M/S A.B.N.A. Vs MNG.DIR.M/S U.P.S.I.D.C.KANPUR
Bench: A.K. PATNAIK,SWATANTER KUMAR
Case number: SLP(C) No.-016116-016117 / 2010
Diary number: 9984 / 2010
Advocates: Vs
RAKESH UTTAMCHANDRA UPADHYAY
Page 1
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE PETITION (C) Nos. 16116-16117 OF 2010
M/s A.B.N.A. and Ors. … Petitioners
Versus
The Managing Director, M/s. U.P.S.I.D.C. Limited, Kanpur & Anr. … Respondents
O R D E R
A. K. PATNAIK, J.
These are petitions under Article 136 of the
Constitution for leave to appeal against the order dated
04.03.2009 of the Monopolies and Restrictive Trade
Practices Commission, New Delhi, (for short ‘the MRTP
Commission’) in Review Application No.16 of 2007 and the
Page 2
order dated 05.01.2010 of the Competition Appellate
Tribunal, New Delhi, in Review Application No.06 of 2009.
2. The facts very briefly are that the respondents
published an advertisement in the Hindustan Times, New
Delhi inviting applications from entrepreneurs for allotment
of industrial land in Greater NOIDA on payment of 10% of
the cost of allotted land. In response to the advertisement,
the petitioners applied for a plot and on 05.03.1994 a plot of
800 square metres in Site-C was allotted. The petitioners
paid 10% of the cost of the plot on 23.03.1994. However,
physical possession of the plot was not given to the
petitioners on the ground that the petitioners had not paid
all the dues for the plot. The petitioners then filed a
complaint UTPE No.119 of 2000 before the MRTP
Commission and after notice to the respondents the
complaint was heard from time to time. While the
complaint was pending, petitioners filed I.A. No.18 of 2004
before the MRTP Commission to take possession of the
allotted plot. On 13.09.2007, the MRTP Commission passed
an order directing that the respondent shall handover
possession of the allotted plot within next two weeks to the
2
Page 3
complainant and as regards the balance amount, if any due,
the respondents shall submit a detailed chart giving the
dates on which the subsequent installments were due and
the amount payable on each due date. By the order dated
13.09.2007, the MRTP Commission also directed the
petitioners to furnish a fresh SSI certificate to the
respondents and directed that the matter be listed on
01.11.2007 for further directions. Instead of handing over
possession of the allotted plot to the petitioners, the
respondents filed Review Application No.16 of 2007 on
18.12.2007 and by the impugned order dated 04.03.2009
the MRTP Commission allowed the Review Application and
recalled the order dated 13.09.2007 insofar as it directed
the respondents to handover possession of the plot to the
petitioners. Aggrieved, the petitioners filed Review
Application No.06 of 2009 before the Competition Appellate
Tribunal and by the impugned order dated 05.01.2010, the
Competition Appellate Tribunal dismissed the Review
Application of the petitioners.
3
Page 4
3. The petitioner No.3, who appeared in-person and
argued on behalf of the petitioners, submitted that the order
dated 13.09.2007 of the MRTP Commission directing the
respondents to handover physical possession of the allotted
plot to the petitioners was a consent order as it was passed
on the consent of the two advocates appearing for the
respondents, namely, Mr. Shakti Singh Dhakray and Mr.
D.K. Sharma. He submitted that the order dated
13.09.2007 of the MRTP Commission being a consent order,
the same could not have been reviewed by the MRTP
Commission and on this ground the impugned order dated
04.03.2009 of the MRTP Commission recalling the order
dated 13.09.2007 in Review Application No.16 of 2007 is
illegal and is liable to be set aside. He further submitted
that Review Application No.16 of 2007 was filed before the
MRTP Commission by the respondents on 18.12.2007 more
than thirty days period prescribed for filing of the Review
Application. He submitted that by the time Review
Application No.16 of 2007 was filed, the petitioners had filed
contempt petition for violation of the order dated
18.12.2007 as well as a petition for executing the order
4
Page 5
dated 18.12.2007 before the MRTP Commission. He
submitted that the MRTP Commission should not have
entertained the Review Application after such long delay.
He finally submitted that the stand taken by the
respondents in Review Application No.16 of 2007 was that
the MRTP Commission had no jurisdiction to direct the
respondents to handover possession of the plot to the
petitioners but there are decisions of this Court which make
it clear that the MRTP Commission has the power to even
direct handing over possession to the complainant.
4. Learned counsel for the respondents, on the other
hand, submitted that the order dated 13.09.2007 of the
MRTP Commission was an interim order and the MRTP
Commission has rightly held in the impugned order dated
04.03.2009 that it could not have directed the respondents
by an interim order to handover possession of the plot to the
petitioners as this was the final relief claimed by the
petitioners in the complaint before the MRTP Commission.
Relying on the decision of this Court in Ghaziabad
Development Authority v. Ved Prakash Aggarwal [(2008) 7
5
Page 6
SCC 686], he submitted that the MRTP Commission has no
power to direct handing over possession of the plot to the
complainant and it is only the Civil Court which could while
granting a decree of specific enforcement of the contract
direct the defendants to handover possession to the
plaintiffs. He submitted that the order dated 13.09.2007
passed by the MRTP Commission directing handing over
possession of the plot to the complainant is thus without
jurisdiction. He submitted that this Court in Kiran Singh
and Others vs. Chaman Paswan and others (AIR 1954 SC
340) has held that an order without jurisdiction is a nullity
and can be challenged in collateral proceedings. In reply to
the submission on behalf of the petitioners that Review
Application No. 16 of 2007 was filed beyond 30 days and
belatedly, he submitted that under Section 13(2) of the
MRTP Act, the MRTP Commission has the power to revoke
any order passed by it “at any time”.
5. For deciding the contention raised on behalf of the
petitioners that the order dated 13.09.2007 of the MRTP
Commission was a consent order, we must look at the order
6
Page 7
dated 13.09.2007 of the MRTP Commission, which is quoted
hereinbelow:
“We have heard the arguments for some time of the parties. The parties are at issue regarding the balance amount payable by the complainant to the respondent towards balance installments or interest thereon. The other controversy is regarding the formalities namely certificate of SSI Registration and a NOC from Pollution Control Department of the State. Earlier the complainant had submitted a provisional SSI certificate which is already expired.
Complainant now undertakes to furnish the fresh SSI certificate to the respondent positively within one month. Respondent shall handover the possession within next two weeks thereafter to the complainant. As regards the balance amount if any due, the respondents shall submit a detailed chart giving the dates at which the subsequent installments were due and amount payable on each due date.
It has been pointed out by the learned counsel for the respondent that the complainant should hand over these documents to Mr. Dinesh Jain, Legal Adviser of UPSIDC at Surajpur Office with intimation to the counsel for the respondent who will ensure that the possession is delivered to the complainant within next two weeks.
The SSI certificate earlier submitted by the complainant was provisional and has already expired. Therefore, an issuance of that certificate by the concerned authority will not stand in the way of their issuing a fresh SSI certificate. The General Manager, District Industry Centre, Greater NOIDA is directed to issue the SSI certificate at the earliest after compliance of the necessary
7
Page 8
formalities. A copy of the order be given “dasti” to the complainant.
List on 1st November, 2007 for further directions.
Sd./- (Hon’ble J. Sri O.P. Dwivedi, Chairman) & (Sri D.C. Gupta, Member)”
On a reading of the order of the order dated 13.09.2007, we
do not find that the directions in the said order to the
respondents to handover the possession of the plot to the
petitioners was based on the consent of the learned
Advocates appearing for the respondents and this is what
has been held by the MRTP Commission also in the
impugned order dated 04.03.2009. Thus, the contention of
the petitioners that the order dated 13.09.207 of the MRTP
Commission was a consent order is misconceived.
6. It is not disputed by the petitioners that Review
Application No. 16 of 2007 was entertained by the MRTP
Commission under sub-section (2) of Section 13 of the
MRTP Act. Sub-section (2) of Section 13 of the MRTP Act is
quoted hereinbelow:
8
Page 9
“13(2) Any order made by the Commission may be amended or revoked at any time in the manner in which it was made.”
The language of sub-section (2) of Section 13 makes it clear
that the MRTP Commission may amend or revoke any order
in the manner in which it was made “at any time”. The
expression “at any time” would mean that no limitation has
been prescribed by the legislature for the MRTP Commission
to amend or revoke an order passed by it. Hence, the
argument on behalf of the petitioners that the MRTP
Commission could not have entertained the Review
Application for recalling the order dated 13.09.2007 beyond
the period of 30 days has no foundation in law. Moreover,
the order dated 13.09.2007 of the MRTP Commission on its
plain reading was only an interim order and the MRTP
Commission could modify or revoke the interim order
directing the respondents to handover physical possession
of the plot to the petitioners if it thought that such a
direction could only be considered at the time of finally
deciding the complaint. We therefore do not find any
infirmity in the order dated 04.03.2009 of the MRTP
Commission recalling the direction to handover physical
9
Page 10
possession of the allotted plot to the petitioner saying that
this direction can be considered at the stage of final
adjudication of the complaint.
7. On a perusal of the impugned order dated
04.03.2009, however, we find that although the respondents
cited the judgment of this Court in Ghaziabad Development
Authority v. Ved Prakash Aggarwal (supra) and contended
before the MRTP Commission that the MRTP Commission
had no authority to order handing over of possession and
that the jurisdiction was only with the Civil Court to order
specific performance of the contract, the MRTP Commission
has observed that this contention cannot be dealt with while
passing the interim order and can only be decided at the
time of final adjudication of the complaint. Hence, we are
not called upon to decide the question whether the MRTP
Commission has power to direct handing over the
possession of the plot to the complainant and this question
can be decided by the MRTP Commission at the stage of
final adjudication of the complaint.
10
Page 11
8. In the result, we do not find any merit in these
Special Leave Petitions and accordingly we decline to grant
special leave to the petitioners to appeal against the order
dated 04.03.2009 of the MRTP Commission and the order
dated 05.01.2010 of the Competition Appellate Tribunal.
The Special Leave Petitions are dismissed with no order as
to costs.
.……………………….J. (A. K. Patnaik)
………………………..J. (Swatanter Kumar)
New Delhi, May 08, 2012.
11