YASH DEEP TREXIM PRIVATE LIMTED Vs NAMOKAR VINIMAY PVT LTD
Bench: P SATHASIVAM,RANJAN GOGOI
Case number: C.A. No.-008440-008445 / 2013
Diary number: 38674 / 2012
Advocates: R. C. KOHLI Vs
VIKAS MEHTA
Page 1
1
REPORTABLE IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS.8440-8445 OF 2013
(Arising out of SLP (C) Nos.39005-39010 of 2012)
Yash Deep Trexim Private Limited ... Appellant (s)
Versus
Namokar Vinimay Pvt. Ltd. & Ors. ... Respondent (s)
With Civil Appeal Nos.8446-8451 of 2013
(Arising Out of SLP (C) Nos.39011-39016 of 2012)
Civil Appeal Nos.8452-8457 of 2013 (Arising Out of SLP (C) Nos.39017-39022 of 2012)
Civil Appeal Nos.8458-8463 of 2013 (Arising Out of SLP (C) Nos.39023-39028 of 2012)
J U D G M E N T
RANJAN GOGOI, J.
Leave granted.
2. The common challenge in these appeals is against the
judgment and order dated 19.10.2012 passed by a Division
Bench of the High Court of Calcutta holding that the provisions
Page 2
2
of the Sick Industrial Companies (Special Provisions) Act, 1985
(hereinafter for short “SICA”) are applicable to the “foreign
companies” registered in India under the provisions of Section
591 of the Companies Act, 1956 (hereinafter for short “the
Act”) and, therefore, the revival scheme framed by the Board
for Industrial and Financial Reconstruction (hereinafter referred
to as “BIFR”) in respect of the Baranagore Jute Factory Plc.
(hereinafter for short ‘the Respondent Company’) is required to
be implemented. Though the question raised in these appeals
is short and precise, as noticed above, learned counsels for the
parties have raised various issues and contentions which, in no
way, appear to be even remotely connected with the question
of law that arises from the order of the High Court. We would,
therefore, like to make it clear at the outset that in spite of the
strenuous efforts on the part of the learned counsels for the
parties to persuade us to go into the said questions we have
considered it wholly unnecessary to do so for reasons indicated
hereinafter. Instead, we must deal with what strictly arises for
our answer in the present appeals leaving the parties to avail of
such remedies as may be open to them in law in respect of all
other grievances raised.
Page 3
3
3. We may now take note of a few relevant facts. The
Respondent Company was wound up by an order dated
28.10.1987 of the learned Company Judge of the Calcutta High
Court. The appeal filed against the winding up order by some
of the workers of the Company came to be dismissed by the
Appellate Bench of the High Court on 18.11.1987. Thereafter,
on an approach being made, the winding up proceedings were
stayed for a period of six months on 22.9.1988 and a scheme
for revival of the Company suggested by some of the
shareholders was accepted by the learned Company Judge.
Our perusal of the relevant facts and the voluminous pleadings
brought on record would seem to suggest that the initial order
of stay of the winding up dated 22.9.1988 has been extended
from time to time and till the present date different schemes
for running the affairs of the Respondent Company has been
framed and implemented pursuant whereto the Company has
been functioning as a going concern. We also deem it
necessary to put on record that it has been contended before
us that several applications registered and numbered as C.A.
No. 126/2005, C.A. No. 302/2005, C.A. No. 303/2005,
C.A.No.370/2009, C.A.No.957/2010 for a permanent stay of the
Page 4
4
winding up proceedings have been filed before the Calcutta
High Court and the same are presently pending. The above
plea has been urged notwithstanding the observations of this
Court in Radheshyam Ajitsaria & Anr. v. Bengal Chatkal
Mazdoor Union & Ors.1 to the effect that in permanent stay
of the winding up proceedings in respect of the Respondent
Company had been granted by the High Court.
4. From the pleadings of the parties placed before us it
appears that the Respondent Company is the owner of vast
immovable properties in and around Kolkata which, with the
passage of time, have enormously appreciated in value. It is
this particular asset of the Respondent Company which has
been the bone of contention between different groups of
shareholders who have claimed the right to run the affairs of
the Company under the schemes framed by the learned
Company Judge from time to time. The action of one group of
shareholders purportedly to the disadvantage of another and
the acquisition of majority share holding by one such group to
the detriment of the other by enlarging the equity base of the
Respondent Company has been the bone of contention giving
1 (2006) 11 SCC 771
Page 5
5
rise to serious contentious issues, which issues, as indicated
earlier, we are not inclined to go into as the same not only has
to be agitated before the appropriate forum but also does not
arise from the order passed by the High Court which has been
subjected to challenge in the appeals before us. All that would
be necessary for us to note, in addition to the facts stated
above, is that a Reference made in the year 2004 to the BIFR
by two of the Directors of the Respondent Company claiming to
be in office at that point of time was ordered by the Calcutta
High Court to be disposed of on merits. The said order is dated
20.02.2006 passed in W.P. No. 221 of 2006. On the basis of the
said order proceedings before the BIFR were taken up and a
scheme under Sections 18(4) and 19(3) of the SICA was framed
and notified for immediate implementation by the order of the
BIFR dated 4.11.2009. The said order came to be challenged
before the High Court in W.P. No. 1166/2009 (re-numbered as
W.P. 5535(W)/2010). There was an interim order in the said
writ petition restraining the respondents therein from taking
any steps in the matter of sale of any property of the
Respondent Company or from creating any charge in respect of
the assets of the Company without the leave of the Court. The
Page 6
6
writ petition was, however, withdrawn on 16.6.2010 whereafter
three separate writ petitions bearing Nos. 12377/2010,
12406/2010 and 12412/2010 were filed challenging the
jurisdiction of the BIFR to entertain the reference; frame the
scheme in question and pass orders for implementation of the
same. The aforesaid writ petitions were disposed of by the
learned Single Judge of the High Court by order dated
25.1.2011 holding that the SICA is not applicable to the
Respondent Company, it being incorporated outside India.
Consequently, the scheme framed by the BIFR was set aside
and quashed. As against the aforesaid order dated 25.1.2011
passed by the learned Single Judge of the High Court six
appeals were filed by the aggrieved parties bearing
Nos.169/2012, 170/2012, 171/2012, 172/2012, 173/2012 and
1115/2011. The Appellate Bench of the High Court by order
dated 19.10.2012 took the view that on a purposive
interpretation of the provisions of SICA the said Act would be
applicable to the Respondent Company. In this regard the
Division Bench of the High Court specifically took note of the
fact that the only factory of the Company is located in India at
Baranagore; 90% of its shareholders are Indians and 3700
Page 7
7
workers are working in the jute factory in West Bengal.
Aggrieved, the present appeals have been filed before us.
5. Having noticed the question(s) arising from the order of
the High Court which has been challenged in the appeals
presently under consideration, we may now briefly take note of
the contentions raised in the appeals filed by the respective
appellants before this Court.
The appellant in the appeals arising out of SLP (C) Nos.
39005-39010/2012, apart from questioning the jurisdiction of
the BIFR, also contends that the first respondent (Namokar
Vinimay Pvt. Ltd.) in the said appeals had fraudulently
increased its equity holding from 9% to 90% on payment of a
paltry sum of Rs. 5 crores by committing acts of cheating,
forgery, fraud etc. The majority shareholding of the appellant
has been thereby reduced, it is claimed.
In the appeals arising out of SLP (C) Nos.39011-
39016/2012 the workers’ union has raised grievances with
regard to the competence of the existing Management
Committee to function and contends that the Committee
consisting of the two Directors who have instituted the appeals
Page 8
8
arising out of SLP(C) Nos. 39017-39022/2012 would be
competent in law to run the affairs of the Respondent
Company. Certain alleged fraudulent acts in the matter of
disposition of the property/transfer of shares by the existing
Management Committee are also alleged by the workers’
union.
On the other hand in the appeals arising out of SLP(C) Nos.
39017-39022/2012, two Directors, namely, Chaitan Choudhury
and Ridh Karan Rakhecha who have purportedly filed the
appeal on behalf of the Respondent Company, apart from
raising the issue of jurisdiction of the BIFR and the applicability
of the SICA to the Company, had also struck issues with regard
to the changes in the composition of the Management
Committee and the frauds and the misdeeds allegedly
committed by the first respondent, i.e., Namokar Vinimay Pvt.
Ltd. in bringing out the above changes. Peculiarly, the
reference of the case of the respondent Company to the BIFR
was made by the very same appellants. In the last set of
appeals in chronological order, i.e., appeals arising out of
SLP(C) Nos. 39023-39028/2012, the appellant Radheshyam
Ajitsaria is one of the promoters of the revival scheme under
Page 9
9
which a Committee of Management had been constituted in the
year 1988/1989 by the learned Company Judge of the High
Court to run the affairs of the Company. The appellants therein
are aggrieved by the BIFR’s scheme which, according to the
appellant, would be in serious derogation of the scheme
approved by the High Court.
6. Having noted the broad features of the grievances raised
in each of these appeals we may now take note of certain
connected facts on the basis of which we will be required to
decide the necessity and expediency to adjudicate the core
question arising in these appeals and the other issues that have
been sought to be agitated before us. It has already been
stated in the earlier part of this order that the Respondent
Company is the owner of vast tracts of immovable property in
and around Kolkata which has, with the passage of time,
appreciated in value. Way back in the year 1988 an area of
about 24 acres of land owned by the Company was acquired for
the purpose of building, maintenance, management and
operation of the second Vivekananda Bridge across the river
Hoogly. In the year 2003 provisional compensation was
Page 10
10
assessed at Rs.21,28,21000/- and on deposit of the said
amount possession of the land was taken over. The acquisition
of the land came to be challenged before the High Court and
the said challenge was also carried to this Court. The net result
of the aforesaid exercise(s) was an enhancement of the
compensation initially by the High Court to the extent of 30%
and thereafter by this Court by fictionally shifting the date of
entitlement of compensation from the date of acquisition to the
date of taking over of possession. An award dated 30.01.2006
was made in terms of the order of this Court which had led to
further disputes between the parties. Eventually, all parties
agreed to refer the matter to the sole arbitration of a retired
Chief Justice of this Court who by a final Award dated 13.9.2012
awarded an additional compensation package of Rs.57 crores
along with interest, which on computation, would amount to
about Rs.50 crores. A sum of Rs.95 crores has been
deposited by the National Highway Authority of India with the
Registrar of the Calcutta High Court on 9.11.2012 in the
account of the Respondent Company. In this manner the
Respondent Company has received/entitled to receive a sum of
nearly Rs.170 crores on account of compensation for
Page 11
11
acquisition of the land. The Respondent Company has clearly
and categorically and on the basis of the precise details of its
liabilities has contended that even after meeting all its
statutory and contractual obligations and liabilities it would still
be left with a surplus of nearly Rs.50 crores and, therefore,
would not be a ‘sick company’ any more. The aforesaid
claim/position has been admitted by the appellant in the
appeals arising out of SLP (C) Nos.39005-39010/2012 in
paragraph ‘I’ of the SLP by stating as follows :
“It is submitted that in all an amount of Rs.170 crores has been paid by NHAI to the Respondent No.22 Company out of which Rs.95 crores has been deposited with the Registrar of the High Court on 9.11.2012 to the credit of the Respondent No.22 Company pursuant to the award dated 13.9.2012 and as such the Respondent No.22 Company would be out of BIFR as it will have a surplus fund available and profits of about Rs.50 crores even after meeting out all losses and liabilities.”
7. To appreciate the effect of the aforesaid facts on the
necessity of any adjudication of the present appeals, the object
behind enactment of the SICA and the statutory scheme
contemplated by the Act may be briefly noticed. An elaborate
exposition of the legislative history and object behind
Page 12
12
enactment of the SICA as well as the scheme under provisions
of the Act is to be found in a recent pronouncement of this
Court in Raheja Univeral Limited v. NRC Limited & Ors.2.
At the cost of repetition it may be usefully recapitulated that
the Act was enacted to overcome the grossly inadequate and
time consuming institutional arrangements that were then in
place for revival and rehabilitation of sick industrial companies.
The Act was brought into force to provide timely identification,
by an expert body, of sick industrial companies and to design
suitable rehabilitation packages in order to obviate the
enormous loss that would be occasioned by such units going
permanently out of business. The provisions of Sections 15 to
19 contained in Chapter III of the Act dealing with references to
the Board by the Management of sick industrial companies;
enquiries into the working of such companies and the measures
to be undertaken by the Board to make a sick industry viable
had received a full consideration of this Court in Raheja
Univeral Limited (supra). The details in this regard need not
be noticed once again save and except that the Act has cast
upon the BIFR the duty to cause a detailed inquiry to be made
2 (2012) 4 SCC 148
Page 13
13
into the functioning of any sick industrial company and to take
steps to revive the functioning of such company failing which to
refer the cases of such companies to the jurisdictional High
Court for winding up in accordance with the provisions of the
Companies Act. In this regard, specific notice must be had of
Section 3(o) of the Act which defines a sick industrial company
in the following terms:
“(o) “sick industrial company” means an industrial company (being a company registered for not less than five years) which has at the end of any financial year accumulated losses equal to or exceeding its entire net worth.
Explanation.—For the removal of doubts, it is hereby declared that an industrial company existing immediately before the commencement of the Sick Industrial Companies (Special Provisions) Amendment Act, 1993 registered for not less than five years and having at the end of any financial year accumulated losses equal to or exceeding its entire net worth, shall be deemed to be a sick industrial company;”
8. In the present case the entitlement of the respondent
company to receive a total amount of Rs.170 crores
(approximately) by way of acquisition compensation and the
payment of Rs.95 crores by NHAI which is presently lying in
Page 14
14
deposit with the Registrar of the Calcutta High Court is not in
dispute. That the respondent company would be left with a
surplus of about Rs.50 crores after meeting all its losses and
liabilities is a common ground amongst all the contesting
parties. The rehabilitation scheme framed by the Board by its
order dated 04.10.1999 is yet to be implemented. In the
aforesaid situation keeping in view the object and scheme of
the Act and the virtual consensus of the contesting parties with
regard to the present financial health of the respondent
company it is clear that the company can no longer fall within
the ambit of the expression “sick industrial company” as
defined in Section 3(o) of the Act. Further applicability of SICA
to the respondent company, therefore, does not arise.
9. If the respondent company no longer falls within the ambit
of a ‘sick industrial company’ as defined by Section 3(o) of the
Act and the Act has ceased to apply to the company and the
rehabilitation package worked out by the Board has not yet
been implemented, the question(s) arising in the present
appeals have surely become academic and redundant. If that
be so, we do not see why we should answer the said
Page 15
15
question(s) in the present group of appeals. Instead, in fitness
of things, we should leave the said question (s) open for
determination in an appropriate case and as and when the
occasion would arise.
10. In so far as the other issues, particularly, with regard to
the management of the company is concerned we have already
found that none of the said issues arise from the order of the
High Court under appeal before us. Even otherwise, we will not
be justified to go into any of the said issues and express any
opinion thereon inasmuch as this Court exercising jurisdiction
under Article 136 of the Constitution is not the appropriate
forum to adjudicate grievances/claims with regard to the right
of management of the affairs of the company by one group of
shareholders or the other. It has been urged before us that
several contentious issues with regard to the rights of one
group of shareholders or the other to be in control of the
management of the Company had been raised and some of
such claims are still pending before the High Court. Coupled
with the above is the pendency of several other proceedings
with regard to permanent stay of the winding up of the
Page 16
16
Company. Taking into account all that has been stated above
we are of the view that it would be just, proper and equitable to
leave the contesting parties to pursue their remedies before
the High Court or such other forum as may be competent in
law. For the present, the Management of the Company as on
date will continue until orders, if any, varying the current
position are passed by any forum competent in law. It is made
clear that the above is a mere working arrangement that we
have considered appropriate for the present and the same
should not be understood as any expression of opinion by us on
the entitlement of any particular group of shareholders to run
and manage the affairs of the company which issue is left
open.
11. Consequently, all these appeals shall stand disposed of in
terms of our above observations and directions.
...………………………CJI. [P. SATHASIVAM]
.........……………………J. [RANJAN GOGOI]
New Delhi,
Page 17
17
September 23, 2013.