WESTERN ELECT.SUP.CO.OF ORISSA LD. Vs M/S BABA BAIJANATH ROLLER & FLOUR MIL.LD
Bench: GYAN SUDHA MISRA,PINAKI CHANDRA GHOSE
Case number: C.A. No.-004023-004023 / 2014
Diary number: 672 / 2011
Advocates: SURESH CHANDRA TRIPATHY Vs
SIBO SANKAR MISHRA
Page 1
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO . 4023 of 2014 (Arising out of Special Leave Petition (Civil) No. 3396 of 2011)
Western Electricity Supply Co. of Orissa Ltd & Ors. ...Appellants
vs
M/s Baba Baijanath Roller and Flour Mill P. Ltd. ...Respondent
With CA No.4024 of 2014
(arising out of SLP (Civil) No.3397 of 2011)
J U D G M E N T
Pinaki Chandra Ghose, J.
1. Leave granted.
2. This appeal is directed against an order dated August 3, 2010
passed by the High Court of Orissa allowing the writ petition
filed by the respondent, quashing the bill issued by the
appellant for a sum of 5,10,930/- as well the notice of
disconnection dated October 5, 2010.
Page 2
3. The respondent-writ petitioner is a registered company, inter
alia, carrying on its business under the name and style of M/s.
Baba Baijnath Roller and Flour Mill Pvt. Ltd., having installed a
Mill in the district of Jharsuguda and is the consumer of the
appellant herein.
4. The facts of the case, briefly, are as follows :
4.1 The respondent alleged in the writ petition that on an
inspection conducted by the appellant on September 9, 2002
at the premises of the respondent, the appellant intimated
that at the time of inspection it was found that H.T. Meter,
T.P Box’s inner door and meter terminal cover quick seals,
plastic seals and paper seals were tampered. In addition,
L.T.T.P Box inner door quick seals, plastic seals and paper
seals were found tampered. The B-Phase P.T wire was found
cut as such the meter was not getting B-Phase potential.
4.2 It was further brought to the notice of the respondent by the
appellant that the interference with the metering
arrangement was made by the respondent in order to
prevent the meter from recording actual consumption which
2
Page 3
attracts Regulation 64 of the Orissa Electricity Regulatory
Commission Distribution (Conditions of Supply) Code, 1998
(hereinafter referred to as “the Code”). Accordingly, the
penal charges as per rules were intimated and raised on the
respondent on September 30, 2002. The appellant further
called upon the respondent to submit its representation, if
any, within seven days. It was intimated that in default of
payment of such charges within seven days from the date of
receipt of the penal bill, the power supply to the premises
will be disconnected without any further notice. The penal
bill was raised on the respondent/writ petitioner for a sum of
5,10,930/-. On October 5, 2002 the electricity supply was
disconnected since the respondent failed to make the
payment.
4.3 In these circumstances, a writ petition was filed by the
respondent challenging the action on the part of the
appellant before the High Court. The respondent-writ
petitioner made out a case that the bill used to be received
by the writ petitioner was around 80,000/- per month and
3
Page 4
according to the writ petitioner/respondent, the meter was
defective and recording excessive consumption.
4.4 The writ petitioner/respondent challenged the action on the
part of the appellant that when the inspection was made, at
that point of time the officers of the appellant made a
demand for illegal gratification since refused by the Manager
of the respondent-company, the officers of the appellant
raised such allegations and further the Manager was forced
to sign several papers under duress and coercion.
4.5 It was urged before the High Court on behalf of the
respondent-company on the ground (i) that the penal bill had
been issued in violation of the principles of natural justice;
(ii) that the inspection was made without giving a notice and
in the absence of the representative of the firm; (iii) that the
allegation of tampering with seals cannot be sustained as
there was no allegation that the outer seal of T.P. box was
broken or tampered with; and (iv) that the penal bill could
not have been raised since the meter was defective and was
not recording proper consumption. By filing a counter
4
Page 5
affidavit, the appellant herein duly contested the writ
petition and stated that an alternative remedy was available
to the respondent under the Code. It was further submitted
that in the instant case, there is no question of alleging that
the meter is defective. It is a clear case of theft of electricity
by the consumer and Section 26 of the Indian Electricity Act,
1910 (hereinafter referred to as “the Act of 1910”) has no
application. It is submitted that Section 26(6) of the Act of
1910 is attracted only when a meter is defective and is
incapable of recording the correct consumption of electricity.
It was further contended on behalf of the appellant before
the High Court that inspection of the meter was done in the
presence of the representative of the writ-
petitioner/respondent.
4.6 The High Court after hearing the parties held that in case of
violation of principles of natural justice even if alternative
remedy is available, a writ court can interfere for
redressal of grievance of the petitioner. The High Court
further held that the representation filed by the writ
petitioner was never considered before the imposition of
5
Page 6
penalty, far less giving an opportunity of hearing to the writ
petitioner. Accordingly, the High Court held that this action
of the appellant is in clear violation of the principles of
natural justice. In these circumstances, the High Court set
aside the penalty charges imposed by the appellant on the
writ petitioner/respondent. The inspection report was also
quashed on the ground that such inspection was never done
in the presence of the authorised persons of the writ
petitioner. The High Court further held that since the penalty
is untenable, the appellant was not entitled to levy delayed
payment surcharge on the penal charges treating it as old
arrears or current arrears. In these circumstances, the High
Court further directed to refund the amount so paid within
three months.
4.7 Being aggrieved, this appeal has been filed by the appellant.
5. Learned counsel appearing on behalf of the appellant
contended before us that the High Court has erred in holding that
the matter should come within the purview of Section 26(6) of the
Act of 1910. He submitted that the High Court ignoring the judicial
pronouncements on this question undermined the authority of the
6
Page 7
licensee (appellant) to impose penalty as a consequence on a
consumer even if the consumer has committed theft of electricity.
By this process, the provisions of the statutory Code have been
made nugatory. The meter could be subjected to tampering in
various ways. The methods as detected on inspection by the
officers of the appellant are more than sufficient to conclude that
the meter was tampered with and did not record the actual
consumption of energy consumed by the writ
petitioner/respondent. He further contended that the theft of
electricity is governed by the Code and not under the provisions
of the Act of 1910.
6. The relevant provisions of the Act of 1910 as well as the
Code, in particular Clauses 54, 56, 64, 105, 110 and 115, were
duly placed before us. It will be proper for us to reproduce those
hereunder:
“Section 26 - Meters. – (1) In the absence of an agreement to the contrary, the amount of energy supplied to a consumer or the electrical quantity contained in the supply shall be ascertained by means of a correct meter, and the licensee shall, if required by the consumer, cause the consumer to be supplied with such a meter:
Provided that the licensee may require the consumer to give him security for the price of a meter and enter into
7
Page 8
an agreement for the hire thereof, unless the consumer elects to purchase a meter.
(2) Where the consumer so enters into an agreement for the hire of a meter, the licensee shall keep the meter correct, and, in default of his doing so, the consumer shall, for so long as the default continues, cease to be liable to pay for the hire of the meter.
(3) Where the meter is the property of the consumer, he shall keep the meter correct and, in default of his doing so, the licensee may, after giving him seven days’ notice, for so long as the default continues, cease to supply energy through the meter.
(4) The licensee or any person duly authorised by the licensee shall, at any reasonable time and on informing the consumer of his intention, have access to and be at liberty to inspect and test, and for that purpose, if he thinks fit, take off and remove, any meter referred to in sub-section (1); and, except where the meter is so hired as aforesaid, all reasonable expenses of, and incidental to, such inspecting, testing, taking off and removing shall, if the meter is found to be otherwise than correct, be recovered from the consumer, and, where any difference or dispute arises as to the amount of such reasonable expenses, the matter shall be referred to an Electrical Inspector, and the decision of such Inspector shall be final:
Provided that the licensee shall not be at liberty to take off or remove any such meter if any difference or dispute of the nature described in sub-section (6) has arisen until the matter has been determined as therein provided.
(5) A consumer shall not connect any meter referred to in sub-section (1) with any electric supply-line through which energy is supplied by a licensee, or disconnect the same from any such electric supply-line, but he may by giving not less than forty-eight hours’ notice in writing to the licensee require the licensee to connect or disconnect such meter and on receipt of any such requisition the licensee shall comply with it within the period of the notice.
8
Page 9
(6) Where any difference or dispute arises as to whether any meter referred to in sub-section (1) is or is not correct, the matter shall be decided, upon the application of either party, by an Electrical Inspector; and where the meter has, in the opinion of such Inspector ceased to be correct, such Inspector shall estimate the amount of the energy supplied to the consumer or the electrical quantity contained in the supply, during such time, not exceeding six months, as the meter shall not, in the opinion of such Inspector, have been correct; but save as aforesaid, the register of the meter shall, in the absence of fraud, be conclusive proof of such amount or quantity:
Provided that before either a licensee or a consumer applies to the Electrical Inspector under this sub-section, he shall give to the other party not less than seven days’ notice of his intention so to do.
(7) In addition to any meter which may be placed upon the premises of a consumer in pursuance of the provisions of sub-section (1), the licensee may place upon such premises such meter, maximum demand indicator or other apparatus as he may think fit for the purpose of ascertaining or regulating either the amount of energy supplied to the consumer, or the number of hours during which the supply is given, or the rate per unit of time at which energy is supplied to the consumer, or any other quantity or time connected with the supply:
Provided that the meter, indicator or apparatus shall not, in the absence of an agreement to the contrary be placed otherwise than between the distributing mains of the licensee and any meter referred to in sub-section (1):
Provided also that, where the charges for the supply of energy depend wholly or partly upon the reading or indication of any such meter, indicator or apparatus as aforesaid, the licensee shall, in the absence of an agreement to the contrary, keep the meter, indicator or apparatus correct; and the provisions of sub-sections (4), (5) and (6) shall in that case apply as though the meter, indicator or apparatus were a meter referred to in sub- section (1).
9
Page 10
Explanation.—A meter shall be deemed to be “correct” if it registers the amount of energy supplied, or the electrical quantity contained in the supply, within the prescribed limits of error, and a maximum demand indicator or other apparatus referred to in sub-section (7) shall be deemed to be “correct” if it complies with such conditions as may be prescribed in the case of any such indicator or other apparatus.”
“CHAPTER - IV
METERS
54. Initial power supply shall not be given without a correct meter. Meters will be installed at the point of supply or at a suitable place as the engineer may decide. The same shall be fixed preferably in the basement or ground floor in multi- storied buildings where it will be easily accessible for reading and inspection at any time. The consumer shall run his wiring from such point of supply and shall be responsible for the safety of the meter or metering equipment on his premises from theft, damage or interference.
x x x
56. The meters and associated equipment shall be properly sealed by the engineer and consumer’s acknowledgement obtained. The seals, nameplates, distinguishing numbers or marks affixed on the said equipment or apparatus shall not be interfered with, broken, removed or erased by the consumer. The meter, metering equipment, etc. shall on no account be handled or removed by any one except under the authority of the engineer. The engineer can do so in the presence of the consumer or his representative. An acknowledgement shall be taken from the consumer or his representative when seal is broken.
x x x 64. If a meter or metering equipment has been found to have been tampered or there is resistance by the consumer to the replacement of obsolete or defective meters by the
1
Page 11
engineer, the engineer may disconnect the supply after giving seven clear days show cause notice and opportunity to the consumer to submit his representation.
x x x
Penal Charges --
105. (1) On detection of unauthorised use in any manner by a consumer, the load connected in excess of the authorised load shall be treated as unauthorised load. The quantum of unauthorised consumption shall be determined in the same ratio as the unauthorised load stands to the authorised load.
(2) The period of unauthorised use shall be determined by the engineer as one year prior to the date of detection or from the date of initial supply if the initial date of supply is less than one year from the date of detection. If the consumer provides evidence to the contrary, the period may be varied according to such evidence. The engineer may levy penal charges in addition to the normal charges for aforesaid period of unauthorised use. Where addition of the unauthorised installation or sale or diversion would result in a reclassification according to this Code, the whole of the power drawn shall be deemed to have been drawn in the reclassified category. The consumer shall also be required to execute a fresh agreement under the reclassified category.
(3) The penal energy charges for unauthorised use of power shall be two times the charges applicable to the particular category of consumer.
(4) The penal demand charges for unauthorised use of power in cases covered under two part tariff shall be calculated on un-authorised connected load expressed in KVA multiplied by two times the rate of demand charges applicable.
x x x
CHAPTER - XII
1
Page 12
CONSUMER PROTECTION
110. (1) A consumer aggrieved by any action or lack of action by the engineer under this Code may file a representation within one year of such action or lack of action to the designated authority of the licensee, above the rank of engineer who shall pass final orders on such a representation within thirty days of receipt of the representation.
(2) A consumer aggrieved by the decision or lack of decision of the designated authority of the licensee may file a representation within forty five days to the chief executive officer of the licensee who shall pass final orders on such a representation within forty five days of receipt of the representation.
(3) In respect of orders or lack of orders of the chief executive officer of the licensee on matters provided under Section 33 of the Act, the consumer may make a reference to the Commission under Section 37(1) of the Act.
x x x
Overriding effect --
115. (1) The provisions of this Code shall override the provisions of OSEB (General Condition of Supply) Regulation, 1995.
(2) Nothing contained in this Code shall have effect, in so far as it is inconsistent with the provisions of Indian Electricity Act, 1910, Electricity (Supply) Act, 1948 and Rules framed thereunder as amended by the Act.”
1
Page 13
7. Therefore, it would be evident from Section 26(6) which
carves out an exception, that where there is an allegation of
“fraud”, the same provision is not attracted. He further
contended that invariably a plea is being taken by the consumer
found to have committed theft of electricity that his meter was
defective. In the instant case, in accordance with Section 26(4),
an inspection was conducted in the presence of the
representative of the respondent. If the meter is found to be
defective on such inspection and if the respondent was desirous
of availing the benefit of Section 26(6), it is the duty of the
consumer under the said Section to move an application before
the Electrical Inspector for getting the meter tested.
8. It was submitted that the Orissa Electricity Regulatory
Commission (for short “OERC”) by virtue of Section 54 of the
Orissa Electricity Reforms Act, 1995 has framed a Code on
different issues including the manner in which theft of energy is
to be determined. They are statutory in character. Accordingly,
he submitted that the High Court has erred in dealing with the
matter without taking into account the clauses of the Code which
are framed to deal with the theft of electricity. Factually also, the
1
Page 14
High Court was incorrect in recording that the inspection was
conducted in the absence of the consumer. It is further submitted
that the decision relied on by the High Court is totally
inapplicable in the facts and circumstances of this case since
Belwal Spinning Mills Ltd. v. U.P. State Electricity Board 1 did not
deal with the Code of 1998 framed by the Orissa Electricity
Regulatory Commission and the distinguishable feature of the
said decision is that the said decision made it clear that when
there is an allegation of fraud or tampering of meter, Section
26(6) of the Act of 1910 has no application. Learned counsel
further relied upon the decision in Madhya Pradesh Electricity
Board & Ors. v. Smt. Basantibai 2 and drew our attention to
paragraph 9 of the said decision and contended that Section
26(6) of the Act of 1910 has no application where there is a
dispute regarding the commission of fraud in tampering with the
meter and breaking the body seal is totally outside the ambit of
Section 26(6) of the said Act. It is further contended that after
the inspection was conducted in the presence of the
representative of the consumer, details of the illegalities found
1 1997 (6) SCC 740 2 1988 (1) SCC 23
1
Page 15
on such inspection were shared with the respondent consumer,
resulting in receipt of a vague reply from the consumer and was
processed to raise a demand by way of a penal bill. Therefore,
according to him, the requirement under the law was followed
before issuance of the said penal bill. He further pointed out that
on being aggrieved by such decision, the writ
petitioner/respondent could have followed the statutory remedy
as envisaged under Section 110 of the Code. It is further stated
that the High Court did not even give any reason for the direction
to refund the delayed payment surcharge.
9. In these circumstances, it is submitted that the order of the
High Court cannot be sustained under the provisions of law. The
penal bill was quashed only on the ground that the unit of the
respondent was closed. Such fact is immaterial and irrelevant in
respect of demand of a penal bill. The approach of the High Court
is patently erroneous.
10. Per contra, it is submitted on behalf of the respondent that
the argument of the appellant could have succeeded if the
appellant could prove that the respondent had indulged in theft
1
Page 16
of electricity. It is pointed out that on October 10, 2002, the High
Court directed the respondent to deposit 30,000/- without
prejudice and for restoration of power supply since the electricity
was disconnected on October 5, 2002. The power supply was
restored on deposit of 10,000/- and subsequently, the
respondent further deposited a sum of 20,000/- in terms of the
direction. It is submitted that in spite of the interim order passed
by the High Court directing stay of realisation of the penal bill,
the appellants went on charging delayed payment surcharge on
the penal charges in monthly bills raised subsequently on the
respondent. It is submitted that the meter had actually inherent
defects as only the inner seal was broken but the outer seal was
intact. It is true that the matter was not referred to Electrical
Inspector. It is further stated that in case of a dispute between
the Central Act and the State Act, Central Act will prevail upon
the State Act.
11. We have noticed the facts in this case. We have also
considered the Sections of the Act of 1910 and it appears to us
that Section 26 is relevant only when there is any difference or a
dispute arises in connection with correctness of a meter, in that
1
Page 17
case the matter shall be decided, upon being applied by either
party, by an Electrical Inspector and in the opinion of the
Inspector if it is found that the meter is defective, the Inspector
shall estimate the amount of energy supplied to the consumer or
the electrical quantity contained in the supply during such time
not exceeding six months but if there is a question of fraud in
tampering with the meter, in that case there is no question of
applicability of Section 26 of the said Act in such a matter. In the
instance case, we have asked the learned counsel appearing for
the respondent whether following Section 26(6), the respondent
ever asked or applied for checking of the meter by the Electrical
Inspector on the ground of defective meter. The answer was in
the negative. Therefore, it shows that the ingredients of Section
26(6) were not followed by the respondent to meet the necessity
of checking the meter in question in accordance with the said
provision.
12. We have further noticed that the inspection was made in the
presence of the representative of the respondent who is a
Manager of the said company and in his presence the meter was
checked up and was found to be tampered with. We have also
1
Page 18
noticed that the plea of duress or coercion in signing the
inspection report was raised by the respondent but in reality no
allegation was made by the respondent before an appropriate
authority excepting such bald allegations have been made before
the writ court without any basis or evidence. Therefore that fact
cannot have any bearings in deciding this matter. We cannot
brush aside the said fact from the mind while dealing with the
matter concerning tampering of meter. It appears to us that the
said aspect has escaped the attention of the High Court and
therefore, in our opinion, the High Court failed to appreciate the
facts in their proper perspective. Therefore, on this ground, we
find that the High Court has misconstrued the facts and the
provisions of law in dealing with the matter. The provision of law
which deals with tampering of metering equipments, i.e. clauses
56, 64 and 105 of the Code have not been considered by the
High Court and in our opinion the High Court has failed to
construe such provisions and erred in deciding the matter
ignoring the said provisions. The High Court accepted the
position submitted on behalf of the respondent/writ-petitioner
that it was a case of defective meter and there is no question of
1
Page 19
any tampering with the meter in question. The High Court has
failed to appreciate that the inspection was made and the fact of
tampering of meter would appear from the inspection report and
such inspection report was signed on behalf of the
respondent/writ-petitioner. Therefore, the High Court ignoring the
said fact, came to the conclusion without giving any reason, that
the inspection report is bad and has erred in setting aside such
inspection report. Hence, such findings of the High Court cannot
be sustained.
13. Therefore, in our opinion, the High Court was also wrong in
not considering the rights of the appellant to raise penal charges
on the respondent on the ground of unauthorised consumption
by way of tampering the meter or metering equipment and has a
right to raise penal bill in accordance with the provisions of Code.
On this ground the High Court has erred in allowing the writ
petition in favour of the respondent, quashing the penal charges
and further the direction given to refund the amount. The said
order is without any reason and cannot be sustained in the eyes
of law. Hence, the same is set aside.
1
Page 20
14. We have also noticed in Madhya Pradesh Electricity
Board & Ors. v. Smt. Basantibai (supra), this Court held:
“9. It is evident from the provisions of this section that a dispute as to whether any meter referred to in sub-section (1) is or is not correct has to be decided by the Electrical Inspector upon application made by either of the parties. It is for the Inspector to determine whether the meter is correct or not and in case the Inspector is of the opinion that the meter is not correct he shall estimate the amount of energy supplied to the consumer or the electrical quantity contained in the supply during a period not exceeding six months and direct the consumer to pay the same. If there is an allegation of fraud committed by the consumer in tampering with the meter or manipulating the supply line or breaking the body seal of the meter resulting in not registering the amount of energy supplied to the consumer or the electrical quantity contained in the supply, such a dispute does not fall within the purview of sub- section (6) of Section 26. Such a dispute regarding the commission of fraud in tampering with the meter and breaking the body seal is outside the ambit of Section 26(6) of the said Act. An Electrical Inspector has, therefore, no jurisdiction to decide such cases of fraud. It is only the dispute as to whether the meter is/is not correct or it is inherently defective or faulty not recording correctly the electricity consumed, that can be decided by the Electrical Inspector under the provisions of the said Act.”
In Sub-Divisional Officer (P), UHBVNL v. Dharam Pal3, it
appears to us that in case of tampering, there is no scope for
reference to Electrical Inspector. It was held :
“9. In State of W.B. v. Rupa Ice Factory (P) Ltd. [2004 (10) SCC 635], it was observed as follows: (SCC p. 637, para 5)
3 2006 (12) SCC 222
2
Page 21
“5. As regards the second claim, namely, the claim for the period from December 1993 to December 1995, the finding of the High Court is that the Vigilance Squad had found that Respondent 1 had tapped the electric energy directly from the transformer to the LT distribution board bypassing the meter circuit. If that is so, we do not know as to why the High Court would go on to advert to Section 26 of the Electricity Act and direct reference to the Electrical Inspector for decision under Section 26(6). In two decisions of this Court in M.P Electricity Board v. Basantibai [1988 (1) SCC 23] and J.M.D. Alloys Ltd. v. Bihar SEB [2003 (5) SCC 226] it has been held that in cases of tampering or theft or pilferage of electricity, the demand raised falls outside the scope of Section 26 of the Electricity Act. If that is so, neither the limitation period mentioned in Section 26 of the Electricity Act nor the procedure for raising demand for electricity consumed would arise at all. In this view of the matter, that part of the order of the Division Bench of the High Court, directing that there should be a reference to the Electrical Inspector, shall stand set aside. In other respects the order of the High Court shall remain undisturbed. The appeal is allowed accordingly.”
15. In these circumstances, in our opinion, the High
Court was wrong in bringing the matter within the scope of the
provision of Section 26(6) of the said Act, and further the High
Court was totally wrong in appreciation of facts even on the
question of inspection and stated that no representative was
present at that point of time. On the contrary, admittedly the
Manager of the respondent at the time of the inspection was
present.
2
Page 22
16. In these circumstances, the appeals are allowed, the
writ petitions filed by the respondent/writ-petitioner are
dismissed and the order passed by the High Court is set aside.
....................................J. (Gyan Sudha Misra)
New Delhi; .....................................J. March 26, 2014. (Pinaki Chandra Ghose)
2