IN RE : T.N. GODAVARMAN THIRUMULPAD Vs UNION OF INDIA AND ORS.
Bench: S.H. KAPADIA,AFTAB ALAM,K.S. PANICKER RADHAKRISHNAN, ,
Case number: W.P.(C) No.-000202-000202 / 1995
Diary number: 2997 / 1995
Advocates: BY COURTS MOTION Vs
ANIL KATIYAR
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
Page 29
Page 30
Page 31
Page 32
Page 33
Page 34
Page 35
Page 36
Page 37
Page 38
Page 39
Page 40
Page 41
Page 42
Page 43
Page 44
Page 45
Page 46
Page 47
Page 48
Page 49
Page 50
Page 51
Page 52
Page 53
Page 54
Page 55
Page 56
Page 57
Page 58
Page 59
Page 60
Page 61
Page 62
Page 63
Page 64
Page 65
Page 66
Page 67
Page 68
Page 69
Page 70
Page 71
Page 72
Page 73
Page 74
Page 75
Page 76
Page 77
Page 78
Page 79
Page 80
Page 81
Page 82
Page 83
Page 84
Page 85
Page 86
Page 87
Page 88
Page 89
Page 90
Page 91
Page 92
Page 93
Page 94
Page 95
Page 96
Page 97
Page 98
Page 99
Page 100
Page 101
Page 102
Page 103
Page 104
Page 105
Page 106
Page 107
Page 108
Page 109
Page 110
Page 111
Page 112
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION
I.A. NOS. 1868, 2091, 2225-2227, 2380, 2568 and 2937
IN
WRIT PETITION (C) No. 202 OF 1995
Lafarge Umiam Mining Pvt. Ltd. … Applicant
T.N. Godavarman Thirumulpad … Petitioner(s)
versus
Union of India & Ors. … Respondent(s)
J U D G M E N T
S. H. KAPADIA, CJI
Facts
1. Lafarge Surma Cement Ltd. (‘LSCL’ for short) is a
company incorporated under the laws of Bangladesh. It has
set up a cross-border cement manufacturing project at
Chhatak in Bangladesh, which inter-alia has a captive
limestone mine of 100Ha located at Phlangkaruh, Nongtrai,
East Khasi Hills District in the State of Meghalaya. The mine
is leased out in favour of Lafarge Umium Mining Pvt. Ltd.
(‘LUMPL’ for short), which is an incorporated company under
the Indian Companies Act, 1956 and which is a wholly owned
subsidiary of LSCL. The entire produce of the said mine is
used for production of cement at the manufacturing plant at
Chhatak, Bangladesh under the agreement/arrangement
between Government of India and Government of Bangladesh.
There is no other source of limestone for LSCL except for the
captive limestone mine situated at Nongtrai, East Khasi Hills
District in the State of Meghalaya. The limestone as mined by
LUMPL is conveyed from the mine situated at Nongtrai after
crushing in a crusher plant. The limestone mined is conveyed
by a conveyor belt to LSCL plant in Bangladesh.
2. The National Forest Policy, 1988 stood enunciated
pursuant to Resolution No. 13/52-F, dated 12th May 1952 of
GOI to be followed in the management of State Forests in
India. The said Policy stood enunciated because over the
years forests in India had suffered serious depletion due to
relentless pressures arising from ever increasing demand for
fuel wood, fodder and timber; inadequacy of protection
2
measures; diversion of forest lands to non-forest uses without
ensuring compensatory afforestation and essential
environmental safeguards; and the tendency to look upon
forests as revenue earning resource. Thus, there was a need
to review the situation and to evolve, for the future, a strategy
of forest conservation including preservation, maintenance,
sustainable utilisation, restoration and enhancement of the
natural environment. It is this need which led to the
enunciation of National Forest Policy dated 7th December,
1988. The principal aim of the Policy was to ensure
environmental stability and maintenance of ecological balance.
The derivation of direct economic benefit was to be
subordinate to the principal aim of the Policy (See para 2.2).
Under essentials of forest management it is stipulated that
existing forests and forest lands should be fully protected and
their productivity improved. It is further stipulated that forest
cover should be increased rapidly on hill slopes, in catchment
areas and ocean shores. It is further stipulated that diversion
of good and productive agricultural lands to forestry should be
discouraged in view of the need for increased food production
3
(See para 3.2). Under the Policy a strategy was prescribed vide
para 4. The goal is to have a minimum of one-third of the
total land area under forest or tree cover. In the hills and in
mountains the aim is to maintain two-third of the area under
forest or tree cover in order to prevent erosion and land
degradation and to ensure the stability of the fragile eco-
system. Under para 4.2.3, village and community lands,
which is the common feature in north-east regions, not
required for other productive uses, should be taken up for
development of tree crop and fodder resources and the
revenue generated through such programmes should belong to
the panchayats where lands are vested in them and in other
cases such revenues should be shared with local communities
to provide an incentive to them and accordingly land laws
should be so modified wherever necessary so as to facilitate
and motivate individuals and institutions to undertake tree
farming. Vide para 4.3.1, the Policy lays down that schemes
and projects which interfere with forests that cover steep
slopes, catchment of rivers, lakes and reservoirs, geologically
unstable terrain and such other ecologically sensitive areas
4
should be severely restricted. Tropical rain/moist forests,
particularly in areas like Arunachal Pradesh, Kerala, Andaman
& Nicobar Islands should be totally safeguarded. No forest
should be permitted to be worked without the government
having approved the management plan in a prescribed form
and in keeping with the National Forest Policy (See para 4.3.2).
Under para 4.3.4.2 the rights and concessions from forests
should primarily be for the bonafide use of the communities
living within and around forest areas, specially the tribals.
The Policy recognizes the fact that the life of tribals and other
poor people living within and near forests revolves around
forests and therefore the Policy stipulates vide para 4.3.4.3
that the rights and concessions enjoyed by such persons
should be fully protected and that their domestic requirements
of fuel wood, fodder, minor forest produce and construction
timber should be the first charge on the forest produce. Para
4.4 deals with diversion of forest lands for non-forest
purposes. Under the said para it is stipulated that forest land
or land with tree cover should not be treated merely as a
resource readily available to be utilised for various projects,
5
but as a national asset which requires to be properly
safeguarded for providing sustained benefits to the
community. Diversion of forest land for non-forest purpose
therefore should be subject to most careful examination by
experts from the stand point of social and environmental costs
and benefits. Construction of dams and reservoirs, mining
and industrial development should be consistent with the
need for conservation of trees and forests. Projects which
involve such diversion should at least provide in their
investment budget, funds for regeneration/compensatory
afforestation. Beneficiaries who are allowed mining and
quarrying in forest lands and in lands covered by trees should
be required to re-vegetate the area in accordance with forestry
practices and, therefore, by para 4.4.2 it is stipulated that no
mining lease shall be granted without a proper mine
management plan. Under para 4.5 it is stipulated that forest
management should take special care for wildlife conservation
and consequently forest management plans should include
prescriptions for that purpose. Under para 4.6 of the Policy it
is stipulated that a primary task of all agencies responsible for
6
forest management shall be to associate the tribals and
communities living in such areas in the protection,
regeneration and re-development of forests as wells as to
provide gainful employment to people living in and around the
forest.
3. On 27.1.1994, in exercise of the powers conferred by
Section 3(1) read with clause (v) of sub-Section (2) of Section 3
of the Environment (Protection) Act, 1986 (for short “the 1986
Act”) read with Rule 5(3)(d) of Environment (Protection) Rules,
1986 the Central Government issued Environmental Impact
Assessment Notification whereby it directs that on and from
the date of publication of the said Notification in the official
gazette expansion or modernization of any activity or a new
project listed in Schedule-I shall not be undertaken in India
unless it has been accorded environmental clearance by the
Central Government in accordance with the procedure
specified in the Notification. Under clause (2)(I) any person
who desires to undertake any new project listed in Schedule-I
shall submit an application to MoEF, New Delhi in the
proforma specified in Schedule-II to be accompanied by a
7
project report which shall include EIA report/environment
management plan prepared in accordance with the guidelines
issued by MoEF. Under clause 2(II) in case of mining as a site
specific project the project authority (project proponent) will
intimate the location of the project site to the MoEF while
initiating any investigation and survey. The MoEF will convey
its decision regarding suitability of the proposed site within a
specified period. Thus, site clearance will be granted for a
sanctioned capacity and shall be valid for five years for
commencing construction, operation or mining. The EIA
Report submitted with the application by the project
proponent shall be evaluated and assessed by the Impact
Assessment Agency, and if deemed necessary, it may consult a
Committee of Experts having a composition as specified in
Schedule-III. The Impact Assessment Agency (IAA) is MoEF.
The Committee of Experts shall have full right of entry and
inspection of the site. The IAA shall prepare a set of
recommendations based on technical assessment of
documents and data, furnished by the project authorities
(project proponent), supplemented by data collected during
8
visits to sites which would include interaction with the affected
population and environmental groups, if necessary. The
summary of the reports, the recommendations and the
conditions, subject to which environmental clearance is given,
shall be made available subject to public interest to the
concerned parties or environmental groups on request.
Comments of the public may be solicited within the specified
period by IAA in public hearings arranged for that purpose.
The pubic shall be provided access, subject to public interest,
to the summary of the EIA report/environment management
plan. The clearance granted shall be valid for five years for
commencement of the construction or operation of the plant.
The monitoring of the implementation of the recommendations
and conditions of IAA is also provided for in the said
notification vide clause IV.
4. The said notification dated 27.1.1994 stood slightly
amended by notification dated 10.4.1997. By the said
notification detailed procedure for public hearing has been
prescribed. It also prescribes composition of public hearing
panels.
9
5. On 1.9.1997 LMMPL made an application for granting
environmental clearance for limestone mining project at
Nongtrai, East Khasi Hills District, Meghalaya. The
application was made under EIA Notification, 1994. It was
made in the form prescribed by the Notification, 1994. 20
copies of Rapid EIA Report (NEHU Report) were also annexed
therewith. However, the said proposal dated 1.9.1997 was
returned by MoEF vide letter dated 24.10.1997. The reason
being that on 10.4.1997, as stated hereinabove, the MoEF had
amended the EIA Notification of 1994 making public hearing
mandatory for the development projects listed in Schedule-I of
the Notification. By reason of the said Notification dated
10.4.1997 the then project proponent (M/s. LMMPL) was
asked to seek Site Clearance as well as Project Clearance
separately. The Site Clearance proposal was called for
through the State level agency dealing with the mines.
Accordingly, by application dated 23.9.1998 M/s. LMMPL
applied for Site Clearance for Limestone Mining Project at
Nongtrai village, East Khasi Hills District, Meghalaya. This
application was made in the prescribed form. The application
10
indicates that there exists an approach/access road to the site
that is described as Shillong-Mawsynram-Nongtrai or Shillong-
Cherrapunjee-Shella-Nongtrai. The application further states
that all villages represent tribal population. The application
further indicates that there exists many private limestone
quarries in the area. It is further stated in the application that
the topography of the area is hilly. Against the column ‘Forest
Land Involved in the Project’ the answer given by the project
proponent was “Nil”. According to the application the site is
not a habitat/corridor for endangered/rare/endemic species.
The source of this information was the NEHU Report.
According to the said Report, mining of limestone in Khasi
Hills was a source of revenue right from 1858. The limestone
deposit in Meghalaya is estimated to be 2165 million tonnes.
Exploitation of Nongtrai limestone dates back to 1885. Even
today, a number of private parties quarry limestone in this
area. An area of 100 hectares stood acquired by LMMPL on
lease basis for mining. For that an agreement was signed with
Village Durbar. The limestone bearing area around Nongtrai
and Shella falls under the Karst topography. This area falls on
11
the southern fringe of the Meghalaya plateau. [See Land Use/
Land Cover Map (March 1997) submitted by Mr. F.S. Nariman,
Source: IRS-1C LISS-3 MX DATA, Path & Row: 111-054, Date:
March 1997] Karst topography is a landscape formed by the
dissolution of a layer(s) of soluble bedrock, usually carbonate
rock such as limestone. Karst topography is characterized by
limestone caverns carved by groundwater. Karst landscapes
are formed by the removal of bedrock (composed in most cases
of limestone, gypsum or salt). [See Article from Encyclopedia
Britannica by William B. White] Alongwith the application, a
certificate dated 27.8.1997 was annexed. It was issued by
Khasi Hills Autonomous District Council, Shillong which
council is the constitutional authority under Sixth Schedule
of the Constitution. By the said certificate the council
specifically stated that it had no objection for mining operation
in the area at Nongtrai village since the area does not fall
within a forest land. This application for site clearance was
allowed by MoEF vide letter dated 18.6.1999 addressed to the
Project Proponent. Site clearance was, thus, granted under
the 1994 Notification as amended on 4.5.1994 and 10.4.1997
12
subject to strict compliance of terms and conditions
mentioned therein. One of the conditions was that the Project
Proponent shall obtain environmental clearance for the
proposed limestone mine as per the procedure laid down in
the 1994 Notification before taking up developmental work at
the site. The said clearance was not to be construed as grant
of mining permission. No developmental activity relating to
the project was to start prior to environmental clearance.
Accordingly, on 17.4.2000, LMMPL made an application for
environmental clearance to MoEF in the prescribed form to
excavate 2.0 million tonnes per annum of limestone and to
transport the same to Chhatak in Bangladesh through belt
conveyor (7.2 km long within Indian territory). The mining
lease area was indicated to be 100 hectare. The description of
land was shown as “barren”. In the application, it was further
stated that there is no notified forest land within 25 kms. from
the proposed mine. Along with the application vide Annexure
A, copy of No Objection Certificate (NOC) for mining operations
at the proposed site dated 27.8.1997 stood annexed. That
certificate was issued by Khasi Hills Autonomous District
13
Council, Shillong, which, as stated above, inter alia states that
the Council has no objection for mining operations at Nongtrai
Village since the area of 100 hectare does not fall within forest
land. Similarly, vide letter dated 6.7.1997 issued by Village
Durbar, NOC was granted for withdrawal of water for the
project. Vide Annexure G to the application, consent to
establish the project stood issued by Meghalaya Pollution
Control Board. By Annexure H to the application, minutes of
Environmental Public Hearing of the project has been
annexed. These minutes indicates the presence of Addl.
Deputy Commissioner, East Khasi Hills District, various
government officials including nominees of Forest
Conservators and Member Secretary of the Pollution Control
Board. According to the Headman of Nongtrai Village,
limestone is abundantly available in the area; the same has
not been utilized by local villagers due to lack of
infrastructure; for economic development, the Village Durbar
had decided to lease the area; the environmental implications
of the project stood discussed; complaint received from
Meghalaya Adventures Association was read out which
14
complaint mainly dealt with destruction of caves which stood
rebutted by the Headman and, thus, the meeting stood
concluded. All this indicates even public participation and
grant of NOCs by various competent authorities. Vide
Annexure J to the application for environmental clearance, we
find approval being granted under Section 5(1) of the Mines
and Minerals (Regulation and Development) Act, 1957. Along
with the application for environmental clearance M/s. LMMPL
also forwarded to MoEF Rapid EIA of Limestone Mine prepared
by Environmental Resources Management India Pvt. Ltd. This
report describes in detail the topography of the mining site.
According to the said report the leased area lies on the western
side of Umium river valley. It is approachable from Shillong
via Mawsynram and Nongtrai villages by motorable road. It is
also accessible from Shillong by road via Cherrapunji.
According to the report the site is at the Phalngkaruh which
originates from the foot hills of the proposed mine site.
According to the said report the site is on uneven terrain with
a rugged topography. There are heaps of fractured rocks all
over the place. It is a rocky region. The site rejects any
15
possibility of natural growth of forest. It is an area of low
botanical and floral diversity. It is an area covered with rocks.
The area can be termed as a wasteland.
6. On receipt of the application for environmental clearance,
certain queries were raised by MoEF with regard to the scope
of the site clearance (the original site clearance was for 0.8
million tonnes whereas subsequently that capacity was revised
to 2 million tonnes); that, as per this Court’s order dated
12.12.1996, “forests” has to be understood in terms of the
dictionary meaning and, accordingly, a certificate was asked
for in that regard from local DFO; the effect due to disposal of
waste water through soak pit and whether the existing road
width was sufficient to carry on heavy equipments for mining
purposes. These were some of the queries/ objections on the
basis of which clarification was sought vide letter dated
1.5.2000 by MoEF with regard to environmental clearance
under the 1994 notification. As requested by MoEF, the
project proponent vide letter dated 11.5.2000 requested the
local DFO to issue necessary certificate as called for by MoEF
in terms of the order of this Court dated 12.12.1996.
16
Accordingly, on 13.6.2000, the DFO forwarded the certificate
to the project proponent in respect of Limestone Mining Project
at Nongtrai, East Khasi Hills District, Meghalaya by which it
was certified that the mining site was not a forest area as per
this Court’s Order dated 12.12.1996 and nor did it fall under
any of the notified reserved or protected forests. Moreover, the
certificate once again reiterated that the site area stood
covered with Karst topography which supported only a
sporadic growth of a few tree shrubs. Despite such certificate
of DFO, MoEF in continuation of their letter dated 1.5.2000
called for additional information inter alia including list of
flora and fauna in compliance of Wildlife (Protection) Act,
1972, list of species under the 1972 Act, consent from the
State Pollution Control Board for 3000 TPD of limestone,
information on ground water potential, information regarding
water requirement, etc. Clarifications sought by MoEF vide
letters dated 1.5.2000 and 16.6.2000 for environmental
clearance were answered by LMMPL vide letter dated
17.8.2000. As per the said reply, the environmental public
hearing notice was published in three newspapers; that,
17
earlier the project proposal was for 0.8 million tonnes per
annum but later on based on the increased cement plant
production capacity in Bangladesh, it stood increased to 2.0
MTPA; that, earlier the lease period was proposed to be 35
years which stood reduced to 30 years; that, the mine site was
on Karst topography which neither MoEF nor the Shella Action
Committee (“SAC” for short) denies; that, the equipment to the
mine site would be brought through Guwahati – Shillong –
Mawsynram route which contains an established route whose
width was 7.5 m wide; that, there was no proposal to cut any
trees for the purpose; that, no sanctuary/ national park is
located within 25 kms. radius from the proposed mine
location; that, the mine site is situated in the southern slopes
of the Central Plateau of Meghalaya; that, the core area
comprising of the mining site consisted of uneven terrain with
a rugged Karst topography (see page 484 of Volume III); the
minutes of the environmental public hearing dated 3.6.1998
were also annexed; site clearance dated 18.6.1999 granted by
MoEF was also annexed; that, a report regarding impact of
limestone mining on Nongtrai, Meghalaya on Siltation Process
18
prepared by Center for Study of Man and Environment dated
April, 2000 also stood annexed to the clarifications given by
LMMPL. We need to comment on that report. Firstly, it
indicates that the mining site is located on the southern fringe
of the Meghalaya Plateau adjoining the plains of Bangladesh
having a rich endowment of high grade limestone. Secondly, it
highlights that the site is approachable from Shillong (109
km.) by motorable road via Mawsynram and Nongtrai.
Thirdly, it states that on account of dissolution of the
limestone, Karst topography has resulted which topography is
characterized by caverns and caves which are so prominent
that even in 1:50,000 toposheet, they could be plotted. In
other words, the karst features are intimately tied up with
hydrological situation. Certain recommendations have been
made in the report with regard to possible impact of limestone
mining on the Phalangkaruh river system. Despite
clarification, MoEF once again examined the matter through
Expert Committee which held its meeting on 19th and 20th
October, 2000 in New Delhi under the aegis of MoEF. In the
meeting, the project proponent made a presentation on their
19
proposal for production of limestone at the rate of 30,000
tonnes per annum for five years. Certain queries were raised
by the Expert Committee on the basis of which once again
further clarification was sought by MoEF from LMMPL vide
letter dated 6.11.2000. According to the query, the area in
question supports diversity of plants and animals. It also
represents the remnants of the rapidly vanishing humid
rainforest. That, the area is a home of endemic insectivorous
plants, butterflies; All this, according to MoEF, would require
a detailed survey of plants and animals to be carried out with
the help of BSI and ZSI offices located in Shillong.
Accordingly, the project proponent submitted report on
Ecological Status Survey prepared by Centre for Environment
and Development; report on Afforestation Reclamation Plan,
report on Physiography and Hydrogeology of Fugro Milieu
Consult B.V. and report on Catchment Area Treatment Plan,
vide letter dated 9.2.2001 addressed to MoEF. One more
aspect may be noted. These reports were placed before the
Expert Committee once again on 7.3.2001. Even Wild Life
Division also gave its report on 1.6.2001. After placement of
20
all these reports, at the end of the day, EIA Clearance was
given by MoEF on 9.8.2001 which again contained further
conditions which were to operate once the developmental work
started. According to the environmental clearance dated
9.8.2001, the total lease area of the mine is 100 hectares; that
no diversion of forest land was involved; that the targeted
annual production capacity of the mine had to be 2.0 million
tonnes and, lastly, certain general conditions were stipulated
with regard to steps to be taken during the developmental
work. On EIA Clearance being granted by MoEF, LMMPL
became desirous of transferring and assigning the lease in
favour of LUMPL having its registered office at Shillong on
which the State Government granted permission to transfer
the mining lease vide order dated 29.8.2001. Accordingly, a
transfer deed stood executed on 28.2.2002 in the prescribed
form under Rule 37-A of Mineral Concession Rules, 1960.
Accordingly, on 30.7.2002, environmental clearance which
was earlier granted to LMMPL stood transferred to LUMPL by
MoEF.
21
7. However, vide letter dated 1.6.2006, from Chief
Conservator of Forests (C), Shri Khazan Singh, addressed to
MoEF it was pointed out that he had visited Limestone Mining
Project of M/s. Lafarge when it was found that project had
completed developmental works and opening of mine benches
had also been accomplished for 7Ha of the mining lease land.
According to the said letter the mining lease area around the
developed mine benches stood surrounded by thick natural
vegetation cover with sizeable number of tall trees. The said
vegetation included trees being cleared for developing the
mining benches. That the wood obtained from felling of trees
was collected by the lessor who were from Nongtrai Village.
According to the said letter, for such clearance no permission
was taken under Forest (Conservation) Act, 1980 (for short the
‘1980 Act’). Further, even the Rapid EIA report submitted by
the project proponent described the land as wasteland though
the visit of the Chief Conservator found it to be otherwise.
Consequently, by the said letter the Chief Conservator of
Forests (C) informed the MoEF that the project proponent may
be directed to obtain forest clearance under the 1980 Act and
22
not to proceed with the mining activities till such clearance. A
copy of the said letter was also sent to the project proponent.
By letter dated 11.8.2006, the project proponent replied to the
Chief Conservator of Forests (C) stating that it had proceeded
with the developmental work on the basis of the certificate
given by DFO dated 13.6.2000 under which it was certified
that the project area was not a forest area and it did not fall in
any of the notified reserved or protected forests. It was further
clarified that in the core area there were only a few trees,
shrubs growing in some soil trapped in the crevices and only
those shrubs and trees which are growing in the area
demarcated on the excavation plan have been cut. According
to the said letter the 1980 Act was not applicable as there was
no diversion of forest land for non-forestry purposes.
Accordingly, a letter was addressed by MoEF on 15.11.2006 to
M/s. LMMPL. The complaint made by the Chief Conservator
of Forests (C) was conveyed to the project proponent. In terms
of the said complaint, MoEF directed M/s. LMMPL to obtain
forest clearance under the 1980 Act before taking steps to
clear vegetation including trees for developing mining benches.
23
On 14.9.2006, MoEF issued EIA Notification 2006 whereunder
concerns of local affected persons were required to be taken
into account through public consultation. By letter dated
29.1.2007, M/s. Lafarge took the stand that there is some
natural growing vegetation; that only those shrubs which are
growing in the excavation plan have been cleared and since
there was no diversion of forest land for non-forestry purposes
the 1980 Act was not applicable. Vide letter dated 9.4.2007
addressed by the Chief Conservator of Forests (C) to the
Secretary, Department of Forest and Environment,
Government of Meghalaya as well as to the Khasi Hills
Autonomous District Council, it was pointed out that the
mining project was undertaken in the virgin and natural
forest; that the forest is standing all around the periphery of
the broken area; that the mine was operating on forest land
without clearance under the 1980 Act; that the area is a
natural/virgin forest; that the land belonged to village Durbar
of Nongtrai and in the circumstances forest clearance was
required to be obtained under the provisions of 1980 Act in
terms of the order of the Supreme Court dated 12.12.1996.
24
According to the said letter, there was a clear violation of the
1980 Act. Accordingly, the Chief Conservator of Forests(C)
Shri B.N. Jha requested the Government of Meghalaya to stop
fresh clearance of vegetation, breaking of land, extension of
mining area, removal of felled trees and stoppage of non-
forestry activities with immediate effect. A copy of the said
letter was also forwarded to MoEF. By letter dated 17.4.2007
addressed by MoEF to Government of Meghalaya a report was
asked for indicating justification for continuance of mining by
the project proponent within a week failing which MoEF had
no option but to direct mine closure. Thereafter response was
given by M/s. Lafarge vide letter dated 25.4.2007. However,
MoEF, vide letter dated 30.4.2007, directed complete closure
of all on going non-forestry activities by M/s. Lafarge in
compliance of the directions of the Supreme Court dated
12.12.1996. Suffice it to state without going into further
correspondence that M/s. Lafarge submitted its application for
forest clearance under the 1980 Act vide application dated
3.5.2007. The application makes it clear that permission is
sought for forest clearance without prejudice to the rights and
25
contentions of the project proponent. After reciting the above
facts, M/s. Lafarge submitted that the project was a cross-
border project; that it had put in ten years of efforts for
obtaining approvals; that had the reservation on the legal
status of the land and the use of the mine site as forest land
been made clear by Chief Conservator of Forests (C) and had
such reservation been conveyed to M/s. Lafarge earlier or even
at the time of consideration of the proposal for environmental
clearance, they (project proponent) would have sought
approval under the 1980 Act before implementing the mining
project. It was pointed out that the mining lease area was 100
Ha. At the time of making the application for forest clearance
the broken up area was 21.44 Ha. In the said application
M/s. Lafarge undertook to bear the cost of raising and
maintenance of compensatory afforestation. They also
undertook to fulfill all other conditions leviable under the law.
By letter dated 11.5.2007 addressed by the Principal Chief
Conservator of Forests, Meghalaya to the Government of
Meghalaya, it was pointed out that the project proponent had
broken up area of about 21.44Ha; that the topography in the
26
leased mine around the broken up areas was Karst topography
consisting of limestone surface having natural fissures and
crevices; that a sizeable quantity of limestone was lying in and
around the broken up area; that the non-broken up area in
the leased mine was forest land falling within the purview of
the 1980 Act. By the said letter, the Principal Chief
Conservator of Forests submitted that the project proponent
be allowed to remove the already broken limestone from the
site and that the project proponent may be directed to apply
for forest clearance under the 1980 Act for the non-broken up
part of the leased area. It is at this stage that M/s. Lafarge
moved this Court by way of I.A. No. 1868 of 2007 inter alia
seeking orders directing MoEF to expeditiously process its
application under Section 2 of the 1980 Act within a time
bound programme preferably within 60 days. By letter dated
3.7.2007 addressed by M/s. Lafarge to the MoEF (North-East
Region), the regional office of the MoEF, was informed that the
project proponent had already applied for forest clearance to
the MoEF, New Delhi.
27
8. On 6.9.2007 CEC submitted its report to this Court
saying that the project proponent should have taken
permission under the 1980 Act before starting operations in
the area. According to CEC this was a typical case where ex-
post facto approval under the 1980 Act is sought after the
mine has been allowed to operate illegally. Since fait accompli
situation arose according to CEC there was no option but to
recommend the case for grant of permission for the use of
forest land for mining lease, conveyor belt system and
associated activities subject to certain conditions mentioned
therein. By interim order dated 5.2.2010 M/s. Lafarge was
directed to stop all mining activities. On 5.4.2010 a report
was submitted by Shri B.N. Jha, Regional Chief Conservator of
Forests (C) [also known as High Powered Committee (HPC)].
The report was submitted pursuant to the site inspection
carried out by a High Level Committee which also had
interaction with local population and institutions in the first
week of April, 2010. Briefly, it may be stated that the report
indicates assessment of the impact of the mining done by the
project proponent up to April 2010 on forest, wildlife and
28
surroundings. The report indicates details of the area already
broken up. On the impact aspect the report states that the
total clearing involves felling of 9345 trees out of which 1200
trees have already been felled. That, although the area
supports rich flora, the same can be re-forested as a part of
reclamation plan. According to the report, the said impact can
be minimized after a thorough study of Bio-Diversity
Management Plan as well as Catchment Area Treatment Plan
is prepared and executed in a time bound manner. At the
same time the report states that the project is positive and
beneficial to the residents of Nongtrai village due to huge
amount of cash going to village Durbar and reaching the
individual household improving the financial health of the
population of two villages, i.e., Nongtrai and Shella. According
to the report, interaction took place between the High Powered
Committee constituted by MoEF and the locals. That villagers
of Shella are not having any problems from M/s. Lafarge and
that the people are very satisfied with the mining company
which has provided health care facilities, drinking water
facilities, employment, schools etc. According to the report,
29
M/s. Lafarge has been contributing for the benefits of the
village as well as for all the villagers by way of payment of rent
for the use of the community land as well as towards the price
of limestone exported to Bangladesh. The figures of such
payments are also indicated in the report. Further, the report
states that mining is not having any adverse effect on the
human life. When the matter came before the Supreme Court
on 12.4.2010, the learned Attorney General stated that MoEF
will take a final decision under the 1980 Act for the revised
environmental clearance for diversion of 116 Ha of forest land
subject to certain conditions. Accordingly, on 19.4.2010 the
MoEF granted environmental clearance with certain additional
conditions. The environmental clearance dated 19.4.2010 was
followed by forest clearance dated 22.4.2010 (ex-post facto
clearance) granted by MoEF. This letter refers to letter of the
State Government dated 19.7.2007 forwarding its proposal for
diversion of 116.589 Ha of forest land for Lime Stone Mining in
favour of M/s. Lafarge wherein prior approval of Central
Government was sought. The said proposal of the State
Government was examined by FAC constituted by Central
30
Government under Section 3 of the 1980 Act. Thus, forest
clearance was granted by MoEF vide letter dated 22.4.2010
which again stipulated further conditions to be complied with
by the project proponent. Accordingly on 26.4.2010 learned
AGI submitted before this Court that M/s. Lafarge may be
permitted to resume the mining operations subject to
compliance of conditions enumerated in the order passed by
MoEF on 22.4.2010. However, this Court ordered that before
it grants permission to resume the mining operations it was
imperative that plans should be drawn up and relevant reports
be placed before this Court based on a comprehensive
engineering and biological study including assessment of flora
and fauna. A study report was submitted by NEHU on June,
2010 in which it has been stated that the forests in the said
area can be categorized into tropical moist-deciduous forest,
tropical semi-evergreen forest, savanna, subtropical
broadleaved forest, forest gardens, orchards etc. Regarding
the core area, the report states that the broken up area
(already mined) was 38.089 Ha; that the said area was devoid
of any vegetation and could be characterized by limestone floor
31
and benches. However, the vegetation in the rest of the core
area (i.e. proposed mining area) had tropical-moist deciduous
type of vegetation with variable canopy cover and mostly
sparse. It further states that the density of plants is very low
due to rocky terrain and low soil content. It further states that
only a few trees described in that paragraph are present in the
undisturbed core zone. On compliance of various conditions
imposed by MoEF including payment of compensatory
afforestation, penal compensatory afforestation and NPV with
interest as well as the reports submitted by various authorities
were placed before the Expert Appraisal Committee on
29.6.2010 and 21.7.2010 pursuant to the directions of the
Supreme Court vide order dated 26.4.2010. According to the
minutes of Expert Appraisal Committee, the conditions and
environmental safeguards stipulated by MoEF while according
environmental clearance on 9.8.2001 and 19.4.2010 were
comprehensive enough to mitigate any adverse impacts of the
project and to protect the environment if implemented
effectively. The minutes of the meeting of the Expert Appraisal
Committee dated 21.7.2010 also recites that various reports
32
were considered by the Committee. It also recites the fact that
the Government of Meghalaya had addressed a letter to MoEF
on 12.7.2010 conveying their recommendations for the grant
of formal approval under Section 2 of the 1980 Act for
diversion of 116.589 Ha of forest land for Lime Stone Mining.
On 21.10.2010 M/s. Lafarge submitted a compliance chart of
31 conditions.
Submissions
9. According to the learned Amicus Curiae, it is obvious
from all the documents that have come on record including
those filed by M/s. Lafarge that permissions under EIA
Notification, 1994 (as amended) under Section 3 of the 1986
Act have been obtained without a candid disclosure of the
facts. That, even if it is held that in cases of bona fide mis-
interpretation of statutory provisions and Rules the project
stood commenced without obtaining prior permission as
mandated under Section 2 of the 1980 Act, save and except in
cases of absolute candor and where the want of such
permission is solely and entirely on account of bona fide doubt
as to the nature and character of the land and /or statutory
33
regime applicable to such projects, no permission should be
granted specially to private projects established only for profit
where the project presents a ‘fait accompli’. The learned
Amicus submitted that over the years we find commencement
of projects without obtaining prior permission as mandated
under Section 2 of the 1980 Act and, when detected, the
project proponent(s) falls back on the plea of ‘fait accompli’.
According to the learned Amicus, time has, therefore, come for
this Court not to regularize such projects which are
commenced without obtaining prior permission under the
1980 Act except in cases of absolute candor and where the
want of permission is solely and entirely based on account of
bona fide doubt as to the nature and character of the land
and/ or the statutory regime applicable to such projects.
According to the learned Amicus, barring the above
exceptions, this Court should direct removal of the project and
restoration of the environment wherever it is possible or to
take over the project to ensure that all gains from such
projects are allowed to be used only for those whose rights
have been violated. In support of his above submissions,
34
learned Amicus placed reliance on the report of Chief
Conservator of Forests (C) dated 1.6.2006 addressed to the
MoEF in which it was stated that the mining lease area
around the developed benches has been found surrounded by
thick natural vegetation cover with sizeable number of tall
trees; that, the said vegetation including the trees was being
cleared for developing the mine benches; that, the wood
obtained from felling of trees was being collected by Nongtrai
Village Durbar; and that, the said report of the Chief
Conservator of Forests (C) dated 1.6.2006 contradicts the
Rapid EIA report submitted by the project proponent which
describes the land in question as waste land. The learned
Amicus also relied upon the second report dated 9.4.2007
again by the Chief Conservator of Forests (C) based on his site
visit on 7.4.2007 in which report it has been stated that the
mining lease lies in the midst of virgin and natural forest.
According to the said report, the said mine in question is
operating on forest land without clearance under the 1980 Act.
According to the said report, calling the area / site by any
other name than a forest would be travesty which could only
35
be assigned to an ulterior motive of obtaining exemption or
avoiding taking prior approval of Government of India under
the 1980 Act. The learned Amicus also placed reliance on the
report dated 11.5.2007 of the Principal Chief Conservator of
Forests. In the said report dated 11.5.2007, the Principal
Chief Conservator of Forests also agreed with the view of the
Chief Conservator of Forests (C) stating that the project
proponent should have taken permission under the 1980 Act
to start the operation in the area. According to the learned
Amicus, though the mine commenced commercial production
w.e.f. October, 2006, the said commencement was based on
approvals granted by statutory authorities on the assumption
that the mining lease area is a non-forest land. In this
connection, learned Amicus pointed out that the entire case of
the project proponent is based on only one certificate issued
by DFO, Khasi Hills Division dated 13.6.2000 in which it has
been certified that the mining site for limestone mining project
at Nongtrai, East Khasi Hills District, Meghalaya is not a forest
area in terms of the order of this Court dated 12.12.1996 and
that it does not fall under any notified reserved or protected
36
forests. In the said certificate, it has been further stated that
the project site is on Karst topography which supports only a
sporadic growth of a few trees shrubs and creepers. Besides
the said certificate dated 13.6.2000, the project proponent also
seeks to place reliance on letters dated 28.4.1997 and
27.8.1997 addressed by Khasi Hills Autonomous District
Council which took the view that the area is a non-forest land.
According to the learned Amicus, it is not open to the project
proponent to rely upon the certificate of DFO dated 13.6.2000
as the said certificate was given without any intimation to the
higher authorities and that an inquiry has been instituted to
determine the circumstances in which the certificate was
issued by DFO. Learned Amicus further pointed out that the
prospecting licence held by the project proponent was allowed
to be converted into a mining licence in 1997 which was after
the order of the Supreme Court dated 12.12.1996. That apart,
there is a special law in the State of Meghalaya, i.e. The United
Khasi-Jaintia Hills Autonomous District (Management and
Control of Forests) Act, 1985 under which forest has been
defined to mean an area in which there are twenty five trees
37
per acre. Thus, according to the learned Amicus by all these
definitions the area in question is a forest. Thus, according to
the learned Amicus even if the project proponent ultimately
succeeded in getting forest clearance under Section 2 of the
1980 Act on 22.4.2010 since the said project stood established
originally in the forest area in a brazen violation of the 1980
Act such a project cannot be allowed to be regularized by grant
of permission ex-post facto dated 22.4.2010.
10. Shri Shyam Divan, learned senior counsel appearing on
behalf of Shella Action Committee (SAC) while adopting the
submissions of the learned Amicus Curiae with regard to the
project being illegal, submitted that having regard to para
4.3.1 of the National Forest Policy, 1988, tropical rain/moist
forest are required to be totally safeguarded. According to SAC
the forest in the region is a tropical moist forest and no forest
clearance ought to have been granted because of the ecological
significance recognized by the 1988 Policy. According to SAC
this fact was known to M/s. Lafarge at all material times as
can be seen from the Rapid EIA Report prepared by NEHU
which specifically states that the vegetation at the study site is
38
a mixed moist deciduous forest. Reliance is also placed by the
learned counsel on the assessment of floral diversity prepared
by NEHU in June, 2010 which indicates that the forest in the
study area can be categorized into tropical moist-deciduous
forest, tropical semi evergreen forest, savanna, sub-tropical
broad leaves forest, forest garden, orchards and riparian
forest. According to the said assessment of 2010, the
vegetation in the core area is tropical moist-deciduous types
whereas the vegetation in the proper zone can be categorized
into tropical and sub-tropical types. Thus, according to the
learned counsel having regard to the undisputed position
emerging from the record the subject area is covered by a
tropical moist forest deserving highest degree of ecological
protection and therefore this Court should set aside the
environmental clearance dated 9.8.2001 given under Section 3
of the 1986 Act by MoEF. In this connection it may be
mentioned that SAC has also moved this Court by way of I.A.
No. 2937 of 2010 seeking revocation of the environmental
clearance dated 9.8.2001. They have also challenged the
revised environmental clearance dated 19.04.2010 granted by
39
MoEF as also Stage-I forest clearance dated 22.04.2010 issued
by MoEF.
11. According to the learned counsel, M/s. Lafarge was duty
bound to make an honest disclosure of all facts when seeking
environmental and forest clearances as it is an express
requirement under Clause 4 of the EIA notification 1994.
That, where a false information, false data, engineered reports
are submitted or factual data is concealed, the application is
liable to be rejected, and where granted, it is liable to be
revoked. According to SAC, M/s. Lafarge had given an express
undertaking in its application for environmental clearance
dated 17.4.2000 that if any part of the information submitted
was found to be false or misleading the project clearance could
be revoked at M/s Lafarge’s risk and cost. According to SAC,
the region where the mining is taking place and with regard to
which permissions were obtained is governed by a specific
local Act and Rules framed thereunder, namely, United Khasi
Jaintia Hills Autonomous District (Management and Control of
Forests) Act, 1958 which Act was enacted by the District
Council of the United Khasi Jaintia Hills Autonomous District
40
in exercise of its powers under the Sixth Schedule to the
Constitution of India. According to the learned counsel, the
1958 Act classifies forests and regulates forest resource
management and use and applying the definition of “forest”
under Section 2(f), the region where the mining is taking place
is a forest as the said area has not less than 25 trees per acre.
Thus, according to the learned counsel for SAC, it ought to be
assumed that the officials of M/s. Lafarge had full knowledge
of the local law as well as the forest cover and the lay out of
the land. From every perspective, M/s. Lafarge could not have
commenced the project without a detailed survey of the
physical topography of the land and the forest cover. Thus,
M/s. Lafarge had knowledge of the forest cover in the region
and yet it falsely withheld this information from the concerned
authorities including the MoEF. In this connection, learned
counsel placed reliance on the NEHU Report of 1997, letter
dated 1.6.2006 from the Chief Conservator of Forests (C) to
the MoEF, letter dated 9.4.2007 from the Chief Conservator of
Forests (C) to the Government of Meghalaya and assessment of
floral diversity prepared by NEHU in June, 2010. According to
41
the learned counsel, despite knowledge of the definition of
“forest” and the provisions of the 1958 Act, the government
officials issued letters containing incorrect information in
relation to the forest cover. These letters are the letter dated
28.4.1997 from Khasi Hills Autonomous District Council,
letter from the Deputy Commissioner, East Khasi Hills District
dated 10.7.1997 enclosing a spot inquiry report which stated
that there was no forest on the land proposed to be leased out,
letter dated 27.8.1997 from Khasi Hills Autonomous District
Council granting NOC on the basis that there was no forest
and certificate dated 13.6.2000 issued by DFO, Khasi Hills
Division stating that there was no forest on the land proposed
to be leased out. According to the learned counsel, the
environmental clearance dated 9.8.2001 issued by MoEF was
premised on “No diversion of forest land or displacement of
people is involved”. According to the learned counsel, the said
premise is per se incorrect as there is a tropical moist –
deciduous forest in the area being mined. According to the
learned counsel, the environmental clearance dated 9.8.2001
was clearly granted on the basis of false representations made
42
by M/s. Lafarge regarding absence of forests; engineered
reports projecting the site as “a near wasteland”; and the
concealment of factual data available with M/s. Lafarge
including the 1997 NEHU Report which showed the subject
land as forest land. Thus, according to the learned counsel,
the MoEF ought to revoke the environmental clearance dated
9.8.2001 having regard to Para 4 of the EIA Notification 1994
and inasmuch as the MoEF has failed and neglected to revoke
the clearance dated 9.8.2001, this Court may quash the said
clearance. According to the learned counsel, the
environmental clearance dated 9.8.2001 is the parent
clearance and, consequently, the revised environmental
clearance dated 19.10.2010 (the correct date is 19.4.2010)
must automatically fall if the parent clearance is quashed. In
any event, the learned counsel submitted that the revised
clearance is liable to be set aside since the mandatory
procedure of conducting a public consultation had not taken
place. According to the learned counsel, a public consultation
is mandatory in terms of para 7 of the EIA Notification dated
14.9.2006. Such consultation has not taken place. The
43
public hearing held on 3.6.1998 was without a disclosure of
the forest and, hence, there has been no public consultation in
accordance with para 7 of the EIA Notification dated
14.9.2006. Thus, according to the learned counsel, the
revised environmental clearance dated 19.4.2010 is liable to
be quashed on the ground of non-compliance of the
mandatory provisions of the EIA Notification of 2006.
According to the learned counsel, consequently, the stage-I
forest clearance dated 22.4.2010 is also liable to be rejected.
It may be noted that the stage-I forest clearance dated
22.4.2010 has been granted by FAC of MoEF. The learned
counsel submits that under National Forest Policy, 1988
tropical rain/ moist forest is required to be totally
safeguarded. That, it is a no-go area. According to the
learned counsel, since the region where mining is taking place
falls within tropical rain/ moist forest, FAC ought not to have
given the clearance on 22.4.2010. For the afore-stated
reasons, it is the case of SAC that both on account of the
nature of the land in question and the conduct of M/s.
Lafarge, this Court should dismiss the IA No. 1868 of 2007
44
filed by M/s. Lafarge and that the IA No. 2937 of 2010 filed by
SAC seeking revocation of the parent environmental clearance
dated 9.8.2001 and revised environmental clearance dated
19.4.2010 and forest clearance dated 22.4.2010 be allowed.
12. On the nature of the land in question, learned Attorney
General submitted that in the EIA Report (NEHU Report),
annexed along with the application dated 1.9.1997 for grant of
environmental clearance, a description of the vegetation area
at the proposed mining site which is distributed in three
distinct layers indicated that the third and the lower layer
consisted of shrubs and herbs and their poor growth was due
to lack of soil. It was also mentioned that the majority of
valuable timber trees had already been extracted from the
mining site in the past in Meghalaya by the tribals who lived
on timber. In para 4.9 of the Report the site was described to
be mostly covered with pole sized trees, shrubs and herbs.
This EIA Report did not make reference to the Certificate dated
28.4.1997 of the Khasi Hills Autonomous District Council, the
Spot Inspection Report dated 10.7.1997 nor the Certificate
dated 27.8.1997 issued by the Council all of which referred to
45
absence of forest. According to the learned Attorney General
at each stage MoEF had raised queries and requisitions and
after a thorough probe MoEF gave ultimately Environment
Clearance on 19.4.2010 and 22.4.2010 being the Forest
Clearance. In this regard it was pointed out by MoEF vide
letter dated 24.10.1997 that the EIA Notification 1994 was
amended on 10.4.1997 making public hearing mandatory for
the development projects listed in Schedule-I of the
Notification. Consequently, the proposal required two stage
clearance, namely, site as well as project clearance. This is
the reason why the project proponent made Site Clearance
application on 23.9.1998. Before that the project proponent
approached the Meghalaya State Pollution Control Board for
consent to establish limestone mining project. Similarly, a
public hearing notice was given on 27.4.1998. The public
hearing was conducted on 3.6.1998. This was followed by Site
Clearance Application dated 23.9.1998. All these steps were
taken by M/s. LMMPL, the predecessor of M/s. Lafarge. Even
before granting of the Site Clearance on 18.6.1999, a letter
dated 8.4.1999 was received from M/s. LMMPL sending a
46
certificate dated 20.3.1999 from DFO, Khasi Hills Division,
Shillong indicating absence of forest. Thus, at the stage of Site
Clearance MoEF had two certificates before it, one dated
27.8.1997 issued by the Executive Committee, Khasi Hills
Autonomous District Council and the other being the
certificate dated 20.3.1999 issued by DFO, both indicating
absence of forest. To the same effect is the main application
for Environmental Clearance dated 17.4.2000. One more fact
needs to be mentioned. Along with the application for
Environmental Clearance dated 17.4.2000, an EIA Report
prepared by Environmental Resources Management India Pvt.
Ltd. giving a detailed description of the topography of the area
was forwarded to MoEF. It was called as Karst Topography.
In that Report it was categorically stated that the project area
did not fall in the designated forest land; that the terrain at
the site was described as Karst Topography which did not
allow normal plant growth. Despite clarification, MoEF wrote
a letter dated 1.5.2000 to the project proponent seeking
further clarification as to whether there existed forest in terms
of the Supreme Court order dated 12.12.1996 and if so a
47
certificate to that extent should be obtained from the local
DFO. In reply, M/s. LMMPL forwarded a certificate of DFO
dated 13.6.2000 which stated that the proposed mining site
for limestone mining project at Phalangkaruh, Nongtrai, East
Khasi Hills District, Meghalaya leased out by M/s. LMMPL is
not a forest area as per Supreme Court judgment and it does
not fall under any of the notified reserves or protected forests.
The area is covered with Karst topography and supports only a
sporadic growth of a few trees, shrubs and creepers. The
proposal of M/s. LMMPL was once again discussed at the
meeting of the Expert Committee (Mining) held on 19-
20.10.2000. This Committee sought further information and
clarification, one of the clarifications sought was a detailed
survey of the plant and animals to be carried out with the help
of BSI and ZSI officers situated in Shillong. It also sought a
video film of the site and other areas. Accordingly, on
9.2.2001 M/s. LMMPL gave the requisite response as desired
by MoEF as well as additional information was also provided
in respect of a comprehensive survey and Flora and Fauna
Report dated January, 2001 of Dr. A.K. Ghosh (Former
48
Director ZSI). The said Report of January, 2001 extensively
dealt with tropical semi-evergreen forest at different elevations.
This Report of Dr. Ghosh (Centre for Environment and
Development) was placed before the Expert Committee on
7.3.2001. The minutes of the meeting indicate that a video
film of the site was also shown. The Report indicates the Karst
features, extensive flora and fauna survey carried out by the
Centre for Environment and Development in conjunction with
the Botanical Survey of India and Zoological Survey of India.
After elaborate discussion, the Expert Committee
recommended Environmental Clearance of the project once
again subject to certain conditions. Even after such
recommendation, the MoEF once again wrote to the Chief
Conservator of Forest, Meghalaya. This was on 19.4.2001
regarding Environmental Clearance. The Chief Conservator of
Forest (Wildlife Division) vide letter dated 1.6.2001 gave his
comments as per the annexures which was on the basis of
Field Verification Report submitted by DFO, Khasi Hills
Wildlife Division, Shillong. According to the Chief Conservator
of Forest (Wildlife Division) the project area is sloppy, ending
49
in the nearby plains of Bangladesh and covered wholly by
degraded forests and grassland vegetation. Further, he stated
that there is a motorable road used for traffic and the forest is
farther away up the slope. It was concluded that there was no
likelihood of any wildlife presence in the area. Thus,
according to the learned Attorney General it is incorrect to say
that the EIA clearance dated 9.8.2001 was granted without
proper consideration. There has been a detailed consideration
at every stage. That, at the time of the submission of the
application for Site Clearance dated 23.9.1998 there existed
an NOC of the Pollution Control Board, a certificate dated
27.8.1997 issued by East Khasi Hills Autonomous Council
and thus it cannot be said that the EIA clearance indicated
non-application of mind or that it was liable to be set aside on
the ground that the EIA Division of the MoEF did not properly
consider the matter. In the circumstances, according to the
learned Attorney General, it cannot be said that the
Environmental Clearance dated 9.8.2001 came to be issued by
MoEF arbitrarily, capriciously or whimsically. At that stage of
Environmental Clearance dated 9.8.2001 existence of the
50
forest land was not established. If it had been so established
then the project proponent had to obtain forest clearance
under the 1980 Act also.
13. At the outset, Shri F.S. Nariman, learned senior counsel
appearing on behalf of M/s. Lafarge adopted the submissions
made on behalf of MoEF by the learned Attorney General. As
regards the nature of the land, the learned counsel invited our
attention to the approved mining plan which was submitted by
LMMPL to the Regional Controller of Mines, IBM, Calcutta for
limestone extraction which plan was duly approved in
February, 1998. In this approved mining plan, the project
area was described as having Karst topography with the
presence of deep caverns, caves and cracks which permit
surface water to percolate downwards and circulate
underground only to reappear as hills side springs at certain
outlets. According to the mining plan, the terrain over the
entire area is rocky with very little soil and devoid of hard
overburden rocks. The vegetation of the area is seen to be
mixed deciduous type. There is no agricultural activity in the
area as thin soil cover is unable to sustain crops. That, even
51
according to the NEHU Report of 1997, the site selected for
mining has commercially viable limestone deposit. According
to the said report, the land was left unused covered with
degraded forests and this was the reason why the Durbar
preferred to lease out the site to LMMPL for mining. Other
factors responsible for selecting the proposed site were
availability of water resource, away from human habitation,
closer to the cement plant at Chhatak, easy accessibility by
road and minimum damage to the rich biodiversity (see page
19 of the NEHU Report). The learned counsel submitted that
Section 2 of the 1980 Act stipulates “prior approval”. Thus,
prior determination of what constituted forest land is required
to be done. This lacuna in the 1980 Act was supplied by the
order of this Court dated 12.12.1996 which inter alia provided
that every State Government shall first constitute an Expert
Committee within one month and based on its
recommendations the State Government will identify the land
as forest land on the criteria mentioned in the said Order. The
learned counsel also invited our attention to Rule 4 of the
Forest (Conservation) Rules, 1981 in which it is stipulated that
52
every State Government seeking prior approval under Section
2 of the 1980 Act shall send its proposal to the Central
Government in the form appended to the Rules. Thus,
according to the learned counsel, under the 1980 Act read
with the Rules, the requirement of submission of the proposal
for forest diversion under the 1980 Act is exclusively the
obligation of the State Government. This was also spelt out in
the guidelines issued on 25.10.1992. Later on the
Government of India amended the said guidelines in respect of
the diversion of forest lands for non-forest purpose under the
1980 Act by letter dated 25.11.1994 and in para 2.4 the
concept of “User Agency” was introduced but that concept was
made applicable only to cases of renewal of mining leases.
However, on 10.1.2003, Rule 4 of the 1981 Rules stood
reframed (as Rule 6 of the 2003 Rules) which inter alia
provided that every “User Agency” who wants to use any forest
land for non-forest purpose shall make its proposal in the
specified form appended to the Rules to the concerned Nodal
Officer along with the requisite information before undertaking
any non-forest activity on the forest land; after receiving the
53
proposal and if the State Government is satisfied that the
proposal required prior approval under Section 2, it had to
send the said proposal to the Central Government in the
appropriate form within 90 days of the receipt of the proposal
from the “User Agency”. The threshold limit was kept at 40
hectares. Where the proposal involved forest land of more
than 40 hectares, it was to be sent by the State Government to
the Government of India with the copy to the Regional Nodal
Officer. According to the learned counsel, insofar as M/s.
Lafarge was concerned, its predecessor LMMPL was already
given environmental clearance on 9.8.2001 and while granting
the clearance there was an express finding in the
environmental clearance that “no diversion of forest land was
involved”. Thus, it was never stipulated at any time as a
condition to the grant of environmental clearance dated
9.8.2001 that permission under the 1980 Act should be
obtained. The learned counsel further pointed out that
pursuant to the Order of this Court dated 12.12.1996 an
Expert Committee was formed by the State of Meghalaya vide
notification dated 8.1.1997 with the Principal Chief
54
Conservator of Forests as its Chairman. On 10.2.1997, the
State of Meghalaya, on the subject of “Order of the Supreme
Court dated 12.12.1996” wrote to the Khasi Hills Autonomous
District Council that the land in question was reckoned by the
State as non-forest land. The Council was asked to inform/
clarify whether the area in question under the mining lease fell
on forest land as per the records of the District Council. By
letter dated 28.4.1997, the Council informed the State
Government that the area in question did not fall on forest
lands. Moreover, pursuant to the Order of this Court dated
12.12.1996, the Chairperson of the Expert Committee
appointed by the State of Meghalaya also filed the report of the
Expert Committee in which it was expressly stated that the
mining lease granted by the State Government did not fall on
the forest land. Thus, it was under the above circumstances,
having regard to the order of this Court dated 12.12.1996,
that the State Government was not required to and it did not
submit any proposal to the Central Government under Section
2 of the 1980 Act read with Rule 4 of the 1981 Rules as it
treated the site in question as a non-forest land. This position
55
has not been disputed by MoEF. Thus, according to the
learned counsel, there was no obligation on the project
proponent or on the State of Meghalaya to move MoEF under
Section 2 of the 1980 Act.
14. According to the learned counsel, what has happened in
the present case is that almost after 9 years there was a
change of view on the part of MoEF, i.e., between 1997 and
2007. Under this change of view of MoEF, the report of the
Chairperson of the Expert Committee of the State of
Meghalaya which report stood annexed to the affidavit dated
3.5.1997 in this Court to the effect that the mining lease did
not fall on forest land was given a go-by and an entirely new
stand was taken only on and from 2006-07. One more aspect
has been highlighted by the learned counsel for M/s. Lafarge.
On 1.6.2006, the Chief Conservator of Forests (C), Shri
Khazan Singh stated that he had visited the limestone mining
project of M/s. Lafarge on 24.5.2006 when he found that the
mining lease area is surrounded by thick natural vegetation
cover with sizeable number of tall trees. According to the
Chief Conservator of Forests (C), the Rapid EIA Report (ERM
56
India Pvt. Ltd.) submitted by the project proponent describes
the land as waste land which was not a fact. Thus, according
to the Chief Conservator of Forests (C), the project proponent
should be directed to obtain clearance under the 1980 Act and
not to expand mining activities till such clearance is obtained.
After the said letter dated 1.6.2006, the then Principal Chief
Conservator of Forests now stated vide letter dated 11.5.2007
that he too agreed with the opinion of the Chief Conservator of
Forests (C), Shri Khazan Singh. However, according to the
learned counsel, even the Principal Chief Conservator of
Forests stated in his letter dated 11.5.2007 that though M/s.
Lafarge had failed to take forest clearance, they were not at
fault because of the certificate of the Council that the site fell
in a non-forest area. The letter dated 11.5.2007 further goes
on to state that the activities of the company will provide
employment to large number of local tribals and rural people
and that since the company had applied for forest clearance
on 3.5.2007 forest clearance may be considered. Thus,
according to the learned counsel, there was no collusion
between M/s. Lafarge and the DFO as alleged to get the
57
certificate dated 13.6.2000.
15. On the question of alleged suppression by M/s. Lafarge
from MoEF of the NEHU Report 1997, learned counsel
submitted that an application was prepared and submitted by
M/s. LMMPL for Environmental Clearance to MoEF vide letter
dated 1.9.1997; along with the said letter there were several
enclosures. One of the enclosures was the NEHU Report, the
other was NOC from Khasi Hills Autonomous Council for
mining operation in the project area. This letter dated
1.9.1997 was duly acknowledged by MoEF vide its letter dated
24.10.1997. As stated above, in view of the amendment to the
Notification of 1994, the project proponent was advised to
make a new proposal in two different parts, namely, site
clearance and project clearance. Pursuant to the said advice
the project proponent preferred Site Clearance Application on
23.9.1998 made to MoEF in which once again the project
proponent enclosed maps which were verbatim reproduction of
the relevant pages (including maps) in the NEHU Report.
MoEF granted Site Clearance on 18.6.1999. Further even the
Mining Plan submitted by the project proponent contained a
58
Chapter on Environment Management Plan (EMP) which is a
verbatim copy of Chapter 6 of NEHU Report. The said plan
was approved by Bureau of Mines. Moreover, in the
Sociological and Ecological Impact Assessment Report dated
16.2.1998 prepared by ERM it has been expressly stated that
Environmental Impact Assessment was carried out in 1997
and it was submitted to MoEF in September, 1997. To the
same effect one finds reference in the Executive Summary of
the EIA of proposed Limestone Mining of 9.4.1998 by ERM.
According to the learned counsel the above documents
indicate that there was no suppression by the project
proponent from MoEF of NEHU Report of 1997 as alleged.
One of the points which SAC has argued before us was
absence of public hearing as required under EIA Notification of
1994. On this aspect Shri Nariman, learned counsel
appearing on behalf of M/s. Lafarge invited our attention to
the requisite correspondence. On 22.4.1998 a Notification
was issued by Meghalaya State Pollution Control Board of
constituting an Environmental Public Hearing Panel to
evaluate and assess the documents submitted by the project
59
proponent and to verify the comments, views and suggestions
made by the public on the proposed project. This Notification
was issued in terms of the EIA Notification of 1994, as
amended on 10.4.1997. On 27.4.1998 a public notice was
also issued by MPCB informing the general public about the
limestone project of M/s. LMMPL. On 5.5.1998 MPCB
informed two local newspapers in writing asking them to
publish the Khasi translation of the public notice. On
6.5.1998 MPCB wrote to Shella Confederacy asking its
Headman to display two sets of executive summary each in
Khasi and English. On 13.5.1998 the State PCB wrote to the
Director of Information asking him to publish public notice in
Shillong Times. On 25.5.1998 the State PCB wrote to the
Secretary, Shella village informing him of date and time of
public hearing. 31 members attended the public hearing on
3.6.1998. As stated above, the entire proceedings have been
recorded in the minutes of the meeting. On 4.9.1998 the
Deputy Director, Govt. of India, MoEF forwarded a letter to the
State PCB enclosing proceedings of the public hearing
conducted for proposed limestone mining project of M/s.
60
LMMPL, Nongtrai. Thus, according to the learned counsel
there is no merit in the submission advanced on behalf of SAC
that public hearing as per EIA Notification of 1997 did not
take place.
16. Shri Nariman, learned counsel appearing on behalf of
M/s. Lafarge further submitted that on facts and
circumstances of the present case it is clear that both the
project proponent and the MoEF were at all relevant times
under the bona fide impression that the project site was not
forest land; in fact the consistent view of all authorities,
including MoEF, was that the project site (mining lease area)
was not located on “forest land”. In this connection our
attention was invited to the application dated 23.9.1998 made
by M/s. LMMPL to MoEF for Site Clearance, the NOC from
KHADC dated 27.8.1997 stating that the project area does not
fall within a forest land, grant of Site Clearance on 18.6.1999
by MoEF, application for Environmental Clearance dated
17.4.2000, grant of Environmental Clearance on 9.8.2001. All
these documents and series of letters exchanged during the
relevant time, according to the learned counsel, indicate that
61
both the project proponent and MoEF were at all relevant
times under the bona fide impression that the project site
(mining lease area) was not located on forest land.
17. Learned counsel further submitted that after stop mining
order dated 30.4.2007 and the direction of CCF(C) of even date
to obtain Forest Clearance under Section 2 of the 1980 Act, an
application was filed by M/s. Lafarge on 3.5.2010 to the State
Government under Rule 6 of the Forest Conservation Rules,
2003, as amended in 2004. Accordingly, on 11.5.2007 the
Principal Chief Conservator of Forest, Meghalaya wrote to the
Government of Meghalaya agreeing with the views of the CCF
(C) to the effect that M/s. Lafarge should obtain permission
under the 1980 Act. At the same time, as stated above, the
PCCF made it clear that no fault lay on the door step of M/s.
Lafarge for not seeking Forest Clearance earlier. Accordingly,
on 19.6.2007 a formal proposal was made by State
Government on 19.6.2007 to MoEF for diversion of 116.589
Ha of forest land for limestone and other ancillary activities in
favour of M/s. Lafarge in Khasi Hills Division under Section 2
of the 1980 Act. Thus, all necessary steps were taken, as
62
indicated hereinabove, by M/s. Lafarge which ultimately
culminated in the Environmental Clearance by MoEF dated
19.4.2010 and Forest Clearance dated 22.4.2010. In the
circumstances, learned counsel submitted that I.A.
1868/2007 preferred by M/s. Lafarge be allowed.
Issues
18(i) Nature of land;
(ii) Whether ex post facto environmental and forest
clearances dated 19.4.2010 and 22.4.2010 respectively
stood vitiated by alleged suppression by M/s. Lafarge
regarding the nature of the land. In this connection it
was contended by learned Amicus and by the learned
counsel appearing on behalf of SAC that the EIA
clearance under Section 3 of the 1986 Act dated 9.8.2001
(being a parent clearance) was obtained by M/s. Lafarge
on the basis of “absence of forest” with full knowledge
that the project site was located on forest land.
Findings
63
(a) Legal Position
19. Universal human dependence on the use of
environmental resources for the most basic needs renders it
impossible to refrain from altering environment. As a result,
environmental conflicts are ineradicable and environmental
protection is always a matter of degree, inescapably requiring
choices as to the appropriate level of environmental protection
and the risks which are to be regulated. This aspect is
recognized by the concept of “sustainable development”. It is
equally well-settled by the decision of this Court in the case of
Narmada Bachao Andolan v. Union of India and Others [(2000)
10 SCC 664] that environment has different facets and care of
the environment is an on-going process. These concepts rule
out the formulation of across-the-board principle as it would
depend on the facts of each case whether diversion in a given
case should be permitted or not, barring “No Go” areas (whose
identification would again depend on undertaking of due
diligence exercise). In such cases, the Margin of Appreciation
Doctrine would apply.
64
20. Making these choices necessitates decisions, not only
about how risks should be regulated, how much protection is
enough, and whether ends served by environmental protection
could be pursued more effectively by diverting resources to
other uses. Since the nature and degree of environmental risk
posed by different activities varies, the implementation of
environmental rights and duties require proper decision
making based on informed reasons about the ends which may
ultimately be pursued, as much as about the means for
attaining them. Setting the standards of environmental
protection involves mediating conflicting visions of what is of
value in human life.
(b) Nature of the land
21. In the NEHU Report of June, 1997 (Rapid EIA of
Proposed Limestone Mining Project at Nongtrai, Meghalaya), a
brief history of limestone mining in Khasi Hills of Meghalaya is
spelt out. It indicates that mining of limestone in Khasi Hills
dates back to July 10, 1763 when an agreement was signed
between East India Company and the Nawab of Bengal for
preparation of chunam. Regular trade of limestone from Khasi
65
Hills of Bengal started on and from 1858. Substantial revenue
was earned by the British Government from these limestone
quarries as rentals, which was Rs. 23,000/- in 1858 and
which subsequently stood increased to Rs. 67,000/- in 1878.
The first historical account of exploitation of Nongtrai
limestone dates back to 1885 when Don Rai of Shella obtained
permits from the Wahadars (Head of Confederacy) of Shella to
quarry limestone in Nongtrai village. There are historical
records about continuance of limestone trade between Khasi
Hills and Bengal up to 1947. The business declined after
partition. Limestone mining and trade slipped into the hands
of unorganized sector. According to the NEHU Report of 1997,
today a number of private parties quarry limestone using
unscientific methods and export it to counterparts in
Bangladesh, often illegally. These private parties sell the
product at a very low price. This aspect is also being
examined by CEC which has now filed its report in I.A. No.
3063 of 2011. One more aspect needs to be highlighted.
According to the State of Forest Report, 2001, the North
Eastern Hill State of Meghalaya is predominantly tribal with
66
86% population being tribal. According to the NEHU Report of
1997, approximately 60 settlements consisting of 50-200
inhabitants each with a total estimate population of 16500
persons exist within 10 km radius of the proposed mining site.
Under an agreement dated 29.9.1993 (lease agreement), the
village Durbar represented by a Special Committee headed by
the Headman as lessor granted lease of the limestone quarry
in Nongtrai to M/s. LMMC (the predecessor-in-interest of M/s.
LMMPL). Thus, an area of 100 hectares stood acquired on
lease basis for mining whose lessor was the village Durbar of
Nongtrai. Coming to the topography of the area, one finds that
the limestone bearing area around Nongtrai and Shella villages
falls under Karst topography. This area falls on the southern
fringe of the Meghalaya plateau. Karst topography is
characterized by a limestone caverns/ caves. The factum of
limestone bearing area around Nongtrai and Shella falling
under Karst topography is also borne out by the certificate
dated 27.8.1997 issued by KHADC, Shillong. This Council is a
constitutional authority under Sixth Schedule of the
Constitution. As stated above, the limestone bearing area
67
around Nongtrai and Shella falls on the southern fringe of
Meghalaya plateau. The site is approachable from Shillong via
Mawsynram and Nongtrai villages by a motorable road. The
site is also accessible from Shillong by road via Cherrapunji.
This road is wide enough for crushers and heavy machines to
be brought from Shillong. The site is on the uneven terrain
with a rugged topography. (See Rapid EIA Report submitted by
ERM India Pvt. Ltd. dated 6.4.2000). According to the said
report, the Karst topography of the area supports sporadic
growth of a few tree shrubs. According to the NEHU Report of
1997, the site selected for mining has commercially viable
limestone deposit. The site was selected after thorough
consultation with the concerned village Durbar who is the
custodian of the land. The land was left unused covered with
degraded forests and this was the reason for the Durbar to
lease out the said land to the project proponent for mining.
The village Durbar also felt that in the area unscientific
limestone quarrying was going on resulting in loss of revenue
both to the State as well as the inhabitants of the village
particularly because the said mining was undertaken by
68
unorganized sectors and, thus, it was decided to enter into the
lease with the project proponent so that mining could be done
on scientific basis. The site was also selected because of easy
accessibility by road and less vegetation clearance stood
involved. According to the NEHU Report, the site is located in
the area on the outskirts of the forest. (See page 19 of the said
Report)
(c) Validity of ex post facto clearance
22. An important argument has been advanced on behalf of
SAC that the site clearance dated 18.6.1999 and EIA clearance
dated 9.8.2001 were based on misrepresentation by M/s.
Lafarge. They proceeded on the basis that there was no forest.
That, both the said clearances stood vitiated by suppression of
material fact of existence of forest by M/s. Lafarge and as a
sequel the subsequent revised environmental clearance dated
19.4.2010 and forest clearance (Stage – I) dated 22.4.2010
stood vitiated. In this connection, it was submitted that
having regard to Para 4.3.1 of the National Forest Policy, 1988
tropical rain/ moist forest is required to be totally
safeguarded; that, the project is located in a tropical moist
69
forest and no forest clearance ought to have been granted by
MoEF because of the special ecological significance recognized
by the 1988 policy. According to SAC, the fact that tropical
moist forest existed in the area and continues to exist was
known to M/s. Lafarge at all material times as can be seen
from the NEHU Report of 1997 in which it has been
categorically stated that the vegetation at the study site is a
mixed moist deciduous forest composed of deciduous and
evergreen tree elements; that, in the same Report it has been
further stated that the vegetation of the area is a tropical semi-
evergreen forest composed of deciduous and evergreen
elements which is further corroborated by the assessment of
Floral Diversity prepared by NEHU dated June, 2010 in which
it has been stated that the forest in the study area is tropical
moist deciduous forest, tropical semi-evergreen forest,
savanna, sub-tropical broad leaves forest, forest garden,
orchards and riparian forest; that, the vegetation in the
unbroken area is tropical moist deciduous type with variable
canopy cover mostly sparse. Thus, according to SAC and
CEC, the undisputed position emerging from the record that
70
the subject area is covered by a tropical moist forest deserving
highest degree of ecological protection ought to have been
taken into account by MoEF which was not done at the time of
initial clearances dated 18.6.1999 and 9.8.2001. Shri Divan,
learned senior counsel appearing for SAC submitted before us
that the case in hand essentially deals with the decision
making process in relation to the grant of environmental
clearance and to test whether the decision making process
stood up to judicial review. According to the learned counsel,
the following basic points regarding the legal framework must
be kept in view: - From the environmental perspective, in
relation to a mining project, there are three main sets of
permissions that are required to be obtained:
(i) The first set of permissions is at the State level. This
set of permissions primarily has to do with pollution.
In each State or a group of States, a Pollution Control
Board issues consent/ permit. These consents or
permits are granted from a pollution perspective. The
scope of enquiry is limited to pollution impacts.
Obtaining such consents and permits are essential but
71
they are not a substitute for compliance with other
environmental laws.
(ii) The second set of permissions, according to the
learned counsel, is with regard to environmental
clearance. The scope of environmental clearance is
wider than a pollution control clearance. The
authority granting environmental clearance will look at
broader impacts beyond pollution and will examine the
effect of the project on the community, forests, wild
life, ground water, etc. which are beyond the scope of
Pollution Control Board examination. The exercise of
granting environmental clearance with regard to a
limestone mining project of the present magnitude
requires MoEF clearance.
(iii) A clearance for diversion of forest under the 1980 Act
which is granted by MoEF on the recommendation of
the FAC should logically precede the grant of
environmental clearance as the environmental
clearance is broader in scope and deals with all
aspects, one of which may be forest diversion.
72
23. Applying the said legal framework to the facts of the
present case, the learned counsel appearing for SAC
submitted that the MoEF, as the authority which decides on
diversion of forests and which grants environmental
clearances, is duty bound to examine the diversion application
in the context of the 1988 Policy, particularly, where tropical
moist forests are sought to be cleared by the project
proponent. According to the learned counsel, where MoEF
grants environmental clearance in ignorance of the existence
of a forest due to mis-declaration, it is duty bound to take
severest possible action against the party that made the false
declaration for profit. According to the learned counsel, since
impact assessment and EIA clearances are processes based on
self declarations by the project proponent (s), the decision
making by MoEF depends upon honest and cogent material
supplied by the project proponent and since the said process
is premised on a full and fair disclosure of relevant facts by
the project proponent, in cases where material facts are not
disclosed, the MoEF should withdraw both the site as well as
the environmental clearances. According to the learned
73
counsel, the most important input in this regard must be
received by MoEF in the course of its decision making from the
public which is an essential check for a failure to disclose
correct facts or to have regard to environmental issues that
may have escaped the attention of the project proponent.
According to the learned counsel, the requirement of public
hearing is, thus, mandatory both under the 1994 Notification
and the 2006 Notification. That, the requirement for payment
of NPV does not automatically mean that environmental
clearance is to be granted.
24. We are in full agreement with the legal framework
suggested by the learned counsel for SAC. There is no dispute
on that point. The question is confined to the application of
the legal framework to the facts of the present case. Can it be
said on the above facts that a mis-declaration was wilfully
made by M/s. Lafarge or its predecessor (project proponent)
while seeking site and environmental clearances? Was there
non-application of mind by MoEF in granting such clearances?
Was the decision of MoEF based solely on the declarations
made by the project proponent(s)?
74
25. At the outset, one needs to take note of Section 2 of the
1980 Act which stipulates prior approval. That Section refers
to restriction on the dereservation of forests or use of forest
land for non-forest purpose. It begins with non-obstante
clause. It states that “Notwithstanding anything contained in
any other law for the time being in a State, no State
Government or other authority shall make, except with the
prior approval of the Central Government, any order directing
that any forest land or any portion thereof may be used for
any non-forest purpose”. This is how the concept of prior
approval by the Central Government comes into picture.
Thus, prior determination of what constitutes “forest land” is
required to be done. By an order dated 12.12.1996 by a
Division Bench of this Court in Writ Petition (C) No. 202 of
1995 with another in case of T.N. Godavarman Thirumulpad
v. Union of India, this Court directed each State Government
to constitute within a specific period an Expert Committee to
identify areas which are forests irrespective of whether they
are so notified, recognized or classified under any law and also
identify areas which were earlier forests but stand degraded,
75
denuded or cleared. The Committee was to be headed by the
Principal Chief Conservator of Forests. This order dated
12.12.1996, thus, clarified that every State Government
seeking prior approval under Section 2 of the 1980 Act shall
first examine the question relating to existence of forests
before sending its proposal to the Central Government in
terms of the form prescribed under the Forest (Conservation)
Rules, 1981 (see Rule 4). Thus, the requirement of submitting
the proposal for forest diversion under the 1980 Act is
exclusively the obligation of the State Government. This
position was spelt out initially in the guidelines dated
25.10.1992. However, later on, the Government of India
amended the guidelines in respect of diversion vide letter
dated 25.11.1994 and by the said letter the concept of “User
Agency” stood introduced. On 10.1.2003, Rule 4 of the 1981
Rules stood reframed which inter alia provided that every
“User Agency” who wants to use any forest land for non-forest
purpose shall make its proposal in the specified form
appended to the Rules to the concerned Nodal Officer along
with the requisite information before undertaking any non-
76
forest activity on the forest land and after receiving the said
proposal and if the State Government is satisfied that the
proposal required prior approval under Section 2, the State
Government had to send the said proposal to the Central
Government in the appropriate form within the specified
period of 90 days from the receipt of the proposal from the
“User Agency”. At this stage, it may be noted that the earlier
project proponent in the present case was M/s. LMMPL. That
project proponent had obtained EIA clearance given by MoEF
dated 9.8.2001 which clearance stood transferred to M/s.
Lafarge only on 30.7.2002. While granting environmental
clearance dated 9.8.2001 there was an express finding to the
effect that “no diversion of forest land was involved”. In terms
of the order of this Court dated 12.12.1996, an Expert
Committee was in fact formed by the State of Meghalaya vide
notification dated 8.1.1997 with the Principal Chief
Conservator of Forests as its Chairman. On 10.2.1997, the
State of Meghalaya had addressed a specific letter to the Khasi
Hills Autonomous District Council, which as stated above is a
Constitutional Authority, stating that the land in question was
77
reckoned as non-forest land and the Council was asked to
clarify whether the area in question under the mining lease fell
in the forest as per the records of the Council. The Council by
its letter dated 28.4.1997 had informed the State Government
that the area in question did not fall in the forest. Apart from
the said letter, the Chairperson of the Expert Committee
appointed by the State of Meghalaya being the Principal Chief
Conservator of Forests also submitted his report in which it
was expressly stated that the mining lease granted by the
State Government did not fall in the forest. Since the mining
lease granted by the State did not fall in the forest, the State
Government did not submit any proposal to the Central
Government under Section 2 of the 1980 Act as it treated the
site in question as falling on the outskirts of the forests. It is
almost after nine years that there was a change of view on the
part of MoEF under which the report of the Expert Committee
headed by the Principal Chief Conservator of Forests was given
a go-by. Between 1997 and 2007, the view which prevailed
was that the project site stood located on the outskirts of the
forests. In this connection, it needs to be stated that on
78
1.6.2006 for the first time the Chief Conservator of Forests (C),
Shri Khazan Singh came out with the change of view which
was ultimately accepted in 2007 by MoEF. According to the
Chief Conservator of Forests (C), he had visited the limestone
mining project of M/s. Lafarge on 24.5.2006 when he found
that the mining lease area stood surrounded by thick natural
vegetation covered with sizeable number of tall trees and in
the circumstances he recommended that the project
proponent should be directed to obtain clearance under the
1980 Act and not to carry on the mining activities till such
clearance is obtained. The most important fact is that
subsequent to the letter dated 1.6.2006, addressed by the
Chief Conservator of Forests (C), Shri Khazan Singh, the
Principal Chief Conservator of Forests agreed with the opinion
of the Chief Conservator of Forests (C). This was by letter
dated 11.5.2007. However, even according to the Principal
Chief Conservator of Forests, who was the Chairperson of the
Expert Committee appointed by the State Government, M/s.
Lafarge was not at fault because the certificate indicating
absence of forests was given by Khasi Hills Autonomous
79
District Council. In fact the letter dated 11.5.2007 further
goes to state that the activities of M/s. Lafarge will provide
employment to a large number of local tribals and rural people
and consequently the application for forest clearance made by
M/s. Lafarge without prejudice to their rights and contentions
dated 3.5.2007 be considered by MoEF. Apart from the above
circumstances, on 22.4.1998, a notification was issued by the
State Pollution Control Board constituting an Environmental
Public Hearing Panel to evaluate and assess the documents
submitted by M/s. LMMPL. A public notice was also issued in
local newspapers on 25.5.1998. The State Pollution Control
Board also sent a letter to the Secretary, Shella Village
informing him of the date and time of public hearing and
accordingly on 3.6.1998, a public hearing did take place.
According to the minutes of the meeting, 31 citizens of Shella
Nongtrai, Pyrkan attended the hearing. In the hearing, the
purpose, objective, composition and procedure of
environmental public hearing was discussed. The Headman of
Nongtrai was also present. He gave reasons as to why the
village Durbar had agreed to the proposed project. The main
80
reason being that the limestone was abundantly available in
the area but the same remained unutilized by local villagers
themselves due to lack of infrastructure. That, for economic
development of the local population, the village Durbar had
decided to lease the area required for the project to M/s.
Lafarge. In the meeting, the economic benefits of the local
people from the project proponent were also discussed. The
environmental implications were also discussed. The
mitigating measures to be adopted by the project proponent
were also discussed to maintain the ecology and
environmental balance of the area. The objections of certain
persons were also noted and discussed. The Durbar came to
the conclusion that there was no destruction of any caves.
The complainant was not even present during the hearing.
Thus, a public hearing did take place on 3.6.1998. One more
aspect at this stage needs to be mentioned. Public
participation provides a valuable input in the process of
identification of forest. Today, amongst the tribals of the
North East, there is a growing awareness of the close
relationship between poverty and environmental pollution.
81
According to Environmental Law and Policy in India by Shyam
Divan and Armin Rosencranz, “many native and indigenous
people are fully aware of what constitutes preservation and
conservation of biodiversity. Many native and indigenous
people have many a times opposed government policies that
permit exploitation on traditional lands because such
exploitation threatens to undermine the economic and
spiritual fabric of their culture, and often results in forced
migration and resettlement, the struggle to protect the
environment is often a part of the struggle to protect the
culture of the native and indigenous people” (see page 591). In
our view, the natives and indigenous people are fully aware
and they have knowledge as to what constitutes conservation
of forests and development. They equally know the concept of
forest degradation. They are equally aware of systematic
scientific exploitation of limestone mining without causing of
“environment degradation”. However, they do not have the
requisite wherewithal to exploit limestone mining in a
scientific manner. These natives and indigenous people know
how to keep the balance between economic and environment
82
sustainability. In the present case, the above is brought out
by the Minutes of the meeting held on 3.6.1998. In fact the
written submissions filed by the Nongtrai Village Durbar
(respondent No. 5) in I.A. No. 1868 of 2007 preferred by M/s.
Lafarge have specifically averred that the total area of the land
that falls within the jurisdiction of Nongtrai Village is about
2200 hectares; that, the said lands fall in two categories,
namely, individual ownership lands, and community lands.
The management and control of community lands is
completely within the jurisdiction of the community. Such
community lands in highlands of Khasi Hills are termed as Ri
Raid whereas community lands in low-lying areas are termed
as Ri Seng. Nongtrai village has about 1300 hectares of
community land out of which 900 hectares are limestone
bearing land. The manner and method of allocation, use and
occupation of the community lands are decided by the Village
Durbar. The Village Durbar has granted lease of 100 hectares
of community land out of 900 hectares which as stated above
is limestone bearing land. It is important to note that apart
from the minutes of the meeting held on 3.6.1998 which was
83
attended by the Headman of the Nongtrai Village, a detail
written submission has been filed on 13.5.2011 by the
Nongtrai Village Durbar fully supporting the impugned project.
Thus, this is a unique case from North East. We are fully
satisfied that the natives and the indigenous people of
Nongtrai Village are fully conscious of their rights and
obligations towards clean environment and economic
development. There is ample material on record which bears
testimony to the fact of their awareness of ecological concerns
which has been taken into account by MoEF. In the
circumstances, it cannot be said that the impugned project
should be discarded and that the decision of MoEF granting ex
post facto clearances stands vitiated for non-application of
mind as alleged by SAC. At this stage one more argument
advanced on behalf of SAC needs to be addressed. According
to SAC, in this case a decisive factor which clearly shows that
there is “forest” on the core area is the statutory definition of
forest contained in the United Khasi – Jaintia Hills
Autonomous District (Management and Control of Forests)
Act, 1958. Section 2(f) defines the expression “forest” and the
84
tree count emerging from the High Powered Committee (HPC)
Report which establishes that the area answers the statutory
definition. According to SAC, in terms of the said definition of
forest, if there exists more than 25 trees per acre then it is a
forest. This argument has no merit. According to Shri
Krishnan Venugopal, learned senior counsel appearing on
behalf of the Village Durbar of Nongtrai Village (respondent
No. 5), SAC has not stated the full facts in this regard. We
find merit in this contention. Section 5 of the 1958 Act inter
alia provides that no timber or forest produce shall be removed
for the purpose of sale, trade and business without prior
permission. Section 7 of the said Act deals with restrictions
on felling of trees and further provides that no tree below 1.37
metre in girth at the breast level shall be felled. Thus, it is the
trees of a particular girth and breast height and not every tree
should be counted while computing whether a particular area
is a forest area or not. In fact in the year 2007, a survey of the
unbroken area was conducted by the Forest Department of the
State of Meghalaya wherein an inventory of the existing trees
was prepared based on their nature and girth. The said record
85
confirms that the unbroken area has less than 25 trees per
acre having girth of more than 120 cms per acre. It is in view
of the existence of the 1958 Act, which is a local legislation,
that the native people as also the State officials like the DFO
understood the area in the light of the said Act. It is
important to note once again that this understanding of the
natives and tribals about the Local Act is an important input
in the decision making process of granting environmental
clearance. It is deeply engrained in the local customary law
and usage. It is so understood by the Expert Committee
headed by the then Principal Chief Conservator of Forests on
the basis of which the State granted the mining lease saying
that there was no forest. This certificate was granted by the
State in terms of the order of this Court dated 12.12.1996.
This understanding also existed in the mind of KHADC when it
gave certificates on 28.4.1997, 10.7.1997 and 27.8.1997. In
fact this has been the understanding of the Council as is
apparent even from its letter dated 18.1.2011 (see page 126 of
the affidavit dated 9.3.2011 filed by the State of Meghalaya).
As stated above, this view prevailed with the MoEF between
86
1997 and 2007. The word “environment” has different facets
[see para 127 of the judgment of this Court in Narmada
Bachao Andolan (supra)]. On the above facts, it is not possible
for us to hold that the decision to grant ex post facto
clearances stood vitiated on account of non-application of
mind or on account of suppression of material facts by M/s.
Lafarge as alleged by SAC.
26. Similarly, it is not possible for us to hold on the above
facts that ex post facto clearances have been granted by MoEF
in ignorance of the existence of forests due to mis-declaration.
Two points are required to be highlighted at the outset.
Firstly, the ex post facto clearance is based on the revised EIA.
In the circumstances, EIA Notification of 2006 would not
apply. Secondly, IA preferred by SAC being I.A. No. 2225-
2227/08 was preferred only in March, 2008. Thus, during the
relevant period of almost a decade, SAC did not object to the
said project. In fact an IA is now pending in this Court being
IA No. 3063 of 2011 preferred by CEC which indicates that
there are 28 active mines out of which 8 are located along the
Shella-Cherrapunjee Road which are operating without
87
obtaining approval and in violation of the 1980 Act. Further,
the said I.A. alleges that 6 registered quarry owners are under
the Shella Wahadarship, East Khasi Hills and that there are
12 individuals involved in mining limestone in the Shella Area
during 2008-09. All these aspects require in-depth
examination. The locus of SAC is not being doubted.
However, the I.A. No. 3063 of 2011 preferred by CEC which
has acted only after receiving inputs from the respondent No.
5 prima facie throws doubt on the credibility of objections
raised by SAC. However, we do not wish to express any
conclusive finding on this aspect at this stage. On the ex post
facto clearance, suffice it to state that after Shri Khazan Singh,
Chief Conservator of Forests (C) submitted his report on
1.6.2006, MoEF directed the project proponent to apply for
necessary clearances on the basis that there existed a forest in
terms of the order of this Court dated 12.12.1996 and the ex
post facto clearance has now been granted on that basis
permitting diversion of forest by granting Stage-I forest
clearance subject to compliance of certain conditions imposed
by MoEF and by this Court. On the question of non-
88
application of mind by the MoEF, we find that at various
stages despite compliances by the project proponent and
despite issuance of certificates by various authorities, MoEF
sought further clarifications/ information by raising necessary
requisitions. To give a few instances in terms of the 1994 EIA
Notification, the then project proponent made an application
to MoEF for grant of environmental clearance. With that
application, the then project proponent submitted the NEHU
Report of 1997. However, in the mean time there was an
amendment to the EIA Notification of 1994. That amendment
took place on 10.4.1997 by which two stage clearances were
required to be obtained, namely, site clearance and project
clearance. Therefore, immediately MoEF returned the
application to the project proponent asking it to submit
applications for site clearance as well as for project clearance.
Similarly, although the then project proponent had made site
clearance application which fulfilled the 1994 Notification (as
amended), the MoEF gave site clearance on 18.6.1999 with
additional conditions. Similarly, despite the project proponent
making application for environmental clearance on 17.4.2000
89
enclosing Rapid EIA prepared by ERM India Pvt. Ltd. referring
to absence of forest, the MoEF asked project proponent to
obtain certificate of DFO in terms of the definition of the word
“forest” as laid down in the order of this Court dated
12.12.1996. Similarly, despite the certificate given by DFO on
13.6.2000 stating that the proposed mining site is not a forest
area, the MoEF sought further details in terms of the
connotation of the word “forest” as laid down in the order of
this Court dated 12.12.1996. Similarly, from time to time the
Expert Committee of MoEF asked for details with regard to
flora and fauna, list of species in that area, types of forests
existing in that area, etc. Similarly, after receipt of letter from
Shri Khazan Singh, the then Chief Conservator of Forests (C)
on 1.6.2006, the MoEF called upon the project proponent to
submit an application for forest clearance on the basis that
the site was located in the forest. A number of queries have
been raised from time to time by the MoEF as indicated from
the facts enumerated hereinabove. Even a report from the
High Powered Committee (HPC) was called for by MoEF which
was submitted on 5.4.2010. There were four terms of
90
references given to the HPC. According to the report, all
conditions imposed with regard to environmental clearance
had been substantially complied with by M/s. Lafarge. The
report also refers to the steps taken by M/s. Lafarge with
regard to reforestation. The most important aspect of the HPC
Report is regarding the topography of the area. It states that
though the area can be treated as forest, still it is a hilly
uneven undulating area largely covered by “Karstified”
limestone. The Report further states that the area can be
reforested as a part of the reclamation plan. It further states
that the indigenous and native people are satisfied with the
credentials of M/s. Lafarge as the company is providing health
care facilities, drinking water facilities, employment for local
youth, construction of village roads, employment for school
teachers, scholarship programme for children, etc. It also
indicates that the issue of mining was thoroughly discussed
with the Village Durbar by the members of the HPC who
visited the site and that the community was in agreement to
allow M/s. Lafarge to continue mining. The report further
notes that most of the members of the SAC were not the
91
residents of the locality (Shella Village) and were living in
Shillong while occasionally visiting Shella. The report further
states that 200 persons participated in a long interaction with
the members of HPC. The report further states that in fact the
villagers became very upset in the apprehension of M/s.
Lafarge not being allowed to mine on their community land.
As stated above, even according to the letter dated 11.5.2007,
the Principal Chief Conservator of Forests states that though
the site falls in the forest as pointed out by Shri Khazan Singh,
the Chief Conservator of Forests (C) vide letter dated 1.6.2006,
still it is not the fault of M/s. Lafarge. Thus, under the above
circumstances, we are satisfied that the parameters of
intergenerational equity are satisfied and no reasonable
person can say that the impugned decision to grant Stage – I
forest clearance and revised environmental clearance stood
vitiated on account of non-application of mind by MoEF. On
the contrary, the facts indicate that the MoEF has been
diligent. That, MoEF has taken requisite care and caution to
protect the environment and in the circumstances, we uphold
the stage-I forest clearance and the revised environmental
92
clearance granted by MoEF.
27. Before concluding, we would like to refer to our order
dated 12.4.2010 which recites agreed conditions between the
parties which conditions are imposed by this Court in addition
to the conditions laid down by MoEF. These agreed conditions
incorporated in our order dated 12.4.2010 are in terms of our
judgment in T.N. Godavarman Thirumulpad v. Union of
India [(2006) 1 SCC 1] with regard to commercial exploitability
which even according to SAC was not considered by MoEF at
the time of granting revised environmental clearance on
19.4.2010 or at the time of granting forest clearance on
22.4.2010. We reproduce our order dated 12.4.2010, which
reads as under:
“Heard both sides. Learned Attorney General for India stated that the Ministry of Environment & Forests will take a decision under the Forest Conservation Act and shall consider granting permission subject to the following conditions :
1. The applicant shall deposit a sum of Rs.55 crores towards five times of the normal NPV (as recommended by the CEC) with interest @ 9% per annum from 1st April, 2007, till the date of payment. Such payment shall be made in totality in
93
one instalment within 4 weeks from the date of the order.
2. An SPV shall be set up under the Chairmanship of the Chief Secretary, Meghalaya with the Principal Chief Conservator of Forests, Meghalaya, Tribal Secretary, Meghalaya, Regional Chief Conservator of Forests, MoEF at Shillong and one reputed NGO (to be nominated by the MoEF) as Members. The SPV will be set up within 4 weeks.
3. The User Agency will deposit with the SPV a sum of Rs.90/- per tonne of the limestone mined from the date on which mining commenced within 4 weeks of the SPV being constituted.
4. The SPV shall follow the principles and procedure presently applied for utilization of CAMPA money. The account will be audited by the Accountant General, Meghalaya. The money will be kept in interest bearing account with a Nationalized Bank. The Accountant General and the SPV shall file an Annual Report before this Hon'ble Court detailing all the work done by it in relation to the welfare projects mandated upon it including the development of health, education, economy, irrigation and agriculture in the project area of 50 kms. solely for the local community and welfare of Tribals.
5. The User Agency will comply with all the conditions imposed on it earlier as well as further recommendations made
94
by the Committee constituted by the MoEF under the order dated 30th march, 2010, including, in particular, the following :
(a) It shall prepare a detailed Catchment Area Treatment Plan.
(b) It shall explore the use of surface miner technology.
(c) It shall monitor ambient area quality as per New National Ambient Air Quality Standards.
(d) It shall take steps to construct a Sewage Treatment Plant and Effluent Treatment Plant.
(e) It shall discontinue any agreement for procuring limestone on the basis of disorganized and unscientific and ecologically unsustainable mining in the area.
(f) It shall prepare a comprehensive forest rehabilitation and conservation plan covering the project as well as the surrounding area.
(g) It shall prepare a comprehensive Biodiversity Management Plan to mitigate the possible impacts of mining on the surrounding forest and wildlife.
(h) It shall maintain a strip of at least 100 meter of forest area on the boundary of mining area as a green belt.
6. The MoEF shall take a final decision under the Forest Conservation Act, 1980 for the revised environmental
95
clearance for diversion of 116 hectares of forest land, taking into consideration all the conditions stipulated hereinabove and it may impose such further conditions as it may deem proper.
List on 26.04.2010 at 2.00 p.m.”
28. This order indicates the benefit which will accrue to the
natives and residents of the Nongtrai Village. The site covers
100 hectare required for limestone mining. The Village Durbar
seeks to exploit it on scientific lines. The minutes of the
meeting of the Village Durbar and the submissions filed by the
Durbar indicate the exercise of the rights by the tribals and
the natives of Nongtrai Village seeking economic development
within the parameters of the 1980 Act and the 1986 Act.
29. At the request of the learned counsel for SAC, we wish to
state that none of the observations made hereinabove in the
context of the nature of the land (the extent of the lands
owned by the community and by private persons) shall be
taken into account by the competent court in which title
dispute is pending today.
(d) Summary
96
30. Time has come for us to apply the constitutional
“doctrine of proportionality” to the matters concerning
environment as a part of the process of judicial review in
contradistinction to merit review. It cannot be gainsaid
that utilization of the environment and its natural
resources has to be in a way that is consistent with
principles of sustainable development and
intergenerational equity, but balancing of these equities
may entail policy choices. In the circumstances, barring
exceptions, decisions relating to utilization of natural
resources have to be tested on the anvil of the well-
recognized principles of judicial review. Have all the
relevant factors been taken into account? Have any
extraneous factors influenced the decision? Is the
decision strictly in accordance with the legislative policy
underlying the law (if any) that governs the field? Is the
decision consistent with the principles of sustainable
development in the sense that has the decision-maker
taken into account the said principle and, on the basis of
relevant considerations, arrived at a balanced decision?
97
Thus, the court should review the decision-making process
to ensure that the decision of MoEF is fair and fully
informed, based on the correct principles, and free from
any bias or restraint. Once this is ensured, then the
doctrine of “margin of appreciation” in favour of the
decision-maker would come into play. Our above view is
further strengthened by the decision of the Court of
Appeal in the case of R v. Chester City Council reported in
(2011) 1 All ER 476 (paras 14 to 16).
31. Accordingly, this matter stands disposed of keeping
in mind various facets of the word “environment”, the
inputs provided by the Village Durbar of Nongtrai
(including their understanding of the word “forest” and
the balance between environment and economic
sustainability), their participation in the decision-making
process, the topography and connectivity of the site to
Shillong, the letter dated 11.5.2007 of the Principal Chief
Conservator of Forests and the report of Shri B.N. Jha
dated 5.4.2010 (HPC) (each one of which refers to
98
economic welfare of the tribals of Village Nongtrai), the
polluter pays principle and the intergenerational equity
(including the history of limestone mining in the area
from 1858 and the prevalent social and customary rights
of the natives and tribals). The word “development” is a
relative term. One cannot assume that the tribals are not
aware of principles of conservation of forest. In the
present case, we are satisfied that limestone mining has
been going on for centuries in the area and that it is an
activity which is intertwined with the culture and the
unique land holding and tenure system of the Nongtrai
Village. On the facts of this case, we are satisfied with due
diligence exercise undertaken by MoEF in the matter of
forest diversion. Thus, our order herein is confined to the
facts of this case.
Conclusion
99
32. Accordingly, we see no reason to interfere with the
decision of MoEF granting site clearance dated 18.6.1999, EIA
clearance dated 9.8.2001 read with revised environmental
clearance dated 19.4.2010 and Stage-I forest clearance dated
22.4.2010. Accordingly, I.A. No. 1868 of 2007 preferred by
M/s. Lafarge stands allowed with no order as to costs.
Consequently, I.A. No. 2937 of 2010 preferred by SAC is
dismissed. The interim order passed by this Court on
5.2.2010 shall also stand vacated. All other I.As. shall stand
disposed of.
Part II
Guidelines to be followed in future cases
(i) As stated in our order hereinabove, the words
“environment” and “sustainable development” have
various facets. At times in respect of a few of these
facets data is not available. Care for environment is
an ongoing process. Time has come for this Court to
declare and we hereby declare that the National Forest
100
Policy, 1988 which lays down far-reaching principles
must necessarily govern the grant of permissions
under Section 2 of the Forest (Conservation) Act, 1980
as the same provides the road map to ecological
protection and improvement under the Environment
(Protection) Act, 1986. The principles/ guidelines
mentioned in the National Forest Policy, 1988 should
be read as part of the provisions of the Environment
(Protection) Act, 1986 read together with the Forest
(Conservation) Act, 1980. This direction is required to
be given because there is no machinery even today
established for implementation of the said National
Forest Policy, 1988 read with the Forest (Conservation)
Act, 1980. Section 3 of the Environment (Protection)
Act, 1986 confers a power coupled with duty and,
thus, it is incumbent on the Central Government, as
hereinafter indicated, to appoint an Appropriate
Authority, preferably in the form of Regulator, at the
State and at the Centre level for ensuring
implementation of the National Forest Policy, 1988.
101
The difference between a regulator and a court must
be kept in mind. The court / tribunal is basically an
authority which reacts to a given situation brought to
its notice whereas a regulator is a pro-active body with
the power conferred upon it to frame statutory Rules
and Regulations. The Regulatory mechanism warrants
open discussion, public participation, circulation of
the Draft Paper inviting suggestions. The basic
objectives of the National Forest Policy, 1988 include
positive and pro-active steps to be taken. These
include maintenance of environmental stability
through preservation, restoration of ecological balance
that has been adversely disturbed by serious depletion
of forest, conservation of natural heritage of the
country by preserving the remaining natural forests
with the vast variety of flora and fauna, checking soil
erosion and denudation in the catchment areas,
checking the extension of sand-dunes, increasing the
forest/ tree cover in the country and encouraging
efficient utilization of forest produce and maximizing
102
substitution of wood. Thus, we are of the view that
under Section 3(3) of the Environment (Protection)
Act, 1986, the Central Government should appoint
a National Regulator for appraising projects,
enforcing environmental conditions for approvals
and to impose penalties on polluters. There is one
more reason for having a regulatory mechanism in
place. Identification of an area as forest area is solely
based on the Declaration to be filed by the User
Agency (project proponent). The project proponent
under the existing dispensation is required to
undertake EIA by an expert body/ institution. In
many cases, the court is not made aware of the terms
of reference. In several cases, the court is not made
aware of the study area undertaken by the expert
body. Consequently, the MoEF/ State Government
acts on the report (Rapid EIA) undertaken by the
Institutions who though accredited submit answers
according to the Terms of Reference propounded by
the project proponent. We do not wish to cast any
103
doubt on the credibility of these Institutions. However,
at times the court is faced with conflicting reports.
Similarly, the government is also faced with a fait
accompli kind situation which in the ultimate analysis
leads to grant of ex facto clearance. To obviate these
difficulties, we are of the view that a regulatory
mechanism should be put in place and till the time
such mechanism is put in place, the MoEF should
prepare a Panel of Accredited Institutions from which
alone the project proponent should obtain the Rapid
EIA and that too on the Terms of Reference to be
formulated by the MoEF.
(ii) In all future cases, the User Agency (project
proponents) shall comply with the Office Memorandum
dated 26.4.2011 issued by the MoEF which requires
that all mining projects involving forests and for such
non-mining projects which involve more than 40
hectares of forests, the project proponent shall submit
the documents which have been enumerated in the
said Memorandum.
104
(iii) If the project proponent makes a claim regarding
status of the land being non-forest and if there is any
doubt the site shall be inspected by the State Forest
Department along with the Regional Office of MoEF to
ascertain the status of forests, based on which the
certificate in this regard be issued. In all such cases,
it would be desirable for the representative of State
Forest Department to assess the Expert Appraisal
Committee.
(iv) At present, there are six regional offices in the country.
This may be expanded to at least ten. At each regional
office there may be a Standing Site Inspection
Committee which will take up the work of ascertaining
the position of the land (namely whether it is forest
land or not). In each Committee there may be one
non-official member who is an expert in forestry. If it
is found that forest land is involved, then forest
clearance will have to be applied for first.
105
(v) Increase in the number of Regional Offices of the
Ministry from six presently located at Shillong,
Bhubaneswar, Lucknow, Chandigarh, Bhopal and
Bangalore to at least ten by opening at least four new
Regional Offices at the locations to be decided in
consultation with the State/UT Governments to
facilitate more frequent inspections and in-depth
scrutiny and appraisal of the proposals.
(vi) Constitution of Regional Empowered Committee,
under the Chairmanship of the concerned Chief
Conservator of Forests (Central) and having
Conservator of Forests (Central) and three non-official
members to be selected from the eminent experts in
forestry and allied disciplines as its members, at each
of the Regional Offices of the MoEF, to facilitate
detailed/in-depth scrutiny of the proposals involving
diversion of forest area more than 5 hectares and up to
40 hectares and all proposals relating to mining and
encroachments up to 40 hectares.
106
(vii) Creation and regular updating of a GIS based decision
support database, tentatively containing inter-alia the
district-wise details of the location and boundary of (i)
each plot of land that may be defined as forest for the
purpose of the Forest (Conservation) Act, 1980; (ii) the
core, buffer and eco-sensitive zone of the protected
areas constituted as per the provisions of the Wildlife
(Protection) Act, 1972; (iii) the important migratory
corridors for wildlife; and (iv) the forest land diverted
for non-forest purpose in the past in the district. The
Survey of India toposheets in digital format, the forest
cover maps prepared by the Forest Survey of India in
preparation of the successive State of Forest Reports
and the conditions stipulated in the approvals
accorded under the Forest (Conservations) Act, 1980
for each case of diversion of forest land in the district
will also be part of the proposed decision support
database.
107
(viii) Orders to implement these may, after getting
necessary approvals, be issued expeditiously.
(ix) The Office Memorandum dated 26.4.2011 is in
continuation of an earlier Office Memorandum dated
31.03.2011. This earlier O.M. clearly delineates the
order of priority required to be followed while seeking
Environmental Clearance under the Environment
Impact Assessment Notification 2006. It provides that
in cases where environmental clearance is required for
a project on forest land, the forest clearance shall be
obtained before the grant of the environment
clearance.
(x) In addition to the above, an Office Memorandum dated
26.04.2011 on Corporate Environmental
Responsibility has also been issued by the MoEF. This
O.M. lays down the need for PSUs and other Corporate
entities to evolve a Corporate Environment Policy of
their own to ensure greater compliance with the
environmental and forestry clearance granted to them.
108
(xi) All minutes of proceedings before the Forest Advisory
Committee in respect of the Forest (Conservation) Act,
1980 as well as the minutes of proceedings of the
Expert Appraisal Committee in respect of the
Environment (Protection) Act, 1986 are regularly
uploaded on the Ministry’s website even before the
final approval/decision of the Ministry for
Environment and Forests is obtained. This has been
done to ensure public accountability. This also
includes environmental clearances given under the
EIA Notification of 2006 issued under the Environment
(Protection) Act, 1986. Henceforth, in addition to the
above, all forest clearances given under the Forest
(Conservation) Act, 1980 may now be uploaded on the
Ministry’s website.
(xii) Completion of the exercise undertaken by each
State/UT Govt. in compliance of this Court’s order
dated 12.12.1996 wherein inter-alia each State/UT
Government was directed to constitute an Expert
Committee to identify the areas which are “forests”
109
irrespective of whether they are so notified, recognized
or classified under any law, and irrespective of the
land of such “forest” and the areas which were earlier
“forests” but stand degraded, denuded and cleared,
culminating in preparation of Geo-referenced district
forest-maps containing the details of the location and
boundary of each plot of land that may be defined as
“forest” for the purpose of the Forest (Conservation)
Act, 1980.
(xiii) Incorporating appropriate safeguards in the
Environment Clearance process to eliminate chance of
the grant of Environment Clearance to projects
involving diversion of forest land by considering such
forest land as non-forest, a flow chart depicting, the
tentative nature and manner of incorporating the
proposed safeguards, to be finalized after consultation
with the State/ UT Governments.
(xiv) The public consultation or public hearing as it is
commonly known, is a mandatory requirement of the
environment clearance process and provides an
110
effective forum for any person aggrieved by any aspect
of any project to register and seek redressal of his/her
grievances;
(xv) The MoEF will prepare a comprehensive policy for
inspection, verification and monitoring and the overall
procedure relating to the grant of forest clearances and
identification of forests in consultation with the States
(given that forests fall under entry 17A of the
Concurrent List).
33. Part II of our order gives guidelines to be followed by the
Central Government, State Government and the various
authorities under the Forest (Conservation) Act, 1980 and the
Environment (Protection) Act, 1986. These guidelines are to
be implemented in all future cases. These guidelines are
required to be given so that fait accompli situations do not
recur. We have issued these guidelines in the light of our
experience in the last couple of years. These guidelines will
operate in all future cases of environmental and forest
clearances till a regulatory mechanism is put in place. On the
111
implementation of these Guidelines, MoEF will file its
compliance report within six months.
………..……………………….CJI (S. H. Kapadia)
……..……………………………..J. (Aftab Alam)
……..……………………………..J. (K.S. Panicker Radhakrishnan)
New Delhi; July 06, 2011
112