BIPROMASZ BIPRON TRADING SA Vs BHARAT ELECTRONICS LIMITED(BEL)
Bench: SURINDER SINGH NIJJAR
Case number: ARBIT.CASE(C) No.-000019-000019 / 2011
Diary number: 22475 / 2011
Advocates: M. R. SHAMSHAD Vs
S. N. BHAT
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
Page 29
Page 30
Page 31
Page 32
Page 33
Page 34
Page 35
Page 36
Page 37
Page 38
Page 39
Page 1
1
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION NO.19 OF 2011
Bipromasz Bipron Trading SA ...Petitioner
VERSUS
Bharat Electronics Limited (BEL) …Respondent
O R D E R
SURINDER SINGH NIJJAR, J.
1. In this petition, under Section 11(6) of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as “the
Arbitration Act”) read with paragraphs 2 and 3 of the
appointment of the Arbitrators by the Chief Justice of
India Scheme, 1996, the petitioner seeks reference of the
disputes to an independent and impartial sole Arbitrator.
In terms of the arbitration agreement, the petitioner has
issued the necessary notice and the respondent has not
agreed for such appointment of an independent
arbitrator.
Page 2
2
2. It appears that the respondent is not opposing the
petition on the ground that the disputes cannot be
referred to arbitration. The only objection raised by the
respondent is that the disputes have to be referred to the
Chairman and Managing Director of the respondent or
his nominee, in terms of the arbitration clause 10 of
General Terms and Conditions of Purchase Order
(Foreign). The aforesaid arbitration clause reads as
under:-
“Arbitration – All disputes regarding this order shall be referred to B E L Chairman & Managing Director or his nominee for arbitration who shall have all the powers conferred by the Indian Arbitration & Conciliation Bill 1996 or any statutory modification thereof in force.”
3. In view of the above, reference need only be made to the
skeletal facts necessary for adjudicating the issues raised
by the parties.
4. On 6th October, 2008, the respondent issued a Purchase
Order (PO) to the petitioner through which it sought to
purchase the materials/goods, namely, Hydraulic Motor,
Page 3
3
Actuating Cylinder, EL Motor EDM, Converter and GYRO
Unit.
5. The purchase order was issued along with a printed
Annexure IV of “General Terms and Conditions of
Purchase Order (Foreign)”. As noticed above, the relevant
arbitration clause is contained in the aforesaid general
terms and conditions. The petitioner claims that fifth
item, as stated above, was GYRO Unit EK.2.369.113.CE
in 174 Nos. The entire agreed terms of sale by the
petitioner was against 100% payment through Letter
of Credit through the State Bank of India, Trade Finance
CPC, 16, Whannels Road, Egmore, Chennai, India, to the
petitioner and the said Letter of Credit was to be opened
immediately after getting confirmation regarding
readiness of the stock with the petitioner. The
GYRO Unit (174 in Nos.) were to be provided by the
petitioner to the respondent as per the aforesaid
agreement and the petitioner took immediate steps to
supply the said units to the respondent. The petitioner
made huge investments in that regard and procured
Page 4
4
required materials. The specifications of GYRO Units, as
per the specifications, did not stipulate, expressly or
impliedly, the type of damping. While the entire process
was going on, the respondent issued a letter dated 5th
June, 2009 to the petitioner stating that as per the
respondent’s directives, all pending supplies as on that
date, from the petitioner were to be “put on hold” and
directed the petitioner not to dispatch any pending items
including those for which Letter of Credit had been
established until further communication from the
respondent. After the aforesaid communication, the
respondent did not issue any communication to the
petitioner for supply of the said goods till 3rd December,
2009. In response to the aforesaid communication, the
petitioner sent 10 units of GYRO Stabilizers along with
the Certificate which was issued by the Russian Company
(manufacturer) for a lot of 24 units. It appears that the
respondent, on the basis of the inspection report dated
17th November, 2009, rejected two GYRO Units (out of
total 10) on the ground that the same were defective. The
defects pointed out were that “Turret not moving in ‘Auto’
Page 5
5
mode” and “vibration in elevation observed in Turret”. The
other 8 Units were accepted. The petitioner, therefore,
called for payment of 8 accepted GYRO Units and assured
the rectification of two rejected units. Through the
communication dated 28th December, 2009, the
respondent claimed that the goods supplied by the
petitioner were not of Russian Origin and, therefore, all
the 10 GYRO Units supplied by the petitioner were
rejected. The orders were to be cancelled and no more
supply of GYRO Units were to be permitted with electrical
damping. The petitioner claims that the action of the
respondent firstly stopping all the supplies of the
petitioner and secondly rejecting the 10 GYRO Units,
subsequently supplied, is arbitrary, extra contractual,
illegal and without any basis whatsoever.
6. The petitioner claims that 10 GYRO Units were rejected
on the baseless ground that certain corruption cases had
come to light against certain other companies. The
respondent, therefore, stopped receiving supply from
various companies including the petitioner and directly
Page 6
6
contacted the Russian manufacturer company and
obtained the said units from them through another
Russian Exporter company to frustrate the purchase
order of the petitioner. It is claimed that the objection
taken by the respondent are frivolous and without any
basis.
7. The petitioner also claims that the order dated
5th June, 2009 putting on hold the supplies that were to
be made by the petitioner was issued by the Ministry of
Defence, under which the respondent is a Public Sector
Undertaking. The aforesaid order was, however, set aside
by the Delhi High Court in Writ Petition (Civil) No.821 of
2010 by an order dated 11th February,
2010. Thereafter, inspite of the efforts made by the
petitioner, the respondent did not accept the plea that the
purchase order did not contain any specific, express or
implied condition for air damping. The petitioner also
offered to supply 50 GYRO Units with Air damping to
maintain good relations. The respondent, however, issued
a letter dated 18th August, 2010 showing interest to
Page 7
7
accept 50 GYRO Units with Air Damping with condition
that the payment will be made after the acceptance of the
units by the respondent. According to the petitioner, this
was contrary to the terms contained in the original
purchase order. The petitioner, though not obliged as per
the contract, started process of procuring GYRO with air
damping but due to the short validity of the Letter of
Credit, only 14 such units were supplied and the
petitioner had to stop the procurement of the said unit
due to the expiry of the Letter of Credit. Thereafter, the
petitioner has sent a number of communications to the
respondent to which there has been no response, hence,
the petitioner claims that number of disputes which are
mentioned in paragraph 14 (a) to (g) have arisen between
the parties.
8. Vide notice dated 20th May, 2011, the petitioner requested
the respondent to agree on a name of an independent and
impartial sole arbitrator preferably a former Judge of this
Court by mutual consent between the petitioner and the
respondent.
Page 8
8
9. The petitioner claims on the basis of the postal
acknowledgement that the respondent received the
aforesaid notice on or about 23rd May, 2011. The receipt
of the notice has been acknowledged by the respondent
by a letter dated 8th June, 2011. On 29th June, 2011,
the authorised representative of the petitioner has sworn
the necessary affidavit in Poland for filing of the present
petition after the expiry of 30 days of the statutory period
and the same were dispatched to the counsel at New
Delhi.
10. In the meantime, the respondent replied by a
communication dated 29th June, 2011 to the notice
dated 20th May, 2011, stating that the Chairman-cum-
Managing Director is a competent person as the petitioner
has subscribed the contract which states the nominated
arbitrator, and hence the correspondence between the
parties has been placed before the Chairman-cum-
Managing Director for appropriate action. The petitioner
Page 9
9
claims that the aforesaid reply was received on 1st July,
2011.
11. The respondent, in the detailed counter affidavit, accepts
that certain disputes have arisen with regard to the
supply of GYRO Units. It, however, claims that the
reference of the disputes has to be made to the
Chairman-cum-Managing Director of the respondent or
his nominee for arbitration. Therefore, the prayer made in
the petition for appointment of a sole arbitrator to
adjudicate the dispute is contrary to the express clause in
the contract and thus not maintainable. It is also the case
of the respondent that prior to the filing of the petition
before this Court, the Chairman-cum-Managing Director,
as sole arbitrator, has duly acted and exercised the power
in appointing Mr. R. Chandra Kumar, General Manager
(Kot), Bharat Electronics Ltd., District Pauri Garhwal,
Kotdwara-246149, as the arbitrator and communicated
by fax on 19th July, 2011 itself. It is denied that merely
because the Chairman-cum-Managing Director is in
control and supervision of the respondent Public Sector
Page 10
10
Undertaking would render him ineligible to be appointed
as the arbitrator. The respondent having accepted the
arbitration clause with open eyes cannot be permitted to
avoid the same on the ground of perceived partiality. The
petitioner in the rejoinder has emphasised that both the
issues raised by the respondent are without any basis.
The petitioner relies on the facts enumerated in
paragraph 4 of the rejoinder. It is claimed that the
arbitrator had not been appointed on 9th July, 2011 as
claimed by the petitioner. The following facts have been
highlighted as under:
“20.05.2011 – Notice, through counsel was sent to the
respondent seeking appointment of Arbitrator.
29.06.2011 – Petitioner sworn affidavit in Poland for filing of
the petition for appointment of Arbitrator.
29.06.2011 – Respondent’s sent reply to the advocate at New
Delhi received on 1.7.2011 stating that the
correspondence is being placed before the
Chairman and Managing Director.
Note: Due to the new communication received, the fresh affidavit was needed and hence petition was with held to await fresh affidavit from Poland.
Page 11
11
08.07.2011 – Petitioner sent further Notice to the respondent
stating that the action shall not be proper.
21.07.2011 – The present petition seeking the appointment
of Arbitrator was filed.
26.07.2011 – Respondent sent email to the counsel of the
petitioner at new attaching the letter of the
counsel dated 26.7.2011 along with the letter
of respondent dated 19.7.2011 stating the
arbitrator had been appointed. The hard copy
of the said letter was received by the counsel
for the petitioner at New Delhi on 28.7.2011.”
12. The petitioner further claims that no fax was ever sent by
the respondent on 19th July, 2011, as no e-mail or postal
communication was received by the petitioner in Poland
in the whole month of July, 2011. It is further pointed out
that neither the said fax nor email was sent to the
counsel for the petitioner before 26th July, 2011. The
petitioner further pointed out that a perusal of the copy of
the letter dated 19th July, 2011 sent to the
Page 12
12
counsel for the petitioner at New Delhi itself indicates
that the letter was faxed on 25th July, 2011 by
MD’s Office of the respondent to the concerned person of
the respondent to communicate further. The petitioner
further claims that mere passing of the order will not
have any relevance as the same was not communicated to
the petitioner till after the filing of the petition.
13. I have heard the learned counsel for the parties.
14. Mr. Viswanathan, learned senior counsel appearing for
the petitioner submits that the disputes cannot be
referred to CMD or his nominee as neither of them would
be able to act impartially. In any event, the petitioner
would always be under a reasonable apprehension that
CMD or his nominee would be favorably inclined towards
the respondent. He points out that CMD has been in
control and supervision of the works of the respondent
and, therefore, cannot be expected to be impartial in any
dispute between the petitioner and the respondent.
Similarly, any employee of the respondent would suffer
Page 13
13
from the same disability. In support of the submission,
the learned counsel has relied on Indian Oil Corporation
Limited & Ors. Vs. Raja Transport Private Limited 1 ,
Denel (Proprietary) Limited Vs. Bharat Electronics
Limited & Anr. 2 , and Denel (Proprietary) Limited Vs.
Ministry of Defence 3 .
15. Mr. Viswanathan then submitted that the plea taken by
the respondent that one Mr. R. Chandra Kumar, the
General Manager, Bharat Electronics Limited was
appointed as the sole arbitrator on 19th July, 2011 and
communicated by fax on that date itself is without any
basis. He submits that factually the aforesaid averment
has not been proved. The affidavit filed by the respondent
is not supported by any document including purported
appointment letter dated 19th July, 2011. The said
affidavit is completely silent as to whom the said
communication was faxed, where it was faxed and what
is the proof of same having been faxed. He further
1 (2009) 8 SCC 520 2 (2010) 6 SCC 394 3 (2012) 2 SCC 759
Page 14
14
submits that, in fact, the said communication was sent to
the advocate for the petitioner on e-mail on 26th July,
2011, attaching the letter of counsel which was also
dated 26th July, 2011. Prior to that, no communication
had been received by the petitioner or his counsel either
by fax or otherwise stating that the arbitrator had been
appointed. He emphasised that even the aforesaid
appointment letter purportedly signed on 19th July, 2011
shows that it was faxed from Bangalore Office only
on 25th July, 2011 to their Solicitor who in turn further
communicated to the counsel for the petitioner on
26th July, 2011. Therefore, according to Mr. Viswanathan,
it is unbelievable that the communication released from
Bangalore office (Head quarter where the Chairman sits)
could have been conveyed to the petitioner on 19th July,
2011, though the communication states “CC” to the
petitioner but it was never sent to the petitioner. The
aforesaid communication was sent by the Solicitor of the
respondent to the petitioner’s counsel on e-mail on 26th
July, 2011 and thereafter by way of postal
communication. He, therefore, submits that even if it is
Page 15
15
assumed that the aforesaid letter was signed on
19th July, 2011, but it was certainly not communicated
till after the filing of the present petition, therefore, the
same would have no legal sanctity.
16. In support of the submission, the petitioner relies on
Section 3(2) of the Arbitration Act, 1996 which provides
that “The communication is deemed to have been
received on the day it is so delivered”. He submits that
without delivery of the communication dated 19th July,
2011, the same shall be of no effect.
17. Mr. Viswanathan further submits that apart from the
Arbitration Act, as a general principle of law, it is settled
that an order takes effect only when it is served on the
person affected. In support of this submission, learned
counsel relied on in the case of Bachhittar Singh Vs.
State of Punjab & Anr. 4and BSNL & Ors. Vs. Subash
Chandra Kanchan & Anr. 5 and State of Punjab Vs.
4 AIR 1963 SC 395 5 (2006) 8 SCC 279
Page 16
16
Amar Singh Harika 6 . On the basis of the above, he
submits that the petition deserves to be allowed and the
matter be referred to an independent and impartial
arbitrator.
18. On the other hand, Mr. Bhat, learned counsel appearing
for the respondent has submitted that the petitioner
having agreed to the provisions of arbitration contained in
Clause 10 of the general conditions cannot now be
permitted to turn around and contend that someone else
has to be appointed as an arbitrator, thus giving a go-by
to the arbitration agreement. He submits that it is well
settled that once the parties have agreed upon a named
arbitrator, the parties cannot resile therefrom. In support
of the submission, he relied on the judgment of this Court
in the cases of Union of India & Anr. Vs. M.P.Gupta 7 ,
You One Engineering & Construction Co. Ltd. & Anr.
Vs. National Highways Authority of India (NHAI) 8 ,
National Highways Authority of India & Anr. Vs.
6 AIR 1966 SC 1313 7 (2004) 10 SCC 504 8 (2006) 4 SCC 372
Page 17
17
Bumihiway DDB Ltd.(JV) & Ors 9 , Northern Railway
Administration, Ministry of Railway, New Delhi Vs.
Patel Engineering Company Limited 10 and Indian Oil
Corporation Limited & Ors. Vs. Raja Transport Private
Limited 11 .
19. He further submits that the present petition is not
maintainable as even prior to the filing of the petition, the
Chairman-cum-Managing Director had duly acted and
exercised his powers and had appointed Mr. R. Chandra
Kumar, General Manager (Kot) as the arbitrator. It is his
claim that the appointment was made on 19th July, 2011
and the same was duly communicated by fax on 19th
July, 2011 itself to the petitioner.
20. Mr. Bhat further submits that the order of the Managing
Director came into force from the moment it was signed
on 19th July, 2011. In support of this submission, he
relies on the judgment of this Court in the case of
9 (2006) 10 SCC 763 10(2008) 10 SCC 240 11 (2009) 8 SCC 520
Page 18
18
Collector of Central Excise, Madras Vs. M/s M.M.
Rubber & Co., Tamil Nadu 12 . According to the learned
counsel, the aforesaid principle has been reiterated by
this Court in Municipal Corporation of Delhi Vs. Qimat
Rai Gupta & Ors .13 On the issue of perceived partiality of
the CMD or his nominee, Mr. Bhat submits that the
petitioner cannot rely on the judgment of this Court in
Denel (Proprietary) Limited (supra). The facts in the
aforesaid case were different from the facts in the present
case inasmuch as in Denel case (supra) this Court has
directed the appointment of an independent arbitrator
only on the ground that there was certain directions
issued by the Ministry of Defence, Government of India
and as such the Managing Director of BEL may not be in
a position to independently decide the dispute between
the parties. He further submits that in the event this
Court accepts the submission of the petitioner then
Chairman and Managing Director of any other Public
Sector Undertaking, for example, Hindustan Aeronautics
12 1992 Supp.(1) SCC 471 13 (2007) 7 SCC 309
Page 19
19
Limited or Bharat Earth Movers Ltd. may be appointed to
arbitrate the dispute.
21. I have considered the submissions made by the learned
counsel for the parties.
22. The first issue which needs to be addressed is as to
whether the present petition is maintainable in view of
the claim made by the respondent that Mr. R. Chandra
Kumar had been appointed as the Sole Arbitrator on 19th
July, 2011.
23. I am of the considered opinion that the aforesaid
submission of Mr. Bhat can not be accepted in view of the
provision contained in Section 3(2) of the Arbitration Act.
Section 3 of the Act provides for different modes in which
any written communication is deemed to have been
received. Section 3(2) specifically provides as under:-
“The communication is deemed to have been received on the day it is so delivered.”
Page 20
20
24. In view of the aforesaid provision even if the order
appointing the Sole Arbitrator, Mr. R. Chandra Kumar,
was made on 19th July, 2011, it would be deemed to be
received only on the day it is delivered.
25. Apart from the aforesaid statutory provision, it is also
settled that an official order takes effect only when it is
served on the person affected. In the case of Bachhittar
Singh Vs. State of Punjab & Anr. (supra), this Court has
clearly enunciated the Principle of Law in the following
words:-
“Thus it is of the essence that the order has to be communicated to the person who would be affected by that order before the State and that person can be bound by that order. For, until the order is communicated to the person affected by it, it would be open to the Council of Ministers to consider the matter over and over again and, therefore, till its communication the order cannot be regarded as anything more than provisional in character.”
26. Similarly, in this case until the order was communicated
to the petitioner, the Chairman-cum-Managing Director
would have been at liberty to reconsider the matter and
thus rendering the order only provisional in character.
Page 21
21
Similar question arose before this Court in the case of
BSNL & Ors. Vs. Subash Chandra Kanchan & Anr.
(supra) wherein it has been clearly observed as under:-
“12. Evidently, the Managing Director of the appellant was served with a notice on 7-1-2002. The letter appointing the arbitrator was communicated to the respondent on 7-2-2002. By that time, 30 days' period contemplated under the Act lapsed. The Managing Director of the appellant was required to communicate his decision in terms of clause 25 of the contract.”
27. In reaching the aforesaid conclusion, this Court relied on
earlier judgment rendered in the case of State of Punjab
Vs. Amar Singh Harika (supra), wherein this Court has
held as follows:-
“The first question which has been raised before us by Mr. Bishan Narain is that though the respondent came to know about the order of his dismissal for the first time on the 28th May 1951, the said order must be deemed to have taken effect as from the 3rd June 1949 when it was actually passed. The High Court has rejected this contention; but Mr. Bishan Narain contends that the view taken by the High Court is erroneous in law. We are not impressed by Mr. Bishan Narain’s argument. It is plain that the mere passing of an order of dismissal would not be effective unless it is published and communicated to the officer concerned. If the appointing authority
Page 22
22
passed an order of dismissal, but does not communicate it to the officer concerned, theoretically it is possible that unlike in the case of a judicial order pronounced in Court, the authority may change its mind and decide to modify its order.”
28. The aforesaid observations make it clear that an order
passed by an authority can not be said to take effect
unless the same is communicated to the party affected.
The order passed by a competent authority or by an
appropriate authority and kept with itself, could be
changed, modified, cancelled and thus denuding such an
order of the characteristics of a final order. Such an
uncommunicated order can neither create any rights in
favour of a party, nor take away the rights of any affected
party, till it is communicated. The aforesaid proposition
has been reiterated in the case of Laxminarayan R.
Bhattad & Ors. Vs. State of Maharashtra & Anr. 14 ,
wherein it has been held that “it is now well known that a
right created under an order of a statutory authority
must be communicated so as to confer an enforceable
right.” Similar view has been reiterated in Greater
14 (2003) 5 SCC 413
Page 23
23
Mohali Area Development Authority & Ors. Vs. Manju
Jain & Ors. 15 , wherein it is observed as follows:-
“24. Thus, in view of the above, it can be held that if an order is passed but not communicated to the party concerned, it does not create any legal right which can be enforced through the court of law, as it does not become effective till it is communicated.”
29. Mr. Bhat on the contrary relied on the judgment of this
Court in the case of Collector of Central Excise, Madras
Vs. M/s M.M. Rubber & Co., Tamil Nadu (supra) and
submitted that the order of the Managing Director came
into force from the moment it was signed on 19th July,
2011. In Paragraph 12 of the aforesaid judgment, it is
observed as follows:-
“12. It may be seen therefore, that, if an authority is authorised to exercise a power or do an act affecting the rights of parties, he shall exercise that power within the period of limitation prescribed therefor. The order or decision of such authority comes into force or becomes operative or becomes an effective order or decision on and from the date when it is signed by him. The date of such order or decision is the date on which the order or decision was passed or made : that is to say when he ceases to have any authority to tear it off and draft a different order and when he ceases to have any locus paetentiae.
15 (2010) 9 SCC 157
Page 24
24
Normally that happens when the order or decision is made public or notified in some form or when it can be said to have left his hand. The date of communication of the order to the party whose rights are affected is not the relevant date for purposes of determining whether the power has been exercised within the prescribed time.”
30. In my opinion, the aforesaid observations do not deviate
from the observations made by this Court in Bachhittar
Singh’s case (supra) and reiterated consistently
thereafter by this Court. The observations herein were
made with regard to the exercise of power by the
competent authority with regard to determination of the
date from which the period of limitation was to be
calculated to make an appeal. In that case, an order in
favour of the respondent was passed by the Collector of
Central Excise, as an adjudicating authority on 28th
November, 1984. Its copy was supplied to the respondent
on 21st December, 1984. The Central Board of Excise
and Customs, however, in exercise of its powers under
Section 35-e(1) directed the Collector on 11th December,
1985 to make an appeal to the Customs, Excise Board
(Control) Appellate Tribunal against this order. The point
Page 25
25
at issue was whether limitation under Section 35-e(3) of
the Central Excise and Salt Act, 1944 for the order of the
Board under Section 35-e(1) commenced from 28th
November, 1984 or 21st December, 1984. The Appellate
Tribunal rejected the Collector’s application on the
ground that it was beyond limitation period of one year
commencing from 28th November, 1984. The aforesaid
decision of the Appellate Tribunal was upheld by this
Court with the observations made in Paragraph 12 above
(supra). However, the aforesaid observation can not be
read divorced from the observations made in Paragraph
13 and 18, which are as under:-
“13. So far as the party who is affected by the order or decision for seeking his remedies against the same, he should be made aware of passing of such order. Therefore courts have uniformly laid down as a rule of law that for seeking the remedy the limitation starts from the date on which the order was communicated to him or the date on which it was pronounced or published under such circumstances that the parties affected by it have a reasonable opportunity of knowing of passing of the order and what it contains. The knowledge of the party affected by such a decision, either actual or constructive is thus an essential element which must be satisfied before the decision can be said to have been concluded and binding on him. Otherwise the party affected by it will have no means of obeying the order or acting in conformity with it or
Page 26
26
of appealing against it or otherwise having it set aside. This is based upon, as observed by Rajmannar, C.J. in Muthia Chettiar v. CIT “a salutary and just principle”. The application of this rule so far as the aggrieved party is concerned is not dependent on the provisions of the particular statute, but it is so under the general law.
18. Thus if the intention or design of the statutory provision was to protect the interest of the person adversely affected, by providing a remedy against the order or decision any period of limitation prescribed with reference to invoking such remedy shall be read as commencing from the date of communication of the order. But if it is a limitation for a competent authority to make an order the date of exercise of that power and in the case of exercise of suo moto power over the subordinate authorities' orders, the date on which such power was exercised by making an order are the relevant dates for determining the limitation. The ratio of this distinction may also be founded on the principle that the government is bound by the proceedings of its officers but persons affected are not concluded by the decision.”
31. From the above, it becomes evident that the order dated
19th July, 2011 would be binding on the Chairman-cum-
Managing Director for the purposes of working out the
limitation, but so far as the petitioner is concerned, the
relevant date would be the date when the order is
communicated to the petitioner. The order made by a
Statutory Authority or an Officer exercising the powers of
Page 27
27
that Authority comes into force so far as the Authority
Officer is concerned, from the date it is made by the
concerned Authority Officer. But, so far as the affected
party is concerned, the order made by the Appropriate
Authority would be the date on which it is communicated.
In my opinion, Section 3(2) of the Arbitration and
Conciliation Act, 1996, is a mere reiteration of the
aforesaid general principle of law.
32. In view of the above, I am of the considered opinion that
the reliance placed on the aforesaid judgment by Mr.
Bhat is misplaced. In my opinion, the reliance placed by
Mr. Bhat on the judgment in Municipal Corporation of
Delhi (supra) is also misplaced as therein the Court has
reiterated the principle laid down in Collector of Central
Excise, Madras (supra); by observing as follows:-
“26. A distinction, thus, exists in the construction of the word “made” depending upon the question as to whether the power was required to be exercised within the period of limitation prescribed therefor or in order to provide the person aggrieved to avail remedies if he is aggrieved thereby or dissatisfied
Page 28
28
therewith. Ordinarily, the words “given” and “made” carry the same meaning.
27. An order passed by a competent authority dismissing a government servant from services requires communication thereof as has been held in State of Punjab v. Amar Singh Harika11 but an order placing a government servant on suspension does not require communication of that order. (See State of Punjab v. Khemi Ram12.) What is, therefore, necessary to be borne in mind is the knowledge leading to the making of the order. An order ordinarily would be presumed to have been made when it is signed. Once it is signed and an entry in that regard is made in the requisite register kept and maintained in terms of the provisions of a statute, the same cannot be changed or altered. It, subject to the other provisions contained in the Act, attains finality. Where, however, communication of an order is a necessary ingredient for bringing an end result to a status or to provide a person an opportunity to take recourse to law if he is aggrieved thereby, the order is required to be communicated.”
These observations, in my opinion, do not support the
submissions made by Mr. Bhat.
33. Keeping in view the aforesaid principle of law, the fact
situation with regard to the making and the
communication of the order dated 19th July, 2011 can
now be examined. Even though the respondent claims
that the order was sent by fax on 19th July, 2011, there is
Page 29
29
clear denial of the same by the petitioner. Prima facie, it
would appear that even though the order may have been
made on 19th July, 2011, it was served for the first time
on the counsel of the petitioner by e-mail on 26th July,
2011. Therefore, prima facie, it would not be possible to
accept the submission of Mr. Bhat that the petition would
not be maintainable on the ground that the arbitrator
had already been appointed at the time when the present
petition was filed. The issue needs to be decided on the
basis of the evidence produced by the parties, at the
appropriate time.
34. I am also not much impressed by the submission made
by Mr. Bhat that this Court is bound to appoint the
Chairman-cum-Managing Director or its nominee as the
arbitrator in view of the arbitration clause. However, it is
necessary to consider the judgments relied upon by Mr.
Bhat. In the case of Union of India & Anr. Vs.
M.P.Gupta (supra), this Court observed that in view of
the express provision contained in the arbitration clause
that two Gazetted Railway Officers shall be appointed as
Page 30
30
arbitrators; a Former Judge of the Delhi High Court can
not be appointed as the Sole Arbitrator. It must be
noticed here that in the aforesaid case, no facts have
been pleaded in justification of the plea for the
appointment of an independent arbitrator in spite of the
arbitration clause. In You One Engineering &
Construction Co. Ltd. & Anr. Vs. National Highways
Authority of India (NHAI) (supra), Justice B.N.
Srikrishna, sitting as a Chamber Judge in a petition
under Section 11(6) has observed as follows:-
“10. In my view, the contention has no merit. The arbitration agreement clearly envisages the appointment of the presiding arbitrator by IRC. There is no qualification that the arbitrator has to be a different person depending on the nature of the dispute. If the parties have entered into such an agreement with open eyes, it is not open to ignore it and invoke exercise of powers in Section 11(6).”
35. In this matter also, there was no plea that the Arbitral
Tribunal constituted under the arbitration clause was
likely to be favorably inclined towards the respondent.
This Court has merely reiterated the legal position that in
normal circumstances, arbitrator has to be appointed in
Page 31
31
terms of the agreement of the parties contained in the
arbitration clause.
36. In the case of National Highways Authority of India &
Anr. Vs. Bumihiway DDB Ltd.(JV) & Ors. (supra), the
question which was before this Court was again as to
whether a presiding arbitrator could be appointed beyond
the scope of the arbitration clause, by the High Court in a
petition under Section 11(6). It was submitted on behalf
of the appellant that when the arbitration agreement
clearly envisages the appointment of the presiding officer
by the IRC and there is no specification that the
arbitrator has to be different person depending on the
nature of the dispute, it is not open to ignore it and
invoke the exercise of power under Section 11(6) of the
Act. It was also submitted that the High Court was not
justified in referring to the principle of hierarchy and
ignoring the express contractual provision for
appointment of the presiding arbitrator. Upon
consideration of the rival submissions, this Court
considered the questions of law which had arisen. The
Page 32
32
relevant question for the purposes of this case is
“Whether an arbitration clause, which is a sacrosanct
clause, can be rewritten by appointment of a judicial
arbitrator when no qualification therefor is provided in
the agreement?”
37. The answer to the aforesaid question was in the negative.
It was held that the appointment made by the High Court
was beyond the arbitration agreement which clearly
envisages the appointment of the presiding arbitrator by
IRC, there is no qualification that the arbitrator has to be
a different person depending on the nature of the dispute.
It was emphasised that “if the parties have entered into
such an agreement with open eyes, it is not open to ignore it
and invoke exercise of the powers in Section 11(6).” The
observations made by this Court in RITE Approach
Group Ltd. Vs. Rosoboronexport 16 , were reiterated,
wherein this Court has clearly held that :-
“In view of the specific provision contained in the `agreement specifying the jurisdiction of the court to decide the matter, this Court cannot assume the jurisdiction, and hence, whenever there is a specific
16 (2006) 1 SCC 206
Page 33
33
clause conferring jurisdiction on a particular court to decide the matter, then it automatically ousts the jurisdiction of the other court.”
38. In Northern Railway Administration, Ministry of
Railway, New Delhi Vs. Patel Engineering Company
Limited (supra), a three Judge bench of this Court
reiterated the general principle as noticed in the
judgments relied upon by Mr. Bhat. At the same time, it
is emphasised that in exercise of its powers under Section
11(6) of the Act, the Court has to take into consideration
the provision contained in Section 11(8) of the Act. The
aforesaid provision requires that the Chief Justice or the
person or an institution designated by him in appointing
an arbitrator shall have due regard to any qualifications
required of the arbitrator by the agreement of the parties
and other considerations as are likely to secure the
appointment of an independent and impartial arbitrator. It
is also observed that a bare reading of the Scheme of
Section 11 shows that the emphasis is on the term of the
agreement being adhere to and /or give effect to as
closely as possible. But it is not mandatory for the Chief
Page 34
34
Justice or any person or institution designated by him to
appoint the named arbitrator or arbitrators. But at the
same time, due regard has to be given to the
qualifications required by the agreement and other
considerations.
39. In Indian Oil Corporation Limited & Ors. Vs. Raja
Transport Private Limited (supra), this Court whilst
emphasizing that normally the Court shall make the
appointment in terms of the agreed procedure, has
observed that the Chief Justice or his designate may
deviate from the same after recording reasons for the
same. In Paragraph 45 of the aforesaid judgment, it is
observed as follows:-
“45. If the arbitration agreement provides for arbitration by a named arbitrator, the courts should normally give effect to the provisions of the arbitration agreement. But as clarified by Northern Railway Admn., where there is material to create a reasonable apprehension that the person mentioned in the arbitration agreement as the arbitrator is not likely to act independently or impartially, or if the named person is not available, then the Chief Justice or his designate may, after recording reasons for not following the agreed procedure of referring the dispute to the named arbitrator,
Page 35
35
appoint an independent arbitrator in accordance with Section 11(8) of the Act. In other words, referring the disputes to the named arbitrator shall be the rule. The Chief Justice or his designate will have to merely reiterate the arbitration agreement by referring the parties to the named arbitrator or named Arbitral Tribunal. Ignoring the named arbitrator/Arbitral Tribunal and nominating an independent arbitrator shall be the exception to the rule, to be resorted for valid reasons.”
40. In view of the aforesaid observations, it would not be
possible to reject the petition merely on the ground that
this Court would have no power to make an appointment
of an arbitrator other than the Chairman-cum-Managing
Director or his designate. This Court would have the
power to appoint a person other than the named
arbitrator, upon examination of the relevant facts, which
would tend to indicate that the named arbitrator is not
likely to be impartial. In this case, the petitioner had
clearly pleaded that the named arbitrator is a direct
subordinate of the CMD and employee of the respondent.
CMD is the controlling authority of all the employees, who
have been dealing with the subject matter in the present
dispute and also controlling authority of the named
Page 36
36
arbitrator. Apprehending that the CMD, who had been
dealing with the entire contract would not act impartially
as an arbitrator, the petitioner had issued a notice on 20th
May, 2011. In this notice, it was pointed out that while
the entire process of the performance of the contract was
going on, the CMD had issued a letter on 5th June, 2009
to the petitioner stating that as per the company’s
directives, all pending supplies as on that date were “put
on hold”. After the aforesaid communication, no
communication was issued to the petitioner for supply of
the goods as per the Purchase Order dated 3rd December,
2009. Even subsequently, there were difficulties when a
further lot of 24 units were supplied. The detailed
submissions made by the petitioner have been noticed in
the earlier part of the judgment.
41. Keeping in view the aforesaid facts, I am of the opinion
that it would not be unreasonable for the petitioner to
entertain the plea that the arbitrator appointed by the
respondent would not be impartial. The CMD itself would
not be able to act independently and impartially being
Page 37
37
amenable to the directions issued by the Ministry of
Defence. In similar circumstances, this Court in the case
of Denel (Proprietary) Limited Vs. Bharat Electronics
Limited & Anr. (supra), this Court observed as follows:-
“21. However, considering the peculiar conditions in the present case, whereby the arbitrator sought to be appointed under the arbitration clause, is the Managing Director of the Company against whom the dispute is raised (the respondents). In addition to that, the said Managing Director of Bharat Electronics Ltd. which is a “government company”, is also bound by the direction/instruction issued by his superior authorities. It is also the case of the respondent in the reply to the notice issued by the respondent, though it is liable to pay the amount due under the purchase orders, it is not in a position to settle the dues only because of the directions issued by the Ministry of Defence, Government of India. It only shows that the Managing Director may not be in a position to independently decide the dispute between the parties.”
42. In my opinion, the facts in the present case are similar
and, therefore, a similar course needs to be adopted.
43. In exercise of my powers under Sections 11(4) and 11(6)
of the Arbitration and Conciliation Act, 1996 read with
Para 2 of the Appointment of Arbitrators by the Chief
Page 38
38
Justice of India Scheme, 1996, I hereby appoint Hon’ble
Mr. Justice Ashok C. Agarwal, Retired Chief Justice of the
Madras High Court, r/o No. 20, Usha Kiran, 2nd Pasta
Lane, Colaba, Mumbai 400 005, as the sole arbitrator, to
adjudicate the disputes that have arisen between the
parties, on such terms and conditions as the learned sole
arbitrator deems fit and proper. Undoubtedly, the learned
sole arbitrator shall decide all the disputes arising
between the parties without being influenced by any
prima facie opinion expressed in this order, with regard to
the respective claims of the parties.
44. The Registry is directed to communicate this order to the
sole arbitrator forthwith to enable him to enter upon the
reference and decide the matter as expeditiously as
possible.
45. The Arbitration Petition is accordingly disposed of.
Page 39
39
……..…………………..J. [Surinder Singh Nijjar] New Delhi; May 08, 2012.
CORRIGENDUM
PARA NO.39, LAST LINE OF PARA, FOR (EMPHASIS SUPPLIED),
READ (THE LINE STANDS DELETED)