CHITTARANJAN MAITY Vs UNION OF INDIA
Bench: HON'BLE MR. JUSTICE J. CHELAMESWAR, HON'BLE MR. JUSTICE S. ABDUL NAZEER
Judgment by: HON'BLE MR. JUSTICE S. ABDUL NAZEER
Case number: C.A. No.-015545-015546 / 2017
Diary number: 17196 / 2012
Advocates: P. PARMESWARAN Vs
SHREEKANT N. TERDAL
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURSIDCITON
CIVIL APPEAL NOS. 15545-15546 OF 2017 (Arising out of SLP (C) Nos.39038-39039 of 2012)
SRI CHITTARANJAN MAITY … APPELLANT
VERSUS
UNION OF INDIA … RESPONDENT
J U D G M E N T
S.ABDUL NAZEER, J.
1. Leave granted.
2. The appellant, in these appeals, has challenged the
legality and correctness of the judgment and order dated
29.9.2011 in A.P.O. No.213/2009 in A.P. No.35/2006
whereby the Division Bench of the High Court of Calcutta
2
has set aside the judgment and order of the learned
Single Judge in A.P. No.35/2006 dated 27.1.2009.
3. Brief facts necessary for the disposal of these appeals are
as follows:
4. On 20.3.1991, respondent invited tender for the
execution of balance of earth for formation of banks for
laying railway line, roads, platforms and miscellaneous work
in connection with new goods terminal yard of South-Eastern
Railway at Sankrail in Howrah District. The appellant’s tender
dated 23.3.1991 for Rs.61,24,159/- was accepted by
issuance of Letter of Acceptance dated 17.6.1991. In this
connection, an agreement was entered into between the
appellant and the respondent on 22.8.1991. In the said
agreement, General Conditions of the Contract (for short
‘GCC’) were incorporated and the parties were bound by the
terms and conditions thereof.
5. Various disputes and differences arose between the
parties regarding execution of work and its purported
abandonment. The respondent issued notice dated
3
24.10.1991, seeking termination of the agreement. Another
notice dated 15.11.1991 was issued to the appellant under
Clause 62(1) of the GCC for rescission of the contract.
However, at the request of the appellant through letter dated
2.4.1992, the validity of the contract was extended till
30.6.1992. The respondent further granted extension of
time to complete the work upto July 1993. According to the
appellant, the delay and/or hindrances occurred due to
breaches committed by the Railway Administration. The
remaining work was abandoned by the appellant w.e.f.
3.11.2003.
6. The appellant raised the claim before the respondent by
his letter dated 30.10.1996. By a subsequent letter dated
22.6.1998, the appellant demanded reference of the dispute
to the arbitration. Finally, the appellant filed an application
under Section 11(6) of the Arbitration and Conciliation Act,
1996 (for short ‘the 1996 Act’) for appointment of an
Arbitrator for adjudication of the claims and disputes before
the High Court of Calcutta. The Chief Justice of the High
4
Court of Calcutta passed an order dated 6.12.2001,
whereupon the General Manager, South-Eastern Railway,
was directed to appoint Arbitrators from their panel within
four weeks from the said date. Pursuant to the said order,
the Arbitral Tribunal was constituted which adjudicated the
disputes and claims raised by the appellant, as also the
respondent.
7. The Arbitral Tribunal passed an award on 20.9.2006.
The respondent moved an application, being A.P. No.35 of
2006 under Section 34 of the 1996 Act, for setting aside the
said award. The said application was dismissed by the Single
Judge of the High Court. The respondent assailed the order
of the learned Single Judge by filing an appeal in A.P.O. No.
213 of 2009, wherein it was contended that the appellant
had issued a ‘No Claims Certificate’ to the respondent,
thereby forfeiting his right for any claim from the respondent
in regard to which the dispute could not be adjudicated by
the Arbitral Tribunal. As noticed above, the Division Bench
has set aside the order of the learned Single Judge and also
5
the award and directed holding of fresh reference by the
Arbitral Tribunal.
8. Learned senior counsel appearing for the appellant
submits that the Division Bench failed to appreciate the
question that issuance of ‘No Claims Certificate’ by the
appellant was not urged before the Chief Justice in the
proceedings under Section 11(6) of the 1996 Act. The said
plea was not even urged before the Arbitral Tribunal or
before the learned Single Judge. The issue relating to
existence of any live claim or the arbitrability of the dispute
ought to have been urged in the proceedings under Section
11(6) of the 1996 Act or at least before the Arbitral Tribunal.
The question as to whether there was any arbitral dispute or
not, could not have been entertained by the Division Bench
for the first time. It is further submitted that the Tribunal
has rightly passed an award and granted pre-award and
pendente lite interest from 17.7.1992 till the realization of
the award amount.
6
9. On the other hand, learned Additional Solicitor General
appearing for the respondent submits that having regard to
the ‘No Claims Certificate’ issued by the appellant, the
appellant has no right to make any claim except for security
deposit of Rs.15,000/- from the respondent. There was no
arbitral dispute between the parties. Therefore, the claim
itself was not maintainable. It is further argued that, at any
rate, the appellant was not entitled for any interest having
regard to the terms of the contract. He prays for dismissal
of the appeals.
10. Having regard to the contentions urged, the first
question for our consideration is whether the Division Bench
was justified in considering the arbitrability of the dispute for
the first time in the appeal. It is evident from the materials
on record that the dispute had arisen between the parties in
relation to the contract in question. Therefore, the appellant
filed an application before the Chief Justice of the High Court
of Calcutta under Section 11(6) of the 1996 Act, for
appointment of an Arbitrator in terms of the contract which
7
was allowed and an Arbitral Tribunal was constituted for
adjudication of the dispute. The Arbitrator after giving the
parties opportunities of hearing and after considering the
materials placed on record made and published the award.
The amounts claimed and the amounts awarded against
each item of the claim are briefly mentioned as follows:
CLAIM CLAIMED AMOUNT (RS.)
AWARDED AMOUNT (RS.)
1.Balance amount payable
45,37,230/- 2,39,657/-
2.Claim for price variation due to rise in price of materials, labour and fuel
21,82,719.58 1,17,060/-
3.Claim for security deposit.
15,000/- 15,000/-
4.Claim on account of advance payment towards labour supplier
51,000/- 15,300/-
5.Claim for advance payment to the earth supplier.
1,80,000/- 54,000/-
6.Claim for remaining idle wage payment.
1,80,000/- 54,000/-
7.Claim for overhead charges, i.e., staff salary and house rent
22,000/- 15,000/-
8.Claim for 12,75,000/- 6,03,119/-
8
blockage of capital and business loss 9.Claim for interest
1,58,23,193.16 12,44,546/-
11. Learned Single Judge had dismissed the application
filed by the respondent for setting aside the said award. The
issue relating to arbitrability of the dispute was not raised in
the proceeding under Section 11(6) of the 1996 Act. One of
the issues which can be considered by the Chief Justice
under this provision is whether the claim is a live claim.
This issue can also be kept open to be decided by the
Arbitral Tribunal provided the said plea is urged before the
Chief Justice. [(See : National Insurance Company
Limited vs. Boghara Polyfab Private Limited (2009) 1
SCC 267)]. The respondent had not raised the said plea
before the Chief Justice. Be that as it may, the respondent
has not urged the said plea either before the Arbitral
Tribunal or before the learned Single Judge in the
proceedings under Section 34 of the 1996 Act.
9
12. This Court, in Mcdermott International Inc. vs.
Burn Standard Co. Ltd. and Others (2006) 11 SCC 181,
has held that the party questioning the jurisdiction of the
Arbitrator has an obligation to raise the said question before
the Arbitrator. It has been held as under:
“51. After the 1996 Act came into force, under Section 16 of the Act the party questioning the jurisdiction of the arbitrator has an obligation to raise the said question before the arbitrator. Such a question of jurisdiction could be raised if it is beyond the scope of his authority. It was required to be raised during arbitration proceedings or soon after initiation thereof. The jurisdictional question is required to be determined as a preliminary ground. A decision taken thereupon by the arbitrator would be the subject-matter of challenge under Section 34 of the Act. In the event the arbitrator opined that he had no jurisdiction in relation thereto an appeal thereagainst was provided for under Section 37 of the Act.”
13. It is also necessary to observe that intervention of the
court is envisaged only in few circumstances like fraud or
bias by the Arbitrators, violation of natural justice. The court
cannot correct the errors of the Arbitrators. That is evident
from para 52 of the judgment in Mcdermott International
Inc (supra), which is as under:
10
“52. The 1996 Act makes provision for the supervisory role of courts, for the review of the arbitral award only to ensure fairness. Intervention of the court is envisaged in few circumstances only, like, in case of fraud or bias by the arbitrators, violation of natural justice, etc. The court cannot correct errors of the arbitrators. It can only quash the award leaving the parties free to begin the arbitration again if it is desired. So, the scheme of the provision aims at keeping the supervisory role of the court at minimum level and this can be justified as parties to the agreement make a conscious decision to exclude the court’s jurisdiction by opting for arbitration as they prefer the expediency and finality offered by it.”
14. Therefore, the Division Bench was not justified while
considering the arbitrability of the disputes for the first time,
particularly, when the respondent has not urged the issue
relating to ‘No Claims Certificate’ before the Chief Justice,
Arbitral Tribunal or before the learned Single Judge.
15. The next question for consideration is whether the
Arbitral Tribunal was justified in awarding interest on the
delayed payments in favour of the appellant. The total
interest awarded by the Arbitral Tribunal is Rs.12,44,546/-
which includes interest for the pre-reference period and also
11
pendente lite interest. Section 31(7)(a) of the 1996 Act
provides for payment of interest, as under:
“31(7)(a) - Unless otherwise agreed by the parties, where and insofar as an arbitral award is for the payment of money, the arbitral tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made.”
In this Section, a specific provision has been created,
whereby if the agreement prohibits award of interest for the
pre-award period (i.e. pre-reference and pendente lite
period), the Arbitrator cannot award interest for the said
period.
16. Admittedly, the GCC, governing the contract between
the parties, contains a clause which bars the payment of
interest, which is as under:
“16(2) – No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract, but government securities deposit in terms of sub-clause (1) of this clause will be repayable (with) interest accrued thereon.”
12
17. Relying on a decision of this Court in M/s. Ambica
Construction vs. Union of India (2017) SCC OnLine SC
678, (C.A.No.410 of 2008, disposed of on 26.04.2017)
learned senior counsel for the appellant submits that mere
bar to award interest on the amounts payable under the
contract would not be sufficient to deny payment on
pendente lite interest. Therefore, the Arbitrator was justified
in awarding the pendente lite interest. However, it is not
clear from M/s. Ambica Construction (supra) as to
whether it was decided under The Arbitration Act, 1940 (for
short ‘the 1940 Act’) or under the 1996 Act. It has relied on
a judgment of Constitution Bench in Secretary, Irrigation
Department, Government of Orissa and Others. vs.
G.C. Roy (1992) 1 SCC 508. This judgment was with
reference to the 1940 Act. In the 1940 Act, there was no
provision which prohibited the Arbitrator from awarding
interest for the pre-reference, pendente lite or post award
period, whereas the 1996 Act contains a specific provision
which says that if the agreement prohibits award of interest
13
for the pre-award period, the Arbitrator cannot award
interest for the said period. Therefore, the decision in M/s.
Ambica Construction (supra) cannot be made applicable to
the instant case.
18. Learned Additional Solicitor General appearing for the
respondent submits that the position of law for cases
covered under the 1996 Act, i.e. if agreement prohibits
award of interest then the grant of pre-award interest is
impermissible for the Arbitrator, has been reiterated by this
Court in various judgments.
19. In Sayeed Ahmed and Company vs. State of Uttar
Pradesh and Others (2009) 12 SCC 26, this Court noted
that the 1940 Act did not contain any provision relating to
the power of the Arbitrator to award interest. However, now
a specific provision has been created under Section 31(7)(a)
of the 1996 Act. As per this Section, if the agreement bars
payment of interest, the Arbitrator cannot award interest
from the date of cause of action till the date of award. The
Court has observed that in regard to the provision in the
14
1996 Act, the difference between pre-reference period and
the pendente lite interest has disappeared insofar as award
of interest by the Arbitrator is concerned. Section 31(7)(a)
recognizes only two periods, i.e. pre-award and post-award
period.
20. In Sree Kamatchi Amman Constructions vs.
Divisional Railway Manager (Works), Palghat and
Others (2010) 8 SCC 767, this Court was dealing with an
identical case wherein Clause 16 of the GCC of Railways had
required interpretation. This is the same Clause 16(2) of the
GCC prohibiting grant of interest which is also applicable in
the facts of the present case. The Court held that where the
parties had agreed that the interest shall not be payable, the
Arbitral Tribunal cannot award interest between the date on
which the cause of action arose to the date of the award.
21. In Union of India vs. Bright Power Projects
(India) Private Limited (2015) 9 SCC 695, a three-Judge
Bench of this Court, after referring to the provisions of
Section 31(7)(a) of the 1996 Act, held that when the terms
15
of the agreement had prohibited award of interest, the
Arbitrator could not award interest for the pendente lite
period. It has been held thus:
“10. Thus, it had been specifically understood between the parties that no interest was to be paid on the earnest money, security deposit and the amount payable to the contractor under the contract. So far as payment of interest on government securities, which had been deposited by the respondent contractor with the appellant is concerned, it was specifically stated that the said amount was to be returned to the contractor along with interest accrued thereon, but so far as payment of interest on the amount payable to the contractor under the contract was concerned, there was a specific term that no interest was to be paid thereon.
11. When parties to the contract had agreed to the fact that interest would not be awarded on the amount payable to the contractor under the contract, in our opinion, they were bound by their understanding. Having once agreed that the contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed interest either before a civil court or before an Arbitral Tribunal.”
Therefore, it is clear that the appellant is not entitled for any
interest on the amount awarded by the Arbitral Tribunal.
16
22. The Arbitral Tribunal had determined the amount
payable to the appellant in a sum of Rs.11,13,136/- and
interest of Rs.12,44,546/-. A sum of Rs.38,82,150/- was
deposited by the respondent which includes the award
amount, interest for the pre-reference period, pendente lite
and post-award interest. We have held that the appellant is
not entitled for any interest. The appellant has already
withdrawn 50% of the amount deposited by the respondent,
which is in excess of the award amount exclusive of interest.
Having regard to the facts and circumstances of the case,
we deem it proper to direct the respondent not to recover
the excess amount withdrawn by the appellant. Ordered
accordingly.
17
23. The appeals are partly allowed and disposed of in the
aforesaid terms without any order as to costs.
………………………………..J.
(J. CHELAMESWAR)
………………………………..J.
(S. ABDUL NAZEER)
New Delhi; October 03, 2017.