M/S. DSR STEEL (P) LTD Vs STATE OF RAJASTHAN .
Bench: T.S. THAKUR,GYAN SUDHA MISRA
Case number: C.A. No.-003814-003814 / 2007
Diary number: 9716 / 2007
Advocates: Vs
MILIND KUMAR
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3814 OF 2007
M/s. DSR Steel (P) Ltd. …Appellant
Versus
State of Rajasthan & Ors. …Respondents
(With Civil Appeal No.4393/2007 and No.4396/2007)
O R D E R
T.S. THAKUR, J.
1. These appeals under Section 125 of the Electricity Act,
2003 call in question the correctness of an order dated 23rd
November, 2006, passed by the Appellate Tribunal for
Electricity whereby a batch of appeals including those filed
by the appellants against an order dated 8th June, 2006
1
Page 2
passed by the Rajasthan Electricity Regulatory Commission,
have been dismissed.
2. Jaipur Vidyut Vitran Nigam Limited (‘JVVNL’ for short),
Jodhpur Vidyut Vitran Nigam Limited (‘JDVVNL’ for short)
and Ajmer Vidyut Vitran Nigam Limited (‘AVVNL’ for short),
submitted separate applications before the Rajasthan
Electricity Regulatory Commission (for short ‘Commission’)
at Jaipur in terms of Sections 62 and 64 of the Electricity
Act, 2003 for revision of tariff to be effective from
December 1, 2004. Each one of these distribution
companies (‘Discoms’ for short) had an existing tariff but in
their respective applications they sought an identical tariff
revision which requests were taken up by the Commission
for consideration together and disposed of in terms of a
common order dated 17th December, 2004, passed after
notices regarding filing of the said applications were
published in different newspapers having circulation in the
State of Rajasthan. Several objections were filed and
suggestions made by nearly 100 individuals and
organisations in the course of the proceedings before the
Commission. All these objections were then considered by 2
Page 3
the Commission no matter only 38 of those who had filed
the same had complied with the requirement laid down by
the former. A large number of people and organisations
even applied for personal hearing and were heard on
different dates at different venues fixed for the purpose.
Some of these objections also related to individual
problems of the consumers or disputes relating to bills and
other matters which were directed to be considered by the
Discoms and decision taken on the same under intimation
to the persons concerned. Other issues including those
questioning the maintainability of the petitions and alleging
non-compliance with the regulations and directions of the
Commission were also raised. Issues touching reforms in
power sector, non-determination of the Rajasthan Vidyut
Utpadan Nigam’s tariff from whom the Discoms purchase
electricity, poor performance of Vidyut Vitran Nigams were
also agitated. Similarly objections to the proposed increase
in tariff, interest charges, depreciation etc. too were raised
and examined by the Commission. Suggestions regarding
improvement, objections relating to high T&D losses,
inadequacy of staff, continuation of un-metered supply,
3
Page 4
issue of deemed licensee and tariff for deemed licensee
were also examined. Questions relating to high voltage
supply, segregation of mixed load, billing demand, demand
based tariff for MIP consumers, power factor and shunt
capacitor surcharge, vigilance checking of consumers,
minimum billing, agriculture, domestic and industrial tariff
too were examined by the Commission apart from several
other issues that were placed before the Commission to
which the Commission has made a reference in its order
dated 8th June, 2006. The Commission eventually directed
that the revised tariff determined by it will become effective
from 1st January, 2005 and remain in force till the same is
amended by the Commission by a separate order passed by
it.
3. Aggrieved by the order passed by the Commission, the
appellants and a large number of other consumers in that
category filed review petitions under Section 94 (1)(f) of
the Electricity Act, 2003 seeking review and continuation of
the incentive scheme. These review petitions were
dismissed by the Commission in terms of its order dated 8th
June, 2006. The Commission noted the contention urged on 4
Page 5
behalf of the petitioners that they were affected by the
withdrawal of the incentive scheme. It was also urged that
these consumers had made investments on the basis of the
incentive scheme bona fide believing that the same would
continue for at least three years. The review petitioners,
therefore, sought continuation of the said scheme by
suitable review of the Commission’s order dated 17th
December, 2004. The Commission also noted the
opposition of the Discoms to the said prayer and the
contention that the incentive scheme was to be effective
upto 31st March, 2003 or till the Commission issued a tariff
order whichever was earlier.
4. The Commission noted the submissions made on
behalf of the Discoms that the tariff petitions had been filed
in August 2004 and the details of the scheme had been
published in newspapers including the incentive scheme
which was deliberated in the course of the public hearing
and dealt with in the Commission’s tariff order dated 17th
December, 2004. It was also argued on behalf of the
Discoms that the modified incentive scheme was free from
any legal flaw. 5
Page 6
5. Consideration of the rival submissions led the
Commission to the conclusion that its order dated 17th
December, 2004 had examined the question raised by the
petitioners regarding the continuation of the incentive
scheme and found that the scheme had a limited validity
and its withdrawal did not offend the principles of
promissory estoppel. It also held that the modification of
the scheme was not without public notice and the
discontinuance of the old incentive scheme had been given
wide publicity pursuant to which large industries and
associations had been heard on the question of introduction
of a new scheme in place of the old. The Commission also
held that the question of applicability of Promissory
Estoppel had been raised before the Commission at the
hearing of the tariff petitions and that the material sought
to be introduced in support of the said plea at the stage of
review could not be taken into consideration. The
Commission, accordingly, concluded that there was no
mistake or error apparent on the face of the record in the
order passed by it to call for a review of the same. In
support the Commission noted several decisions of this
6
Page 7
Court on the question of Promissory Estoppel including
those delivered in M/s Motilal Padampat Sugar Mills
Co. Ltd. v. State of Uttar Pradesh and Ors. (1979) 2
SCC 409, Kasinka Trading and Anr. v. Union of India
an Anr. (1995) 1 SCC 274, Shrijee Sales Corporation
and Anr. v. Union of India (1997) 3 SCC 398, Union of
India & Ors. v. Godfrey Philips India Ltd. (1985) 4
SCC 369.
6. Aggrieved by the orders dated 17th December, 2004
and 8th June, 2006 passed by the Commission, the
appellants and few others filed Appeal Nos.180-197 of 2006
and Appeal No.226 of 2006 before the Appellate Tribunal
for Electricity, at New Delhi which were as noticed above
dismissed by the Tribunal by the order impugned in these
appeals. The Tribunal noted that there was no challenge
before it as to the revision of the tariff order issued by the
Commission. It also found that the Regulatory Commission
could exercise its power of review in terms of Section 94(1)
(f) of the Electricity Act, 2003 read with Order XLVII of the
Civil Procedure Code and that it could review an order,
provided a case for any such review was made out. The
7
Page 8
Tribunal rejected the contention urged on behalf of the
appellants that the doctrine of Promissory Estoppel was
attracted in the facts of the case. It concurred with the
view taken by the Commission that the incentive scheme
was applicable only upto 31st March, 2007 or till the
Commission issued a tariff order whichever was earlier. The
Tribunal observed:
“As has been held in Pawan Alloys & Casting Pvt. Ltd., Meerut v. U.P. State Electricity Board And Others, (1997) 7 Supreme Court Cases 251, in this case, no promise was held out to any new industries nor there was an invitation for investments of large scale fund but it only imposed a condition that existing industries could avail of the incentive subject to the stipulations in the scheme and nothing more. The tariff fixation is a statutory function in terms of The Electricity Act 2003 and tariff is to be fixed in the larger interest of consumer public at large. That being the position and when in the very tariff scheme, it has been specifically provided that the scheme will come to an end on 31.03.2007 or when the Regulatory Commission determines distribution tariff which ever is earlier. This is only meaning it is not known as to how the appellants could advance the said contention that the scheme is to be given any other meaning is impermissible. This sentence which is incorporated in the scheme is fatal to the claim of the appellants and none of the precedents pressed into service by the appellants will come to their rescue. It will be sufficient to answer this point, however, as the appellants on all the contentions pressed for a decision.”
7. We have heard learned counsel for the parties at
considerable length. An appeal under Section 125 of the
8
Page 9
Electricity Act, 2003 is maintainable before this Court only
on the grounds specified in Section 100 of the Code of Civil
Procedure. Section 100 of the C.P.C. in turn permits filing
of an appeal only if the case involves a substantial question
of law. Findings of fact recorded by the Courts below, which
would in the present case, imply the Regulatory
Commission as the Court of first instance and the Appellate
Tribunal as the Court hearing the first appeal, cannot be re-
opened before this Court in an appeal under Section 125 of
the Electricity Act, 2003. Just as the High Court cannot
interfere with the concurrent findings of fact recorded by
the Courts below in a second appeal under Section 100 of
the Code of Civil Procedure, so also this Court would be
loathed to entertain any challenge to the concurrent
findings of fact recorded by the Regulatory Commission and
the Appellate Tribunal. The decisions of this Court on the
point are a legion. Reference to Govindaraju v.
Mariamman (AIR 2005 SC 1008), Hari Singh v.
Kanhaiya Lal (AIR 1999 SC 3325), Ramaswamy
Kalingaryar v. Mathayan Padayachi (AIR 1992 SC
115), Kehar Singh v. Yash Pal and Ors. (AIR 1990 SC
9
Page 10
2212), Bismillah Begum (Smt.) (Dead) by LRs. v.
Rahmatullah Khan (Dead) by LRs. (AIR 1998 SC 970)
should, however, suffice.
8. The Regulatory Commission has, in the case at hand
recorded a clear finding of fact that the old incentive
scheme was limited only upto 31st March, 2007 or till the
Commission issued a tariff order whichever was earlier. It
has also recorded a finding that while considering revision
of tariff it had gone into the proposals regarding
introduction of a new incentive scheme and approved the
same, effectively bringing to an end the existing scheme
and introducing a new scheme in its place. The Commission
had declined to accept the contention that the appellant
companies had altered their position to their detriment by
making additional investments or that there was any
specific representation or promise made to them that the
old scheme would inevitably continue till 31st March, 2007.
The additional material which the appellants had sought to
introduce belatedly at the review stage had also been
declined by the Commission. In its order dated 17th
December, 2004 revising tariff the Commission had dealt
10
Page 11
with the question relating to the incentive scheme in the
following words:
“70. The incentive scheme was proposed by the Nigams as a stopgap arrangement to arrest the decline in industrial consumption. The Commission while conveying its approval to extension of the incentive scheme clearly stipulated that it shall be valid till 31.3.07 or revision of tariff whichever was earlier. The scheme itself had a limited validity and therefore, did not attract the principle of promissory estoppel. The Commission had envisaged review of incentive scheme at the time of tariff revision, as the proceeding would have provided opportunity to public to express their views to enable appropriate changes in incentive scheme or tariff.
71. After considering the petitioners’ proposal and the views expressed before us, the Commission is of the view that no separate scheme is called for at this stage. The need to provide incentive to promote consumption of electricity by large industrial power (LIP) consumers should be taken care of by the tariff itself. An incentive which encourages better load factor will serve the purpose. Consequently, an incentive scheme linked to consumption per KVA of contract demand is proposed. Accordingly we direct that the incentive shall be available to all LIP consumers including railways and public water works, and eligibility for incentive shall be as follows:
(i) The annual consumption of the consumer for the current financial year shall not be less than his annual consumption of the previous financial year.
(ii) In respect of new LIP consumers and existing LIP consumers who reduce their contract demand, incentive shall be admissible from the quarter following six months from the date of new connection or reduction of contract demand, as the case may be.
(iii) Consumer should have no arrear outstanding against him.
11
Page 12
72. Incentive shall be allowed to eligible consumers provisionally on quarterly basis provided that consumption during the quarter is not less than his consumption during the corresponding quarter during the previous year. Incentive so allowed shall be subject to final assessment at the end of the year, on year-to-year basis. If consumption of a consumer in any quarter is less than that of the corresponding quarter of the previous year but the annual consumption is more than that of the previous year, he shall be eligible for the incentive for the year as a whole. Incentive shall be as under on energy charges:-
(i) Energy consumption of 250 KWh per month per kVA of contract demand and upto 400 KWh per month per kVA of contract demand.
1.0%
(ii) Energy consumption exceeding 400 KWh per month per kVA of contract demand and upto 550 KWh per month per kVA of contract demand.
4.0%
(iii) Energy consumption in excess of 550 KWh per Month per kVA of contract demand.”
7.0%
9. The Tribunal concurred with the above view taken by
the Commission and repelled the contention based on the
principle of promissory estoppel not only on the ground that
there had been no unequivocal representation regarding
continuation of the scheme till 31st March, 2007 but also on
the ground that there was no material to support the
contention that the appellants had indeed made any
12
Page 13
investment or changed their position to their detriment so
as to attract the doctrine of promissory estoppel. In coming
to that conclusion the Commission has also relied upon
several decisions of this Court to which we have made a
mention above. We do not see any perversity in any one of
those findings nor do we see any substantial question of
law arising in the fact situation of these appeals. We have,
therefore, no hesitation in dismissing these appeals on
merits although the same have been filed beyond the
period stipulated for the purpose under Section 125 of the
Electricity Act, 2003.
10. We may before parting mention that in Civil Appeal
No.3814 of 2007 filed by DSR Steel (P) Ltd., one of the
questions that was urged before us was whether the period
of limitation would start running from the date of
pronouncement of the order or the date of communication
thereof. Relying upon the decision of this Court in
Chhattisgarh State Electricity Board v. Central
Electricity Regulatory Commission and Ors. (2010) 5
SCC 23 it was contended on behalf of the respondent that
the date on which the order was pronounced would also be
13
Page 14
the date on which the same is deemed to have been
communicated.
11. Section 125 of the Electricity Act, 2003 makes it
abundantly clear that the period of limitation commences
from the date of communication of the decision or order
and not from the date of its pronouncement. As a matter
of fact, Rules 94 and 98 of the Rules framed under the Act
make a clear distinction between intimation regarding
pronouncement of the order on the one hand and the
communication of the order so pronounced to the parties
on the other. While Rule 94 appears to us to provide for
notice of pronouncement of an order, it makes no mention
about the ‘communication’ of such an order as is referred to
in Section 125 of the Act. Transmission of the order by the
Court Master to the Deputy Registrar of the Tribunal and its
onward communication to the parties is dealt with by Rule
98 of the said Rules which communication alone can be
construed as a communication for purposes of Section 125
of the Electricity Act, 2003. The decision of this Court in the
Chattisgarh State Electricity Board’s case (supra) may
in that view require reconsideration if the same were to be
14
Page 15
understood to be laying down that the date of
pronouncement is also the date of communication of the
order. We would have, in the ordinary course, made a
reference to a larger Bench for that purpose but having
regard to the fact that we have dismissed the appeals on
merits, we consider it unnecessary to do so in the present
case.
12. So also the question whether an order passed by the
Tribunal in appeal merges with an order by which the
Tribunal has dismissed an application for review of the said
order was argued before us at some length. Learned
counsel for the appellants contended that since a review
petition had been filed by two of the appellants namely,
J.K. Industries Ltd. (Now known as J.K. Tyres and
Industries Ltd.) and J.K. Laxmi Cement Ltd. in this case,
the orders made by the Tribunal dismissing the appeals
merged with the orders passed by it in the said review
applications so that it is only the order dismissing the
review application that was appealable before this Court. If
that were so the period of limitation could be reckoned only
15
Page 16
from the date of the order passed in the review
applications.
13. Different situations may arise in relation to review
petitions filed before a Court or Tribunal. One of the
situations could be where the review application is allowed,
the decree or order passed by the Court or Tribunal is
vacated and the appeal/proceedings in which the same is
made are re-heard and a fresh decree or order passed in
the same. It is manifest that in such a situation the
subsequent decree alone is appealable not because it is an
order in review but because it is a decree that is passed in
a proceeding after the earlier decree passed in the very
same proceedings has been vacated by the Court hearing
the review petition. The second situation that one can
conceive of is where a Court or Tribunal makes an order in
a review petition by which the review petition is allowed
and the decree/order under review reversed or modified.
Such an order shall then be a composite order whereby the
Court not only vacates the earlier decree or order but
simultaneous with such vacation of the earlier decree or
order, passes another decree or order or modifies the one
16
Page 17
made earlier. The decree so vacated reversed or modified
is then the decree that is effective for purposes of a further
appeal, if any, maintainable under law.
14. The third situation with which we are concerned in the
instant case is where the revision petition is filed before the
Tribunal but the Tribunal refuses to interfere with the
decree or order earlier made. It simply dismisses the
review petition. The decree in such a case suffers neither
any reversal nor an alteration or modification. It is an
order by which the review petition is dismissed thereby
affirming the decree or order. In such a contingency there
is no question of any merger and anyone aggrieved by the
decree or order of the Tribunal or Court shall have to
challenge within the time stipulated by law, the original
decree and not the order dismissing the review petition.
Time taken by a party in diligently pursing the remedy by
way of review may in appropriate cases be excluded from
consideration while condoning the delay in the filing of the
appeal, but such exclusion or condonation would not imply
that there is a merger of the original decree and the order
dismissing the review petition.
17
Page 18
15. The decisions of this Court in Manohar S/o Shankar
Nale and Ors. v. Jaipalsing S/o Shivalalsing Rajput
(2008) 1 SCC 520 in our view, correctly settle the legal
position. The view taken in Sushil Kumar Sen v. State of
Bihar (1975) 1 SCC 774 and Kunhayammed and Ors.
v. State of Kerala & Anr. (2000) 6 SCC 359, wherein
the former decision has been noted, shall also have to be
understood in that light only.
16. In the result, we dismiss these appeals as no
substantial question of law arises for our consideration.
The respondent shall also be entitled to cost of Rs.20,000/-
in each case to be deposited in the SCBA Lawyers’ Welfare
Fund within six weeks from today.
……………………..……………..…J. (T.S. THAKUR)
……………………………….………J. (GYAN SUDHA MISRA)
New Delhi May 1, 2012
18