21 February 2014
Supreme Court
Download

THE M.D.,CHENNAI METRO RAIL LTD Vs N. ISMAIL

Bench: A.K. PATNAIK,FAKKIR MOHAMED IBRAHIM KALIFULLA
Case number: C.A. No.-002572-002573 / 2014
Diary number: 22140 / 2013
Advocates: SENTHIL JAGADEESAN Vs


1

Page 1

Reportable IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS.  2572-2573 OF 2014 (@ SLP (C) NOS.26020-26021 OF 2013)

The M.D., Chennai Metro Rail Ltd. …Appellant VERSUS

N. Ismail & Ors. …Respondents With

CIVIL APPEAL NOS.  2575-2578 OF 2014 (@ SLP (C) NOS.26199-26202 OF 2013)

J U D G M E N T

Fakkir Mohamed Ibrahim Kalifulla, J.

1. I.A.  Nos.1-2  &  I.A.  Nos.1-4,  applications  for  impleadment,  

filed in Special Leave Petition (C) Nos.26020-26021 of 2013  

and Special Leave Petition (C) Nos.26199-26202 of 2013, are  

allowed. Registry to carry out necessary amendment.

  

2. Leave granted.

3. These appeals have been filed by the State of Tamil Nadu  

represented by the Managing Director of Chennai Metro Rail  

Ltd. and the Principal Secretary to Government Revenue LD-

1(1)  Department.  The  issue  concerned  in  these  appeals  

relates to an extent of 5 Grounds and 275 sq.ft. of land in  

T.S. No.43/2 in Chennai District, Fort Tondiarpet Taluk, Block  CIVIL APPEAL NOS.               OF 2014 1 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

2

Page 2

No.7  of  Vepery  Village.  The  abovesaid  land  along  with  

another  land in  an extent  of  one Cawni  10 Grounds and  

1871 sq.ft. in T.S. No.41 of the same Vepery Village, Fort  

Tondiarpet  Taluk,  Chennai  District  was  granted  by  the  

Government of Tamil Nadu to one Sir Ramaswamy Mudaliar  

to build a Choultry for the use of persons who come by rail  

from  different  parts  of  the  presidency  and  who  have  no  

homes  or  friends  in  Madras.  The  Government  while  

assigning  the  above  lands  to  Sir  Ramaswamy  Mudaliar  

imposed certain conditions to the effect that the Choultry  

should be available for the free use of railway travelers, that  

the  buildings  constructed  should  be  approved  by  the  

Government and more importantly, “that the land shall be  

liable to resumption, without compensation, if it ceases to  

be employed for the purpose for which it  is granted or is  

used for any other purposes, without the permission of the  

Government”.   

4. The said lands were granted and assigned in favour of Sir  

Ramaswamy Mudaliar  by GO Ms.  Nos.763 and 253 dated  

09.12.1898  and  17.01.1899  respectively  whereas  the  

CIVIL APPEAL NOS.               OF 2014 2 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

3

Page 3

conditions  were  incorporated  in  the  following  words  “(1)  

that the land shall revert to Government when it ceases to  

be used for the purpose for which it is granted and (2) that  

should the property be at any time resumed by Government,  

the  compensation  payable,  therefore,  shall  in  no  case  

exceed the cost or the then present value whichever shall  

be less of any building erected or other works executed on  

the land”.  

5. Subsequently, under a Scheme Decree framed by the High  

Court of Judicature at Madras in C.S. No.90 of 1963 all the  

above  mentioned  properties  held  by  Sir  Ramaswami  

Mudaliar’s  Choultry  were  vested  with  the  Administrator  

General and Official Trustee (hereinafter referred to as “the  

AG & OT) of Tamil Nadu on 18.08.1970. From then onwards  

the management of the Trust and the properties attached  

with it were under the control of the AG & OT. As per the  

Scheme Decree, the AG & OT of Tamil Nadu leased out the  

lands in T.S. No.41 and T.S. No.43/2 to various tenants and  

was collecting the rent. As far as T.S. No.43/2 comprised in  

an  extent  of  5644  sq.ft.  was  concerned,  the  same  was  

CIVIL APPEAL NOS.               OF 2014 3 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

4

Page 4

leased out to the first  respondent herein under the lease  

deed dated 22.12.1972.  According to the AG & OT, the First  

Respondent is in arrears and as on 31.12.2012, the arrears  

payable  by  the  First  Respondent  works  out  to  a  sum of  

Rs.94,84,630/- which has been computed and determined by  

the High Court of Madras.  It  is  also stated that the First  

Respondent has preferred Special Leave Petition(C) No.11-

12 of 2010 against the said determination and claim which is  

pending in this Hon’ble Court.  

6. According to  the First  Respondent,  pursuant  to  the lease  

granted in  his  favour,  which  was registered as document  

105 of 1974 in the Office of Sub-Registrar, West Madras, he  

constructed a Hotel  and started the business in  the year  

1987. According to him, subsequently, an adjacent piece of  

land measuring 4141 sq. ft was granted on lease for a period  

of 30 years to one Smt. Vatsala again based on the Order of  

the High Court of Madras, which was also supported by a  

registered Lease Deed dated 29.04.1982 bearing Document  

No.1492/1984  registered  in  the  office  of  the  Registrar,  

Madras (North). The said Smt. Vatsala also stated to have  

CIVIL APPEAL NOS.               OF 2014 4 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

5

Page 5

transferred her lease hold right in respect of the said extent  

to the First Respondent which was also stated to have been  

approved by the Official  Trustee in  the proceeding dated  

05.04.1989  in  R.O.C.  No.2390  of  1989/OT.  The  First  

Respondent claimed to have put up two pucca structures  

and running two Star Hotels known as ‘Hotel Central Tower’  

and ‘Hotel  Howrah’. The First  Respondent also claimed to  

have got the approval of the Municipality, State Government  

and  other  authorities  and  that  the  buildings  were  duly  

assessed for property tax and other statutory dues. By Order  

dated 10.12.2004 in Application No.915/2003, the lease in  

favour  of  the  First  Respondent  was  stated  to  have  been  

extended for a further period of 25 years by enhancing the  

rent payable by him. The First Respondent also relied upon  

an  Order  of  the  Division  Bench  of  the  High  Court  dated  

20.08.2009 in support of the extension of the lease passed  

in  O.S.A.  No.298  of  2004  and  connected  batch  cases.  

According to the First Respondent because of his old age  

and other physical ailments he entered into a partnership  

arrangement with the applicant in I.A. Nos.1 and 2 of 2014 in  

CIVIL APPEAL NOS.               OF 2014 5 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

6

Page 6

Special Leave Petition (C) No.26020-21 of 2013 under the  

partnership deed dated 28.03.2013.

7. Be  that  as  it  may,  having  regard  to  the  unprecedented  

growth of population in general, as well as with particular  

reference to the Metropolitan City of Chennai, there was an  

imminent  need for  providing better  transport  facilities  for  

the commuters and office goers, as well as business people,  

which  persuaded  the  State  to  expand  the  rail  transport  

facility in the City of Chennai.  With that avowed object, the  

appellant in Special Leave Petition (C) No.26020-21 of 2013  

came into being and the said Chennai Metro Rail  Limited  

planned a project called ‘Chennai Metro Rail Project’ which  

envisaged  construction  of  two  corridors  under  Phase-1.  

Corridor 1 starts from Washermenpet and ends at Airport for  

a length of 23.1 kms. and Corridor 2 starts from Chennai  

Central and ends at St. Thomas Mount Station for a length of  

22 kms. As per the project, the portions of Corridor 1 with a  

length of 14.3 kms. between Washermenpet to Saidapet and  

in  Corridor  -  2  with  a  length  of  9.7  kms.  from  Chennai  

CIVIL APPEAL NOS.               OF 2014 6 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

7

Page 7

Central to Anna Nagar would be underground corridors and  

the remaining in an elevated position.  

8. The Chennai  Metro Rail  Limited is  stated to be a Special  

Purpose  Vehicle  (SPV)  formed  for  the  purpose  of  

implementing the ‘Chennai Metro Rail Project’. The Project is  

stated to be funded by the Government of  India and the  

State Government  by way of  equal  equity  contribution in  

subordinate debt. (Government of India 20%, Government of  

Tamil Nadu 20.78% and the balance 59.22% being met from  

the  loan assistance  from Japan International  Co-operation  

agency).  The  Government  of  India  is  stated  to  have  

accorded  sanction  for  the  project  as  well  as  for  its  

participation.

 

9. The lands concerned in these appeals are covered by the  

project,  namely,  Corridor  1,  i.e.  from  Washermenpet  to  

Chennai Airport. According to the appellant, in Special Leave  

Petition (C) No.26020-21 of 2013, the project is a time bound  

project with an objective to ease out phenomenal growth of  

traffic congestion in the City of Chennai and any delay in  

CIVIL APPEAL NOS.               OF 2014 7 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

8

Page 8

carrying out the project would affect the plans announced  

by  the  Government  of  India,  as  well  as,  the  State  

Government, the convenience of the public of Chennai and  

further  will  lead  to  contractual  implications  such  as  

extension of time and escalation of project costs, which in  

turn would cost the public exchequer several hundred crores  

of rupees. According to the Chennai Metro, any further delay  

on any account,  apart  from causing high amount  of  cost  

escalation, would also deprive the citizens of Chennai a safe  

and quick means of public transport.  It  is  stated that the  

Chennai Metro in its project report has described in detail  

the various length of the projects and in the said statement,  

designed  constructions  of  underground  stations  at  

Washermenpet, Mannadi, High Court, Chennai Central and  

Egmore and associated tunnels, the details of the location,  

the description, the access date from commencement of the  

works with particular reference to the number of days and  

the  vacate  date  from  commencement  of  the  work  with  

particular  reference  of  number  of  days  is  specified  after  

making meticulous calculations.  

CIVIL APPEAL NOS.               OF 2014 8 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

9

Page 9

10. Mr.  Nageswara  Rao,  learned  Additional  Solicitor  General  

appearing for the appellants brought to our notice the work  

which was to be carried out in the land concerned in this  

appeal  which  has  been  noted  in  the  column  under  

locations/drawing  reference  bearing  No.SCC-14  and  the  

description has been shown as entrance area.   As far  as  

access  date  is  concerned,  it  is  noted  as  365  days  from  

commencement of the works and the date to be vacated  

after  completion  of  the  work  from  the  date  of  

commencement is noted as 1520 days. According to learned  

Additional Solicitor General, for the purpose of starting the  

work  in  the  land  in  question,  as  per  the  schedule,  the  

Chennai Metro should have access to the land within 365  

days of the commencement of the project and complete the  

work in that land within 1520 days from the date of such  

access.   It  was  pointed  out  that  such  details  have  been  

specified in the contract agreement and that to ensure that  

the works are carried out without any deviation and within  

the time schedule, the required plans were also prepared in  

so far as it related to SCC-14 and was submitted with the  

details of lands falling under Survey No.43/2.  The learned  CIVIL APPEAL NOS.               OF 2014 9 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

10

Page 10

Additional Solicitor General also submitted that the said land  

were  earmarked  for  erecting  a  mechanical  plant  room,  

electrical plant room, building services, drop-off and pick-up  

facilities and Airport check-in facilities. The plan which were  

enclosed along with the Special Leave Petition paper book  

between pages 164 to 167 disclose the area falling under  

Survey No.43/2, the various facilities to be set up in that  

land along with  the other  facilities  to  be provided in  the  

lands adjacent to the said Survey No.43/2.  

11. It  was also the case of  the Chennai Metro that since the  

lands in Survey No.43/2 belong to the State Government and  

was  imminently  required  for  the  Chennai  Metro  Project  

which  was  out  and  out  in  public  interest,  the  State  

Government  came  forward  to  allot  the  said  lands  after  

retrieving it from Sir Ramaswamy Mudaliar Choultry through  

the  AG  &  OT  and  by  GO  Ms.  No.168  dated  21.05.2012  

passed orders to that effect.  Before issuing the said GO, the  

procedure to be followed for transfer of  the said lands in  

favour of the Chennai Metro Pvt. Limited were also carried  

out. As the lands belong to the State Government there was  CIVIL APPEAL NOS.               OF 2014 10 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

11

Page 11

no  necessity  for  any  acquisition  being  involved  or  any  

payment of compensation to be made in favour of anyone  

except for the Buildings standing thereon. Since the State  

Government’s participation is equal in proportion along with  

the Government of India and inasmuch as the development  

of the project was in the interest of the public at large the  

GO dated 21.05.2012 came to be issued.   

12. Aggrieved by the Order of the Government in GO Ms. No.168  

of  21.05.2012,  the  First  Respondent  and  various  other  

persons who were in possession of the other adjacent lands,  

which were also covered by the abovesaid GO, approached  

the  High  Court  by  filing  Writ  Petitions.  The  First  

Respondent’s  Writ  Petitions  were  Writ  Petition  

Nos.19469/2012  and  19470/2012  wherein  he  sought  for  

issuance of a writ of Certiorari to call for the records of the  

proceedings  in  GO  No.168  of  21.05.2012  and  the  

consequential  proceedings  of  the  Tehsildar  dated  

21.06.2012 as well as the proceedings of the AG & OT dated  

25.06.2012  and  for  quashing  the  said  proceedings.  It  is  

stated that pursuant to the issuance of the GO Ms. No.168  

CIVIL APPEAL NOS.               OF 2014 11 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

12

Page 12

dated  21.05.2012,  the  Tehsildar  of  Fort  Tondiarpet  Taluk  

issued a notice to AG & OT on 21.06.2012 for resumption of  

the land and handover vacant possession.  Individual notices  

were also stated to have been issued to all the occupants  

including the First  Respondent asking them to vacate the  

premises and remove their belonging and handover vacant  

possession. In turn, the AG & OT by its notice 25.06.2012  

called upon the First Respondent and the other tenants to  

vacate the premises immediately to enable the AG & OT to  

handover possession to Chennai Metro.  

13. By Order dated 26.11.2012, the Writ Petitions filed by the  

First Respondent and other occupants came to be allowed  

by the learned Single Judge and the GO Ms. No.168 dated  

21.05.2012 was set aside. Aggrieved by the Judgment of the  

learned Single  Judge the appellants  herein  preferred Writ  

Appeals  68 to  106 of  2013.   The  Division  Bench  after  a  

detailed discussion allowed Writ Appeal Nos. 70 to 88 and 91  

to  106 of  2013 holding  that  the said  Chennai  Metro  Rail  

Project,  a  joint  venture  of  Central  Government  was  to  

enhance the public transport system in Chennai and being a  

CIVIL APPEAL NOS.               OF 2014 12 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

13

Page 13

public project, any delay in implementation would oust the  

public  purpose  for  which  the  lands  were  sought  to  be  

retrieved.  However, Writ Appeal Nos.68, 69, 89 and 90 of  

2013 which related to the lands falling under Survey No.43/2  

which are in the possession of the First  Respondent were  

concerned, according to the Division Bench the same stood  

on a different footing.  The Division Bench in its order held  

as under in paragraph 28:

“28.   The map published by CMRL,  showing various  structures they are going to erect in the area, indicate  that  the area earmarked for  CMRL  project  does  not  include  the  ease  area  of  the  writ  petitioner  in  W.P.  Nos.19469 and 19470 of 2012 (connected to W.A. Nos.  68, 69, 89 and 90 of 2013).  It is also clear from the  map  that  the  entire  lands  required  for  the  CMRL  projects like the Underground Metro Station etc. are on  the Northern side of the Poonamalle High Road, where  vast  extent  of  other  vacant  lands  are  available,  including the erstwhile Hotel Picnic area.  As already  stated supra, pursuant to the lease deed entered into  by this petitioner with AG & OT, this petitioner raised a  huge construction with  his  own funds and doing his  own business and the said lease has been extended  upto the year 2027.  No default of any sort on his part  has  been alleged by any  of  the  parties.   When the  lands and building in possession and occupation of this  petitioner are outside the purview of the CMRL project,  as has been discussed supra, ordering handing over of  the  vacant  possession  of  the  said  lands  by  this  petitioner  for  the  purpose  of  CMRL,  is  nothing  but  requiring  him  to  demolish  the  building  in  his  possession.  At this juncture we feel it apt to hold that  ordering demolition of buildings, for no legal or useful  

CIVIL APPEAL NOS.               OF 2014 13 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

14

Page 14

purposes, is nothing but wastage of public resources.  Given the facts and circumstances of the case that the  lands and building raised by this petitioner are outside  the purview of the CMRL and not in violation of any  law, including the building and tenancy laws, we have  no  doubt  to  hold  that  the  lands  and  building  in  possession  and  enjoyment  of  this  petitioner  are  entitled  to  be  excluded  from  the  project  area.  Thereafter,  the  order  passed  by  the  learned  single  Judge in W.P. Nos. 19469 of 2012 and 19470 of 2012  stands  modified  and  both  the  above  writ  petitions  stand allowed.  Consequently, W.A. Nos. 68, 69, 89 and  90 stand dismissed.”

14. A reading of the said paragraph disclose that in its opinion  

the lands required for Central Chennai Metro Rail Project for  

locating its underground Metro Station etc. were all noted on  

the northern side of the arterial road namely Poonamallee  

High  Road,  that  vast  extent  of  other  vacant  lands  were  

available  including  the  erstwhile  hotel  called  ‘the  Hotel  

Picnic’  and  that  in  so  far  as  the  first  Respondent  was  

concerned,  he  was  granted  a  lease  which  is  to  be  in  

operation till the year 2027 and on these two grounds the  

Division  Bench  took  the  view  that  the  GO  Ms.168  dated  

21.05.2012 cannot be justified and confirmed the order of  

the learned Single Judge in WP 19469 of 2012 and 19470 of  

2012 and dismissed the Writ Appeal Nos.68, 69, 89 and 90  

of 2013.  CIVIL APPEAL NOS.               OF 2014 14 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

15

Page 15

15. Mr. Nageswara Rao, learned Additional Solicitor General in  

his submission while assailing the Judgment of the Division  

Bench  contended  that  the  basis  for  setting  aside  the  

impugned GO Ms. No.168 dated 21.05.2012 by the Division  

Bench was that the land in question, namely, the one which  

fell within Survey No.43/2 was not part of the project land  

and that the First Respondent has been granted a lease by  

the AG & OT till the year 2027 and, therefore, the impugned  

GO  cannot  be  sustained.  The  learned  Additional  Solicitor  

General  by  referring  to  the  above  paragraph  28  of  the  

Division Bench submitted that the Division Bench thoroughly  

misled  itself  when  it  stated  that  the  underground  Metro  

Station has been planned in the project on the Northern side  

of the Poonamallee High Road where certain other lands are  

available which can be acquired and inasmuch as the First  

Respondent has got a long lease in his favour from the AG &  

OT, the Chennai Metro as well as the State Government was  

not justified in passing the impugned GO dated 21.05.2012.  

In  so  far  as  the  lands  in  Survey  No.43/2,  the  learned  

Additional Solicitor General took us to the plans which were  

CIVIL APPEAL NOS.               OF 2014 15 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

16

Page 16

part of  the material  papers placed before the High Court  

which are now annexed and found in pages 164-167 and  

submitted  that  while  on  the  Northern  side  of  the  

Poonamallee High Road the underground Metro Station has  

been planned, the present lands situated in Survey No.43/2  

as well  as the adjacent lands in Survey No.41 have been  

earmarked for various other important developments to be  

carried out as part of the project such as the setting up of  

mechanical  plant  rooms,  electrical  plant  rooms,  building  

services,  drop-off  and  pick-up  facilities  and  the  Airport  

check-in facilities  in  Survey No.43/2 and ventilation shaft,  

entry/exit, sub way, feeder bus stand, multi-model facilities,  

pick-up and drop-off bay, MTC Bus bay and fireman staircase  

in Survey No.41 and that the entire lands in Survey No.41  

and 43/2 belong to the State Government and, therefore,  

the  Division  Bench  unfortunately  failed  to  advert  to  the  

above details which were placed before it which resulted in  

the passing of the impugned judgment.

16. Learned Additional Solicitor General also submitted that as  

against the Division Bench Judgment relating to the other  

CIVIL APPEAL NOS.               OF 2014 16 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

17

Page 17

Writ Appeals which were allowed in favour of the Chennai  

Metro and State Government, Civil Appeal Nos.6065-6068 of  

2013  and  connected  Special  Leave  Petitions  were  filed  

wherein this Court taking note of the submission of learned  

Solicitor General that the State of Tamil Nadu would issue  

notices inviting all the stake-holders liable to be affected by  

adverse orders  an opportunity  to  respond to  the reasons  

which  weighed with  the  State  Government  to  evict  them  

from  the  premises  in  question  permitted  the  State  

Government  to  issue  such  notices  and  after  getting  the  

response  from  those  parties  pass  appropriate  orders.  

Learned Additional Solicitor General also submitted that the  

said exercise was carried out by issuing notices and after  

receipt of the response, orders were passed for taking over  

of the lands from the concerned occupants and that fresh  

proceedings have been initiated by those occupants which  

are  stated  to  be  pending  consideration  before  the  High  

Court.   

17. Mr. Gopal Subramanium, learned Senior Counsel appearing  

for the First Respondent also confirmed the said statement  

CIVIL APPEAL NOS.               OF 2014 17 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

18

Page 18

of  learned  Additional  Solicitor  General.  Mr.  Gopal  

Subramanium, however, contended that similar orders can  

be  passed  in  these  appeals  also  to  enable  the  First  

Respondent  to  submit  his  response  and,  thereafter,  the  

Appellants can pass appropriate orders.  The learned Senior  

Counsel  for  the  First  Respondent  in  his  submission  

contended that in the sketch which are enclosed and kept at  

page  164  to  167  of  the  Special  Leave  Petition  papers  

adjacent  to  the  Survey  No.  43/2,  there  were  some other  

structures  belonging  to  different  parties  and  that  the  

Appellants have excluded those lands on the footing that  

some heritage building was located and, therefore, the First  

Respondent,  whose  leasehold  lands  are  located  closely  

adjacent to those left out built-up area, in the event of an  

opportunity being extended to the First Respondent, he will  

be able to satisfy the authorities to exclude his leasehold  

lands also from the purview of taking over by the Chennai  

Metro. Mr. Gopal Subramanium also referred to an affidavit  

on  behalf  of  Chennai  Metro  dated  April,  2011  in  O.S.A.  

No.100-101  of  2011  to  contend  that  the  averments  

contained therein support the stand of the First Respondent  CIVIL APPEAL NOS.               OF 2014 18 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

19

Page 19

to  persuade  the  Chennai  Metro  to  look  for  some  other  

alternate lands.

18. While  considering  the  submissions  of  learned  Additional  

Solicitor  General  and  Mr.  Gopal  Subramanium,  learned  

Senior Counsel  for  the First  Respondent,  inasmuch as we  

find  that  the  reasoning  of  the  Division  Bench  in  having  

stated that the underground Metro Station has been planned  

in  a  stretch  of  Land on the  Northern  side of  the Arterial  

Road,  namely,  Poonamallee  High  Road  and  that  certain  

other lands were available in that side and, therefore, there  

was no necessity for taking over the lands in the possession  

of the First Respondent is patently a conclusion which was  

contrary to the records placed before the Division Bench and  

the same cannot  be sustained.  In  other words,  as  rightly  

pointed  out  by  learned  Additional  Solicitor  General,  the  

conclusion of the Division Bench that the lands concerned in  

these Appeals, namely, the one situated in Survey No.43/2  

were not  part  of  the project  of  the Chennai  Metro was a  

wrong assimilation of facts. When it has been demonstrated  

before us based on the project details and the plan annexed  

CIVIL APPEAL NOS.               OF 2014 19 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

20

Page 20

with  it,  which  disclose  that  the  lands  situated  in  Survey  

No.43/2 as well as Survey No.41 were all part of the projects  

for  putting  up  various  other  ancillary  units  such  as  

mechanical  plant  rooms,  electrical  plant  rooms,  building  

services,  drop-off  and  pick-up  facilities,  airport  check-in  

facilities, ventilation shafts, subway, feeder bus stand, multi-

modal  facilities,  pick-up  and  drop-off  bay,  MTC  Bus  bay,  

fireman staircase, entry and exit points, if the taking over of  

the lands by the Chennai Metro is not allowed, the same  

would seriously prejudice and cause unnecessary hurdles in  

proceeding  with  the  project.  In  our  considered  view,  the  

failure of the Division Bench in noting the details displayed  

in the plan and the project which were placed before it has  

resulted in the passing of the impugned Order. The Division  

Bench failed to note that the project details pertaining to the  

proposed  underground  Metro  Station  and  the  other  

supporting provisions to be made such as mechanical plant  

rooms,  electrical  plant  rooms,  bus  bay  and  other  

developments to be carried out spread over a vast extent of  

land  both on  the  Northern  side of  the  Poonamallee  High  

Road as well as the lands situated on the Southern side of  CIVIL APPEAL NOS.               OF 2014 20 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

21

Page 21

the said Road with which we are now concerned. Therefore,  

in  the light  of  the above details  placed before  the Court  

which according to learned Additional Solicitor General was  

made available before the Division Bench also, we have no  

reason to reject the said submission in order to sustain the  

conclusion  of  the  Division  Bench.  In  other  words,  the  

conclusion  of  the  Division  Bench  having  been  reached  

without properly examining the relevant documents relating  

to the Chennai Metro Project, namely, the plans, the project  

schedule  and  the  other  averments  placed  before  the  

Division Bench, the impugned order of the Division Bench  

cannot be sustained.   

19. Mr. Gopal Subramanium, learned Senior Counsel appearing  

for the First Respondent in support of his submission that  

the lands situated in Survey No.43/2 were not required at all  

for  the  purpose  of  carrying  out  the  Metro  Project  and  

referred to an affidavit filed before the Division Bench by the  

Managing  Director  of  Chennai  Metro  Rail  Limited.  The  

learned Senior Counsel submitted that in the said affidavit  

the reference to the Metro Rail  Station planned along the  

CIVIL APPEAL NOS.               OF 2014 21 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

22

Page 22

Poonamallee High Road has been stated and while referring  

to the same, a specific reference was made to the private  

buildings  located  opposite  to  Picnic  Hotel  and  that  

acquisition of those private lands would cost dearly to the  

State  Exchequer  apart  from  evacuation  of  the  

tenants/owners would consume considerable length of time  

which would in turn cause delay in the construction of the  

underground Station.  When we perused the said  affidavit  

which has been extracted in the reply affidavit filed by the  

Managing Director  of  Chennai  Metro  in  W.P.  No.19469 of  

2012,  we  find  that  statement  came to  be  made when a  

litigation was launched at the instance of Hotel Picnic and  

while meeting the stand of Hotel Picnic, it was stated that  

the above statement came to be made.  We do not find any  

scope to reject the stand of the Appellant with reference to  

the lands situated in Survey No.43/2 which had nothing to  

do with the construction of the underground Metro Station.  

Though, the various other units to be set up in the lands in  

Survey No.43/2 were also part of the Metro Project as has  

been demonstrated before us based on relevant documents,  

the reference to  the Heritage Buildings and other private  CIVIL APPEAL NOS.               OF 2014 22 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

23

Page 23

buildings situated opposite to Hotel Picnic was referred to by  

Chennai  Metro  while  pointing  out  its  inability  to  plan the  

setting up of underground Metro Station in any other land  

except the lands where Hotel Picnic was situated. Therefore,  

the said submission of the learned Senior Counsel for the  

First Respondent does not in any way support the stand of  

the First Respondent.  As far as the contention of Mr. Gopal  

Subramanium  that  like  in  the  case  of  other  occupants  

wherein a direction was issued by this Court to give a show  

cause  notice  and  decide  the  matter,  the  said  contention  

cannot be countenanced in this case inasmuch as before the  

Division Bench of the High Court as well as before us the  

issue was argued on merits. In fact, the Division Bench after  

hearing  the  Appellants  and  the  First  Respondent  allowed  

both his Writ Petitions by modifying the order of the learned  

Single Judge and thereby held that there was no necessity  

for  a  remand.  Therefore,  since we have also decided the  

whole controversy on merits there is no need for a remand.

20. Therefore,  once we are convinced that the entitlement of  

the Appellant to hold the lands belonging to the State falling  

CIVIL APPEAL NOS.               OF 2014 23 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

24

Page 24

under Survey Nos.43/2 as well as 41 which the Appellant is  

able  to  take  possession  of  from  the  State  Government  

without  payment  of  any  compensation,  the  only  other  

question to be examined is as to whether the lease granted  

in favour of the First Respondent by the AG & OT based on  

the directions of the High Court can have any implication in  

preventing  the  Appellant  from  taking  over  the  lands.  As  

noted  earlier,  indisputably  the  lands  in  Survey  No.43/2  

belong  to  the  State.  At  the  time  when  the  lands  were  

granted and assigned in favour of Sir Ramaswamy Mudaliar  

Trust vide GO Ms. Nos.763 and 253 dated 09.12.1898 and  

17.01.1899  respectively,  conditions  were  imposed  to  the  

effect that the lands would revert back to the Government  

when it ceases to be used for the purpose for which it was  

granted and that should the property at any time resumed  

by  Government,  the  compensation  payable  should  in  no  

case exceed the cost or the then present value whichever  

shall be less of any building erected or other works executed  

in  the  land.  Though,  learned  Additional  Solicitor  General  

sought to contend as was also contended before the High  

Court that by leasing out the lands to different parties the  CIVIL APPEAL NOS.               OF 2014 24 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

25

Page 25

condition No.1 was violated, namely, that the land was put  

to different use than for what it was granted, we do not find  

any good grounds to accept the same. On the other hand,  

we find that the Trust itself was vested with the AG & OT on  

18.08.1970 pursuant  to  a  Scheme Decree  framed by the  

High Court in C.S. No.90 of 1963. From then onwards, the AG  

&  OT  was  administering  the  Trust  and  was  apparently  

fulfilling the purpose for which the Trust came to be created,  

though, by leasing out the lands to different individuals for  

the purpose of generating income from the lands. The AG &  

OT by approaching the High Court, as and when required,  

seem to have granted the lease of  the lands to  different  

parties based on the orders passed by the High Court.  

21. In so far as the First Respondent was concerned, his lease  

came into existence initially on 22.12.1972, and by Order  

dated 10.12.2004 in Application No.915 of 2003, the lease in  

favour of the First Respondent was extended for a further  

period of 25 years by enhancing the rent. The said order was  

also confirmed by the Division Bench in  the Order  dated  

20.08.2009  in  O.S.A.  No.298  of  2004.  In  the  said  

CIVIL APPEAL NOS.               OF 2014 25 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

26

Page 26

circumstances, it  cannot be held that the said possession  

with the First Respondent was unlawful.  However, on that  

basis when it comes to the question of resumption of the  

land  by  the  State  Government  when  the  Government  

through the AG & OT thought it fit to resume the lands which  

was in accordance with the terms contained in the Original  

Grant, namely, GOS No.763 and 253 dated 09.12.1898 and  

17.01.1899,  there  would  be  no  scope  for  the  First  

Respondent to contend that the Appellants are not entitled  

for the resumption of the lands situated in Survey No.43/2.  

22. We, therefore, hold that the State Government as the owner  

of  the land and having regard to  the right retained by it  

while making the grant in the years 1898 and 1899 and in  

the larger public interest of setting up of the Chennai Metro  

Project the lands were required by it, the same cannot be  

questioned by the Original Grantee or by the lessees whose  

holding  was  subordinate  in  character  to  the  Original  

Grantee. Therefore, we do not find any justification in the  

Division Bench in having interfered with the impugned GO  

Ms. No.168 dated 21.05.2012 and the consequential orders  

CIVIL APPEAL NOS.               OF 2014 26 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

27

Page 27

of the Tehsildar dated 21.06.2012 and that of the AG & OT  

dated  25.06.2012  directing  the  First  Respondent  to  

handover possession of the lands.  

23. Therefore,  while  the impugned GO and the consequential  

orders  of  the  Tehsildar  and  AG  &  OT  can  be  sustained,  

having regard to the condition contained in the initial GO Ms.  

Nos.763 and 253 dated 09.12.1898 and 17.01.1899 since  

based on valid orders of the High Court and the AG & OT the  

First Respondent developed its Hotel business in the lands in  

question, while resuming the lands, the State Government  

along with the Chennai Metro is bound to compensate the  

First Respondent for the buildings which were erected in the  

said land in Survey No.43/2 based on the valuation to be  

made by the appropriate Authorities.  

24. Therefore,  while  allowing  the  Appeals  of  the  State  

Government as well as the Chennai Metro and while setting  

aside  the  Judgment  of  the  Division  Bench,  Writ  Appeal  

Nos.68, 69, 89 and 90 of 2013 are allowed. We, however,  

direct the Appellants to value the buildings belonging to the  

First Respondent standing in Survey No.43/2 and determine  

CIVIL APPEAL NOS.               OF 2014 27 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)                                                                                  

28

Page 28

the  compensation  and  pay  the  same  to  the  First  

Respondent. The said exercise of valuation and payment of  

compensation shall  be effected within  three months  from  

this date.   

25. In  the light  of  our  above orders,  the  First  Respondent  is  

directed  to  surrender  possession  of  the  lands  in  Survey  

No.43/2 in an extent of 5644 sq. ft. through the AG & OT  

within four weeks from the date of receipt of copy of this  

judgment.  With  the  above  directions,  these  appeals  are  

allowed.     

      

    …..……….…………………………...J.

                    [A.K. Patnaik]

   …………….………………………………J.                   [Fakkir Mohamed Ibrahim  

Kalifulla] New Delhi; February 21, 2014

CIVIL APPEAL NOS.               OF 2014 28 of 28 (@ SLP (C) NOS.26020-26021 OF 2013)