U.P.POWER CORPORATION LTD. Vs N.T.P.C.LTD.
Bench: T.S. THAKUR,VIKRAMAJIT SEN
Case number: C.A. No.-004117-004117 / 2006
Diary number: 23076 / 2006
Advocates: PRADEEP MISRA Vs
K. V. MOHAN
Page 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.4117 OF 2006
U.P. Power Corporation Ltd. …
Appellant
Versus
N.T.P.C. Ltd. & Ors. …Respondents
WITH CIVIL APPEAL NOS.5361-5362 OF 2007
J U D G M E N T
T.S. THAKUR, J.
1. This appeal under Section 125 of the Electricity Act,
2003 calls in question the correctness of a Judgment and
Order dated 7th July, 2006 passed by the Appellate Tribunal
1
Page 2
for Electricity whereby the Tribunal has while partially
modifying the Order passed by the Central Electricity
Regulatory Commission (‘CERC’ for short) dismissed Appeal
No.36 of 2006 filed by the appellant.
2. The CERC had by the Order impugned before the
Tribunal allowed Petition No.139 of 2004 filed by the
respondent-Corporation and permitted capitalisation of
Rs.4.521 crores over the approved cost for the completion of
Feroz Gandhi Unchahar Thermal Power Station Stage-I for
the period 1st April, 2001 to 31st March, 2004. While doing
so the CERC had in Para 37 of its Order held respondent
No.1 entitled to return on equity and interest on loan on the
said amount payable along with the tariff for the period
2004-2009. What is significant is that both the CERC and
the Appellate Tribunal rejected the contention urged on
behalf of the appellant-Corporation that the additional
capital expenditure incurred by the respondent-Corporation
could not be taken into consideration for tariff fixation
without the same having been approved by the Central
Electricity Authority (“CEA” for short) as required under
2
Page 3
Regulation 2.5 of the CERC (Terms and Conditions for
Determination of Tariff) Regulations, 2001. The primary
question that therefore falls for consideration in this appeal
is whether the CERC and the Tribunal have correctly
interpreted Regulation 2.5 of the said regulations while
permitting capitalisation of the additional expenditure for
purposes of determining the tariff. That question arises in
the following factual backdrop:
3. Feroz Gandhi Unchahar Thermal Power Station Stage-I
was taken over by the respondent-National Thermal Power
Corporation from the erstwhile U.P. State Electricity Board
on 13th February, 1992. The Central Government had
approved the takeover cost of Rs.925 crores in terms of a
communication dated 2nd May, 1993 issued by the Ministry
of Power. By a subsequent letter dated 5th August, 1996 the
CEA accorded approval for an additional Rs.2.85 crores for
R&M under Environment Action Plan, thereby taking the total
approved project cost to Rs.927.85 crores.
4. The CERC (Terms & Conditions for Determination of
Tariff) Regulations, 2001 for the period 1st April, 2001 to 31st
3
Page 4
March, 2004 came to be notified on 26th March, 2001,
pursuant whereto the respondent-Corporation filed Petition
No.41 of 2001 for approval of tariff for the relevant tariff
period in respect of the generating plant in question. By an
Order dated 24th October, 2003, the CERC approved the
tariff taking into consideration the capital cost at Rs.940.70
crores as on 1st April, 2001 but did not consider the
additional capitalisation claimed by the respondent since the
latter was based only on an estimated capital expenditure
and was unsupported by an auditor’s certificate.
Respondent-Corporation then moved petition No.139 of
2004 before the CERC on 5th October, 2004 seeking approval
of the revised fixed charges in respect of the generating
plant for the relevant tariff period taking into account the
additional capital expenditure incurred during the said period
which was estimated at Rs.6.101 crores. By an order dated
31st March, 2005, the CERC disposed of the said petition
approving an amount of Rs.4.521 crores towards capital
expenditure while disallowing the rest.
4
Page 5
5. The CERC held that the respondent would not be
entitled to tariff revision during the relevant period in the
light of Regulation 1.10 of the CERC Regulations which
prohibited allowance of an additional capital expenditure, if
such expenditure happened to be less than 20 per cent of
the approved project cost. It all the same held in Para 37 of
its Order that the respondent was entitled to relief in the
form of return on equity at the rate of 16% and interest on
loan on the approved additional capital expenditure for the
period 2004-2009. The CERC observed :
“37. As there is nothing in the notification dated 26.3.2001 to deny the petitioner the reasonable return to service the capital expenditure incurred by the petitioner and found to be justified by us, we direct that the petitioner shall earn return on equity @ 16% on the equity portion of the additional capitalization approved by us. Similarly, the petitioner shall also be entitled to the interest on loan as applicable during the relevant period. Return on equity and interest shall be worked out on the additional capitalization of Rs.4.521 crore approved by us from 1st April of the financial year following the financial year to which additional capital expenditure relates up to 31.3.2004. The lump sum of the amount of return on equity and interest on loan so arrived at shall be payable by the respondents along with the tariff for the period 2004-09 to be approved by the Commission. The exact entitlement of the petitioner on this account shall be considered by the Commission while approving tariff for the period 2004-09.”
5
Page 6
6. Aggrieved by the order passed by the CERC the
appellant-Corporation approached the Appellate Tribunal for
Electricity in Appeal No.36 of 2006. The appellant thereby
questioned the CERC’s authority to approve the additional
capital expenditure of Rs.4.521 crores as also the power to
award relief in the nature specified in para 37 supra. It was
contended on behalf of the Corporation that in the absence
of approval of the expenditure by CEA as required under
Regulation 2.5 of the CERC Regulations, the CERC had no
authority to hold that the respondent-NTPC was entitled to
additional capitalisation. The Appellate Tribunal for
Electricity, however, repelled that contention and dismissed
the appeal filed by the appellant on the ground that CERC’s
approval of additional capitalisation to the tune of Rs.4.521
crores did not call for any interference and that the
respondent-Corporation had placed sufficient material before
the CERC to substantiate its claim. The Tribunal declared
that the CERC was empowered to undertake a prudent check
and approve additional capitalisation after the deletion of
Section 43-A(2) of the Electricity (Supply) Act, 1948
because of which deletion CEA ceased to have any role in
6
Page 7
such matters. The Tribunal further held that the project had
been originally approved by CEA as far back as on 5th
August, 1986 and was taken over while still incomplete by
the respondent-NTPC in 1992. The incomplete items were
then completed by the respondent NTPC after the takeover
which required investment of additional capital. The
Tribunal was, therefore, of the view that the additional
capital was well within the approved cost of the project
which remained unexecuted on the date of vesting. The
Appellate Tribunal, however, accepted the appellant’s
contention that the relief regarding the return on equity and
interest on loan could not be granted until the next tariff
period. Consequently the Tribunal directed deletion of Para
37 of the CERC’s order giving liberty to the CERC to take the
said relief into consideration while determining the tariff for
the next period. The present appeal assails the correctness
of the view taken by the CERC and the Appellate Tribunal.
7. When this appeal came up for admission on 29th
September, 2006, this Court admitted the same only to
examine the following two questions:
7
Page 8
“a. What is the true scope and ambit of Regulation 2.5 of CERC (Terms and Conditions for Determination of Tariff) Regulations, 2001?
b. xxxxxxx
c. xxxxxxx
d. Whether the CERC could have allowed the additional capitalization which was not approved by the concerned authority i.e. Central Electricity Authority?
e. xxxxxxx”
8. Appearing for the appellant Mr. Pradeep Misra
strenuously contended that the CERC and so also the
Appellate Tribunal had failed to correctly interpret Regulation
2.5 of the Regulations in question. He submitted that
Regulation 2.5 of the Regulations was much too clear to
admit of any equivocation. A plain reading of the Regulation,
argued Mr. Misra, left no manner of doubt that any
additional capital expenditure incurred on the completion of
the project could be taken into consideration for fixation of
tariff only if such excess was allowed by the CEA or an
appropriate independent agency constituted under the said
Regulations. So long as the capital expenditure incurred in
excess of the approved expenditure did not have the
sanction of the CEA or the independent agency nominated
8
Page 9
by the CERC, the same could not, according to the learned
Counsel, constitute a valid input for fixing the tariff. No
such approval having been sought or granted either by the
CEA or any independent agency in this case, the CERC could
not have taken the additional capital expenditure into
consideration for purposes of fixing the tariff. It was also
contended that the CERC as also the Appellate Tribunal had
fallen in error in holding that deletion of Section 43A(2) of
the Electricity (Supply) Act, 1948 made a reference to the
CEA in terms of Regulation 2.5 of the Regulations
unnecessary. The deletion of Section 43A(2)
notwithstanding, the CEA continued to exercise powers in
terms of Sections 28 to 32 of the Act. The statutory
requirement of an approval from the CEA of the additional
cost had not, therefore, been rendered a surplusage by
reason of the removal of Section 43A(2) from the statute
book.
9. On behalf of the respondent it was contended by Mr.
Ramachandran that the CERC as also the Tribunal were
perfectly justified in taking into consideration the additional
9
Page 10
expenditure incurred on the completion of the project, not
only because there was no dispute that such an expenditure
had in fact been incurred but also because the said
expenditure was found to be capital in nature. The question
of an approval from the CEA or the independent agency was,
therefore, rendered academic in the facts and circumstances
of the case.
10. It was further argued that since the appellant itself
accepted the expenditure to have been incurred and the
nature of the expenditure having been found to be capital in
character, the CEA or the independent agency could not
have, even if a reference was made, declined approval to
the same. It was also argued that the deletion of Section
43A(2) of the Electricity (Supply) Act, 1948 from the statute
book made a material difference and that the CERC and the
Tribunal had correctly held that a reference to the CEA or
independent agency was on that count unnecessary.
11. Regulation 2.5 of the Regulations reads as under:
“2.5 Capital Expenditure
The capital expenditure of the project shall be financed as per the approved financial package set
10
Page 11
out in the techno-economic clearance of the Authority or as approved by an appropriate independent agency as the case may be. The project cost shall include reasonable amount of capitalized initial spares.
The actual capital expenditure incurred on completion of the project shall form the basis for fixation of tariff. Where the actual expenditure exceeds the approved project cost, the excess expenditure as allowed by the Authority or an appropriate independent agency shall be considered for the purpose of fixation of tariff.
Provided that such excess expenditure is not attributable to the Generating Company or its suppliers or contractors;
Provided further that where a Power Purchase Agreement entered into between the Generating Company and the beneficiary provides a ceiling on capital expenditure, the capital expenditure shall not exceed such ceiling for computation of tariff.”
12. The term “independent agency” referred to in the
above Regulation is defined in regulation 1.9 as under:
“1.9 ‘Independent agency’ means the agency approved by the Commission by a separate notification.”
13. A plain reading of the above makes it manifest that the
basis for fixation has to be the “actual capital expenditure”
incurred on the completion of the project. But where the
actual expenditure exceeds the approved expenditure the
excess so incurred can be taken into consideration to the
extent the same is allowed by the Central Electricity
11
Page 12
Authority or an appropriate independent agency nominated
for the purpose. This implies that the excess expenditure
must go through a process of scrutiny either by the CEA or
the independent agency before it can constitute an input for
determination of the tariff. Scrutiny of the excess would in
turn primarily involve examination of two distinct aspects
viz.
(a) Whether the excess expenditure has been actually
incurred or is a make believe or an exaggeration
by the generating company; and
(b) Whether the expenditure was capital in nature.
14. In cases where the answers to these two questions is in
the affirmative, the CEA or the Independent Agency would
have no reason to disallow such expenditure, nor would its
consideration for tariff fixation present any difficulty. In
case a lesser amount is allowed by the CEA or the
Independent Agency either because the generating company
fails to substantiate its claim of having incurred the
expenditure as claimed or even if the amount is incurred,
only a part of the same was in the nature of capital
12
Page 13
expenditure, the lesser amount alone will constitute an input
for tariff determination. To that extent, there is no difficulty
nor was Mr. Misra, Counsel for the appellant, able to suggest
any other dimension which the CEA or the Independent
Agency would be entitled to consider while examining the
question of allowing or disallowing the excess expenditure
incurred by the generating unit. If that be so, absence of a
reference under Regulation 2.5 (supra) to the CEA or
Independent Agency would make little or no difference
having regard to the facts of the case at hand. We say so
because although the respondent-Corporation had claimed
an excess expenditure of Rs.6.101 crores the amount
actually taken into consideration for fixation of the tariff was
Rs.4.521 crores only. The CERC had on a prudent check
disallowed a substantial part of the excess that was claimed
by the respondent-Corporation. What is significant is that
the appellant-Corporation had fairly conceded that an
amount of Rs.4.521 crores was indeed spent by the
respondent for the completion of the project. That is
evident from the following observation of the Electricity
Appellate Tribunal, where Mr. Misra learned counsel for the
13
Page 14
appellant made a candid admission as to the extent of the
expenditure incurred over and above the approved Project
cost:
“Mr. Pradeep Misra, learned counsel for the appellant, while relying on Regulation 1.10 which provides that there shall be no tariff revision if the capital expenditure is less than 20% of the approved cost of the project contended that there could be no tariff revision at all much less the appellant shall be made liable to pay 16% ROE as well as interest as directed in Para 37 of the Impugned Order under challenge. Mr. Pradeep Misra also contended that the claim of this additional expenditure, under five Heads, are not disputed but they are only maintenance expenditure. It was also contended by the learned counsel that in the absence of approval of expenditure by CEA and there being no proof of such approval, CERC has no authority to hold that NTPC had incurred additional capital expenditure and entitled to additional capitalisation.” (emphasis supplied)
15. From the above, we have no difficulty in holding that
the first of the two aspects that may have engaged the
attention of the CEA or the Independent Agency was
concluded by the admission of the appellant, which was the
best evidence, in the matter apart from the fact that the
figure arrived at by the Commission was based on a fair and
prudent check of the extent of admissible expenditure said
to have been incurred.
14
Page 15
16. That leaves us with the second aspect which, any
scrutiny or examination by the CEA may have involved viz.
whether the expenditure was capital or revenue in nature.
The CERC has found the expenditure to be capital in nature
which finding has been affirmed by the Appellate Tribunal.
There is nothing perverse about that finding in our opinion
nor has this appeal been admitted on the question whether
the expenditure was capital or revenue. In the absence of
any question relating to the nature of the expenditure, we
find it difficult to appreciate how the absence of a reference
to CEA has caused any miscarriage of justice for the
appellant or vitiated the tariff fixation by the CERC. It
follows that even if a reference to CEA was in the facts of
the case required to be made, the absence of any failure of
justice or prejudice would render it unnecessary for us to
interfere with the orders passed by the CERC and the
Appellate Tribunal.
17. Since the question whether or not a reference to CEA
was necessary under Regulation 2.5 was argued before us at
some length we may as well deal with the same before
parting. A reference to the backdrop in which the question
15
Page 16
arises becomes necessary and may be summarised as
under:
18. The Electricity (Supply) Act, 1948 inter alia dealt with
the generation and supply of electricity by generating
companies. Chapter V comprising Sections 28 to 58 of the
said Act dealt with the preparation of schemes by generating
companies and concurrence of the CEA for such schemes
including the capital cost to be incurred by these generating
companies. Section 43A of the Act dealt with sale of
electricity by the generating companies and provided norms
and parameters to be determined by the CEA and notified by
the Government of India. Since much of the debate at the
Bar was around the said provision and the effect of deletion
of sub-section (2) thereof, it would be useful to reproduce
the same at this stage.
“43A. Terms, conditions and tariff for sale of electricity by Generating Company.- (1) A Generating Company may enter into a contract for the sale of electricity generated by it-
(a) with the Board constituted for the State or any of the States in which a generating station owned or operated by the company is located;
(b) with the Board constituted for any other State in which it is carrying on its activities in
16
Page 17
pursuance of sub-section (3) of section 15A; and
(c) with any other person with consent of the competent government or governments.
(2) The tariff for the sale of electricity by a Generating Company to the Board shall be determined in accordance with the norms regarding operation and the Plant Load Factor as may be laid down by the Authority and in accordance with the rates of depreciation and reasonable return and such other factors as may be determined, from time to time, by the Central Government, by notification in the Official Gazette:
Provided that the terms, conditions and tariff for such sale shall, in respect of a Generating Company wholly or partly owned by the Central Government, be such as may be determined by the Central Government and in respect of a Generating Company wholly or partly owned by one or more State Governments be such as may be determined, from time to time, by the government or governments concerned.”
19. In the year 1998, came the Electricity Regulatory
Commissions Act, 1998, which established the Central
Electricity Regulatory Commission (hereinafter referred to as
“the Central Commission”). The Central Commission was
inter alia charged with the function of determining tariffs of
Central Units such as those owned and controlled by the
respondent-Corporation. Significantly enough Section 51 of
this Act empowered the Central Government to delete sub-
section (2) of Section 43A with effect from such date as the
17
Page 18
Central Government may decide. The Central Government,
invoked that power and by a notification dated 11th
September, 2000, directed the deletion of Section 43A (2) of
the Electricity Supply Act, 1948 in respect of generating
companies regulated by the Central Commission
retrospectively w.e.f. 24th July, 1998. Shortly thereafter the
Central Commission issued an order in regard to operational
norms applicable to generating stations owned among
others by respondent-NTPC. The order was to the following
effect:
“As regards capital costs, the situation is somewhat difficult. As the law stands today in respect to PSUs, the required approvals from the Government and clearance from CEA have to be obtained before the commencement of the project, subject to certain limits for which no clearance is required. After the completion of the project, if the actual expenditure or the scope of the project vary beyond certain limits, they are required to be further approved. This process of approval is time consuming, resulting in a provisional clearance, making a subsequent retrospective revision inevitable. Changes in legislation are being contemplated by which the clearance from CEA for projects might be done away with. However, as the law stands today, approvals are inevitable. Still it is possible to bring about stability in tariff in case a time schedule is worked out by which utilities may submit data of CEA at least 6 months prior to the completion of a project, so that clearance could be obtained sufficiently in time before the tariff for the station/lines is determined. It is hoped that any variations on actual finalization of accounts thereafter should be minor in nature which could be absorbed by the
18
Page 19
utility and if substantial, can be taken care of in the next revision. In view of the above, all utilities seeking determination of tariff in respect of new projects, shall submit their applications to us at least 3 months in advance of the anticipated date of completion, along with the project cost as approved by the appropriate independent authorities, other than the Board of Directors of the Company. This project cost will constitute the basis for tariff fixation, and no revision would be entertained till the next tariff period. This direction presupposes that CEA may hereafter, unlike the past, clear capital cost escalations on factors other than the change in scope as well. We would urge upon CEA to consider and deal with the approval of additional capital costs other than those due to change in the scope of the project as well, in the interest of avoidance of tariff shocks down stream. In case the projects exempted from CEA clearance, the Commission would consider accepting a due diligence clearance from any recognised agency.”
20. The above was followed by the Central Commission
framing Tariff Regulations 2001, in which Regulation 2.5
extracted earlier dealt with capital expenditure. It was in
the above background that the Central Commission
determined the Tariff for the generating unit in question for
the period 1st April, 1997 to 31st March, 2001 by an order
dated 30th October, 2002. Shortly after that order the
Parliament enacted the Electricity Act, 2003 which came into
force w.e.f. 10th June, 2003. The new legislation repealed
the Electricity (Supply) Act, 1948. The effect of this repeal
19
Page 20
was that all provisions of the 1948 Act including those
requiring approval by the CEA of the scheme of the
generating stations and capital cost which the repealed Act
provided for became inapplicable and irrelevant under the
new Act. The new law aimed at deregulating electricity
generation. In the case of Thermal Power Stations the
capital cost was not required to be approved by the CEA, as
was the position under the earlier law.
21. In Petition No.139 of 2004, the respondent-Corporation
sought additional capitalisation of the expenditure on the
project in question relevant to the period 2001-2004. The
Central Commission determined the additional capitalisation
and allowed the same to the respondent, which
determination was upheld by the Tribunal with the
modification to which we have adverted in the beginning of
this order.
22. There is no gainsaying that the prayer for additional
capitalisation was made by the respondent-Corporation and
considered by CERC after the Electricity Act 2003 had come
into force, repealing the earlier enactments. The new
legislation did not set out any role for the CEA, in the matter
20
Page 21
of approval of the schemes for the generating companies or
the capital expenditure for the completion of such projects.
The entire exercise touching the regulation of the tariff of
generating companies owned or controlled by the Central
Government, like the respondent was entrusted to the
Central Commission. The role of the Central Electricity
Authority established under Section 7 of the 2003 Act, was
limited to matters enumerated under Section 73 of the Act,
approval of the scheme for generating companies or the
capital expenditure for the completion of such projects or
capitalisation of the additional expenditure not being one
such function. The CERC was, therefore, right when it said
that the Central Electricity Authority had no part to play in
the matter of approval for purposes of capitalisation of the
extra expenditure incurred on a project. That was so
notwithstanding the continuance of Regulation 2.5 of the
regulations framed by the CERC providing for such an
approval by the CEA. The far reaching changes that came
about in the legal framework with the enactment of the
2003 Act, made Regulation 2.5 redundant in so far as the
same envisaged a reference to the CEA or an Independent
21
Page 22
Agency for approval of the additional capitalisation.
Insistence on a reference, to the CEA for such approval,
despite the sea change in the legal framework would have
been both unnecessary as well as opposed to the spirit of
new law that reduced the role of CEA to what was specified
in Section 73 of the Act. The CERC and the Tribunal were in
that view justified in holding that a reference to the CEA was
not indicated nor did the absence of such a reference
denude the CERC of its authority to fix the tariff after the
2003 Act had come into force. That was so notwithstanding
the fact that proviso to Section 61 of the Electricity Act,
2003 continued the terms and conditions for determination
of tariff under the enactments mentioned therein and those
specified in the Schedule for a period of one year or till such
terms were specified under that section whichever was
earlier. In the result this appeal fails and is hereby dismissed
with costs assessed at Rs.50,000/-
Civil Appeal Nos.5361-5362 of 2007
22
Page 23
23. In these appeals the order impugned by the appellant
places reliance upon the order passed by the Tribunal, in
Appeal No.36 of 2006 against which order we have in the
foregoing part of this judgment dismissed the appeal
preferred by the appellant. On a parity of reasoning these
appeals are also destined to be dismissed and are,
accordingly, dismissed with costs assessed at Rs.50,000/-.
………………….……….…..…J. (T.S. THAKUR)
.……..…………………..…..…J. (VIKRAMAJIT SEN)
New Delhi September 18, 2013
23