UNION OF INDIA Vs M/S. PAM DEVELOPMENT PVT. LTD.
Bench: SURINDER SINGH NIJJAR,RANJANA PRAKASH DESAI
Case number: C.A. No.-005618-005618 / 2006
Diary number: 18984 / 2005
Advocates: SHREEKANT N. TERDAL Vs
PRANAB KUMAR MULLICK
Page 1
REPORTABLE IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5618 OF 2006
UNION OF INDIA ...APPELLANT
VERSUS
M/S PAM DEVELOPMENT PVT. LTD. ...RESPONDENT
ORDER
This appeal has been filed by the Union of
India challenging the judgment and order of the
Calcutta High Court dated 15th June, 2005 rendered
in APOT NO.643 of 2003.
We may notice here the bare essential facts,
which would have a bearing on the legal controversy
involved in the appeal.
On 19th October, 1992, the appellant entered
into an agreement with the respondent for
construction of Industrial Covered Electrical Loco
Shed. Subsequently, according to the appellant,
the agreement was terminated in terms of clause 64
of the General Conditions of Contract by which the
agreement between the parties was governed. The
twin reasons for termination of the contract were
that the respondent initially delayed the
commencement of the work and subsequently executed
...2/-
Page 2
:2:
the work which was of inferior quality. Therefore,
the appellant had to get the balance work completed
from another contractor.
On 24th July, 1996, the respondent raised
certain claims against the appellant.
On 30th September, 1996, the respondent
demanded that the disputes be referred to
arbitration.
Since the disputes were not referred to
arbitration, the respondent approached the High
Court of Calcutta under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (hereinafter
referred to as “the Arbitration Act, 1996”) for the
appointment of a sole arbitrator. The High Court
by its order dated 10th July, 1998 appointed Mr.
Justice Satyabrat Mitra as the sole arbitrator.
The learned arbitrator duly commenced the
arbitration proceedings, in which the appellant
fully participated. The appellant filed statement
...3/-
Page 3
:3:
of defence. Upon completion of the arbitration
proceedings, the learned arbitrator made the award
on 25th January, 2002. The claims of the respondent
were accepted and the award was rendered in favour
of the contractor in the sum of Rs.1,29,89,768/-.
Aggrieved by the aforesaid award, the
appellant filed an application under Section 34 of
the Arbitration Act, 1996 before the High Court for
setting aside the award. The learned single judge
of the High court dismissed the aforesaid
application of the appellant on 28th October, 2003.
Aggrieved by the aforesaid order, the
appellant filed Intra-Court appeal before the
Division Bench of the High court, which has also
been dismissed by the impugned judgment dated 15th
June, 2005.
The present appeal arises out of Special Leave
Petition (Civil) No.20316 of 2005.
...4/-
Page 4
:4:
We have heard the learned counsel for the
parties at length.
Mr. P.P. Malhotra, learned Additional
Solicitor General, appearing for the Union of
India, submitted that the High Court committed an
error of jurisdiction by appointing a former judge
of the High court as the sole arbitrator. The
appointment of the sole arbitrator was against the
contractual conditions which cannot be ignored.
Therefore, the reference was before a Arbitral
Tribunal which had not been properly constituted.
He also submitted that the arbitrator had no
jurisdiction to entertain the claims with regard to
certain excepted matters.
On the other hand, the learned counsel for the
respondent has submitted that the appellant having
participated in the proceedings before the learned
arbitrator without any demur or objection cannot
now be permitted to raise the objection with regard
...5/-
Page 5
:5:
to the jurisdiction of the arbitrator at this
belated stage. Learned counsel further submitted
that in view of express provision contained in
Section 16 of the Arbitration Act, 1996, the
Arbitral Tribunal is competent to rule on its own
jurisdiction. He submits that pleas with regard to
lack of jurisdiction of the learned arbitrator
ought to have been raised not later than the
submission of the statement of defence. Learned
counsel pointed out that no plea of lack of
jurisdiction of the learned arbitrator was taken by
the appellant in the statement of defence.
Furthermore, the appellant also led evidence in
defence. He also pointed out that the appellant,
in fact, categorically accepted the jurisdiction of
the learned arbitrator by filing a counter claim in
the proceedings. He submits that, in such
circumstances, the appellant had clearly waived its
right to object to the constitution of the Arbitral
Tribunal. Similarly, the plea of excepted matters
was also never raised by the appellant during the
entire arbitration proceedings. All claims have
been decided on merits.
We have considered the submissions made by the
learned counsel for the parties.
...6/-
Page 6
:6:
The arbitration agreement contained in clause
64 of the General Conditions of Contract is as
under:
“64(3)(a) ARBITRATION: Matters in question, dispute or difference to be arbitrated upon shall be referred for decision to
3(a)(i) A Sole Arbitrator who shall be the General Manager or a Gazetted Railway Officer nominated by him in that behalf in cases where the claim in question is below Rs.5,00,000/- (Rupees five lakhs) and in cases where the issues involved are not of complicated nature. The General Manager shall be the sole Judge to decide whether or not the issues involved are of a complicated nature.
3(a)(ii) Two Arbitrators who shall be Gazetted Railway Officers of equal status to be appointed in the manner laid in Clause 64(3)(b) or all claims of Rs.5,00,000/- (Rupees five Lakhs) and above, and for all claims irrespective of the amount of value of such claims if the issues involved are of a complicated nature the General Manager shall be the sole Judge to decide whether the issues involved are of a complicated nature or not. In the event of the two Arbitrators being divided in their opinions the matter under disputes will be referred to an Umpire to be appointed in the manner laid down in Clause 3(b) for his decision.
3(a)(iii) It is a term of this contract that no person other than a Gazetted Railway Officer, should act as an Arbitrator/Umpire and if for any reason, that is no possible, the matter is not to be referred to Arbitration at all.
...7/-
Page 7
:7:
3(a)(iv) In cases where the claim is up to Rs.5,00,000/- (Rupees five lakh), the Arbitrator(s) compare so appointed, as the case may be, shall give the award on all matters referred to arbitration indicating therein break-up of the sums awarded separately on each individual item of disputes. In cases where the claim is more than Rs.5,00,000/- (Rupees five lakh), the Arbitrator(s)/Umpire so appointed, as the case may be, shall give intelligible award (i.e. the reasoning leading to the award should be stated) with the sums awarded separately on each individual item of dispute referred to arbitration.
3(b) For the purpose of appointing two arbitrators as referred to in sub-clause (a)(ii) above, the Railway will send a panel of more than three names of Gazetted Railway Officers of one of more departments of the Railway to the contractor who will be asked to suggest to the General Manager one name out the list for appointment as the contractor's nominee. The General Manager, while so appointment the contractor's nominee, will also appoint a second arbitrator as the Railway's nominee either from the panel or from outside the panel, ensuring that one the two arbitrators so nominated is invariably from the Accounts Department. Before entering upon the reference the two arbitrators shall nominate an Umpire who shall be a Gazetted Railway Officer to whom the case will be referred to in the event of any difference between the two arbitrators Officers of the Junior Administrative grade of the Accounts Department of the Railways shall be considered as of equal status to the Officers in the intermediate administrative grade of other departments of the Railway for the purpose of appointment as arbitrators.”
...8/-
Page 8
:8:
A persual of clause 64 would show that in case
of claims which are below Rs.5,00,000/- (Rupees
five lakh), the General Manager or a Gazetted
Railway Officer nominated by him shall be the sole
arbitrator. In case of claims of Rs.5,00,000/-
(Rupees five lakh) and above, the Arbitral Tribunal
shall consist of three arbitrators to be appointed
in terms of clause 64(3)(b). Under clause 64(3)
(b), the Railways will send a panel of more than
three names of Gazetted Railway Officers from whom
the contractor will be asked to suggest one name.
The General Manager will appoint the second
arbitrator on behalf of the Railways. The clause
also provided that two arbitrators shall nominate
an Umpire who shall be a Gazetted Railway Officer.
Since the Arbitration Act, 1940 had been
repealed by the Arbitration Act, 1996 the provision
in the arbitration agreement for appointment of two
arbitrators and an Umpire had become redundant.
Accordingly, the respondent requested the Railways
to appoint the sole arbitrator. Since the Railways
failed to appoint the arbitrator within 30 days of
...9/-
Page 9
:9:
the receipt of the letter dated 30th September,
1996, the respondent moved the application under
Section 11(6) of the Arbitration Act, 1996 for
appointment of a sole arbitrator on 3rd January,
1997 before the High Court. As noticed above, by
order dated 10th July, 1998, the High Court
appointed Mr. Justice Satyabrata Mitra as the sole
arbitrator. It is important to notice that this
order dated 10th July, 1998 was not challenged by
the appellant and, therefore, the same became final
and binding. This apart, the appellant failed to
raise any objection to the lack of jurisdiction of
the Arbitral Tribunal before the learned
arbitrator. As noticed above, the appellant not
only filed the statement of defence but also rasied
a counter claim against the respondent. Since the
appellant has not raised the objection with regard
to competence/jurisdiction of the Arbitral Tribunal
before the learned arbitrator, the same is deemed
to have been waived in view of the provisions
contained in Section 4 read with Section 16 of the
Arbitration Act, 1996.
...10/-
Page 10
:10:
Section 16 of the Arbitration Act, 1996
provides that the Arbitral Tribunal may rule on its
own jurisdiction. Section 16 clearly recognizes
the principle of kompetenz-kompetenz. Section 16(2)
mandates that a plea that the Arbitral Tribunal
does not have jurisdiction shall be raised not
later than the submission of the statement of
defence. Section 4 provides that a party who knows
that any requirement under the arbitration
agreement has not been complied with and yet
proceeds with the arbitration without stating his
objection to such non-compliance without undue
delay shall be deemed to have waived his right to
so object.
In our opinion, the High Court has correctly
come to the conclusion that the appellant having
failed to raise the plea of jurisdiction before the
Arbitral Tribunal cannot be permitted to raise for
the first time in the Court. Earlier also, this
Court had occasion to consider a similar objection
in Bharat Sanchar Nigam Limited and another versus
Motorola India Private Limited [(2009) 2 SCC 337].
Upon consideration of the provisions contained in
Section 4 of the Arbitration Act, 1996, it has been
held as follows:
...11/-
Page 11
:11:
39. Pursuant to section 4 of the Arbitration and Conciliation Act, 1996, a party which knows that a requirement under the arbitration agreement has not been complied with and still proceeds with the arbitration without raising an objection, as soon as possible, waives their right to object. The High Court had appointed an arbitrator in response to the petition filed by the appellants (sic respondent). At this point, the matter was closed unless further objections were to be raised. If further objections were to be made after this order, they should have been made prior to the first arbitration hearing. But the appellants had not raised any such objections. The appellants therefore had clearly failed to meet the stated requirement to object to arbitration without delay. As such their right to object is deemed to be waived.
In our opinion, the obligations are fully
applicable to the facts of this case. The
appellant is deemed to have waived the right to
object with regard to the lack of the jurisdiction
of the Arbitral Tribunal.
...12/-
Page 12
:12:
We, therefore, see no merit in the appeal and
the same is hereby dismissed.
No costs.
....................,J. (SURINDER SINGH NIJJAR)
....................,J. (RANJANA PRAKASH DESAI)
NEW DELHI FEBRUARY 18, 2014