UNION OF INDIA Vs M/S BRIGHT POWER PROJECTS(I) P.LTD.
Bench: ANIL R. DAVE,VIKRAMAJIT SEN,PINAKI CHANDRA GHOSE
Case number: C.A. No.-002404-002404 / 2008
Diary number: 28973 / 2007
Advocates: D. S. MAHRA Vs
AMARJIT SINGH BEDI
Page 1
1 REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 2404 OF 2008
UNION OF INDIA ... APPELLANT VERSUS
M/S. BRIGHT POWER PROJECTS (I) P.LTD. ... RESPONDENT
J U D G M E N T
ANIL R. DAVE, J.
1. Being aggrieved by the judgment delivered in
Appeal (Lodging) No.124 of 2006 in Arbitration
Petition No.321 of 2005 dated 7th August, 2006,
delivered by the High Court of Judicature at Bombay,
this appeal has been filed wherein the issue is
whether the appellant is liable to pay interest to
the respondent though there was a provision in the
contract that no interest should be paid on the
Page 2
2 amount payable to the contractor. The facts which are
relevant for the purpose of deciding the issue, in a
nutshell, are as under.
2. The appellant and the respondent had entered
into a contract whereby the respondent had to
construct certain structures, which had been more
particularly described in the agreement entered into
by the parties on 20th January, 1997.
3. In the course of execution of the contract, a
dispute had arisen between the appellant and the
respondent contractor and as agreed by the parties,
the dispute had been referred to the Arbitral
Tribunal. After hearing the concerned parties, the
Arbitral Tribunal declared an award on 17th May,
2005, whereby it also awarded interest to the
respondent contractor on the amount awarded, from the
date of the reference till the date of the award.
4. Relying upon the judgment delivered in the
case of Secretary, Irrigation Department,
Government of Orissa and Ors. v. G.C. Roy (1992) 1 SCC 508, the Arbitral Tribunal awarded interest on
the amount of the award. In the said case, this
Page 3
3 Court had considered the provisions of
Section 29 of the Arbitration Act, 1940, which
dealt with payment of interest pendente lite.
After analyzing the scheme of the said Act, various
earlier decisions and after considering the very
same issue, namely, whether an arbitrator has power
to award interest pendente lite and, if so, on what
principles, this Court had observed that the
Arbitral Tribunal had power to award interest.
5. Being aggrieved by the Award and especially
because of interest being awarded by the Arbitral
Tribunal, the appellant filed Arbitration Petition
No.321 of 2005 in the High Court of Judicature at
Bombay. The said arbitration petition was dismissed
on 13th December, 2005.
6. Being aggrieved by the dismissal of the
Arbitration Petition, the appellant filed an appeal
which was also dismissed by the Division Bench of the
High Court of Judicature at Bombay on 7th August,
2006. Judgment of a Division Bench of the High Court
of Judicature at Bombay dated 2nd July, 1997,
delivered in the case of Union of India v. Anand
Page 4
4 Builders was relied upon and except for stating the
above reason, no other reason was recorded by the
High Court while dismissing the appeal.
7. According to the learned counsel appearing for
the appellant, it was not open to the Arbitral
Tribunal to award any interest to the contractor in
view of a specific condition incorporated in the
contract entered into between the parties that no
interest would be paid to the contractor.
8. On the other hand, the learned counsel
appearing for the respondent contractor submitted
that the Division Bench of the High Court had
rightly upheld the order passed by the learned
Single Judge as well as the Arbitral Tribunal.
9. On the aforesaid contentions, this Court has
to decide whether the contract between the parties
contained an express bar regarding award of
interest and if so, whether the Arbitral Tribunal
was justified in awarding interest for the period
Page 5
5 commencing from the date of reference till the date
of the award.
10. Clause 13 (3) of the contract entered into
between the parties reads as under:
“13(3). No interest will be payable upon the earnest money and the security deposit or amounts payable to the contractor under the contract, but Government Securities deposited in terms of sub-clause(1) of this clause will be repayable with interest accrued thereon.”
11. Thus, it had been specifically understood
between the parties that no interest was to be paid
on the earnest money, security deposit and the amount
payable to the contractor under the contract. So far
as payment of interest on Government Securities,
which had been deposited by the respondent contractor
with the appellant is concerned, it was specifically
stated that the said amount was to be returned to the
contractor along with interest accrued thereon, but
so far as payment of interest on the amount payable
to the contractor under the contract was concerned,
Page 6
6 there was a specific term that no interest was to be
paid thereon.
12. When parties to the contract had agreed to the
fact that interest would not be awarded on the amount
payable to the contractor under the contract, in our
opinion, they were bound by their understanding.
Having once agreed that the contractor would not
claim any interest on the amount to be paid under the
contract, he could not have claimed interest either
before a civil court or before an Arbitral Tribunal.
13. Section 31(7) of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as
‘the Act’) is clear to the effect that unless
otherwise agreed by the parties, the Arbitral
Tribunal can award interest at reasonable rate for a
period commencing from that date when the cause of
action arises till the date of the award. Section
31(7) of the Act, reads as under:
“31(7) (a) Unless otherwise agreed by the parties, where and in so far as an arbitral award is for the payment of money, the Arbitral Tribunal may include in the sum
Page 7
7 for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made.”
14. Section 31(7) of the Act, by using the
words "unless otherwise agreed by the parties",
categorically specifies that the arbitrator is bound
by the terms of the contract so far as award of
interest from the date of cause of action to date of
the award is concerned. Therefore, where the parties
had agreed that no interest shall be payable, the
Arbitral Tribunal cannot award interest.
15. We may also refer to the decision of this Court
in Union of India v. Saraswat Trading Agency and
others (2009)16 SCC 504. This Court has observed in
the said case that if there is a bar against payment
of interest in the contract, the arbitrator cannot
award any interest for such period. In view of the
specific bar under Clause 13(3) of the contract
entered into between the parties, we are of the view
that the Arbitral Tribunal was not justified in
Page 8
8 awarding interest from the date of entering upon the
reference to the Arbitral Tribunal till the date of
the award.
16. The Arbitral Tribunal had mainly relied upon
the judgment delivered by this Court in G C Roy ’s case (supra). In the said case, the situation was different. The contract between the parties did not
contain any condition that interest would not be
paid. In para 44 of the said judgment, it has been
observed as under :
“44.Having regard to the above consideration, we think that the following is the correct principle which should be followed in this behalf: Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendente lite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes – or refer the dispute as to interest as such – to the arbitrator, he shall have the power to award interest. This does not mean that in
Page 9
9 every case the arbitrator should necessarily award interest pendente lite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.”
17. Relying upon the aforestated judgment
delivered by this Court, the Arbitral Tribunal
thought it proper to award interest on the amount
payable to the contractor for the period commencing
from the date on which the reference was entered
upon till the date of the award. The Tribunal,
however, failed to consider the provisions of
Section 31(7) of the Act and clause 13(3) of the
contract before awarding interest in the present
case.
18. It is also pertinent to note that G.C. Roy’s
case (supra) had been decided on December 12, 1991
on the basis of the provisions of the Arbitration
Act, 1940, which was not operative at the time when
the dispute on hand was decided by the Arbitral
Tribunal.
Page 10
10 19. Section 31(7)(a) of the Act ought to have been
read and interpreted by the Arbitral Tribunal
before taking any decision with regard to awarding
interest. The said Section, which has been
reproduced hereinabove, gives more respect to the
agreement entered into between the parties. If the
parties to the agreement agree not to pay interest
to each other, the Arbitral Tribunal has no right
to award interest pendente lite.
20. By relying upon the judgments which pertained
to different period when statutory provisions were
different, the Arbitral Tribunal had awarded
interest on the amount payable to the contractor
for the period from the date when the reference was
entered upon till the date of the award and the
said view of the Arbitral Tribunal had been
confirmed by the High Court. In our opinion, the
Arbitral Tribunal and the High Court ought to have
considered the provisions of the Act and the terms
of agreement entered upon by the parties.
Page 11
11 21. In the aforestated circumstances, the Arbitral
Tribunal ought not to have awarded interest to the
respondent from the date of reference till the date
of the award.
22. For the aforestated reasons, we set aside the
impugned judgment and the award so far as it pertains
to payment of interest pendente lite and direct that
no interest would be paid on the amount payable under
the contract to the respondent from the date of the
reference till the date of the award.
23. The appeal is allowed with no order as to
costs.
…………………………………………………….J (ANIL R. DAVE)
…………………………………………………….J (VIKRAMAJIT SEN)
…………………………………………………….J (PINAKI CHANDRA GHOSE)
NEW DELHI; JULY 2, 2015.