14 July 2016
Supreme Court
Download

ELECTRICAL MFG.CO.LTD. Vs POWER GRID CORPN.OF INDIA LTD.

Bench: FAKKIR MOHAMED IBRAHIM KALIFULLA,UDAY UMESH LALIT
Case number: C.A. No.-006568-006568 / 2016
Diary number: 20064 / 2008
Advocates: BIJOY KUMAR JAIN Vs SHARMILA UPADHYAY


1

Page 1

1

Non-Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 6568  OF 2016 (Arising out of SLP (C) No.17475/2008)

ELECTRICAL MFG. CO. LTD.                 … APPELLANT

VERSUS

         POWER GRID CORPN. OF INDIA LTD. & ANR   … RESPONDENTS

J U D G M E N T  

Uday Umesh Lalit.J

1. Leave granted.

2. This  appeal  is  directed against  the judgment  and order  dated 04.07.2008

passed by the Division Bench of  the High Court  of Delhi  allowing FAO

(OS) No.196/2006, setting aside the judgment and order dated 10.02.2006

2

Page 2

2

passed by the Single Judge of the High Court of Delhi in CS(OS) No.1201

of 1993.  

3. A Contract for “400 KV Transmission Line Power Package for Rihand –

Kanpur  – Eta – Kanpur Line” was awarded by National  Thermal  Power

Corporation  (hereinafter  referred  to  as  “NTPC”)  to  the  appellant  herein.

Clause 26 of the Contract titled  “Arbitration”  was to the following effect:-

“26.0 ARBITRATION

 26.1 If any dispute or difference of any kind whatsoever shall arise between the Owner and the Contractor, arising out of the Contract for the performance of the Works whether during the progress of the Works or after its completion or whether before or after the termination, abandonment or breach of the Contract, it shall, in the first place, be referred  to  and settled  by the Engineer, who,  within  a period of thirty (30) days after being requested by either party to do so, shall give written notice of his decision to the Owner and the Contractor.  

 26.2 Save as hereinafter provided, such decision in respect of every matter so referred shall be final and binding upon the  parties  until  completion  of  the  Works  and  shall forthwith be given effect to by the Contractor who shall proceed with the Works with all due diligence, whether he  or  the  Owner  requires  arbitration  as  hereinafter provided or not.

 26.3 If  after  the  Engineer  has  given  written  notice  of  his decision to the parties, no claim to arbitration has been communicated to him by either party within thirty (30) days from the receipt  of such notice,  the said decision shall become final and binding on the parties.  

 26.4 In the event of the Engineer failing to notify his decision as aforesaid within thirty (30) days after being requested

3

Page 3

3

as aforesaid, or in the event of either the Owner or the Contractor being dissatisfied with any such decision, or within  thirty  (30)  days  after  the  expiry  of  the  first mentioned period of thirty (30) days, as the case may be, either party may required that the matters in dispute be referred to arbitration as hereinafter provided.  

 26.5 All  disputes  or  differences  in  respect  of  which  the decision, if any, of the Engineer has not become final or binding as aforesaid, shall be settled by arbitration in the manner hereinafter provided.  

 26.6.1 The arbitration shall be conducted by three arbitrators, one  each  to  be  nominated  by  the  Contractor  and  the Owner and the third to be named by the President of the Institution of  Engineers,  India.   If  either  of  the parties fails to appoint its arbitrator within sixty (60) days after receipt  of  a  notice  from  the  other  party  invoking  the Arbitration  Clause,  the  President  of  the  Institution  of Engineers, India, shall have the power at the request of either of the parties, to appoint the arbitrator.  A certified copy of the said President making such an appointment shall be furnished to both the parties.  

26.6.2 The arbitration shall be conducted in accordance with the provisions  of  the  Indian  Arbitration  Act,  1940  or  any statutory modification thereof.  The venue of arbitration shall be New Delhi, India.  

 26.7 The decision of the majority of the arbitrators shall be final and binding upon the parties.  The expenses of the arbitration  shall  be  paid  as  may be  determined by the arbitrators.  The arbitrators may, from time to time, with the consent of all the parties enlarge the time for making the award.  In the event of any of the aforesaid arbitrators dying,  neglecting,  resigning or  being unable  to  act  for any reason, it will be lawful for the party concerned to nominate  another  arbitrator  in  place  of  the  outgoing arbitrator.

4

Page 4

4

 26.8 The arbitrator shall  have full  powers to review and/or revise any decision, opinion, directions, certification or valuation  of  the  Engineers  in  consonance  with  the Contract,  and  neither  party  shall  be  limited  in  the proceedings  before  such  arbitrators  to  the  evidence  or arguments  put  before  the  Engineer  for  the  purpose  of obtaining the said decision.  

 26.9 No decision given by the Engineer in accordance with the aforegoing provisions shall disqualify him as being called as a witness or giving evidence before the arbitrators on any  matter  whatsoever  relevant  to  the  dispute  or difference referred to the arbitrators as aforesaid.”  

4. The Contract was completed and the aforesaid line was taken over by NTPC.

In respect of certain claims and issues raised by the appellant, negotiations

took place and thereafter a Committee constituted to consider the claims by

its report dated 03.01.1991 recommended that claim in respect of Rs.10.35

lakhs could be accepted, provided the appellant confirmed that there were no

further  claims.  The  appellant  thereafter  vide  letter  dated  18.07.1991

addressed  to  the  Executive  Director  (NR),  National  Thermal  Power

Corporation Ltd., Indira Bhawan, Civil Lines, Allahabad, sought decision in

respect  of   pending  disputes/matters.   It  was  stated  that  the  decision  in

respect of issues so raised be conveyed to the appellant within 30 days of the

date of the letter.  It appears that by letter dated 14.08.1991 the appellant was

informed that “Engineer” in respect of the Contract in question was General

Manager (TL-NR) and that  the letter  dated 18.07.1991 was forwarded to

5

Page 5

5

him.   Soon thereafter  i.e.,  on 02.09.1991 the appellant  wrote  to  General

Manager  (TL-NR),  National  Thermal  Power  Corporation  Ltd.,  Indira

Bhawan, Civil Lines, Allahabad that the aforesaid letter dated 18.07.1991

having been forwarded to him as “Engineer” of the Contract, in accordance

with Clause 27 of the Contract required notice was deemed to have been

served and that  the appellant  was waiting for  reply in return.   However,

nothing was heard within 30 days.  

5. On 28.11.1991 NTPC wrote to the appellant that under the directions of the

Government of India, NTPC and National Power Transmission Corporation

Ltd. (“NPTC”, for short) had entered into an agreement on 13.08.1991 for

management  of  construction,  operation  and maintenance  of  Transmission

System  and  assorted  facilities  of  NTPC,  pending  completion  of  legal

formalities for transfer of ownership of the Transmission System to NPTC in

due course of time. It was further stated that NPTC would administer the

Contract  for  and  on  behalf  of  NTPC  and  all  further  correspondence  be

addressed to NPTC.  

6. Though  letters  issued  on  18.07.1991  and  02.09.1991  were  admittedly

received  by  NTPC which  requested  the  Engineer  to  act  in  terms  of  the

relevant Clause of the Contract, no action was taken in that behalf.  Even

after issuance of letter dated 28.11.1991, for next more than three months

6

Page 6

6

nothing was done either  by NTPC or  NPTC.  Therefore,  by letter  dated

20.03.1992 addressed to NTPC the appellant informed that in as much as the

“Engineer” had failed to notify his decision within the period specified as

per Clause 26.4 of the Contract, the appellant was invoking Clause 26.6.1 of

the  Contract  regarding  arbitration  and  nominating  Shri  J.C.  Jain  as  its

Arbitrator.  The appellant requested NTPC to appoint its Arbitrator and give

intimation to the President of the Institution of Engineer (India) in order to

enable appointment of the third Arbitrator so that adjudication proceedings

could be proceeded with. A copy of this letter was forwarded to and received

by NPTC.  However, nothing was done for next more than three months.

7. On 7.07.1992,  the appellant wrote to the  President, Institution of Engineers

(India) drawing his attention to the letter  dated 20.03.1992 and stated that

despite being called upon to appoint an Arbitrator on their behalf within the

period specified,  there was complete failure on the part of  NTPC.  Since the

prescribed period of 60 days had expired, a request was made vide said letter

to appoint an Arbitrator and that a copy of such appointment be furnished to

both the parties and further steps be taken in the matter. A copy of this letter

was sent to the Chairman and Managing Director of NTPC.  On 24.08.1992

a  telegram  was  sent  by  Sr.  Manager  (P&C)  of  NPTC  to  the  President,

Institution of Engineers(India) to the following effect:- “MESSAGE FORM

7

Page 7

7

TO PRESIDENT INSTITUTION OF ENGINEERS(INDIA) 8-GOKHLE  ROAD, CALCUTTA-700 020.

KINDLY REFER LETTER NO. HC/009/1-1 DTD. 7TH JULY, ’92  FROM  M/S  EMC,  REGARDING  APPOINTMENT  OF ARBITRATOR  FOR  DISPUTES  ARISING  OUT  OF CONTRACT  NO.  01/00-75/177/-al,  DTD.7.12.84  FOR KANPUR-ETAH TL (.) REQUEST ACTION  REGARDING APPOINTMENT  OF  ARBITRATOR  ON  BEHALF  OF RESPONDENT BY INSTITUTION  OF  ENGINEERS  MAY BE KEPT IN ABEYANCE(.) DETAIL LETTER FOLLOWS(.) REGARDS(.)

(P.N.GUPTA) SR. MANAGER(P&C)

Confirmation copy by post to:            SIGNATURE (of person By REGD. POST             authorized to approve)

1. President Institution of             NAME:P.N.GUPTA Engineers(India), 8, Ghokhle        DESGN.: SR.MANAGER Road, Calcutta- 700 029          DEPTT. P&C

2. M/s EMC Stealal Ltd., 51, Catnal East Road Calcutta   CHECKED FOR DESPATCH

3. Shri V.L. Dua, S M (C) N.D.

4.  Shri Gurman Singh,      C.L.D. CC.N.D.

         Dt. 24.08.92 Regd. Office:  Hemkunt Chambers, 10th Floor, 89, Nehru Place, New Delhi-110 019 (Tel. 646 3390 91-92 Grams:‘ NATGRID’”

8. Since there was no follow up action and nothing was done for more than a

month, the Institution of Engineers (India) on 29.09.1992 appointed   Shri

P.P.Agrawal,  Chief  Consulting  Engineer,  Water  and  Power  Consultancy

8

Page 8

8

Services (India) Ltd. as the Second Arbitrator in terms of the Contract.  On

the  same  date  Shri  Som  Gupta,  Fellow  of  Institution  of  Engineers  was

appointed as the Third Arbitrator in the matter.  Intimation in that behalf was

sent  by letter  dated 29.09.1992 to the Chairman and Managing Director,

NTPC.   

9. On 08.01.1993,  the  “National  Thermal  Power  Corporation  Ltd,  National

Hydro  Electric  Corporation  Ltd.  and  the  North-Eastern  Electric  Power

Corporation  Ltd.   (Acquisition   and  Transfer  of  Power  Transmission

Systems)  Ordinance, 1993” (No.10/1993) was promulgated by the President

of India.  As per Section 3 of the Ordinance, the Power Transmission System

and the right, title and interest of these three companies in relation to their

power transmission systems stood transferred to and vested in the Central

Government  on  and  with  effect  from  the  appointed  day.  The  power

transmission  system  so  vested  in  the  Central  Government,  immediately

thereafter was deemed to have been transferred to and vested in the Power

Grid Corporation India Ltd., i.e. respondent No.1 herein.   The appointed

day under the Ordinance was 1st April, 1992.   

10.On 13.01.1993,  first  meeting  of  the  Arbitral  Tribunal  consisting  of  three

Arbitrators,  namely, Shri  J.C.  Jain,  nominated  by the  appellant,  Shri  P.P.

Agrawal, nominated as the Second Arbitrator by the President, Institution of

9

Page 9

9

Engineers (India) and Shri Om Gupta, nominated as the Third Arbitrator by

the  President,  Institution  of  Engineers  (India)  was  held.   The  Arbitral

Tribunal entered upon reference in respect of the dispute in question. It was

decided in this meeting to hold the next meeting on 11.02.1993 and copies of

the  minutes  of  this  meeting  were  forwarded  to  the  appellant  and  the

Chairman and Managing Director, NTPC.   

11.On 04.02.1993, a letter was written by respondent No.1 to the appellant that

in terms of Clause 26 of the Contract, arbitration could be invoked only if

there was failure to settle the dispute amicably and this being pre-condition

of the contract, the matter was not mature for arbitration and any step in that

behalf  would be in  violation of  the Contract.   A copy of  this  letter  was

marked to the President, Institution of Engineers (India).  

12.On 06.02.1993,  the appellant  filed its  Statement  of  Claim in the  sum of

Rs.3.98 crores before the Arbitral Tribunal. On 11.02.1993 second meeting

of  the  Arbitral  Tribunal  was  held.   The  representative  of   the  appellant

brought the aforesaid Ordinance to the notice of  the Arbitral Tribunal and

submitted that in view of the Ordinance,  respondent No.1 be  made party to

the proceedings.  The Statement of Claim along with annexures and copy of

the Contract were taken on record and the appellant was directed to supply

copies  of  the  Statement  of  Claim  to  both  NTPC  and  respondent  No.1.

10

Page 10

10

NTPC  was  directed  to  submit  their  reply  to  the  statement  of  claim  by

04.03.1993  and  all  parties,  namely, the  appellant,  NTPC and  respondent

No.1  were  requested  to  attend the  next  meeting  of  the  Arbitral  Tribunal

which was fixed on 25.03.1993.  Copies of the minutes of this meeting were

forwarded to NTPC as well as respondent No.1. On 23.02.1993, a letter was

written on behalf of NTPC with copies to the Arbitrators and respondent

No.1 that after promulgation of the aforesaid Ordinance, NTPC had nothing

to do in the matter.  Copy of the minutes of the meeting dated 11.02.1993 of

the Arbitral Tribunal was forwarded  by NTPC to respondent No.1 along

with copy of this letter dated 23.02.1993.

13.As the date fixed for the next meeting, i.e., 25.03.1993 was a public holiday,

a telegram was sent by the appellant to the Arbitrators and to respondent

No.1 that the meeting be adjourned. On 12.03.1993 the Convener Arbitrator

sent  telegram  to  the  appellant  and  respondent  No.1  confirming  the

adjournment of the case to 05.04.1993.  On 20.03.1993 another telegram

was sent by the Convener Arbitrator to the appellant and to respondent No.1

that the date of hearing was shifted to 07.04.1993.

14.On 07.04.1993 third meeting of the Arbitral Tribunal was held. Though the

appellant was present, respondent No.1 was absent.  It was noted that the

minutes of the second meeting held on 11.02.1993 were sent to NTPC and

11

Page 11

11

respondent No.1 and were received by them.  The relevant portion of the

minutes of the meeting dated 07.04.1993 was as under:

“It was also noted the minutes of the second meeting held on 11.02.1993 had been sent both to M/s NTPC and M/s PGCIL and received by them.

It was however noted with regret that no representative of M/s NTPC and/or M/s PGCIL turned up for the hearing.

No  compliance  was  made  by  the  aforesaid  two respondents  to  the  directive  given  to  them  in  the  second meeting regarding filing their replies to the statement of claim filed by M/s EMC.

During the third meeting Mr. M.K. Kureshi of M/s EMC requested that despite no response from respondents, the case should be proceeded with and the arbitrators were requested to deliver the award within the statutory period of 4 months which expired on 12th May, 1993.

Under  the  circumstances,  it  was  decided  that  the  next hearing  in  the  matter  will  commence  from  10.30  a.m.  on 20.04.1993 and continue on all the days upto 25th April, 1993. Each  day  the  meeting  shall  commence  from 10.30 a.m.  and continue during the day in an effort to complete the items on the agenda as specified in the following para.

In the meantime  respondents are again requested to file their replies to the statement of claim filed by the claimants and such  other  documents  that  they  may  like  to  file  before  the Arbitrators  by 14th April,  1993 giving copies to  all  the three arbitrators and the claimants.

M/s EMC are also requested to file such other documents that they may like to present to the arbitrators by 14.04.1993 giving copies to respondents.

12

Page 12

12

Following matters will be taken up during the hearings from 20th April, 1993 upto 25th April, 1993:

i) Framing of the issues. ii) Admission/Denial  of  documents  filed  and taking

the same on record. iii) Evidences by the claimants and respondents. iv) Arguments  by  claimants;  counter  arguments  by

respondents; replies by the claimants.”

15.On 09.04.1993, a letter was addressed by one Mr. Sunil Narula, Advocate,

on behalf of respondent No.1 to three Arbitrators and the appellant.  It was

stated in the letter as under:- “…………..Since M/s Electrical Mfg. Co. Ltd. Calcutta,

have  raised  some  disputes  in  the  above-said  contract  and instead of settling the  matter amicably with our client despite our  client’s   repeated  requests,   have  directly  invoked  the Arbitration Clause which is not in consonance  with the terms and conditions of the above referred agreement and therefore, the appointment of the arbitrators in this matter is void ab initio. M/s Electrical Mfg. Co. Ltd., Calcutta have chosen to neglect their own written submissions to our  client in which they had agreed to discuss  and settle the  matter amicably with our client in accordance with  the terms and conditions of the agreement and  this was also a  condition precedent to the invocation of Arbitration Clause 26.1 of the said agreement.

Our clients M/s Power Grid Corporation of India Ltd. are initiating the appropriate legal proceedings in the Hon’ble High Court of Delhi to challenge the appointment of Shri J.C.Jain, Shri P.P. Agarwal and Shri Som Gupta, the addressee No. 1,2 and 3,  herein as Arbitrators in the above mentioned matter.  As the  dispute  in  this  matter  is  to  the  effect  of  legality  of  the appointment  of  all  the  three  learned  Arbitrators,   you  are requested  to  abstain  from   and/or  postpone  the  arbitration proceedings  for  a  period  of  60  days,  which  shall  be  just, reasonable and in the interest of justice and during this period

13

Page 13

13

our client  shall  be  able to obtain necessary orders from the Hon’ble High Court of Delhi.”

16.On 20.4.1993, fourth meeting of the Arbitral Tribunal was held at 10.30 a.m.

as scheduled.  The relevant minutes of the meeting were as under:-

“It was noted that the minutes of the third meeting held on 7th April,  1993 were sent  to  M/s NTPC and M/S PGCIL and have  been  acknowledged  by  them.   Acknowledgement  copy taken into record.

It was, however, noted that regret that no representative of M/s NTPC, M/s PGCIL turned up for the hearing.

No compliance was made by the aforesaid respondents to the directives given to them in the second and third meetings dated 11.02.1993 and 7th April, 1993, respectively.  

Despite  repeated  directives  from  the  Arbitrators respondents  did  not  appear  for  the  hearing  of  20.04.1993  at 10.30 a.m..  In pursuance of the decision taken by the Arbitrators at the hearing dated 7.04.1993 the Arbitrators proceeded with the hearing ex-parte.

The  Arbitrators  received  on  17.04.1993  at  Lucknow  a letter dated 9th April, 1993 from one Mr. Sunil Narula, Advocate claiming  to  be  acting  under  instructions  from  PGCIL.   The contents of the letter were considered.   Arguments of EMC’s representative  Mr.  M.K.  Kureshi  were  also  heard.   The Arbitrators decided to proceed with the hearing.

At 11.10 a.m. Mr. Sunil Narula accompanied by an officer of PCGIL came to the hearing.  Since Mr. Narula did not have a proper  letter  of  authority  to  appear  before  the  Arbitrators  on behalf of PGCIL in respect of the dispute under arbitration, and since  the  directives  given  by  the  Arbitrators  in  the  previous meetings had not been complied with by PGCIL, the Arbitrators

14

Page 14

14

were unable  to  entertain any submission of  Mr. Narula.   The hearing proceeded further thereafter.   

M/s  EMC  submitted  through  their  letter  No. EMC/009/ARB dated 20.4.1993 additional documents (12 nos.) as per list attached with the letter.  These were taken on record.

The following issues were framed:

1. Whether  EMC  is  entitled  to  the  various  claims mentioned in para 6, Clause (i) to (xvi) and para 7, 8, 9 and 17(d) of the Statement of Claim?  If so, to what effect and extent.

2. Whether EMC is entitled to claim interest mentioned at the end of Para 17(d)?  If so, to what effect and extent.

3. Whether  EMC  is  entitled  to  say  other  relief  in  the present circumstances? If so, to what effect and extent.

Mr.  M.K.  Kureshi  proceeded  to  get  various  documents produced   by  him before  Arbitrators,  proved  by  Mr. Kalyan Kumar Ghosh, Manager (Project Monitoring) EMC Ltd., Exhibit I to XXV as per details enclosed with minutes were got proved.

The hearing will  continue on Wednesday the 21st April, 1993 at the same place and venue i.e. 89, Sundar Nagar, New Delhi at 10.30 a.m.”

17. The aforesaid minutes noted the appearance of  Mr. Sunil Narula at

about 11.10 a.m. and that since he did not  have appropriate  authority, and

the directives  given in the  previous meeting  were not complied with,  no

submissions  were entertained by the Arbitrators.  Said Mr. Narula within an

hour  thereafter  sent  an  Express  Telegram to  the  Convener  Arbitrator  as

under:-

15

Page 15

15

“EXPRESS TELEGRAM

Sh. Som Gupta Convenor Arbitrator Sh Som Gupta 89, Sunder Nagar (Ist Floor) C-8/3, Park Road New Delhi Lucknow-226 001

Ref.: Arbitration proceedings regarding contract 01/CC/75-77  for 400KV Kanpur-Etah & Kanpur-Kanpur Line.  

I appeared on 20.4.93 on behalf of POWERGRID before the  learned  arbitrators  at  89,  Sunder  Nagar,  New Delhi  and submitted  a  Vakalatnama  duly  authorizing  me  to  represent (POWERGRID  CORPORATION  before  the  learned Arbitrators.   The  learned  arbitrators  refused  to  accept  the Vakalatnama  and  made  a  pre-condition  to  the  effect  that POWERGRID should first  make the payment of expenses of the Arbitration Proceedings and also submit a proper authority letter  granting  extension  of  time  for  making  the  award  by another 4 months in order to allow the POWERGRID to present the case before the Learned Arbitrators.  

In the above circumstances,  the arbitration proceedings being held by the Learned Arbitrators in the above matter  is illegal, arbitrary and against the principles of natural justice.  

(SUNIL NARULA) ADVOCATE, DELHI 20.4.1993”  

18. Nobody appeared on behalf  of  respondent No.1 before the Arbitral

Tribunal  on  21st,  22nd and  23rd April,  1993.   The  matter  having  been

concluded  by  23.04.1993,  the  Arbitral  Tribunal  by  its  award  dated

05.05.1993 found that the appellant had proved its case and was entitled to a

16

Page 16

16

sum of    Rs. 72,69,096/-  as against its claim of Rs.3.98 crores.  The award

was then forwarded to the Court to be made Rule of the Court in terms of the

provisions of the Arbitration Act, 1940 (hereinafter referred to as the “Act”).

Copy of the award and notice of filing of the award in Court were given to

all the parties.  The application for making the award Rule of the Court was

registered as CS(OS) No.1201 of  1993 and  objections  under Section 30

and 33 of the Act filed by respondent No.1 were numbered as  IA No.8638

of 1993.  

19. By his judgment and order dated 10.02.2006,  the  Single Judge  of the

High Court dismissed the objections preferred by respondent No.1 and made

award  dated  5.05.1993  awarding  a  sum of  Rs.  72,69,096/-  in  favour  of

appellant, Rule of the Court against  respondent No.1.   The appellant was

also held entitled to simple interest @ 12 % per annum from the date of the

award till the date of the   decree and to simple interest @ 9% per annum

from the date of the decree till its realization.   The appellant was also held

entitled to costs from respondent No.1 which were quantified at Rs.7,500/-.

During the course of his judgment, the learned Single Judge observed as

under:-

“29.It  is  not  in  dispute  that  notices  were  duly  served  upon respondent No.1.  It is also not in dispute that respondent No.2

17

Page 17

17

had knowledge of the proceedings as the relevant documents had  been  forwarded  to  respondent  No.2.   Despite  this  fact respondent No.2 failed to enter appearance.  I am also unable to accept the plea of the learned senior counsel for the respondent No.1  that  there  was  no  power  in  the  Arbitrators  to  add respondent  No.2  as  a  party.   In  fact  no  such  addition  was necessary  and  what  ought  to  have  been  done  was  only  to substitute respondent No.2 in place of respondent No.1.

30.The respondent No.2 even appeared subsequently but instead of participating in the matter was only interested in adjournment. The Arbitrators,  even assuming the arguments of  the counsel appearing  before  the  Arbitrator  to  be  correct,  wanted  an extension of time failing which they wanted to proceed with the Arbitration so that the award could be made within the statutory period of time.  Respondent No.2 was not willing to join in the extension of time.  In such a situation respondent No.2 ought to have taken immediate  legal  remedy to at  least  challenge the constitution of the Tribunal if so advised.  This respondent No.2 did not do but just kept silent over the matter.  The allegations and submissions that the statement of claim was not available with respondent No.2 or that the record is silent about the same or as to what transpired on 20.4.1993 are clearly afterthoughts. It  is  also  to  be  kept  in  mind  that  there  was  a  panel  of Arbitrators.  Two Arbitrators were appointed by an independent agency.  There could have been hardly any grievance made by respondent No.2 about the composition of the Tribunal.

31.Respondent No.2 itself had addressed a communication dated 24.8.1992  to  the  Institute  of  Engineers  and  have  made admission themselves in paragraph 2.26 (iii) of the objections that  they  had  received  intimation  of  the  appointment  of Arbitrators  on  12.11.1992.   The  proceedings  have  also  been sent  to  respondent  No.  2.  Respondent  No.  2  having  not appeared  negligently  or  willfully,  a  further  opportunity  was given  by  the  Arbitrators  to  the  said  respondent  on 7.4.1993……….…………….. Respondent  No.  2  apparently was  not  willing  to  join  the  Arbitration  proceedings  and negligently kept away and did not even take steps to challenge such  Arbitration  proceedings.   There  cannot  be  an  indefinite

18

Page 18

18

period for pre-Arbitration settlement proceedings to continue. The  Contract  stood  concluded  in  1988  and  despite  all discussions no settlement could be finalized right till 1991.  The dispute resolution mechanism was followed in view of the letter of  the petitioner  dated 18.7.1991 with a  copy marked to  the Engineer of the project and the petitioner clarified in terms of letter dated 2.09.1991 that the disputes raised by its earlier letter had been raised before the Engineer or the Contract in terms of Clause  26.4  of  the  terms  and  conditions  of  Contract.   The Engineer did not answer to the claim within thirty(30) days of the receipt of the notice as was required to be done and it is in view  thereof  that  the  Arbitration  Clause  was  invoked  on 20.3.1992.”

20. The matter was carried further by  respondent No.1 by filng FAO(OS)

No.196 of 2006 which appeal came to be allowed  by the  Division Bench of

the High Court vide its judgment and order dated 4.07.2008.   The Division

Bench found that the Arbitral Tribunal had acted in utter haste in rushing

through the arbitration proceedings without affording proper and adequate

opportunity to respondent No.1 in presenting its case.  The  Division Bench

felt  that  the  interest  of  justice  would  be  best  served  if   the  matter  was

referred again to a Sole  Arbitrator to adjudicate the dispute between the

parties afresh after giving due opportunity to both the parties.   Allowing the

appeal and setting aside the order passed by the learned Single Judge and the

award made by the Arbitrator, the matter was referred to the Sole Arbitrator.

During the course of its judgment, the Division Bench of the High Court

observed, inter alia:-

19

Page 19

19

“……..We  are  of  the  view  that  the  Arbitrators  have unnecessarily  acted  in  haste  in  concluding  the  arbitral proceedings. Once the appellant had appeared before them, the least they should have done was to afford some reasonable time to the appellant to file its objections to the statement of claim filed by the respondent EMC. The Arbitrators also could have given a pre-emptory notice to the appellant before proceeding ex parte against them. Even after proceeding ex-parte against the appellant the Arbitrators still could have called upon them to cause appearance in the matter……………….”

“… The appellant had appeared on 9th April, 1993 as well as on 20th April, 1993, but they were not allowed to participate in the proceedings1 and thereafter  within four  days i.e.  from 21.4.1993 to 25.04.1993 the same were concluded. ……..”

“……….Although, the conduct of both the corporations i.e., NTPC & NPTC, (appellant) in adopting a very casual and lackadaisical  approach,  in  not  timely  taking  the  actions including for an appointment of an arbitrator and also for their non-appearance before the Arbitral Tribunal exhibits their total insensitivity  to  the  monetary  claims  of  the  duly  appointed contractor and their own financial interests yet at the same time the said contractor i.e., EMC cannot completely absolve itself to share the blame by not adhering to the said communication dated 28.11.1992. The respondent EMC was not oblivious of the said fact of transfer of ownership of the transmission system by NPTC in favour of the appellant (NPTC), although the same came to be notified through an ordinance on 8.1.1993.”

21. While  issuing  notice  in  the  petition  for  special  leave  to  appeal

preferred by the appellant, this Court by its order dated 01.08.2008 stayed

1

This observation is not correct. On 9.4.1993 a letter was addressed by the Advocate.  No hearing was fixed on 9.4.1993.

20

Page 20

20

the  operation  of  the  judgment  and  order  passed  by  the  Division  Bench.

Consequently, the matter did not proceed before the Sole Arbitrator named

in the judgment of the Division Bench.  The parties having exchanged the

pleadings,  we  heard  Mr.  C.Mukund,  learned  Advocate  in  support  of  the

appellant and Mr. Parag Tripathi,  learned Senior Advocate for respondent

No.1.  

22.      Having heard the learned Counsel and gone through the record, in our

view, the instant matter raises questions ; a) Whether arbitration was validly

invoked in the matter; b) Whether the appointment of the Arbitrators was in

terms of the relevant Clauses of the Contract; c) Whether respondent No.1

was  aware  of  such  invocation  and  consequential  proceedings;  and  d)

Whether  the  Arbitral  Tribunal  was  right  in  refusing  to  adjourn  the

proceedings and proceed with the matter.  Our answers to these questions are

as under:-

a)      In  terms of  the provisions  of  Clause  26 (1)  of  the Contract,  the

appellant  vide  letters  dated  18.7.1991  and  02.09.1991  had  requested  the

“Engineer” to look into the disputes as raised by the appellant.  These letters

were admittedly received by NTPC.  As stipulated in Clause 26 (1) read with

Clause 26 (4), in the event of the “Engineer” failing to notify his decision

21

Page 21

21

within 30 days after being requested, the concerned party would be within its

rights to require that the matters in dispute be referred to arbitration.  Since

nothing was done with respect to the request made by the appellant within

30 days of the receipt of communication dated 18.07.1991 or even the one

dated  02.09.1991,  the  appellant  could  validly  require  that  the  matters  in

dispute be referred to arbitration.  Even assuming that in terms of letter dated

28.11.1991,  it  was  NPTC who was  to  be  concerned  with  the  matters  in

dispute,  no  appropriate  decision  was  taken  even  within  30  days  of  this

communication.   In  the  circumstances,  invocation  of  arbitration  by  the

appellant vide its letter dated 20.03.1992 was perfectly valid and in terms of

the Contract.   

b)   A copy of aforesaid letter dated 20.03.1992 addressed to NTPC was

admittedly  forwarded  to  and  received  by  NPTC.   Neither  of  them took

appropriate and required steps in the matter within 60 days as contemplated

by Clause 26.6.1 of the Contract.  In the circumstances, the step taken by the

appellant to approach Institution of Engineers (India) requesting its President

to  appoint  the  arbitrator  in  terms  of  said  Clause,  vide  its  letter  dated

07.07.1992 was also in keeping with the express terms of the Contract.  It is

crucial to note that a telegram was sent on 24.08.1992 on behalf of NPTC

requesting the President, Institution of Engineers (India) to keep the action

22

Page 22

22

regarding appointment  of  arbitrator  on  their  behalf  in  abeyance.   It  was

stated that a detailed letter was to follow.  However nothing was done in the

matter for more than a month and the detailed letter was never sent. In the

circumstances, the President, Institution of Engineers (India) was absolutely

right and justified in making the appointment of the Second Arbitrator on

29.09.1992.  The appointment of the Third Arbitrator was in any case within

the powers of the President.  Thus, appointment of the Second and Third

Arbitrator and constitution of the Tribunal cannot be found fault with.

c) The  record  is  clear  that  NTPC was  aware  of  the  communications

dated 18.07.1991 and 02.09.1991.  If under the directions of the Government

of India, NPTC was to take over matters including those related with the

Contract in question, NPTC ought to have been appraised of the issues in

question by NTPC.  In any case, the telegram dated 24.08.1992 as stated

above, expressly shows complete awareness on part of NPTC and yet no

further  steps  were  taken  by  NPTC.   No  detailed  letter  as  stated  in  the

telegram was ever sent. Further, respondent No.1 which is the successor-in-

interest was made aware of the pendency of proceedings before the Arbitral

Tribunal but chose not to appear and take part. Minutes of first two meetings

of  the  Arbitral  Tribunal  were  forwarded  to  and  received  by  respondent

No.1.  Even telegrams seeking and granting adjournment of the proceedings

23

Page 23

23

were sent to respondent No.1. When in the meeting dated 07.04.1993 the

Schedule for days beginning from 20.04.1993 was fixed and copy of the

minutes was sent to respondent No.1, the Advocate for the respondent No.1

addressed  a  letter  to  the  Arbitration  on  09.04.1993.  This  letter  not  only

indicates complete awareness of the proceedings but displays definite idea

having crystallized to initiate appropriate proceedings in the High Court. If

that be so, nothing stopped respondent No.1 from initiating such challenge,

which never happened. The least that it could do in the circumstances was to

be ready to participate in the proceedings and be ready on merits  of  the

matter. However even on 20.04.1993, i.e.  eleven days after the letter was

sent, it was not willing to participate. If it wanted adjournment in the matter,

it ought to have consented to the extension of time as the Arbitral Tribunal

had rightly indicated.  The conduct of respondent No.1 as rightly commented

by the Division Bench of the High Court, was extremely casual.   

d)   The Arbitral Tribunal in the present case had entered upon reference and

held its first meeting on 13.01.1993. The mandate of Section 28(1) and (2)

of the Act read with Schedule I, Clause 3 of the Act was that the statutory

period to complete the proceedings and make the award was four months

after entering on the reference. The minutes of the meeting dated 07.04.1993

show awareness that the period would expire on 12.05.1993. The law on the

24

Page 24

24

point is clear that in such circumstances, the enlargement of time could be

possible if parties to the arbitration agreement consent to such enlargement.

The  decision  of  this  Court  in  Hari  Krishna  Wattal  v.  Vaikunth  Nath

Pandya by L.RS. & Ors.2 is quite eloquent and relevant paragraphs thereof

are:-   

“6. Section 3 of the Arbitration Act, 1940 provides:

“An arbitration agreement, unless a different intention is expressed therein, shall be deemed to include the provisions set out in the First Schedule insofar as they are applicable to the reference.”

7. The  First  Schedule  has  8  clauses  describing  the  implied conditions  of  an  arbitration  agreement.  Clause  3  reads  as follows:

“The  arbitrators  shall  make  their  award within four months after entering on the reference or after having been called upon to act by notice in writing from any party to the arbitration agreement or  within  such  extended  time  as  the  Court  may allow.”

10. The  question  depends  upon  the  true  construction  of Section 28. There is no doubt that the Arbitrator is expected to make  his  award  within  four  months  of  his  entering  on  the reference  or  on  his  being called  upon  to  act  or  within  such extended time as the Court may allow. Reading Clause 3 of the Schedule  along with Section  28 one  finds  that  the power  to

2

1973 (2) SCC 510

25

Page 25

25

enlarge the time is vested in the Court and not in the Arbitrator. Clause 3 and Section 28(1) exclude by necessary implication the  power  of  the  Arbitrator  to  enlarge  the  time.  This  is emphasised by Section 28(2) which provides that  even when such a provision giving the Arbitrator power to enlarge the time is contained in the agreement, that provision shall be void and of no effect. The head-note of Section 28 brings out the force of this position in law by providing that the power is of the Court only to enlarge time for making the award.  

11. Sub-section  (2)  of  Section  28,  however,  indicates  one exception to the above rule that the Arbitrator cannot enlarge the  time,  and  that  is  when  the  parties  agree  to  such  an enlargement. The occasion for the Arbitrator to enlarge the time occurs  only  after  he  is  called  upon  to  proceed  with  the arbitration or he enters upon the reference. Hence,  it  is clear that  if  the parties  agree to  the enlargement  of  time after  the Arbitrator has entered on the reference, the Arbitrator has the power to enlarge it in accordance with the mutual agreement or consent  of  the  parties.  That  such  a  consent  must  be  a  post reference  consent,  is  also  clear  from  Section  28(2)  which renders null and void a provision in the original agreement to that effect. In a sense where a provision is made in the original agreement  that  the  Arbitrator  may  enlarge  the  time,  such  a provision always implies mutual  consent for  enlargement but such  mutual  consent  initially  expressed  in  the  original agreement does not save the provision from being void. It is, therefore,  clear  that  the  Arbitrator  gets  the  jurisdiction  to enlarge the time for  making the award only in a case where after  entering on the Arbitration the parties to the arbitration agreement consent to such enlargement of time.”

In the circumstances, if the Arbitral Tribunal insisted upon appropriate

consent to extend the time, no fault could be found with. At the same time, if

respondent No.1 was not willing to give such consent, the Arbitral Tribunal

had to go on with the matter and make the award within the statutory period.

26

Page 26

26

The Division Bench was not right in observing that the Arbitral Tribunal

showed undue haste in the matter.  

23.   In our view, the Division Bench was not right and justified in allowing

the appeal and setting aside the judgment and order passed by the Single

Judge.  We, therefore, allow this appeal, set aside the judgment and order

passed by the Division Bench of the High Court of Delhi and restore the

judgment and order dated 10.02.2006 passed by the Single Judge of the High

Court of Delhi.

24.  This appeal is allowed with no order as to costs.

….....………………………………J.                 (Fakkir Mohamed Ibrahim Kalifulla,)

                                                               ....…………………………………J.                  (Uday Umesh Lalit)

New Delhi, July 20, 2016