DLF HOMES PANCHKULA PVT. LTD. Vs D.S. DHANDA ETC. ETC.
Bench: HON'BLE DR. JUSTICE D.Y. CHANDRACHUD, HON'BLE MR. JUSTICE HEMANT GUPTA
Judgment by: HON'BLE MR. JUSTICE HEMANT GUPTA
Case number: C.A. No.-004910-004941 / 2019
Diary number: 3495 / 2019
Advocates: KARANJAWALA & CO. Vs
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
REPORTABLE IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 4910-4941 / 2019 (@ SLP(C) Nos. 3623-3654 OF 2019)
DLF HOMES PANCHKULA PVT. LTD …… APPELLANT
vs.
D.S. DHANDA, ETC.ETC. .…..RESPONDENTS WITH
CIVIL APPEAL NOS. 4942-4945 2019 (@ SLP(C) Nos. 4363-4366 OF 2019)
DLF HOMES PANCHKULA PVT. LTD. & ANR. …… APPELLANTS
vs.
SUDESH GOYAL, ETC. .…..RESPONDENTS
J U D G M E N T
Hemant Gupta, J.
CIVIL APPEAL NOS.4910-4941 OF 2019 (@ SLP(C) Nos. 3623-3654 OF 2019)
Leave granted.
2. The present appeals are directed against orders dated
24.10.2018 & 12.12.2018 passed by the National Consumer Disputes
1
Redressal Commission1 disposing 16 First Appeals wherein the appeals
filed by the Appellant were decided by partially modifying the order
passed by the State Consumer Disputes Redressal Commission2 on
02.06.2016 wherein SCDRC directed the Appellant to hand over the
physical possession of the units allotted to the respondents
(Complainants), complete in all respects within a period of four
months. However, for facility of reference, facts are taken from the
complaint filed by Shri D.S. Dhanda. The SCDRC issued the following
directions:
“Consumer Complaint bearing No. 94 of 2016, titled as D.S. Dhanda Vs DLF Homes Panchkula Private Limited and anr. The opposite parties are jointly and severally directed as under:-
1. To hand over physical possession of the unit, allotted in favour of the complainant, complete in all respects, as per the terms and conditions of the Agreement, to the complainant, within a period of four months, from the date of receipt of a certified copy of this order, on payment of the amount, legally due against him.
2. To execute and get registered the sale deed, in respect of the unit, in question, within one month from the date of handling over possession, as indicated in Clause (i) above, on payment of registration charges and stamp duty, by the complainant, directly to the Registering Authorities concerned.
3. To pay compensation, by way of interest @ 12% p.a., on the deposited amount, to the complainant, from 10.02.2014(promised date in view of the extension sought vide letter dated 05.06.2013 i.e. 12 months after the stipulated date as per Agreement i.e. from 10.02.2013) to 31.05.2016, within 2 months, from the date of
1 NCDRC 2 SCDRC
2
receipt of a certified copy of this order, failing which, the said amount shall carry penal interest @ 15% p.a. instead of 12% p.a., till realization.
4. To pay compensation by way of interest @12% p.a. on the deposited amount, due to the complainant w.e.f. 01.06.2016, onwards (per month) by the 10th of the following month, failing which, the same shall also carry penal interest @ 15% p.a., instead of 12% p.a., from the date of default, till the delivery of possession.
5. To pay compensation by way of interest @12% p.a. on the deposited amount, due to the complainant w.e.f. 01.06.2016, onwards (per month) by the 10th of the following month, failing which, the same shall also carry penal interest @ 15% p.a., instead of 12% p.a., from the date of default, till the delivery of possession.
6. To pay cost of litigation, to the tune of Rs. 50,000/-, to the complainant, within two months from the date of receipt of a certified copy of this order, failing which, the same shall also carry interest @12% p.a., from the date of filing the complaint till realization.”
3. The Appellant preferred appeal against such order passed by
SCDRC before the NCDRC. The NCDRC issued inter-alia the following
directions:
“(C) Compensation:
The compensation for loss and injury, for mental agony and physical harassment, hardship and difficulty, uncertainty and helplessness, can be neither meagre nor exorbitant, but has to be just and equitable, commensurate with the loss and injury (note: it could be less than or more than what the complainant asked for or what the State Commission determined, at the considered wisdom
3
of the adjudicating authority/court in the facts and specificities of the case).
And it is always desirable and preferable, to the extent feasible and appropriate in the facts and specificities of a case, that some objective logical criteria be identified and adopted to determine the compensation. The compensation cannot be arbitrary or whimsical, some reasonable and acceptable rational has to be evident subjectivity has to be minimized.
We note that the State Commission has given compensation in two parts, one, by way of interest on the deposited amount from the ‘promised’/ assured date after taking in view the extension sought vide letter dated 05.06.2013 i.e. 12 months after the 24 months’ conveyed and understood time period for completing construction and handling over possession, and, two, a lumpsum amount.
If compensation comprises of two parts, (i) by way of interest on the deposited amount from the assured date (milestone date) of completing construction and handling over possession to the actual date of handling over possession, and, (ii) lumpsum amount, we find nothing wrong in it.
We do not agree with the builder co.’s contentions that interest on the deposited amount should not be provided since it is not a case of refund but a case of delay in possession. The interest on the deposited amount has to be viewed in the light of the purpose for which it is intended. It is but a way of computing compensation for delay in possession that is commensurate with the amount deposited by the complainant, and here it has been computed after adopting a milestone date as per the builder co.’s own (unfair and deceptive) letter of 05.06.2013. There can be and is no question of not agreeing to an endorsing the award of interest from the said milestone date.
Here we may however add that the rate of interest also cannot be arbitrary or whimsical, some reasonable and acceptable rationale has to be
4
evident, subjectivity has to be minimized, a logical correlation has to be established. Albeit detailed arithmetic or algebra is not required. Logical (to the extent feasible) objective parameters should be adopted. Rounding off simplification etc. to make the computation doable could be adopted.
We feel it appropriate that, considering that the subject units in question are dwelling units, in a residential housing project, the rate of interest for house building loan for the corresponding period in a scheduled nationalized bank (take, State Bank of India) would be appropriate and logical, and , if ‘floating’/ varying/different rates of interest were/ are prescribed, the higher rate of interest should be taken for this instant computation.
We also feet it appropriate and logical that the lumpsum amount awarded should be commensurate with the period for which there has been delay in possession beyond the milestone date, and be objectively and logically computed so.
In our considered view, a sum of Rs. 1 lakh per year from the assured date of handing over possession to the actual date of possession (pro- rata to the nearest whole month, with part month to be taken as one month) would be objective, logical, just and equitable in the facts and specificities of the case.
(D) Cost of litigation:
In respect of cost of litigation, too, just and equitable cost is necessary (this, by its very nature needs no elaboration).
In our considered view, cost of litigation of Rs. 1 lakh is just and appropriate in the facts and specificities of the case.”
4. The Complainant book a built up flat for purchase in pursuance
of a brochure on 30.03.2010 in a project known as “DLF Valley” in
Sector 3, Kalka-Pinjore Urban Complex, Panchkula, Haryana. The
5
Buyer’s Agreement was executed on 11.02.2011. The possession of
the unit was contemplated to be delivered within 24 months from the
date of execution of the agreement i.e. up to 10.2.2013 failing which
the Appellant was liable to pay Rs. 10/- per sq. ft. per month for the
period of delay. The complaints were filed before the SCDRC alleging
delay in delivery of possession of the escalation free flats and
compensation on account of delay in handing over possession
including mental agony and litigation expenses etc.
5. In the return, the stand of the Appellant was, construction could
not be completed on account of stay granted on construction activities
by this Court which operated from 19.04.2012 to 12.12.2012.
Thereafter, the Appellant sought consent from the Complainant to
extend the period of handing over possession by one year vide letter
dated 05.06.2013. In the alternative, option was given to get back the
money deposited by the Complainant along with simple interest at the
rate of 9 per cent per annum. It is also pointed out that on the day
reply was filed, construction of 258 independent floors was complete
and another 1517 built-up units were near completion. Even
occupation certificate has been received for the units for which
construction was complete.
6. The similar dispute in respect of same project came up for
decision before this Court in DLF Homes Panchkula Pvt. Ltd. and
Another Etc. v. Himanshu Arora and Another, Etc.3. The said set
of appeals were decided on consent granting interest at the rate of 9 3 C.A No. 11097/2018 with C.A. Nos. 11098-11138 of 2018 decided on 19.11.2018
6
per cent per annum.
7. Subsequently, another set of appeals, Civil Appeal Nos. 2285-
2330 of 2019 titled DLF Homes Panchkula (P.) Ltd. vs. Sushila
Devi and Another came up for decision before this Court including
appeals filed by the Appellants as well as by the Complainants. Such
appeals were also decided by consent. The agreed terms are as under:
“(a) In all Refund cases, the award of interest @ 9% would be payable in respect of deposits from the day they were made till the date of refund.
(b) In cases where, upon transfer, a subsequent purchaser had stepped into the shoes of the original allottee and had prayed for Refund, the reckoning date for computing the interest be from the date of his transfer in respect of all the amounts that were deposited by the original allottee and if any subsequent deposits were made by the transferee, from the dates of such deposits;
(c) In cases where Possession was sought, the period available to the Developer under the agreement being three years (that is to say original period of two years which was extendable, at the option of the Developer, by further period of one year) ought not to be computed while calculating compensation in the form of interest. Therefore, the period to be reckoned shall be after expiry of three years from the date of agreement and in respect of such period the compensation shall be at the same rate of 9%.
(d) In Possession cases, if there was any transfer and the transferee had stepped into the shoes of the original allottee, the compensation shall be paid from the date of expiry of three years from the agreement as aforesaid or from the date of transfer, whichever is later.”
8. Learned Senior Counsel for the Appellant submitted that in terms
of the consent orders passed by this Court, the consumer complaints
7
be decided in terms of the Court orders passed in two sets of appeals
that is the cases of delay in handing over possession as well the cases,
where the complainants have sought refund of the amount deposited.
However, it is contended that certain allottees are not taking
possession so as to earn interest at the rate of 9 per cent per annum
which is more than a contractual compensation of Rs.10/- per sq. ft.
per month for the delayed possession as well as the loss of rent per
month pleaded by the allottees such as D.S. Dhanda (F.A. No.
853/2016), Sandeep Malik (F.A. No. 1312/2016), Bijender Singh
Sangwan (F.A. No. 1314/2016), Kanwal Mohan (F.A. No. 1356/2016).
9. It is contended that since the rental value is not more than the
compensation awarded by this Court in the consent order referred to
above, therefore, some of the allottees are intentionally not taking
possession so as to continue to earn interest under the guise that it is
the Appellant who is not handing over the possession. It is contended
that in terms of the chart produced in Sushila Devi's case (supra), 9
per cent interest is payable till two months after offer of possession
though such clause does not find specifically mentioned in the order
passed by this Court.
10. It is argued that the Appellant will hand over possession only
after obtaining occupancy certificate from the Town and Country
Planning Department of the State of Haryana and after ensuring that
the maintenance works are taken care of by Jones Lang LaSalle - the
international real estate maintenance agency.
8
11. On the other hand, learned counsel for the allottees argued that
the possession is being offered of incomplete building and that
allottees are entitled to compensation on account of the mental agony
and litigation expenses awarded by SCDRC and as modified by NCDRC.
12. We have heard learned counsel for the parties and find that the
appellant offered for built up 1775 flats in its project the DLF Valley in
Sector 3, Kalka-Pinjore Urban Complex, Panchkula, Haryana. Some of
the disputes settled in earlier two rounds of appeals, whereas, many
complaints are still pending before different fora.
13. There is no surviving dispute in respect of extended period of
handing over possession available to the Appellant i.e. 36 months. By
virtue of such extended period, the possession was required to be
handed over on or about 11.02.2014. The present set of appeals
relates to the Complainants claiming possession of the flats allotted to
them in the DLF Valley. It is categorical stand of the Appellant that the
flats have been completed and occupation certificate obtained from
the Office of Director, Town and Country Planning Department of State
of Haryana.
14. The learned NCDRC rightly held that compensation for loss, mental
agony, litigation expenses and hardship, uncertainty and helplessness
can neither be meagre nor exorbitant but has to be just and
commensurate with the loss and injury. After holding so, the learned
NCDRC found that the Complainants are not entitled to stipulated
amount on account of delay in handing over possession but damages
9
on the amount deposited apart from interest on the amount so
deposited.
15. A perusal of the order passed by NCDRC shows that it approved
the directions of the SCDRC granting interest on the amount deposited
from the assured date and a lumpsum compensation on the deposited
amount from the assured date of completing construction and handing
over possession to the actual date of handing over possession. The
NCDRC thereafter awarded interest on the amount deposited by the
complainants at the maximum rate of interest on which the House
Building Loans are granted by nationalized Bank such as the State
Bank of India; awarded a sum of Rs. 1,00,000/- per year from the
assured date of handing over possession to the actual date of
compensation and another sum of Rs. 1,00,000/- as cost of litigation.
16. The District Forum under the Consumer Protection Act, 19864 is
empowered inter-alia to order the opposite party to pay such amount
as may be awarded as compensation to the consumer for any loss or
injury suffered by the consumer due to the negligence of the opposite
party including to grant punitive damages. But the forums under the
Act cannot award interest and/or compensation by applying rule of
thumb. The order to grant interest at the maximum of rate of interest
charged by nationalised bank for advancing home loan is arbitrary and
no nexus with the default committed. The appellant has agreed to
deliver constructed flats. For delay in handing over possession, the
consumer is entitled to the consequences agreed at the time of
4 1986 Act
10
executing buyer’s agreement. There cannot be multiple heads to
grant of damages and interest when the parties have agreed for
payment of damages at the rate of Rs.10/- per sq. ft. per month. Once
the parties agreed for a particular consequence of delay in handing
over of possession then, there has to be exceptional and strong
reasons for the SCDRC/NCDRC to award compensation at more than
the agreed rate.
17. Though the 1986 Act empowers the authorities to award
compensation for any loss or injury including building damages but the
order of NCDRC or that of SCDRC of awarding compensation is without
any foundation being laid down by the complainant on judicially
recognised principles and is by rule of thumb. Therefore, we find that
grant of compensation under various heads granted by the NCDRC
cannot be sustained.
18. This Court in a judgment reported as Secretary, Irrigation
Department, Government of Orissa & Others vs. G.C. Roy5
examined the question as to whether an arbitrator has the power to
award interest pendente lite. It was held that a person deprived of use
of money to which he is legitimately entitled has a right to be
compensated for the deprivation which may be called interest,
compensation or damages. Thus, keeping in view the said principle
laid down in the aforesaid judgment, the amount of the interest is the
compensation to the beneficiary deprived of the use of the
investment made by the complainant. Therefore, such interest will
5 (1992) 1 SCC 508
11
take into its ambit, the consequences of delay in not handing over his
possession. In fact, we find that the learned SCDRC as well as NCDRC
has awarded compensation under different heads on account of
singular default of not handing over possession. Such award under
various heads in respect of the same default is not sustainable.
19. Thus, we find that the complainant is entitled to interest from the
Appellant for not handing over possession as projected as is offered by
it but it is not a case to award special punitive damages as the one of
the causes for late delivery of possession was beyond the control of
the Appellant. Therefore, in view of the settlement proposal submitted
by the Appellant in earlier two set of appeals in respect of same
project, and to settle any further controversy, the Appellant is directed
as follows:
i) To send a copy of the occupation certificate to the
Complainants along with offer of possession. The Appellant shall
also direct the Jones Lang LaSalle - the real estate maintenance
agency, engaged by the Appellant to undertake such
maintenance works as is necessary on account of damage due to
non-occupation of the flats after construction etc.
ii) It shall be open to the Complainants to seek the assistance of
the maintenance agency to attend to the maintenance work
which may arise on account of non-occupation or on account of
natural vagaries.
12
iii) Such maintenance work shall be completed by the Appellant
within two months of the offer of possession but the payment of
interest at the rate of 9 per cent per annum will be for a period of
two months from the date of offer of possession in all situations.
v) Since the Complainants have been forced to invoke jurisdiction
of the consumer forums, they shall be entitled to consolidated
amount of Rs. 50,000/- in each complaint on all accounts such as
mental agony and litigation expenses etc. The complainant shall
not be entitled to any other amount over and above the amount
mentioned above.
vi) In case, the original allottee has transferred the flat, the
transferee shall be entitled to interest at the rate of 9 per cent
per annum from the date of expiry of three years from the
agreement or from the date of transfer, whichever is later.
CIVIL APPEAL NOS.4942-4945 OF 2019 (@SLP (C) Nos. 4363-4366 of 2019)
20. Leave granted.
21. The Complainant in these cases have sought refund of the
amount deposited by them with the Appellant. The learned SCDRC
passed an order on 04.08.2017 directing the Appellant as under:-
“i. To refund the amounts of Rs. 49,25,461/- alongwith simple interest @ 15% per annum, to
13
the complainant, from the respective dates of deposits, till realization, within 45 days, from the date of receipt of a certified copy of this order, failing which, the Opposite Parties shall pay the aforesaid amounts alongwith simple interest @ 18% per annum, instead of 15% per annum, from the date of default till actual payments;
ii. To pay an amount of Rs. 35,000/- as litigation costs, to the complainant, within a period of 45 days from the date of receipt of a certified copy of the order, failing which, the Opposite Parties shall pay the aforesaid amount alongwith simple interest @ 15% per annum from the date of filing the complaint till actual payment.”
22. The appeal filed by the Appellant before NCDRC was dismissed
for non-compliance of an order in an application of condonation of
delay. Still aggrieved, the Appellants are before this Court.
23. We find that the grant of interest at the rate of 15% by SCDRC is
highly excessive. Since in other two set of appeals decided earlier, this
Court has awarded interest at the rate of 9% per annum on the
amount of refund, therefore, the order of SCDRC stand modified so as
to pay interest at the rate of 9% per annum from the date of deposit till
the date of refund.
24. However, in case any transfer of the flat, such interest will be
payable from the date of expiry of three years from the date of
agreement or from the date of transfer whichever is later.
25. The Costs of Rs. 35,000/- imposed by the SCDRC is maintained.
14
26. The amount of refund be paid to the Complainants within two
months along with the costs.
……………………...……………………………..J. (Dr. Dhananjaya Y. Chandrachud)
…………………..………………..……………….J. (Hemant Gupta)
New Delhi May 10, 2019
15