THE MADURAI CORPORATION Vs P. KAYALVIZHI & ANR.
Bench: T.S. THAKUR,A.M. KHANWILKAR
Case number: C.A. No.-010425-010425 / 2014
Diary number: 14488 / 2014
Advocates: ANIL KUMAR MISHRA-I Vs
Page 1
1
Non-reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.10425 OF 2014
The Madurai Corporation ...Appellant.
Versus
P. Kayalvizhi & Anr. …Respondents.
JUDGMENT
A. M. KHANWILKAR, J.
Application for early hearing is allowed.
2. The respondent no.1 had filed a writ petition under Article 226
of the Constitution of India bearing Writ Petition (MD) No.9854 of
2012, which was allowed by the learned Single Judge on the
following terms:
“6. In view of the above, this Court is of the view that since the petitioner is not inclined to put up further construction, there is no need for the petitioner to get permission from the Local Planning Authority. Under such circumstances, recording the undertaking given by the petitioner, this Court is inclined to give a direction to the respondents to grant renewal of permission for the construction, so that the petitioner can complete the building work which was already constructed. The affidavit of undertaking given by the petitioner is placed on record. The respondents are directed to grant renewal of permission so that the petitioner can finish the building which was already constructed by her, within a period of two weeks from the date of receipt of a copy of this order.
7. Accordingly, the writ petition is disposed of No costs.”
Page 2
2
The appellant - Corporation filed a Writ Appeal being Writ
Appeal (MD) No.763 of 2013. That was dismissed by the Division
Bench vide order dated 21.8.2013. These decisions are the subject
matter of the present appeal filed by the Corporation.
3. The principal issue considered by the learned Single Judge of
the High Court was whether the appellant was the Competent
Authority to grant an extension of time to the respondent no.1 for
completing the construction of the building, which was commenced
on the basis of a sanction given by the Local Planning Authority,
Madurai on 25.04.2009. The sanction given by the said Authority
was attached with a condition that the construction of the proposed
building upto 11 floors, should be completed by the respondent
no.1 within two years therefrom. The respondent no.1 within such
period could construct only upto 6 floors. As the respondent no.1
was unable to comply with the condition of completing the
construction as per the sanctioned plan within two years, he
submitted an application on 11.04.2011 to the appellant -
Corporation for an extension of time. The respondent no.1 was
called upon to submit an application in Form 8, which requirement
Page 3
3
was compiled by him. The appellant, however, affixed a notice on
the construction site purported to be under Sections 282, 296(1)
and 296(2) of the Madurai City Municipal Corporation Act, pointing
out that the respondent no.1 had deviated from the original plan in
respect of (a) lift (b) stair case to the building and (c) instead of a
swimming pool open to the sky, a hall was constructed on the first
floor of the building under construction. Based on the said
proceedings, the Corporation rejected the application submitted by
respondent no.1 for extension of time to complete the construction,
vide order dated 21.06.2012. The respondent no.1 challenged that
order by way of writ petition. During pendency of the said writ
petition, the respondent no.1 filed an affidavit cum undertaking
assuring the Authority that he would complete the construction of
the building only up to Ground floor + 6 floors + (1 light roofing
ceiling) and would take corrective steps to remedy the deviations
pointed out in the notice affixed on the construction site. The
appellant, however, contended that it was not the Competent
Authority to grant extension of time as the sanction was originally
granted by the Authority under the Town and Country Planning
Act. This contention did not find favour with the learned Single
Page 4
4
Judge. As a result, the learned Single Judge allowed the writ
petition filed by respondent no.1 in terms of order dated
21.08.2013. The operative part of the said order has been
reproduced in paragraph 2 above. For the same reason, the Division
Bench of the High Court declined to interfere in the writ appeal filed
by the appellant.
4. The respondent no.1 in the present appeal has reiterated the
plea taken before the High Court that he would not carry on any
further construction beyond Ground Floor + 6 floors. The
respondent no.1 also asserts that the construction of the building
upto 6 floors has been substantially completed. Further, the
building can be put to use if the Corporation was to favourably
consider his application for extension of time to complete such
construction. It is contended that on grant of extension, the
construction will be completed upto 6 floors in all respects
including by curing the deviations within the extended time, in
conformity with the original sanction given by the Town Planning
Authority in that behalf. In other words, the respondent no.1 was
not interested in carrying on with construction of additional floors,
Page 5
5
though sanctioned by the Local Planning Authority of Madurai. In
this backdrop, the appellant was called upon to give its response.
The Corporation has now taken an informed stand that it will
consider the request of the respondent no.1 for grant of extension of
time to complete the stated construction of the building as per the
Rules and provisions as may be applicable. This stand of the
Corporation has been communicated in writing to the counsel
appearing for the Corporation before this Court.
5. The respondent no.1 through counsel submits that the
respondent no.1 will abide by the undertaking already given by him
before the High Court and also such terms and conditions as may
be specified by the Corporation. That assurance is accepted.
6. In view of the above, it is unnecessary for us to examine the
wider question involved in the present appeal. This appeal,
therefore, can be disposed of in the following terms:
(1) The respondent no.1 shall forthwith submit a
formal application in writing addressed to the competent
Authority of the appellant Corporation reiterating the
assurance given in the undertaking filed before the High
Court; and also to abide by such terms and conditions as
Page 6
6
may be imposed by the Corporation in lieu of acceptance
of the proposal for extension of time to complete the
construction in conformity with the original plan
sanctioned by the Local Planning Authority upto ground
floor + 6 floors. The respondent no.1 must also assure
the Corporation that he will take corrective measures to
remedy the deviations mentioned in the notice dated
16.05.2012 given by the Corporation and also any other
or further deviations noticed or indicated by the
Corporation within the time specified in that behalf.
(2) On receipt of such written request cum
commitment from the respondent no.1, the competent
Authority of the Corporation may examine the proposal
and after conducting a survey of the building, record its
satisfaction that the construction completed by the
respondent no.1 is in conformity with the original
sanction granted by the Local Planning Authority on
25.04.2009 in respect of ground floor + 6 floors + (1 light
roofing ceiling) and also conforms to the applicable Rules
and provisions. If the Authority is satisfied in that behalf,
may pass an appropriate order including to specify
additional terms and conditions to be fulfilled by the
respondent no.1 as a condition precedent for grant of
extension of time to complete the construction. That
decision be taken within 8 weeks from the receipt of the
written request from the respondent no.1.
Page 7
7
(3) Only after a formal order is passed by the
competent Authority of the Corporation to grant
extension of time to complete the construction and
thereafter issuance of a completion certificate upon
removing all the deviations, respondent no.1 will be free
to effectively use and occupy the building for the purpose
for which it has been allowed by the Local Planning
Authority.
7. We once again reiterate that all other questions raised in this
appeal by the appellant Corporation are left open, to be considered
if and when necessary.
8. Accordingly, this appeal is disposed of in the above terms with
no order as to cost.
…………………………..CJI (T.S.Thakur)
…………………………….J. (A.M.Khanwilkar)
New Delhi, Dated: 7th October, 2016