of this order.
7
15 The appeal is partly allowed in the above terms. There shall be no
order as to costs.
…………...…...….......………………........J. [Dr Dhananjaya Y Chandrachud]
…..…..…....…........……………….…........J. [Hrishikesh Roy]
New Delhi; December 17, 2019
8
ITEM NO.23 COURT NO.8 SECTION XVII-A
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
Civil Appeal No(s). 155/2015
M/S LANCO HILLS TECHNOLOGY PARK PVT LTD. Appellant(s)
VERSUS
MANISHA BALKRISHNA KULKARNI & ANR. Respondent(s)
(WITH IA No. 2/2015 - STAY APPLICATION) Date : 17-12-2019 This appeal was called on for hearing today.
CORAM : HON'BLE DR. JUSTICE D.Y. CHANDRACHUD HON'BLE MR. JUSTICE HRISHIKESH ROY
For Appellant(s) Mr. Deepak Khurana, Adv. Mr. Tejasv Anand, Adv. Mr. Umesh Kumar Khaitan, AOR
For Respondent(s) Mrs. D. Bharathi Reddy, AOR
Ms. D. Tejaswi Reddy, Adv.
UPON hearing the counsel the Court made the following O R D E R
Admit.
The appeal is partly allowed in terms of the signed
reportable judgment.
There shall be no order as to costs.
Pending application, if any, stands disposed of.
(SANJAY KUMAR-I) (SAROJ KUMARI GAUR) AR-CUM-PS COURT MASTER
(Signed reportable judgment is placed on the file)