UNITED INDIA INSURANCE CO.LTD. Vs HYUNDAI ENGINEERING AND CONSTRUCTION CO. LTD.
Bench: HON'BLE THE CHIEF JUSTICE, HON'BLE MR. JUSTICE A.M. KHANWILKAR, HON'BLE DR. JUSTICE D.Y. CHANDRACHUD
Judgment by: HON'BLE MR. JUSTICE A.M. KHANWILKAR
Case number: C.A. No.-008146-008146 / 2018
Diary number: 4141 / 2018
Advocates: MOHIT PAUL Vs
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 8146 OF 2018 (Arising out of SLP(C) No.4260/2018)
United India Insurance Co. Ltd. & Anr. …..Appellant(s)
:Versus:
Hyundai Engineering and Construction Co. Ltd. & Ors. ....Respondent(s)
J U D G M E N T
A.M. Khanwilkar, J.
1. The conundrum in this appeal is whether clause 7 of the
subject Insurance Policy dated 5th September, 2007 posits
unequivocal expression of the intention of arbitration or is
hedged with a conditionality? The learned Single Judge of the
High Court of Judicature at Madras vide impugned judgment
and order dated 30th November, 2017 in O.P. No.537/2017
had held that post amendment of the Arbitration and
2
Conciliation Act, 1966 (for short, “the Act”), with effect from
23rd October, 2015 by insertion of sub-section 6A in Section
11 of the Act, the limited mandate of the Court is to examine
the factum of existence of an arbitration agreement. No more
and no less. The learned Single Judge placed reliance on the
two-Judge Bench decision of this Court in Duro Felguera,
S.A. Vs. Gangavaram Port Limited,1 and another decision of
its own High Court in Jumbo Bags Ltd. Vs. New India
Assurance Co. Ltd.2 The appellants, however, placed
reliance on a three-Judge Bench decision of this Court in
Oriental Insurance Company Limited Vs. Narbheram
Power and Steel Private Limited,3 where this Court had an
occasion to construe a similar clause of an insurance policy
as in the present case. Relying on this decision, it is urged
that the impugned judgment cannot be countenanced and
that the High Court ought to have dismissed the original
petition filed by the respondents under Sections 11(4) & 11(6)
of the Act read with Rule 2 of the Appointment of Arbitrators
1 (2017) 9 SCC 729
2 2016 SCC OnLine Mad 9141 : (2016) 3 CTC 761 : (2016) 2 LW 769
3 (2018) 6 SCC 534
3
by the Chief Justice of Madras High Court Scheme, 1996, to
declare the arbitrator nominated by the respondents herein as
the sole arbitrator; or in addition, appoint one arbitrator on
behalf of the appellants herein so as to adjudicate all the
disputes inter se between the parties in terms of the Act.
2. Shorn of unnecessary facts, be it noted that the
respondent Nos.1 and 2 constitute a Joint Venture (“JV”).
Respondent No.3 awarded a contract on 29th September, 2006
for design, construction and maintenance of a bridge across
the River Chambal, which was to be completed within a period
of 40 months and was commenced on 5th December, 2007 by
the JV after respondent No.3 handed over the site to it. After
commencement of the work, a Contractor All Risk Insurance
Policy (“CAR Policy”) dated 5th December, 2007 was obtained
from the appellants covering the entire project, valued at
Rs.2,13,58,76,000/-. The policy contained clause 7, which
reads thus:
“7. If any difference shall arise as to the quantum to be paid
under this Policy (liability being otherwise admitted) such
difference shall independently of all other questions be
4
referred to the decision of an arbitrator to be appointed in
writing by the parties in difference, or if they cannot agree
upon a single arbitrator to the decision of two disinterested
persons as arbitrators of whom one shall be appointed in
writing by each of the parties within two calendar months
after having been required so to do in writing by the other
party in accordance with the provisions of the Arbitration
Act, 1940, as amended from time to time and for the time
being in force in case either party shall refuse or fail to
appoint arbitrator within two calendar months after receipt
of notice in writing requiring an appointment the other party
shall be at liberty to appoint sole arbitrator and in case of
disagreement between the arbitrators, the difference shall be
referred to the decision of an umpire who shall have been
appointed by them in writing before entering on the reference
and who shall sit with the arbitrators and preside at their
meetings.
It is clearly agreed and understood that no difference or
dispute shall be referable to arbitration as herein before
provided, if the Company has disputed or not accepted
liability under or in respect of this Policy.
It is hereby expressly stipulated and declared that it shall be
a condition precedent to any right of action or suit upon this
policy that the award by such arbitrator, arbitrators or
umpire of the amount of the loss or damage shall be first
obtained.
It is also hereby further expressly agreed and declared that
if the Company shall disclaim liability to the insured for any
claim hereunder and such claim shall not within 3 calendar
months from the date of such disclaimer have been made the
subject matter of a suit in a court of law, then the claim
shall for all purpose be deemed to have been abandoned and
shall not thereafter be recoverable hereunder.”
(emphasis supplied)
5
3. During the construction of the bridge, on 24th December,
2009, an accident occurred causing significant loss to the
contractor. A detailed claim for a sum of Rs.1,51,59,94,543/-
was submitted by the JV to the appellants, in response to
which the appellants appointed one Mr. S.
Ananthapadmanabhan, Surveyor and Loss Adjuster, for
assessing the loss caused to the contractor. A final report was
submitted by the Surveyor on 28th February, 2011 assessing
the loss as Rs.39,09,92,828/-, however, with the finding that
the damage was on account of the faulty design and improper
execution of the project and not payable under the policy.
Besides the stated report, a Committee of Experts was set up
by the Ministry of Road Transport and Highways, Government
of India, to enquire into the accident which then submitted its
report on 7th August, 2010.
4. The appellants took into account both these reports and
vide communication dated 21st April, 2011, intimated the
respondents that the claim put forth by the JV, was found to
6
be not payable, and accordingly, stood repudiated. The said
communication reads thus:
“UNITED INDIA INSURANCE COMPANY LIMITED
Divisional Office:010700 Post Box No.4528
Ist Floor, Silingi Building Gram UNDIVSEVEN 134, Greams Road Phone:28290845/846
Chennai-600 006 Telefax:044-28290844 Ref.:010700/CAR Claim/2011 21st April, 2011
REGISTERED POST WITH ACKNOWLEDGE DUE
M/s National Highways of Authority of India 1-C-10 SFS Colony
Talwandi, Kota Rajasthan-324 005
Dear Sirs
Kind Attn: Mr. Anoop Kulshreshtha, Project Director
Re: Claim under Contractor‟s All Risk Policy No.011900/44/07/03/60000001- Our Claim
No.010703/44/09/03/90000007-Collapse of Cable Stayed Bridge at Kota, Rajasthan.
We refer to the above claim lodged by you under your Contractor‟s All Risk Policy in respect of collapse of
portion of bridge under construction on 24.12.2009.
You are aware that immediately on intimation of the
occurrence, our Company had deputed Mr. S Ananta Padmanabhan, a duly licensed and well experienced civil engineer surveyor for detailed survey as required
by Insurance Act. The surveyor had visited the site on various occasions and was in contact and
correspondence with you when various particulars, information and records were obtained. Besides enquiries with you the surveyor had also made other
enquiries for information including the Government, Police Authorities and gathered reports of the
7
respective agencies. After detailed survey, the surveyor had submitted his Final Report dated 28.2.2011 in
respect of the claim.
Besides the Survey Report, it also found that the
occurrence was the subject matter of enquiry by a Special Committee constituted by the Ministry of Road
Transport and Highways, Govt. of India which had also submitted a detailed report dated 7.8.2010.
We find that there had been a collapse of the lateral span P3-P4, P4 Pylon and main span structures from S1-S10 segments which fell into the river.
On a careful study of the records it is found that the
collapsed portion was affected entirely due to faulty design, besides defective workmanship and materials in execution of the project. A few of the relevant factors
are observed as under:-
In execution of the project it is found that the junction
at Pylon P4 was most critical and vulnerable which had to be handled with due care and diligence. An
instable equilibrium had been caused at this junction, due to shearing of the slab in the lateral span P3-P4 about 15 mts. From the P4 junction, which caused the
tilting of the pylon, dragging with it the spans P3-P4, P3-P2 and Piers P3, P4. The release of restraints on
the movement of the bearings at P4 had not been performed in manner necessary, contributing to a massive failure. Lack of coordination and planning
between various consultants and failure to properly oversee the execution had been found.
There had been change of allocation of work among various joint venture partners which had played a key
role in the quality of workmanship. Even at the affected P4 location, construction of Pier P4 was the responsibility of Hyundai Engg. & Construction Co.
Whereas it was found to have been carried out by Gatnmon India.
There had also been change in the sequence of operations in construction to make up for lost time,
which adversely affected the stability of the P4 joint.
The summary of the findings of the Enquiry committee
is that the collapse was caused, inter alia, by
8
1) absence of stability devices during construction, 2) shortfall in design and 3) deficient workmanship.
The Enquiry Committee have more particularly observed that
a) the contractors are responsible for all during the
structure to reach a vulnerable stage, without taking adequate precautions with respect to stability and robustness of the partially completed structure and
shortfall in the design. b) Since they have been shortfalls at the design responsibility also lies with.
The available records and documents clearly reveal
that the loss has occurred due to faulty design and defective workmanship.
We find that national Highways Authority of India have in fact initiated action by issue of show cause notice against the Contractors.
The Kota Police had lodged FIR against various
employees of the Contractors/Sub contractors and submitted final report which supports the above observations.
The policy does not cover the loss in the above circumstances. In fact the policy specifically
excludes any loss/damage caused by faulty design, defective workmanship/material. Further, the
revelations of the expert body and the surveyors indicate willful acts/negligence in execution of work of such nature resulting in the occurrence.
In view of the above, we regret to inform you that the claim is found to be not payable and
accordingly stands repudiated.
Insurers reserve their right to rely upon any further or other materials/terms in support of the above conclusion and the above circumstances are not
exhaustive of the basis for the above decision.
Thanking You
9
Yours faithfully
Sd/-
Senior Divisional Manager
Copy to:
1) M/s Hyundai Engineering & Construction Co. Ltd &
Gammon India Ltd., Chambal Bridge Project. Behind Tilam Sangh, Rawat Bhata Road, Kota Rajasthan-
324010. 2) Regional Office-Technical-Engineering Dept. 3) Head Office-Technical-Engineering Dept.
Regd. & Head Office: 24, Whites Road, Chennai-600 014.”
(emphasis supplied)
5. The JV nevertheless entered into correspondence with
the appellants to reopen and re-assess its decision of
repudiation of the claim. Finally, the appellants informed the
respondents that it was unable to “reconsider” the claim which
has already been repudiated. The said communication reads
thus:
“UNITED INDIA INSURANCE COMPANY LIMITED
HEAD OFFICE 24, WHITES ROAD CHENNAI
CIN:U93090TN1938GOI000108
Ref:No.UIIC/ENGG/CLAIMS/17-18/01 Dt:17.04.2017
To
KA: Mr. Anupam Gupta
The Project Director
M/s National Highways Authority of India
Project Implementation Unit
A-575, Talwandi, Kota (Rajasthan)-324005
10
Subject: CAR Insurance Policy
No.011900/44/07/03/60000001.
Settlement of Contractors claim
No.010703/44/096/03/90000007.
Dear Sir,
We refer to your letter Ref:17011/27/2006-Kota/CAR/RJ-
05/3909 dt. 18.01.2017 and Contractor letter Ref: HZ-6718,
dated 04.02.2017 and also the subsequent meeting held at
our office Chennai. On perusal of the documents provided,
we find that no further points have emerged in support of
the claim.
In view of the above we regret our inability to reconsider
the claim which was repudiated.
Yours faithfully
(D. Nagalakshmi)
Dy. General Manager
CC: KA: Mr. Haeng Kwon Kang
The Chief Project Manager
Hyundai Engineering & Construction Co. Ltd.
Chambal Bridge Project, Behind Tilam Sangh
Rawat Bhata Road, Kota Rajasthan-324 010”
(emphasis supplied)
6. As a sequel, the JV vide its letter dated 29th May, 2017
informed the appellants that disputes had arisen between the
appellants and the JV and in view thereof it was invoking the
arbitration clause No.7 contained in the Insurance Policy and
had nominated Dr. V.K. Agrawal as its Arbitrator. The
11
appellants were also called upon to either accept the name of
the sole arbitrator or nominate its own arbitrator within 30
days from the date of receipt of the communication.
Eventually, respondent Nos.1 & 2 filed a petition under
Sections 11(4) & 11(6) of the Act before the High Court of
Judicature at Madras being O.P. No.537/2017.
7. The said petition was resisted by the appellants. It was
urged that the subject clause 7 of the policy was hedged with a
pre-condition expressly predicating that no difference or
dispute shall be referable to arbitration, if the appellants
disputed or did not accept its liability under or in respect of
the policy. In other words, in case of repudiation of the claim
by the appellants, the remedy of the insured was to file a suit
within 3 months of such disclaimer. It was asserted that the
appellants had repudiated the liability vide letter dated 21st
April, 2011. That is an indisputable fact. The communication
sent by the appellants on 17th April, 2017 was a mere
reiteration and confirmation of the repudiation already
communicated vide letter dated 21st April, 2011. It was
12
specifically denied that the said letter dated 17th April, 2017
was a final repudiation for the purpose of calculating
limitation as alleged by the applicants (respondent Nos.1 & 2).
It was urged that the dispute raised was not one of quantum
to be paid under the policy but on the very factum of alleged
loss not covered under the policy. By virtue whereof, the
agreement specifically excluded making a reference to
arbitration.
8. Notwithstanding the stand taken by the appellants, the
learned Single Judge of the High Court by the impugned
judgment allowed the petition filed by respondent Nos.1 & 2
and appointed Mr. Justice P. Jyothimani, Former Judge, High
Court of Judicature, Madras to act as an Arbitrator in the
matter, having opined that arbitration agreement existed in
the form of clause 7 of the Insurance Policy, by relying mainly
on the decision in Duro Felguera, (supra) and Jumbo Bags
Ltd., (supra).
13
9. We have heard Mr. P.P. Malhotra, learned senior counsel
appearing for the appellants and Ms. Meenakshi Arora,
learned senior counsel appearing for the respondents.
10. The clause similar to the subject clause 7 of the
Insurance Policy came up for consideration before a three-
Judge Bench of this Court in Oriental Insurance Company
Limited (supra). After analysing the legal principle expounded
in a host of decisions, including the decision in Jumbo Bags
Ltd. (supra), the Court opined as follows:
“23. It does not need special emphasis that an arbitration
clause is required to be strictly construed. Any expression in the clause must unequivocally express the intent of
arbitration. It can also lay the postulate in which situations the arbitration clause cannot be given effect to. If a clause stipulates that under certain
circumstances there can be no arbitration, and they are demonstrably clear then the controversy pertaining to
the appointment of arbitrator has to be put to rest. 24. In the instant case, Clause 13 categorically lays the
postulate that if the insurer has disputed or not accepted the liability, no difference or dispute shall be referred to arbitration…..”
(emphasis supplied)
While adverting to the observation in paragraphs 28 and 32 of
the Jumbo Bags Ltd. (supra), the Court observed thus:
14
“19. We may presently refer to the decision of the Madras
High Court in Jumbo Bags Ltd. In the said case, the learned Chief Justice was interpreting clause 13 of the policy
conditions. Referring to Vulcan Insurance Co. Ltd., he has held thus: (Jumbo Bags Ltd. case, SCC OnLine Mad para 28)
„28. …The dispute which is not referable to arbitration, being not covered by the clause cannot be over the subject-matter of arbitration, and the remedy of the
insured in this case is only to institute a suit.‟
And again : (SCC OnLine Mad para 32)
„32. I am of the view that the remedy of arbitration is not
available to the petitioner herein in view of the arbitration clause specifically excluding the mode of
adjudication of disputes by arbitration, where a claim is repudiated in toto. The remedy would thus only be of a civil suit in accordance with law.‟
We concur with the said view.”
(emphasis supplied)
11. The other decision heavily relied upon by the High Court
and also by the respondents in Duro Felguera (supra), will be
of no avail. Firstly, because it is a two-Judge Bench decision
and also because the Court was not called upon to consider
the question which arises in the present case, in reference to
clause 7 of the subject Insurance Policy. The exposition in this
decision is a general observation about the effect of the
amended provision and not specific to the issue under
15
consideration. The issue under consideration has been directly
dealt with by a three-Judge Bench of this Court in Oriental
Insurance Company Limited (supra), following the exposition
in Vulcan Insurance Co. Ltd. Vs. Maharaj Singh and
Anr.4, which, again, is a three-Judge Bench decision having
construed clause similar to the subject clause 7 of the
Insurance Policy. In paragraphs 11 & 12 of Vulcan Insurance
Co. Ltd. (supra), the Court answered the issue thus:
“11. Although the surveyors in their letter dated April
26, 1963 had raised a dispute as to the amount of any
loss or damage alleged to have been suffered by
Respondent 1, the appellant at no point of time raised
any such dispute. The appellant company in its letter
dated July 5 and 29, 1963 repudiated the claim
altogether. Under clause 13 the company was not
required to mention any reason of rejection of the
claim nor did it mention any. But the repudiation of
the claim could not amount to the raising of a
dispute as to the amount of any loss or damage
alleged to have been suffered by Respondent 1. If
the rejection of the claim made by the insured be on
the ground that he had suffered no loss as a result of
the fire or the amount of loss was not to the extent
claimed by him, then and then only, a difference
could have arisen as to the amount of any loss or
damage within the meaning of clause 18. In this case,
however, the company repudiated its liability to pay any
amount of loss or damage as claimed by Respondent 1.
4 (1976) 1 SCC 943
16
In other words, the dispute raised by the company
appertained to its liability to pay any amount of damage
whatsoever. In our opinion, therefore, the dispute raised
by the appellant company was not covered by the
arbitration clause.
12. As per clause 13 on rejection of the claim
by the company an action or suit, meaning thereby a
legal proceeding which almost invariably in India
will be in the nature of a suit, has got to be
commenced within three months from the date of
such rejection; otherwise, all benefits under the
policy stand forfeited. The rejection of the claim may
be for the reasons indicated in the first part of clause
13, such as, false declaration, fraud or wilful neglect of
the claimant or on any other ground disclosed or
undisclosed. But as soon as there is a rejection of the
claim and not the raising of a dispute as to the amount
of any loss or damage, the only remedy open to the
claimant is to commence a legal proceeding, namely, a
suit, for establishment of the company‟s liability. It may
well be that after the liability of the company is
established in such a suit, for determination of the
quantum of the loss or damage reference to arbitration
will have to be resorted to in accordance with clause 18.
But the arbitration clause, restricted as it is by the
use of the words ‘if any difference arises as to the
amount of any loss or damage’, cannot take within
its sweep a dispute as to the liability of the company
when it refuses to pay any damage at all.”
(emphasis supplied)
Again in paragraph 22, after analysing the relevant judicial
precedents, the Court concluded as follows:
17
“22. The two lines of cases clearly bear out the two distinct situations in law. A clause like the one in Scott v. Avery bars any action or suit if commenced for determination of a dispute covered by the arbitration clause. But if on the
other hand a dispute cropped up at the very outset which cannot be referred to arbitration as being not covered by the clause, then Scott v. Avery clause is
rendered inoperative and cannot be pleaded as a bar to the maintainability of the legal action or suit for
determination of the dispute which was outside the arbitration clause.”
(Emphasis supplied)
12. From the line of authorities, it is clear that the
arbitration clause has to be interpreted strictly. The subject
clause 7 which is in pari materia to clause 13 of the policy
considered by a three-Judge Bench in Oriental Insurance
Company Limited (supra), is a conditional expression of
intent. Such an arbitration clause will get activated or kindled
only if the dispute between the parties is limited to the
quantum to be paid under the policy. The liability should be
unequivocally admitted by the insurer. That is the pre-
condition and sine qua non for triggering the arbitration
clause. To put it differently, an arbitration clause would
enliven or invigorate only if the insurer admits or accepts its
liability under or in respect of the concerned policy. That has
been expressly predicated in the opening part of clause 7 as
18
well as the second paragraph of the same clause. In the
opening part, it is stated that the “(liability being otherwise
admitted)”. This is reinforced and re-stated in the second
paragraph in the following words:
“It is clearly agreed and understood that no difference or dispute shall be referable to arbitration as herein before
provided, if the Company has disputed or not accepted liability under or in respect of this Policy.”
Thus understood, there can be no arbitration in cases
where the insurance company disputes or does not
accept the liability under or in respect of the policy.
13. The core issue is whether the communication sent on
21st April, 2011 falls in the excepted category of repudiation
and denial of liability in toto or has the effect of acceptance of
liability by the insurer under or in respect of the policy and
limited to disputation of quantum. The High Court has made
no effort to examine this aspect at all. It only reproduced
clause 7 of the policy and in reference to the dictum in Duro
Felguera (supra) held that no other enquiry can be made by
the Court in that regard. This is misreading of the said
19
decision and the amended provision and, in particular, mis-
application of the three-Judge Bench decisions of this Court in
Vulcan Insurance Co. Ltd. (supra) and in Oriental
Insurance Company Ltd. (supra).
14. Reverting to the communication dated 21st April, 2011,
we have no hesitation in taking the view that the appellants
completely denied their liability and repudiated the claim of
the JV (respondent Nos.1 & 2) for the reasons mentioned in
the communication. The reasons are specific. No plea was
raised by the respondents that the policy or the said clause 7
was void. The appellants repudiated the claim of the JV and
denied their liability in toto under or in respect of the subject
policy. It was not a plea to dispute the quantum to be paid
under the policy, which alone could be referred to arbitration
in terms of clause 7. Thus, the plea taken by the appellants is
of denial of its liability to indemnify the loss as claimed by the
JV, which falls in the excepted category, thereby making the
arbitration clause ineffective and incapable of being enforced,
if not non-existent. It is not actuated so as to make a reference
20
to arbitration. In other words, the plea of the appellants is
about falling in an excepted category and non-arbitrable
matter within the meaning of the opening part of clause 7 and
as re-stated in the second paragraph of the same clause.
15. In view of the above, it must be held that the dispute in
question is non-arbitrable and respondent Nos.1 & 2 ought to
have resorted to the remedy of a suit. The plea of respondent
Nos.1 & 2 about the final repudiation expressed by the
appellants vide communication dated 17th April, 2017 will be
of no avail. However, whether that factum can be taken as the
cause of action for institution of the suit is a matter which can
be debated in those proceedings. We may not be understood to
have expressed any opinion either way in that regard.
16. Accordingly, we allow this appeal and set aside the
impugned judgment and order and further dismiss the original
petition No.537/2017 filed by respondent Nos.1 & 2 before the
High Court of Judicature at Madras, with liberty to the said
respondents to take recourse to a civil suit for mitigation of its
grievances, if so advised. We are not expressing any opinion
21
either way on the merits of the issues to be answered in the
said proceedings.
17. The appeal is allowed in the aforementioned terms with
no order as to costs.
.………………………….CJI.
(Dipak Misra)
…………………………..….J. (A.M. Khanwilkar)
…………………………..….J. (Dr. D.Y. Chandrachud)
New Delhi;
August 21, 2018.