AL JAZEERA STEEL PRODUCTS COMPANY SAOG Vs MID INDIA POWER & STEEL LTD.
Bench: SURINDER SINGH NIJJAR
Case number: ARBIT.CASE(C) No.-000006-000006 / 2009
Diary number: 5558 / 2009
Advocates: Vs
SANJAY KAPUR
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 1
1
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION NO.6 OF 2009
Al Jazeera Steel Products Company SAOG ...Petitioner
VERSUS
MID India Power & Steel Ltd. …Respondent
O R D E R
SURINDER SINGH NIJJAR, J.
1. This petition under Sections 11(5) and (9) of the
Arbitration and Conciliation Act, 1996 read with
paragraphs 2 and 3 of the appointment of the Arbitrators
by the Chief Justice of India Scheme, 1996 seeks
appointment of an independent and impartial person as
an Arbitrator.
2. The applicant is a Company incorporated in Oman
having Registration No.1550438 and having its registered
Page 2
2
office at Sohar Industrial Estate, PO Box 40, PC 327,
Sohar, Sultanate of Oman. The respondent is an Indian
Company incorporated under the provisions of the
Companies Act, 1956 and having its registered office at
Shanti Heights, 32/2, South Tukoganj, 2nd Floor, Above
Cosmos Bank, Indore 452001 (Madhya Pradesh).
3. The applicant entered into a Sale Purchase Contract
dated 18th June, 2008 bearing
No.MIPSL/BILLET/EXP/08-09/003 (hereinafter referred
to as the ‘Contract’) with the respondent for supply of
2000 metric ton Prime Alloy Steel Billets of specific
chemical composition and physical specifications more
particularly described in Article 3 of the Contract. In
accordance with the terms and conditions of the
Contract, the applicant had opened a Letter of Credit
bearing No. DC BAF 080939 through HSBC Bank Middle
East Limited Muscat. The Letter of Credit was encashed
by the respondent on 21st August, 2008 through its
bankers, State Bank of Travancore. On 23rd August,
Page 3
3
2008, the applicant took delivery of first shipment of
243.2 Metric Ton of Billets at Sohar Port. Upon
unloading the containers, the applicant noticed that far
from complying with the specifications mentioned in the
Contract, the Billets supplied by the respondents were of
a very poor quality. The Billets had cracks which were
visible to naked eyes. Even then, to confirm the defects,
the applicant chose some random Billets and sent the
same to two independent laboratories for testing. Both
the laboratories, after conducting the requisite tests,
confirmed that the Billets supplied by the respondent did
not comply with the specifications mentioned in the
Contract. The applicant sent an e-mail dated 31st August,
2008, informed the respondent about the non-conformity
and made it clear that the same were not acceptable. On
the same day, i.e., 31st August, 2008, another e-mail was
sent setting out in detail the defects in the Billets. It was
also mentioned that the applicant had done random
cross verifications on chemical composition, and the
respondents will be intimated after getting results. It is
Page 4
4
further stated that the applicant has stopped de-stuffing
of containers, the respondent was requested to kindly
arrange to take back the rejected goods urgently and
arrange for the refund of the amount paid at the earliest.
The applicant informed the respondent that all
unloading, loading and demurrage at Port and with the
shipping company will be to your account.
4. The respondent by its letter dated 1st September, 2008
stated that the complaint has been noted and they were
equally and greatly concerned. The applicant was
informed that the complaint was being accorded highest
priority by the respondent that they were investigating at
their end the reasons for the same. The letter states that
it was never the intention of the respondent to send
substandard material to any of their esteemed
customers. It notes that “we understand your concern
and deeply regret the inconvenience caused to you.
However, we would like to assure you that we will sort
out this problem to your entire satisfaction. We wish to
Page 5
5
assure that we believe in ethical business practices and
strive hard for customer satisfaction.” The applicant was
further informed that “in order to ascertain the intensity
of the problem and discuss the various issues involved
for an amicable resolution of the same, it is planned to
send a high level delegation to your site within the next
few days”. In the meanwhile, the applicant was requested
to carry out de-stuffing of the containers and take
delivery of lot 2, 3 and 4 as the same will unnecessarily
incur charges on account of detention and demurrage.
The applicant was once again re-assured that the
issue would be resolved to their entire satisfaction.
Pursuant to the aforesaid assurances, the respondent
cleared the remaining 1234.63 MT of the Billets which,
according to the applicant, were defective. On 10th
September, 2008, there was a meeting between the
representatives of the applicant and the respondent. It
was decided that the joint inspection would be
undertaken to have the sample analyzed from
independent recognized laboratories in Dubai on 13th
Page 6
6
September, 2008. The joint inspection was not arranged.
The applicant issued several reminders informing the
respondent that the defective Billets stood rejected, and
they were requested to remove the same. Since the joint
inspection was not carried out, the applicant got an
inspection conducted through one of the reputed firms in
Dubai on 9th October, 2008. The Expert, known as SGS
Dubai, in its report dated 16th October, 2008 concluding
that “the lot is having lot of serious visual defects” and
that “all the analyzed samples were not complying with
provided contractual specification”. All efforts and
settlements having failed, the applicant invoked the
arbitration clause in terms of Article 10 of the Contract,
through its notice dated 17th December, 2008.
5. No reply was received from the respondent. The
applicant, therefore, nominated the Sole Arbitrator
(Hon.Mr.Justice S.N.Variava, a former Judge of this
Court). Since the respondent did not reply to the
Page 7
7
aforesaid letter, the applicant was left with no alternative
but to move the present petition.
6. In the reply, the respondent claimed that it was issued
inspection certificates dated 28th July, 2008 and 31st
July, 2008 of quality and quantity by Inspectorate
Griffith India Pvt. Ltd., an independent third party
inspection agency of international repute, with respect to
the goods that were to be dispatched to the applicant as
per the said Contract. The goods were duly accepted by
the applicant. The Letter of Credit had been opened by
the applicant in accordance with Article 5 of the
Contract. The applicant took delivery of the first
shipment on 27th August, 2008. It accepts that applicant
had sent e-mail dated 31st August, 2008 to the
representative of the respondent alleging that the Billets
were defective and making the demands, as noticed
earlier. The respondent gave another version as to why
the joint inspection was not carried out. According to the
respondents, all efforts to persuade the applicant had
Page 8
8
failed. They had a cursory meeting with the CEO of the
applicant which lasted two minutes. The applicant
insisted that the respondent lift the material and refund
the money. The applicant, according to the respondent,
is arbitrarily calling upon the respondent to pay
warehousing charges @ US $ 20 per metric ton per day
after 30th September, 2008. The respondent claimed that
the application is not maintainable in view of the fact
that the dispute sought to be referred to arbitration is
“not a dispute arising out of contract” but rather a
dispute which has been deliberately planted post the
completion of the Contract to escape a liability that the
applicant has already incurred, i.e., payment of price for
the goods supplied. According to the respondents, it is
not a dispute in real sense but a “moon shine dispute”.
Further it is a dispute that has been raised after the
Contract has been validly completed. The dispute about
the defective goods is a belated attempt by the applicant
to evade its liability under the Contract. The real reason
Page 9
9
for trying to avoid the Contract is the downfall of the
price in the international market of steel Billets.
7. The applicant in its rejoinder has reiterated the
averments made in the application. It is stated that the
inspection notes mentioned by the respondent had come
to the knowledge of the applicant only from the reply filed
by the respondent to the application. The applicant
denies that the material supplied by the respondent was
in accordance with the specifications given in the
Contract. It is stated that the applicant has not tried to
evade the liability under the Contract. It is also denied
that the Contract has become commercially unviable.
The applicant also denied that the respondent has made
attempts to resolve the issues raised by the applicant.
The further details given by the applicant need not be
noticed at this stage.
8. I have heard the learned counsel for the parties.
Page 10
10
9. Mr. Viswanathan, learned senior counsel appearing for
the applicant submits that the matter herein is
specifically covered by the judgment of this Court in SBP
& Co. Vs. Patel Engineering Ltd. & Anr. 1 and National
Insurance Company Limited Vs. Boghara Polyfab
Private Limited 2 In reference to the arbitration clause,
Mr. Viswanathan submits that the disputes have arisen
between the parties. The disputes relate to live claims
which are not belated. The disputes fall within the scope
and ambit of the arbitration clause which are worded
very widely. The arbitration clause clearly states that “all
disputes and differences whatsoever arising between the
buyer and seller out of or relative to the construction
meaning and operation of effect of this Contract or any
breach thereof shall be settled by the arbitration.”
10. Learned counsel also relied on Nandan Biomatrix
Limited Vs. D 1 Oils Limited 3 and Visa International
1 (2005) 8 SCC 618 2 (2009) 1 SCC 267 3 (2009) 4 SCC 495
Page 11
11
Limited Vs. Continental Resources (USA) Limited 4 and
Reva Electric Car Company Private Limited Vs. Green
Mobil 5 .
11. On the other hand, counsel for the respondent submits
that the petition is not maintainable as the condition
precedent for invoking arbitration, as agreed in the
agreement, has not been satisfied. Since there has been
no joint inspection of the material, no reliance can be
placed on the expert reports submitted by the applicant.
In this case, it was agreed that the parties shall try to
settle the dispute amicably, which was a condition
precedent for invoking the arbitration. According to the
learned counsel, in the present case, the applicant has
not even raised a proper claim, which can be referred to
arbitration.
12. I have considered the submission made by the learned
counsel for the parties. I am of the considered opinion
4 (2009) 2 SCC 55 5 (2012) 2 SCC 93
Page 12
12
that the applicant has clearly raised bonafide disputes
arising out of or relative to the construction of the
contract which contains the arbitration clause. Article
10 of the contract contemplates resolution of disputes
between the applicant and respondent through
arbitration, as per the procedure laid down under the
Arbitration and Conciliation Act, 1996. The clause reads
as under:-
“All disputes and differences whatsoever arising between buyer and seller out of or relative to the construction meaning and operation of effect of this contract or any breach thereof, shall be settled amicably, failing which it shall be settled as per the Indian Arbitration and Conciliation Act, 1996. The place of arbitration would be Mumbai, India the decision made by the arbitration organization shall be taken as final and binding upon both parties. The arbitration expenses shall be borne by the loosing party unless otherwise awarded by the arbitration organizations.”
13. A bare perusal of the aforesaid clause is sufficient to
indicate that it covers all disputes and differences of any
kind arising between the parties. The applicant has
Page 13
13
clearly raised a number of issues, which can be
summarized as follows:-
(a) Failure of the respondent to remove the defective
Billets supplied by the respondent and lying at
applicant’s premises
(b) Failure to remit the amount drawn by respondent
against the Letter of Credit
(c) Failure to pay interests and costs incurred by the
applicant
(d) Failure to pay warehousing charges @ USD 20 per
Metric Ton per day on and from 1st October, 2009
till the actual removal of defective Billets from the
premises of the applicant.
14. In such circumstances, it can not be said that the
applicant has failed to raise bonafide dispute which
cannot be referred to arbitration.
15. As noticed earlier, the applicant through its e-mail dated
31st August, 2008 had informed the respondent about
Page 14
14
defective material. In the second e-mail on the same
date, the applicant had set out the details in the Billets
and informed the respondent that it has stopped de-
stuffing of containers. The respondent was called upon
to take back the rejected goods urgently and arrange to
refund the amount paid at the earliest. In response to
the aforesaid e-mail, the respondent on 1st September,
2008 had indicated its concern and the inconvenience
caused to the applicant was deeply regretted. The
applicant was also assured that the problem would be
sorted out to the entire satisfaction of the applicant.
Thereafter, the respondents have proposed a joint
inspection, which according to the applicant was never
arranged. On the other hand, the respondent claims
that the applicant had rebuffed all the efforts made by
the respondents to resolve the issue. The applicant was
intent on claiming the refund.
16. In my opinion, the aforesaid facts and circumstances are
sufficient to show that the bonafide disputes have arisen
Page 15
15
between the parties, which are within the scope and
ambit of the arbitration clause and need to be resolved
through arbitration. I do not find any substance in the
submission of the learned counsel for the respondent
that the disputes are either belated or raised only to
avoid liability under the contract. The disputes having
arisen in September, 2008 and the present application
having been filed on 4th February, 2009, the petition can
not be said to be belated.
17. Keeping in view the facts and circumstances narrated
above, the application is allowed. All the disputes that
have arisen between the parties are hereby referred to
arbitration. I hereby appoint Hon. Mr. Justice S.N.
Variava, Former Judge of this Court, as the Sole
Arbitrator to adjudicate upon all the disputes and
differences that have arisen between the parties, on such
terms and conditions as the learned Sole Arbitrator
deems fit and proper. Undoubtedly, the learned Sole
Arbitrator shall decide all the disputes arising between
Page 16
16
the parties without being influenced by any prima facie
opinion expressed in this order, with regard to the
respective claims of the parties.
18. The registry is directed to communicate this order to the
Sole Arbitrator to enable him to enter upon the reference
and decide the matter as expeditiously as possible.
19. The Arbitration Petition is accordingly disposed of.
……..…………………..J. [Surinder Singh Nijjar] New Delhi; May 08, 2012.