17 March 2015
Supreme Court
Download

TATA STEEL LTD Vs UOI

Bench: H.L. DATTU,MADAN B. LOKUR,A.K. SIKRI
Case number: C.A. No.-002938-002939 / 2015
Diary number: 10136 / 2014
Advocates: PUNIT DUTT TYAGI Vs


1

Page 1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS. 2938-2939 OF 2015 (Arising out of S.L.P. (C) Nos.8972-8973 of 2014)

Tata Steel Ltd.                    .…Appellant  

Versus

Union of India & Ors.            …Respondents  

AND

CIVIL APPEAL NOS.  2940-2941  OF 2015 (Arising out of S.L.P. (C) Nos.9016-9017 of 2014)

Tata Steel Ltd.                     .…Appellant  

Versus

State of Jharkhand & Ors.                     …Respondents

WITH

CIVIL APPEAL NO. 303 OF 2004

Tata Iron & Steel Co. Ltd.                      .…Appellant  

Versus

State of Jharkhand & Ors.                     .…Respondents

WITH

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 1 of 50

                                                  

2

Page 2

CIVIL APPEAL NO. 307 OF 2004

State of Bihar (Now Jharkhand) & Ors.                    …Appellants

            

Versus

Tata Iron & Steel Co. Ltd.                                        … Respondent

J U D G M E N T

Madan B. Lokur, J.

1. Leave granted.

2. Two sets  of  appeals  are  before  us.  One set  of  appeals  

pertains to the Tata Iron and Steel Company Limited (TISCO)  

and the other set pertains to Tata Steel.

3. In the set of appeals pertaining to TISCO, the first appeal  

is  Civil  Appeal  No.  303/2004  filed  by  TISCO  against  the  

judgment  and  order  dated  23rd July,  2002  passed  by  the  

Jharkhand  High  Court.1 The  grievance  in  this  appeal  is  that  

though the application of  the law laid down by this court in  1 MANU/JH/0590/2002

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 2 of 50

                                                  

3

Page 3

State of Orissa v. Steel Authority of India Ltd.2 (hereafter  

SAIL) has  been  accepted  by  the  High  Court,  namely,  that  

royalty is chargeable [in accordance with Section 9 of the Mines  

and  Minerals  (Development  and  Regulation)  Act,  1957  (the  

MMDR Act)] on the quantity of coal extracted at the pit-head,  

yet the refund of excess royalty paid by TISCO for the period  

from 10th August, 1998 (the date of the decision in  SAIL) till  

June  2002  [about  Rs.29.34  cr.]  has  been  denied.  TISCO  

therefore claims entitlement to  refund on the excess royalty  

paid by it for this period.

4. Civil  Appeal No.307/2004 has been filed by the State of  

Bihar (Now Jharkhand) against the same judgment and order  

dated 23rd July, 2002. The submission is that after the decision  

in SAIL the Government of India issued a notification dated 25th  

September,  2000  inserting  Rule  64B  and  Rule  64C  in  the  

Mineral Concession Rules, 1960 (hereafter MCR) and as a result  

of this, Run-of-Mine (ROM) minerals, after being processed in  

the  leased  area  are  exigible  to  royalty  on  the  processed  

2 (1998) 6 SCC 476

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 3 of 50

                                                  

4

Page 4

mineral.  It is contended that these rules were, unfortunately,  

not  brought  to  the  notice  of  the  High  Court  and  that   the  

decision rendered by  

the High Court accepting the law laid down in SAIL is incorrect.

5. In  this  context,  it  must  immediately  be  noted  that  the  

contention of the State of Jharkhand is not that Rule 64B and  

Rule 64C of the MCR have retrospective effect. That being so,  

the  question  is  whether  TISCO  is  entitled  to  refund  of  the  

excess  royalty  paid  from 10th August,  1998 (the date of  the  

decision in SAIL) to 25th September, 2000 and if so whether the  

High Court was right in denying that refund. Also, the question  

is  whether  TISCO  is  entitled  to  refund  of  royalty  from  25th  

September,  2000 till  June 2002 and if  so,  whether  the  High  

Court was right in denying that refund.

6. The other set of appeals pertaining to Tata Steel consists  

of four appeals. These appeals filed by Tata Steel arise out of  

S.L.P.  (C)  Nos.8972-73/2014 and S.L.P.  (C)  Nos.9016-17/2014  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 4 of 50

                                                  

5

Page 5

and are directed against a common judgment and order dated  

12th March, 2014 passed by the Jharkhand High Court in W.P.  

(C) Nos.1504/2009 & 1505/2009 and W.P. (C) Nos. 2995/2008 &  

2999/2008.3  The grievance of Tata Steel is that despite the  

decision of this court in SAIL and the decision dated 23rd July,  

2002  of  the  Jharkhand  High  Court,  royalty  is  being  charged  

from Tata Steel on processed or beneficiated coal and not on  

extracted coal or Run-of-Mine (ROM) coal at the pit-head. It is  

submitted that this is  despite the affidavit  of  the Ministry of  

Coal of the Government of India that Rule 64B and Rule 64C of  

the MCR “may not be particularly applicable on coal minerals.”  

Tata Steel is also aggrieved by the conclusion of the Jharkhand  

High  Court  that  Rule  64B  and  Rule  64C  of  the  MCR  are  

constitutionally valid.

Appeals filed by Tata Steel

7. The question for our consideration in the set of appeals  

filed  by  Tata  Steel  is  whether  royalty  is  chargeable  under  

Section  9  of  the  Mines  and  Minerals  (Development  and  

3 2014 (2) JLJR 702

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 5 of 50

                                                  

6

Page 6

Regulation) Act, 1957 and the Second Schedule thereto on raw  

or unprocessed or Run-of-Mine (ROM) coal at the pit-head or is  

it chargeable on coal after it is processed and beneficiated in  

the washeries located within the boundaries of the leased area.  

In our opinion, the question of payment of royalty has arisen in  

respect of other minerals and this has been discussed in cases  

relating to those minerals. On an appreciation of the decisions  

rendered,  it  must  be  held  that  royalty  is  payable  on  the  

processed or beneficiated coal only after 25th September, 2000  

and  royalty  is  payable  on  unprocessed,  raw  or  ROM  coal  

extracted at the pit-head only for the period from 10th August,  

1998 to 25th September, 2000.  

Background facts

8. Tata Steel holds several mining leases for coal in the State  

of Jharkhand, in the district of Ramgarh (formerly Hazaribagh)  

known  as  the  West  Bokaro  Colliery  and  in  the  district  of  

Dhanbad  known  as  the  Jamadoba  and  Belatand  group  of  

collieries. The coal mines are captive coal mines. Tata Steel has  

an adequate number of washeries in the leased area where the  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 6 of 50

                                                  

7

Page 7

raw coal extracted from the mine (Run-of-Mine coal) is washed  

to improve its quality and is then dispatched for use in its steel  

plant at Jamshedpur for the production of iron and steel.

9. Initially Tata Steel and TISCO were of the opinion that in  

accordance with the provisions of Section 9 of the Mines and  

Minerals  (Regulation  and  Development)  Act,  1957  [now  

renamed  as  the  Mines  and  Minerals  (Development  and  

Regulation) Act, 1957 or the MMDR Act]4 they were liable to pay  

royalty at the rates mentioned in the Second Schedule to the  

MMDR Act on the tonnage of washed coal, that is after raw coal  

4  With effect from 18th December, 1999 9. Royalties in respect of mining leases.—(1) The holder of a mining lease  

granted before the commencement of this Act shall, notwithstanding anything contained  in the instrument of lease or in any law in force at such commencement, pay royalty in  respect  of  any  mineral  removed  or  consumed  by  him  or  by  his  agent,  manager,  employee, contractor or sub-lessee from the leased area after such commencement, at  the rate for the time being specified in the Second Schedule in respect of that mineral.

(2) The holder of a mining lease granted on or after the commencement of this  Act shall pay royalty in respect of any mineral removed or consumed by him or by his  agent, manager, employee, contractor or sub-lessee from the leased area at the rate for  the time being specified in the Second Schedule in respect of that mineral.

(2-A)  The  holder  of  a  mining  lease,  whether  granted  before  or  after  the  commencement of the Mines and Minerals (Regulation and Development) Amendment  Act, 1972, shall not be liable to pay any royalty in respect of any coal consumed by a  workman engaged in a colliery provided that such consumption by the workman does not  exceed one-third of a tonne per month.

(3) The Central Government may, by notification in the Official Gazette, amend  the  Second Schedule  so as  to  enhance or  reduce the rate at  which royalty  shall  be  payable in respect of any mineral with effect from such date as may be specified in the  notification:

Provided that the Central Government shall  not enhance the rate of royalty in  respect of any mineral more than once during any period of three years.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 7 of 50

                                                  

8

Page 8

or Run-of-Mine (ROM) coal is removed from the washery post  

the beneficiation process.  In fact a writ petition was filed by  

TISCO in the Patna High Court being CWJC No.1 of 1984 (R)  

seeking a declaration to this effect. The State of Bihar (at that  

time)  was  of  the  view that  royalty  was  payable  at  the  rate  

mentioned in  the Second Schedule to the MMDR Act  on the  

tonnage of the extracted coal at the pit-head and not on the  

tonnage of the washed or beneficiated coal.  By its judgment  

and order dated 7th August,  1990 the Patna High Court held  

that  TISCO was  liable  to  pay  royalty  on  the  tonnage  of  the  

washed or beneficiated coal.  It was held:

“From the plain reading of section 9(2) of the Act, it is clear  that royalty is payable on the coal removed from the leased  area and so long it is not removed, no royalty is payable. In  view of the fact that coal is removed from the leased area,  only after it is washed, the petitioner is liable to pay royalty on  the weightage of that coal.”  

10. This decision has attained finality and the position at law  

in this regard continued till 1998.  

11. On  10th August,  1998  this  court  delivered  judgment  in  

SAIL.  The question raised in that case was whether the Steel  

Authority of India Ltd. or SAIL was liable to pay royalty at the  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 8 of 50

                                                  

9

Page 9

rate mentioned in the Second Schedule to the MMDR Act on the  

quantity of mineral (limestone and dolomite) extracted as it is  

or  on  the  quantity  arrived  at  after  these  minerals  have  

undergone a process of removal of waste and foreign matter.  

According to the State of Orissa royalty was chargeable on the  

extracted  minerals  at  the  rate  mentioned  in  the  Second  

Schedule to the MMDR Act while according to SAIL royalty was  

chargeable at the rate mentioned in the Second Schedule to  

the MMDR Act on the quantity of minerals obtained after the  

process of removal of waste and foreign matter.  

12. This court referred to an earlier decision of the Orissa High  

Court  relating to  the National  Coal  Development  Corporation  

Ltd.5   In that case, the High Court held that removal of coal  

from the seam in the mine and extracting it through the pit’s  

mouth to the surface would satisfy the requirement of Section 9  

of  the  MMDR Act  to  give  rise  to  a  liability  for  royalty.   The  

decision of the Orissa High Court was appealed against but the  

appeal  was  dismissed  by  this  court.6  Relying  upon  this  5 National Coal Development Corporation Ltd. v. State of Orissa, AIR 1976 Orissa 159 6 National Coal Development Corporation Ltd. v. State of Orissa, (1998) 6 SCC 480   

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 9 of 50

                                                  

10

Page 10

decision, it was concluded in SAIL that the process of removal  

of  waste  and  foreign  matter  amounts  to  consumption  and,  

therefore, the entire mineral extracted is exigible to a levy of  

royalty.    By necessary implication the decision of the Patna  

High  Court  in  CWJC  No.1  of  1984  (R)  filed  by  TISCO  stood  

reversed.

13. Perhaps as a consequence of the decision in  SAIL, Rule  

64B and Rule 64C were inserted in the MCR by a notification  

dated 25th September, 2000.7

14. Be that as it  may,  in view of  the decision in  SAIL,  the  

stand taken by Tata Steel/TISCO completely changed and the  

view now sought to be canvassed was that royalty is payable at  

the rate mentioned in the Second Schedule to the MMDR Act on  

the tonnage of unprocessed or ROM coal at the pit-head and  

not on processed or beneficiated coal.   

15. With regard to the claim of Tata Steel that it was liable to  

pay royalty only on the tonnage of unprocessed or ROM coal at  

the pit-head in terms of the decision in  SAIL, the response of  7 National  Mineral  Development  Corporation  Ltd.  v.  State  of  M.P.,  (2004)  6 SCC 281  paragraph 32 had earlier echoed this view

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 10 of 50

                                                  

11

Page 11

the State of Jharkhand was that in view of Rule 64B and Rule  

64C  of  the  MCR,  royalty  was  liable  to  be  paid  at  the  rate  

mentioned in  the Second Schedule to the MMDR Act  on the  

tonnage of beneficiated coal and not on the tonnage of the raw,  

extracted or ROM coal at the pit-head. In other words, not only  

was there a volte face by Tata Steel/TISCO but also by the State  

Government.  The High  Court  has  observed in  the  impugned  

judgment dated 12th March, 2014 that the reason for the volte  

face both by Tata Steel and by the State of Jharkhand was that  

by the notifications dated 1st August,  1991 and 14th October,  

1994 the rate of royalty on the washed or beneficiated  coal  

was increased.8

16. In any event, this interpretational dispute led to the filing  

of  a  set  of  writ  petitions by Tata Steel  in  the High Court  of  

Jharkhand, out of which the present appeals have arisen.

The controversy

8 By a notification dated 5th May, 1987 the rate of royalty on coking coal Steel Grade I  was fixed at Rs.7/- per ton and of Washery Grade IV at Rs.5.50 per ton; by a notification  dated 1st August, 1991 the rate of royalty on coking coal Steel Grade I was increased to  Rs.150/- per ton and of coking coal Washery Grade IV to Rs.75/- per ton; by a notification  dated 14th October, 1994 the rate of royalty on coking coal Steel Grade I was further  increased to Rs.195/- per ton and of coking coal Washery Grade IV to Rs.95/- per ton.    

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 11 of 50

                                                  

12

Page 12

Quality of coal and stage of chargeability

17. When coal is extracted from a mine, it is referred to as raw  

coal or unprocessed coal. Depending upon the use to which it  

may be put, which also depends upon its ash content and its  

calorific  value,  raw coal  or  unprocessed  coal  or  Run-of-Mine  

(ROM) coal can be used as it is.   

18. As far as Tata Steel is concerned, it is stated on page 164  

of  the  Convenience  Volume  handed  over  to  us  by  learned  

counsel for Tata Steel that “Most of our raw coal falls in the (on  

average) Washery Grade IV.” It may be mentioned that coal of  

Washery Grade IV has ash content between 28% and 35%. In  

the synopsis and lists of dates filed by Tata Steel in the appeals  

arising out of S.L.P.  (C) Nos.  8972-73 of 2014 it  is  stated as  

follows:

“The coal, when extracted in its raw form also known as ROM  contains high percentage of ash.  Though ROM is fit for many  purposes, it is not fit for the steel industry.”  

19. Even the Union of India in its affidavit filed by the Under  

Secretary in the Ministry of Coal in W.P. (C) No.1504 of 2009 in  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 12 of 50

                                                  

13

Page 13

the Jharkhand High Court states to the same effect,  namely,  

that ROM coal can be used as it is. It is stated in paragraph 11  

thereof as follows:

“Considering the fact that in case of coal,  where the entire  ROM can be generally made usable, the Respondents No. 1 &  2 are of the opinion that rule 64B and the rule 64C [of the  Mineral  Concession  Rules,  1960]  may  not  be  particularly  applicable on coal minerals.”  

20. Similarly, the State of Jharkhand in its affidavit filed in the  

same case has stated in paragraph 79 as follows:

“That with regard to the averments made by the petitioner in  Paragraphs  84  and  85  of  the  instant  writ  application  it  is  stated  and  submitted  that  it  is  not  necessary  that  coal  produced  from  a  mine  should  always  be  subjected  to  processing.   There  are  various  coal  mines  in  the  country  producing raw coal without any processing…….”

21. Therefore, while raw coal or unprocessed coal or ROM coal  

extracted by  Tata  Steel  being Washery  Grade IV  having  ash  

content between 28% and 35% can be used as it is for certain  

purposes, it requires to undergo a process of beneficiation to  

make  it  suitable  for  use  in  steel  making.  This  process  is  

undertaken by Tata Steel in its washeries in the leased areas.  

22. The  controversy  in  the  present  appeals  is,  therefore,  

limited to the question whether royalty is payable at the rate  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 13 of 50

                                                  

14

Page 14

mentioned  in  the  Second  Schedule  to  the  MMDR  Act  on  

processed coal,  that  is,  coal  consumed or  removed from the  

boundaries of the leased area in a beneficiated form or on the  

raw or unprocessed or ROM coal at the pit-head.    

23. That  the  controversy  is  limited  to  the  stage  at  which  

royalty is chargeable on coal is also clear from paragraph 17 of  

W.P.(C) No.2999 of 2008 filed by Tata Steel in the High Court  

wherein it is stated (though ROM coal can be used as it is) as  

follows:-   

“17. That the petitioner all along has been utilizing the entire  coal raised from the said West Bokaro Colliery for the purpose  of  treatment  and/or  washing  thereof  as  to  reduce  the  ash  percentage thereof with a view to use the same in its Steel  Plant, in as much as in the Steel plant only coking coal of high  grade which containing [contains] less ash can be used.”    

24. Similarly, in paragraph 31 of the counter affidavit filed by  

the Union of India in W.P.(C) No.1504 of 2009 in the High Court  

it is stated as follows:-

“31. That in reply to the statements made in para No.84 of the  Writ  Petition  the  Answering  Respondent  most  humbly  and  respectfully state that the applicability of Rule 64B and Rule  64C [of the Mineral Concession Rules, 1960] is necessary for  minerals  that need processing or beneficiation before being  used,  especially  metallic  minerals.  However,  [as  far  as]  its  applicability to coal minerals is concerned considering the fact  that in case of coal, where the entire ROM can be generally  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 14 of 50

                                                  

15

Page 15

made usable the Respondent No. 1 & 2 are of the opinion that  Rule 64B and Rule 64C may not be particularly applicable to  coal mineral.”    

25. It is quite clear from the above that raw or unprocessed or  

ROM coal at the pit-head can be used for certain purposes; it is  

also clear that as far as Tata Steel is concerned, Washery Grade  

IV  coal  that  it  extracts  needs  to  be  beneficiated  to  make  it  

usable in the steel industry and the controversy is limited to the  

issue of payment of royalty - whether it is payable on raw or  

unprocessed or ROM coal  at the pit-head or it  is  payable on  

processed Steel Grade coal.

Coal beneficiation

26. The  question  that,  therefore,  arises  is  what  is  the  

consequence of beneficiation?  Very briefly, the consequence of  

beneficiation of coal is upgrading or improving its quality from  

the ROM coal.  In the Convenience Volume handed over to us,  

with reference to beneficiation of coal, it is stated by Tata Steel  

as follows:9

“The  crushed  raw  coal  (ROM)  has  ash  percentage  varying  from 22% to 40% and moisture of 3% to 5%.  For use in Blast  

9 This has not been disputed by the State of Jharkhand

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 15 of 50

                                                  

16

Page 16

furnace  for  steel  making,  we  require  clean  coal  of  uniform  quality at low ash %.  So, Beneficiation of ROM raw coal is  done to reduce the ash content to bring up to Steel Grade  coal.  

ROM coal of various seams at coal mine is fed in to the Coal  washery (Beneficiation plant) for beneficiation so that the final  clean coal product has ash of below 15% (Steel Grade coal).

For coal beneficiation, gravity separation methods for coarser  (size 13 mm to 0.5 mm) material and froth floatation method  for finer material (size < 0.5 mm) are done.  

So,  before  beneficiation,  the  raw coal  is  crushed in  to  size  below 13  mm at  Coal  Handling  Plant  (Crushing Plant).  The  coarse material i.e. size from 13 mm to 0.5 mm is treated in  dense media cyclone whereas, less than 0.5 mm is treated by  froth  floatation  method.  As  beneficiation  is  a  wet  process  hence, it  increases the moisture percentage of beneficiated  coal by around 8% to 15%.  

After beneficiation, apart from the clean coal (required in Blast  furnace  for  Steel  making),  we  also  get  Coal  by-products  named as, middling (ash 40-45%), Tailings (ash 40-45%) and  Rejects (ash 60-65%).

The  product  quantity  after  beneficiation  process  gets  increased  due  to  wet  process  by  adding  moisture  into  the  output, shown by an example below –

Production (Extraction): The basis figure of production of 100  tonnes of ROM coal has been taken. Therefore, Quantity produced (extracted): = 100 tonnes

Beneficiation: The products are dewatered but still the surface  moisture  gets  adhered  to  the  product  generated.   The  beneficiation is a wet process i.e. raw coal mass flows through  different process in slurry form.  Output is measured on wet  process because it is transported on wet basis (with moisture).  Hence the output is more than the input of raw coal.  

Beneficiation process results in

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 16 of 50

                                                  

17

Page 17

Clean Coal; Middlings; Tailings; and Rejects

Thus 100 tonnes of raw coal will produce approximately 115  tonnes of washed product.

Output from collieries (Average Quantities):

Clean coal = 40 tonnes Middlings = 40 tonnes Tailings = 25 tonnes Rejects = 10 tonnes

Conclusion:     

It  is  quite  clear  that  beneficiation  process  (dense  media  gravity  separation  and  froth  floatation)  are  a  physical  separation process to separate higher ash coal and lower ash  coal, so no chemical changes are there in the coal mineral, as  there  are  no  chemical  reactions  involved  during  this  beneficiation process.   

Referring  below a  flow chart  [not  relevant]……..   From the  quantity  related  table,  it  is  also  quite  evident  that  due  to  addition of water during wet beneficiation, the summation of  beneficiated coal product quantity is higher than fed ROM coal  quantity.”

27. From this, it is quite clear that the beneficiation process,  

as far as coal is concerned, has two significant consequences –  

the grade of coal  improves (from Washery Grade IV it  could  

improve to Steel Grade I) and the weight of the coal increases  

(from 100 tons of raw ROM coal to 105 tons [excluding rejects]  

of beneficiated coal).  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 17 of 50

                                                  

18

Page 18

28. However, the process of beneficiation for other minerals  

does not result in the same consequence.  As mentioned by the  

Union of India in paragraph 9 of its counter affidavit  filed in  

W.P. (C) No. 1504 of 2009 in the High Court, the beneficiation  

of copper has different consequences. It is stated, in this regard  

as follows:

“It  is  stated that the mineral extracted during mining in its  primary state is called run of mine (ROM), which may or may  not be useable in its primary state depending on the minerals  and its grade.  In such a case where the entire ROM cannot be  used  generally,  there  is  a  level  of  processing  required  to  beneficiate the ROM to enhance the grade ore and also take  out  waste  material  occurring  with  the  ore.   Rule  64B  is  specifically applicable in such class of minerals where only a  part of the entire ROM mineral extracted through mining can  be used. For example, in the case of copper ore, in which the  metal contained in ore is in the range of 1% to 2% of the ROM  the ROM is converted into a high as 25%, before it is sent out  the lease area for refining and smelting.  In such cases, the  rule  64B of  MCR provides for  royalty  to be charged by the  State Government on the higher grade of ore that is  being  taken  out  of  the  lease  area,  in  terms  of  the  royalty  rate  prescribed in Second Schedule to the MMDR Act. Rule 64B of  MCR does not specify the royalty rates and its applicability is  only  to  the  extent  of  facilitating  levy  or  royalty  on  the  processed  ore  removed  from  the  lease  area,  and  not  the  mineral  consumed  in  the  lease  area.  Further  royalty  is  required to be paid as per the rates notified by the Central  Government in Second Schedule to the MMDR Act. Rule 64B of  MCR is  therefore applicable  in case of  such minerals  which  cannot be used without processing.

Similarly,  rule  64B  [rule  64C]  of  the  MCR is  applicable  on  removal of tailings or rejects from leased area for dumping  and restricts levy on royalty on tailings or rejects.  However,  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 18 of 50

                                                  

19

Page 19

levy  of  royalty  is  applicable  only  in  case  such  tailings  or  rejects  subsequently  used  for  sale  or  consumption.  For  example, tailing from copper concentrate are likely to contain  silver.

However, royalty on silver generally cannot be levied till silver  is extracted from the tailings and sold or consumed.  Rule 64C  is  therefore  applicable  on  such  cases  of  minerals,  where  tailings or rejects generated during mining or processing are  likely to be dumped due to its limited use.”

29. In other words, the ROM copper ore contains hardly 1% or  

2% of  copper but  after  the beneficiation process the copper  

extract from the ore increases to about 25%. It  is thereafter  

sent  for  refining  and  smelting.  In  other  words,  copper  ore  

cannot be utilized as it is or in the ROM state – it must undergo  

a beneficiation process from the ore and can then be used.

30. As  mentioned  in  SAIL the  consequences  of  processing  

dolomite or limestone has a consequence different from that of  

copper ore, namely, mere removal of waste and foreign matter.  

It appears that this process does not improve the quality of the  

dolomite or the limestone, though with the removal of waste  

and foreign matter,  the weight would decrease somewhat.  It  

may  be  mentioned  that  royalty  is  charged  on  dolomite  and  

limestone on a tonnage basis.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 19 of 50

                                                  

20

Page 20

31. It is in this context that the nature of the mineral and the  

stage at which royalty is to be computed become important.  

The basis of levy would have to be rational and it might have  

different consequences at different stages.  

Computation of royalty

32. As far as the computation of royalty on coal is concerned,  

Tata Steel has given details of the methodology of computation  

in  the  Convenience  Volume  handed  over  to  us.10  For  the  

purposes  of  computing  the  royalty  amount,  the  quantities  

assumed by Tata Steel are given below.  

33. It is said that 100 tons of raw coal post-beneficiation will  

produce approximately 115 tons of the washed products. The  

break-up of this is as follows:

Clean coal = 40 tons Middlings = 40 tons Tailings = 25 tons Rejects = 10 tons

34. The computations made by Tata Steel are on the basis of  

the  above  assumptions.  The  rate  of  royalty  is  given  in  the  

Notification  dated  14th October,  1994  amending  the  Second  10 This has not been disputed by the State of Jharkhand.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 20 of 50

                                                  

21

Page 21

Schedule  to  the  MMDR  Act.  For  coking  coal  Steel  Grade  I,  

coking coal Steel Grade II and coking coal Washery  Grade II  

the rate of  

royalty is Rs.195/- per ton. For coking coal Washery Grade IV  

the rate of royalty is Rs.95/- per ton.

35. Therefore,  for  every  100  tons  of  coking  coal  Washery  

Grade IV extracted by Tata Steel, the royalty payable on ROM  

coal  was  Rs.9500/-  with  effect  from  14th October,  1994.  

However,  if  the  royalty  were  to  be  computed  on  post-

beneficiation coal, the royalty payable by Tata Steel would work  

out to:

Product Grade Quantity  (tons)

Royalty rate  (Rs/ton)

Amount  (in Rs)

Clean coal Steel Grade I 40 195 7800 Middlings Grade E 40 70 2800 Tailings Grade D 25 70 1750 Royalty  payable

105 12350

Since rejects were ungraded and no rate was prescribed, no royalty was  payable on rejects.    36. Based on the above computation, the difference in royalty  

on  post-beneficiation  coal  (as  claimed  by  the  State  of  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 21 of 50

                                                  

22

Page 22

Jharkhand)  and  on  ROM  coal  (as  claimed  by  Tata  Steel)  is  

Rs.2850/- per 100 tons of coal extracted (12350 minus 9500 =  

2850).  

37. This position continued till August 2002 when the Second  

Schedule  to  the  MMDR  Act  was  amended  by  a  notification  

dated 16th August, 2002.   

38. In terms of the notification dated 16th August,  2002 the  

rate of royalty for coking coal Steel Grade I, coking coal Steel  

Grade  II  and  coking  coal  Washery  Grade  II  was  raised  to  

Rs.250/- per ton. For coking coal Washery Grade IV the rate of  

royalty was raised to Rs.115/- per ton.

39. Therefore,  for  every  100  tons  of  coking  coal  Washery  

Grade IV extracted by Tata Steel, the royalty payable on ROM  

coal  was  Rs.11500/-  with  effect  from  16th August,  2002.  

However,  if  the  royalty  were  to  be  computed  on  post-

beneficiation coal, the royalty payable by Tata Steel would work  

out to:

Product Grade Quantity  (tons)

Royalty rate  (Rs/ton)

Amoun t  

(in Rs)

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 22 of 50

                                                  

23

Page 23

Clean coal Steel Grade I 40 250 10000 Middlings Grade E 40 85 3400 Tailings Grade D 25 85 2125 Royalty  payable

105 15525

Rejects have not been included in this calculation.

40. Based on the above computation, the difference in royalty  

on  post-beneficiation  coal  (as  claimed  by  the  State  of  

Jharkhand)  and  on  ROM  coal  (as  claimed  by  Tata  Steel)  is  

Rs.4025/- per 100 tons of coal extracted (15525 minus 11500 =  

4025).  

41. This position continued till August 2007 when the Second  

Schedule  to  the  MMDR  Act  was  amended  by  a  notification  

dated 1st August,  2007.  Through this  notification the  rate  of  

royalty on coal became a combination of a specific rate and an  

ad valorem rate, the formula for calculation being R = a + bP  

where ‘R’ is the royalty in Rs. per ton, ‘a’ is a fixed component,  

‘b’ is a variable or  ad valorem component and ‘P’ is the basic  

pit-head price of ROM coal.

42. The notification provides that for computing royalty (R) on  

Steel Grade I coal, a = Rs.180; b = 5% of ‘P’; P = basic pit-head  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 23 of 50

                                                  

24

Page 24

price  of  ROM coal  as  reflected  in  the  invoice.  Similarly,  for  

payment of royalty (R) on Washery Grade IV coal, a = Rs.90; b  

= 5% of ‘P’; P = basic pit-head price of ROM coal as reflected in  

the invoice.  

43. Tata Steel gives the computation arrived at on the basis of  

the above notification in the Convenience Volume as follows:

“As Tata Steel is not selling ROM, hence we take the prices  notified by CIL [Coal India Limited] for its various collieries. For  example,  we apply the prices notified by Coal  India Ltd for  Central Coalfields Ltd. In the Price Notification No.181 dated  15.10.2009 for CCL, the basic price for ROM Washery Grade IV  is Rs.1120.11

Product Grade Quantity  (in tons)

Royalty  rate  

(a+bP)

Royalty  (Rs. per  

ton

Amount  (in Rs)

Clean coal Steel  Grade I

40 180+5% of  1120

236 9440

Middlings Grade E 40 70+5%  of 790

116 4400

Tailings Grade D 25 70+5%  of 1000

120 3000

Royalty  payable

105 16840

Rejects have not been included in this calculation.

If we were to pay on RoM: 11 Since Tata Steel is not selling ROM coal, the price notified by the Coal India Ltd. for its  various collieries has been taken by Tata Steel as the basic price for ROM Washery Grade  IV as Rs.1120/-.  In terms of the communication dated 16th October, 2009 issued by the  Central  Coalfields Limited, Sales & Marketing Division, Darbhanga House, Ranchi  with  reference to Price Notification No.1181 dated 15th October, 2009 the pit-head/basic price  of Run of Mine (ROM) coal for Washery Grade IV stood revised from 1020 (in Rupees per  tonne) to 1120. This is the figure taken by Tata Steel in its computations given in the  Convenience Volume.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 24 of 50

                                                  

25

Page 25

Washery Grade IV: 90+5% of 1120 (56) (Rs.146 per ton) =  Rs.14600/-”

44. Based on the above computation, the difference in royalty  

payable on post-beneficiation coal (as claimed by the State of  

Jharkhand)  and  on  ROM  coal  (as  claimed  by  Tata  Steel)  is  

Rs.2240/- per 100 tons of coal extracted (16840 minus 14600 =  

2240).

45. We have been given to understand that this position has  

undergone changes, but we are not concerned with them.

46. To summarize the computations, the royalty as computed  

by the State and as computed by Tata Steel is as follows:

Royalty  payable in  Rs.

Period  (from  date)

On beneficiated  coal (per 100  

tons)

On ROM  coal (per  100 tons)

Difference  (per 100  

tons) Royalty  payable  

14.10.199 4

12350 9500 2850

Royalty  payable

16.8.2002 15525 11500 4025

Royalty  payable

1.8.2007 16840 14600 2240

 47. As  is  quite  obvious,  the  difference  in  royalty  payable  

would run into huge figures particularly since coal is mined in  

millions of tons.  

Discussion

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 25 of 50

                                                  

26

Page 26

48. Two  interpretations  have  been  given  to  removal  of  a  

mineral from the leased area as postulated in Sections 9(1) and  

9(2) of the MMDR Act.

49. The first is a literal meaning given by the Patna High Court  

in its judgment and order dated 7th August, 1990.  The High  

Court gave a literal interpretation to Section 9(2) of the MMDR  

Act and effectively interpreted the removal of a mineral from  

the leased area as removal from the boundaries of the leased  

area.  On this basis, it was concluded that since beneficiated  

coal is removed from the leased area, Tata Steel is liable to pay  

royalty on the weight of the beneficiated coal.   

50. The  second  interpretation  is  a  somewhat  restrictive  

interpretation given by the Orissa High Court in National Coal  

Development Corporation Limited.  In that case, it was held  

that:

“The  incidence  of  royalty  under  the  general  tenor  of  the  scheme [of Section 9 of the MMDR Act] arises when coal is  severed from the seam in its natural state within the mine and  removed outside.   Removal  [of  coal]  from the seam in the  mine and extracting the same through the pit’s mouth to the  surface satisfies the requirement of Section 9 [of the MMDR  Act] in order to give rise to liability for royalty.”   

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 26 of 50

                                                  

27

Page 27

51. In other words, the Orissa High Court did not accept the  

literal meaning of removal from the leased area occurring in  

Section 9 of the MMDR Act as removal from the boundaries of  

the leased area but gave a restricted interpretation to removal  

from the leased area as extraction of the coal from the seam in  

the mine which is in the leased area, that is, extraction from  

the pit-head. This restricted interpretation was accepted by this  

court  in  the  appeal  filed  by  National  Coal  Development  

Corporation  and  on  that  basis  this  court  also  upheld  the  

payment of royalty by the lease holder on coal consumed by  

the  workmen of  the  Corporation  prior  to  the  amendment  of  

Section 9 of the MMDR Act in 1972.12

52. Both  the  interpretations  mentioned  above  relating  to  

removal from the leased area, literal and restricted, were given  

in the context of extraction of coal.

53. The controversy regarding the interpretation of removal of  

a mineral (not coal) from the leased area again came up for  

consideration  in  a  petition  filed  by  SAIL  in  the  Orissa  High  

12 National Coal Development Corporation Ltd. v. State of Orissa, (1998) 6 SCC 480

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 27 of 50

                                                  

28

Page 28

Court. This petition concerned itself with the payment of royalty  

on dolomite and limestone. While referring to Section 9(1) of  

the MMDR Act and the lease deed of SAIL, the Orissa High Court  

held as follows:-

“A distinction has to be made between removal from the mine  and  removal  from  the  leased  area.  If  after  the  mineral  is  extracted from the mine, it undergoes some processing and  during processing,  a part  of  the mineral  is  wasted and the  wastage  remains  on  the  leased  area  and  is  not  removed  therefrom, the lessee cannot be asked to pay royalty on that  portion of the wastage.”13

54. In  other  words,  the  Orissa  High  Court  took  the  literal  

interpretation  given  to  removal  from  the  leased  area  as  

removal  from  the  boundaries  of  the  leased  area,  virtually  

reiterating  the  literal  interpretation  given  by  the  Patna  High  

Court in its judgment and order dated 7th August, 1990.

55. This court in the appeal filed by SAIL did not get into the  

question of removal of the mineral from the boundaries of the  

leased area but noted that the extracted mineral undergoes a  

process  of  removal  of  waste and foreign matter  before  it  is  

removed from the boundaries of the leased area. The decision  

of this court on the levy of royalty turned on the consumption  13 The decision of the Orissa High Court does not appear to have been reported.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 28 of 50

                                                  

29

Page 29

of the mineral through that process carried out by the holder of  

the mining lease.  In that context it was held in SAIL that since  

the process of removal of waste and foreign matter amounts to  

consumption, the entire extracted mineral is exigible to royalty.  

It was held:-

“Section 9(1) of the Act also contemplates the levy of royalty  on the mineral consumed by the holder of a mining lease in  the leased area.  If that be so, the case of the appellants that  such processing amounts to consumption and, therefore, the  entire  mineral  is  exigible  to  levy  of  royalty  has  to  be  accepted.”

56. It  is  quite  clear  that  SAIL  did  not  consider  (and  then  

reject)  the  reasoning  given  by  the  Orissa  High  Court  that  

royalty  is  not  payable  on  wastage  that  remains  within  the  

boundaries of the leased area. This was critically adverted to in  

an order dated 25th July, 2006 in C.A. No.5651 of 200514 on the  

ground, inter alia, that the distinction made by the Orissa High  

Court between removal of a mineral from a mine and removal  

from a leased area has been rejected without any reason. This  

is what this court had to say:

14 M/s Central Coalfields Ltd. v. State of Jharkhand decided by this court

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 29 of 50

                                                  

30

Page 30

“A bare reading of this Court’s judgment in Steel Authority of  India’s  case  (supra)  indicates  that  there  is  practically  no  reason indicated as to why the distinction made by the High  Court was found to be unacceptable. As was noticed by the  High Court  in  the impugned judgment in  the said case the  distinction  is  certainly  of  relevance.  As  we  are  unable  to  subscribe to the view expressed in Steel Authority of India’s  case (supra), we refer the matter to a larger Bench. Records  may be placed before Hon’ble  the Chief  Justice of  India for  necessary directions.”

57. We may also mention at this stage that  SAIL has been  

politely  distinguished  in  National  Mineral  Development  

Corporation Ltd. v. State of M.P. (or NMDC).15  

58. In sum and substance this is the issue before us, namely,  

whether for the purposes of payment of royalty, removal of a  

mineral as mentioned in Section 9 of the MMDR Act must be  

restrictively interpreted as removal or extraction of the mineral  

from the  mine  or  the  pit-head  or  a  literal  interpretation  as  

removal of the mineral from the boundaries of the leased area.

59. In  NMDC  the  question  before  this  court  was  whether  

“slimes” are exigible to royalty, as forming part and parcel of  

iron ore.

60. The Second Schedule to the MMDR Act provides rates of  

royalty and Entry 23 relates to iron ore.  Royalty is payable on  15 (2004) 6 SCC 281

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 30 of 50

                                                  

31

Page 31

lumps, fines and concentrates.  In the process of mining, iron  

ore is extracted and separated into ore lumps, fines and waste  

material  which  is  commonly  known  as  “slime”,  that  is  the  

resultant  waste  material  from  the  wet  screening  process  

undertaken for segregation of lumps and fines.  When the issue  

of exigibility of “slimes” was raised in the High Court,16 it was  

held that royalty is payable on the mineral as extracted and  

removed or consumed from the leased area.  The High Court  

also relied upon  SAIL to hold that the entire quantity of ROM  

iron ore as extracted from the earth shall be liable to payment  

of royalty.

61. While disagreeing with the view taken by the High Court, it  

was held by this court that if Section 9 of the MMDR Act was to  

be  read  in  isolation,  perhaps,  the  total  quantity  of  mineral  

removed from the leased area or consumed in the process of  

beneficiating iron ore would have been liable for payment of  

royalty and that quantity may have included the quantity of  

slimes as held in  SAIL. But,  this court went on to hold that  16 The decision of the High Court is reported as AIR 1999 MP 112

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 31 of 50

                                                  

32

Page 32

Section 9 of the MMDR Act cannot be read in isolation and the  

Second Schedule to the MMDR Act must be read as a part and  

parcel of Section 9 of the said Act.  It was also held that though  

the  Parliament  was  fully  aware  that  iron  ore  would  have  to  

undergo  a  process  which  would  lead  to  the  emergence  of  

lumps,  fines,  concentrates  and  slimes  yet  it  chose  to  leave  

slimes out of consideration for the payment of royalty.  For this  

reason, it was held that royalty was not payable on slimes.

62. This court also proceeded to consider Rule 64B and Rule  

64C of the MCR and held that in the case of iron ore the levy of  

royalty is postponed until  the beneficiation process has been  

undertaken and it is only then that royalty is capable of being  

quantified on the quantity of lumps, fines and concentrates.

63. The decision of this court in  SAIL  was also distinguished  

by holding that the removal of waste and foreign matter in the  

processing  of  dolomite  and  limestone  did  not  result  in  any  

removal  from the  leased  area  but  that  the  run-of-mine  was  

itself consumed in the processing in the leased area, thereby  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 32 of 50

                                                  

33

Page 33

making a distinction between removal from the leased area and  

consumption within the leased area.

64.   NMDC has analyzed the scope of Section 9 of the MMDR  

Act in conjunction with the Second Schedule to the MMDR Act.  

It was held that there is no conflict between the two and that  

Section 9 of the MMDR Act cannot be read in isolation but that  

the Second Schedule to the MMDR Act must be read as a part  

and parcel of Section 9 of the MMDR Act.  Paragraphs 23 and  

24 of the Report are significant and they read as follows:

“23.  Section 9 is  not the beginning and end of  the levy of  royalty. The royalty has to be quantified for purpose of levy  and that cannot be done unless the provisions of the Second  Schedule  are  taken  into  consideration.  For  the  purpose  of  levying any charge, not only has the charge to be authorised  by law, it has also to be computed. The charging provision and  the computation provision may be found at one place or at  two  different  places  depending  on  the  draftsman’s  art  of  drafting and methodology employed. In the latter case, the  charging  provision  and  the  computation  provision,  though  placed in two parts of the enactment, shall have to be read  together  as  constituting  one  integrated  provision.  The  charging  provision  and  the  computation  provision  do  differ  qualitatively.  In  case  of  conflict,  the  computation  provision  shall give way to the charging provision. In case of doubt or  ambiguity the computing provision shall be so interpreted as  to  act  in  aid  of  charging provision.  If  the two can be read  together homogeneously then both shall  be given effect to,  more so, when it is clear from the computation provision that  it is meant to supplement the charging provision and is, on its  own,  a  substantive  provision  in  the  sense  that  but  for  the  computation provision the charging provision alone would not  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 33 of 50

                                                  

34

Page 34

work.  The  computing  provision  cannot  be  treated  as  mere  surplusage  or  of  no  significance;  what  necessarily  flows  therefrom shall also have to be given effect to.

24. Applying the abovestated principle, it is clear that Section  9 neither prescribes the rate of royalty nor does it lay down  how the royalty shall be computed. The rate of royalty and its  computation  methodology  are  to  be  found  in  the  Second  Schedule  and  therefore  the  reading  of  Section  9  which  authorises  charging  of  royalty  cannot  be  complete  unless  what is specified in the Second Schedule is also read as part  and parcel of Section 9.”

65. It is clear therefore that Section 9 of the MMDR Act has to  

be  read  and  understood  in  conjunction  with  the  Second  

Schedule to the MMDR Act. There is a good reason for it, which  

is  that  the  scheme  of  the  levy  of  royalty  cannot  be  

straitjacketed in view of the variety of minerals to which the  

MMDR Act applies and for the extraction of which royalty has to  

be paid.  

66. In the case of coal, it has been noted that “Though ROM  

[coal]  is  fit  for  many  purposes,  it  is  not  fit  for  the  steel  

industry”; “in case of coal … the entire ROM can be generally  

made usable” and “it is not necessary that coal produced from  

a mine should always be subjected to processing.  There are  

various coal mines in the country producing raw coal without  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 34 of 50

                                                  

35

Page 35

any processing…….” This is to say that ROM coal can generally  

be used in the raw form without processing and beneficiation is  

not at all necessary. However, if the raw coal is to be utilized  

for some specialized purposes it would need beneficiation.

67. On the other hand, in the case of dolomite or limestone  

(subject matter of SAIL) the process described in paragraph 4  

of  the  Report  is  undertaken  not  to  upgrade  or  improve  the  

quality of the mineral but to remove waste and foreign matter.  

It is not clear whether dolomite or limestone can be utilized as  

it is or in the ROM state without removal of waste and foreign  

matter. That question was adverted to by the Orissa High Court  

but not considered by this court, hence the critical reference.  

As mentioned above, the decision in  SAIL was based not on  

removal but on consumption of the mineral.17 On the basis of  17 In National Mineral Development Corpn. Ltd. v. State of M.P. this court   observed in paragraph 34 of the Report  as follows:

“Both these minerals [dolomite and limestone] were utilised as raw material by  the mining lessees on the leased area itself. The mining lessee claimed that dolomite  and limestone having been extracted from the mine underwent processing wherein a  part of the mineral was wasted and the wastage remained on the leased area and not  removed  therefrom.  The  contention  of  the  lessee  was  that  royalty  could  not  be  demanded on that portion of the wastage which was  not removed from the mining  area. This contention was repelled by this Court by reference to Section 9(1) of the  Act  which  speaks  of  payment  of  royalty  in  respect  of  any  mineral  removed  or  consumed by the lessee. The Court held that though the impurities part of dolomite  and limestone were not removed from the leased area but that would not make any  difference as the run-of-mine was itself consumed in the processing on the leased  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 35 of 50

                                                  

36

Page 36

the mineral extracted and the decision rendered by this court,  

therefore,  no similarity can be found between  SAIL  (case of  

consumption) and National Coal Development Corporation  

Limited (case  of  removal)  although  royalty  is  charged  on  

dolomite and limestone, as in coal, on a per ton basis.   

68. Iron ore (with which NMDC is concerned) falls in the same  

generic category for levy of royalty as dolomite, limestone and  

coal namely on a tonnage basis but there is a crucial difference  

between iron ore and coal (as also between dolomite, limestone  

and iron ore). In the case of iron ore, beneficiation is necessary  

before it can be utilized. It has been observed in NMDC that “in  

iron ore production the run-of-mine (ROM) is in a very crude  

form. A lot of waste material called “impurities” accompanies  

the iron ore. The ore has to be upgraded. Upgrading the ores is  

called  “beneficiation”.  That  saves  the  cost  of  transportation.  

Different  processes  have  been  developed  by  science  and  

technology  and  accepted  and  adopted  in  different  iron  ore  

area.”

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 36 of 50

                                                  

37

Page 37

projects for the purpose of beneficiation.”18 It is for this reason,  

inter alia, that the levy of royalty on iron ore is postponed, as  

held in NMDC, to a post-beneficiation stage.  

69. In the case of coal,  beneficiation is not necessary since  

ROM coal can be used as it is straight from the pit-head.  In the  

case  of   iron  ore,  as  noticed  in  NMDC, waste  material  is  

removed  from  the  extracted  iron  ore  and  through  the  

beneficiation  process  the  ore  is  upgraded.   The  removal  of  

waste material obviously reduces the weight of the iron ore and  

that is why it saves the cost of transportation as observed in  

NMDC. However, in the case of coal apart from the fact that  

beneficiation is not necessary, if the lease holder does in fact  

beneficiate the coal, the weight of the beneficiated coal is more  

than  the  ROM coal  as  has  been  noted  above.   This  would,  

therefore, increase the cost of transportation which is based on  

the weight of the coal.  Under the circumstances,  removal of  

beneficiated  coal  as  against  ROM  coal  might  work  to  the  

disadvantage of the lease holder. For this reason, no similarity  

18 National Mineral Development Corporation Ltd v. State of M.P. paragraph 28.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 37 of 50

                                                  

38

Page 38

can be found between coal and iron ore or between coal and  

dolomite and limestone (apart from the fact that SAIL did not  

deal with removal from the leased area but consumption within  

the leased area).

70. There  are  therefore,  three  categories  of  minerals  dealt  

with by this court – coal that can be utilized in the raw or ROM  

stage straight from the pit-head, iron ore that cannot be utilized  

in the raw or ROM stage and needs beneficiation and dolomite  

and limestone about which it  is  not  clear  whether  it  can be  

utilized in the raw or ROM stage.

71. On  the  other  hand,  there  are  other  minerals  such  as  

copper, gold, lead, zinc and several others where the rate and  

computation  of  royalty  payable  are  arrived  on  a  completely  

different basis. The table below of some sample minerals taken  

from the  Second  Schedule  to  the  MMDR Act  illustrates  this  

position19 and it also illustrates that waste or foreign matter in  

respect of these minerals is much more than someone not in  

the business of extraction of minerals could imagine: 19 This has undergone further changes. These figures have been taken since they pertain  to the period when the dispute arose in the cases referred to.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 38 of 50

                                                  

39

Page 39

Entr y

Mineral Rate as per  Notification of 5th May,  

1987

Rate as per Notification  of 17th February, 1992

7 Cadmium Sixteen rupees per unit  percent of cadmium  metal per ton of ore and  on pro rata basis

Seventy four rupees per  unit percent of cadmium  metal per ton of ore and on  pro rata basis

12 Copper  ore

Five rupees per unit  percent of copper metal  contained per ton of ore  and on pro rata basis

Seventeen rupees per unit  percent of copper metal  contained per ton of ore  and on pro rata basis

21 Gold Two rupees per one gram  of contained gold per ton  of ore and on pro rata  basis

(a) Eleven rupees per one  gram of contained gold per  ton of ore and on pro rata  basis (b) by product gold ten  rupees per gram

27 Lead ore Three rupees per unit  percent of contained lead  metal per ton of ore and  on pro rata basis

Eight rupees per unit  percent of contained lead  metal per ton of ore and on  pro rata basis

28 Zinc ore Six rupees per unit  percent of zinc metal  contained per ton of ore  and on pro rata basis

Sixteen rupees per unit  percent of zinc metal  contained per ton of ore  and on pro rata basis

  72. What follows from this discussion is that though royalty  

may have a definite connotation, the rate of royalty, its method  

of computation and the final levy are different from mineral to  

mineral. It is for this reason that this court held in NMDC that  

the Second Schedule to the MMDR Act has to be read as a part  

and parcel of Section 9 of that Act. If the general conclusion of  

SAIL is to be applied across the board without reference to the  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 39 of 50

                                                  

40

Page 40

Second Schedule to the MMDR Act,  calculation of  royalty on  

copper, gold, lead, zinc and some other minerals would become  

impossible.  

73. It is quite clear that the issue of computation of royalty on  

minerals is rather complex and it is best left to the experts in  

the field and it cannot be painted with a broad brush as has  

been done in  SAIL. That decision must be confined to its own  

facts with reference to consumption of dolomite and limestone.  

Since the Second Schedule to the MMDR Act must be read as a  

part and parcel of Section 9 thereof, the interpretation given in  

SAIL possibly cannot apply to the computation of royalty for  

every mineral, as discussed above.  

74. At  this  stage,  it  is  necessary  to  refer  to  an unreported  

decision of this court.20 That decision pertains to the removal of  

coal  in  relation to Section 9 of  the MMDR Act.  Interestingly,  

though a reference was made to  SAIL this court adopted the  

view expressed  by  the  Orissa  High  Court  in  National  Coal  

Development Corporation Limited which was endorsed by  20 Central Coalfields Ltd. v. State of Jharkhand, C.A. No.8395 of 2001 decided by three  learned judges on 24th September, 2003

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 40 of 50

                                                  

41

Page 41

this court in appeal. The ‘reasons’ given in SAIL were not even  

adverted to. This unreported decision reads as follows:

“The contention put forth in this case is that for the purpose of  Section 9 of the Mines & Mineral (Regulation & Development)  Act, 1957 the expression ‘removal’ would mean that it is not  enough  to  extract  the  mineral  from  pit  but  should  be  dispatched out of the leased area.  In our view word ‘removal’  would mean extracting the mineral from the pit’s mouth after  removal  from  the  seam.    This  exact  point  has  been  considered  by  this  Court  in  State  of  Orissa  and Ors.  v.  Steel Authority of India Ltd. – (1998) 6 SCC 476 in which  this Court has stated as follows:

“Another  Division  Bench  of  the  Orissa  High  Court  in  National  Coal  Development  Corpn.  case  while  considering the question whether the coal extracted by  the  workmen  for  their  own  domestic  consumption  is  exigible to levy of royalty, accepting the contention of  the Revenue held “that removal from the seam in the  mine and extracting the same through the pit’s mouth  to the surface satisfy the requirement of  Section 9 in  order to give rise to liability for royalty.” This view of the  High Court found approval by this Court in National Coal  case (C.A. No.807 of 1976 decided on 5.12.1991) and  this Court held that the lessee in that case was liable to  pay  royalty  for  the  coal  supplied  to  its  workmen  for  consumption.”

In this view of the matter we find no substance in the matter.   The appeal is dismissed accordingly.”  

75. In view of the decision of this court in Central Coalfields  

Ltd. the issue is no longer  res integra and in so far as coal is  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 41 of 50

                                                  

42

Page 42

concerned,  its  “removal  from  the  seam  in  the  mine  and  

extracting  the  same through  the  pit’s  mouth  to  the  surface  

[satisfies] the requirement of Section 9 in order to give rise to  

liability for royalty.”

Rule 64B and Rule 64C of the Mineral Concession Rules

76. The complexities of chargeability, computation and levy of  

royalty on different minerals have now been simplified, clarified  

and standardized with the insertion of Rule 64B and Rule 64C of  

the MCR with effect from 25th September, 2000.21   

77. A plain reading of Rule 64B of the MCR, with which we are  

presently  concerned,  clearly  suggests  that  the  leased  area  

mentioned  therein  has  reference  to  the  boundaries  of  the  

leased area given to a lease holder.  Sub-rule (1) provides that  

21 64B. Charging of Royalty in case of minerals subjected to processing: (1)   In  case of  processing of  run-of-mine mineral  is carried out within the leased area, then  royalty shall be chargeable on the processed mineral removed from the leased area.

(2)   In case run-of mine mineral is removed from the leased area to a processing  plant which is located outside the leased area, then, royalty shall be chargeable on the  unprocessed run-of-mine mineral and not on the processed product.

64C. Royalty on tailings or rejects: On removal of tailings or rejects from the  leased area  for  dumping and not  for  sale  or  consumption,  outside  leased area such  tailings or rejects shall not be liable for payment of royalty:      

Provided  that  in  case  so  dumped  tailings  or  rejects  are  used  for  sale  or  consumption on any later date after the date of such dumping, then, such tailings or  rejects shall be liable for payment of royalty.

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 42 of 50

                                                  

43

Page 43

if the ROM mineral is processed within the boundaries of that  

leased area, then royalty will be chargeable on the processed  

mineral  removed  from  the  boundaries  of  the  leased  area.  

However,  if  the ROM mineral  is  removed without  processing  

from the boundaries of the leased area then in terms of sub-

rule  (2)  royalty  will  be chargeable on  the unprocessed ROM  

mineral.  Rule  64B  of  the  MCR  is  silent  about  removal  of  a  

mineral from the mine/pit-head but which is not removed from  

the boundaries of the leased area.  This is a clear pointer that  

royalty is to be paid by the lease holder only on removal of the  

mineral  from  the  boundaries  of  the  leased  area.   This  

simplification  and  clarification  takes  care  of  some  of  the  

different and difficult situations that we have referred to above,  

namely, the stage of charging royalty on coal at the pit-head or  

post-beneficiation, the stage of charging royalty on iron ore at  

the pit-head or post-beneficiation, the stage of charging royalty  

on dolomite and limestone at the pit-head or after the removal  

of waste and foreign matter and of course the stage of charging  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 43 of 50

                                                  

44

Page 44

royalty on other minerals such as copper, gold, lead and zinc  

amongst others.

78. Similarly,  Rule  64C  of  the  MCR  relates  to  royalty  on  

tailings  or  rejects.  As  far  as  Tata  Steel  is  concerned,  its  

computation given in the Convenience Volume indicates that  

royalty is paid and payable on middlings and tailings.  Rule 64C  

of the MCR makes it  clear that royalty is  payable on rejects  

when they are sold or consumed after being dumped.  This will  

take  care  of  situations  such  as  that  pertaining  to  silver,  as  

mentioned in the affidavit of the Union of India.

79. There is nothing to indicate in Rule 64B and Rule 64C of  

the MCR that coal has been put on a different pedestal from  

other  minerals  mentioned  in  the  MMDR  Act  read  with  the  

Second Schedule thereto.  It is, therefore, difficult to accept the  

view canvassed by the Union of India that these rules “may not  

be particularly applicable on coal minerals.”  That apart,  the  

stand of the Union of India is not definite or categorical (“may  

not  be”).   In  any  event,  we  are  not  bound  to  accept  the  

interpretation given by the Union of India to Rule 64B and Rule  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 44 of 50

                                                  

45

Page 45

64C of the MCR as excluding only coal.   On the contrary, in  

NMDC this court has observed that these rules are general in  

nature, applicable to all types of minerals, which includes coal.  

The expression of opinion by the Union of India is contrary to  

the observations of this court.

80. Therefore, on a plain reading of Rule 64B and Rule 64C of  

the  MCR,  we  are  of  the  opinion  that  with  effect  from  25 th  

September, 2000 when these rules were inserted in the MCR,  

royalty is payable on all  minerals including coal at the stage  

mentioned in these rules,  that is,  on removal of the mineral  

from the boundaries of the leased area. For the period prior to  

that, the law laid down in Central Coalfields Ltd. will operate,  

as far as coal is concerned, from 10th August, 1998 when SAIL  

was decided, though for different reasons.

81. We may mention that learned counsel for Tata Steel had  

reserved his right to challenge the constitutionality of Rule 64B  

and Rule 64C of the MCR should his interpretation of the law be  

not accepted, namely that royalty on coal is chargeable on the  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 45 of 50

                                                  

46

Page 46

extracted tonnage at the pit-head.  Since we have not accepted  

this interpretation post the insertion of Rule 64B and Rule 64C  

in the MCR, we leave it  open to Tata Steel  to challenge the  

constitutionality of these rules either by reviving these appeals  

to this limited extent or by initiating fresh proceedings.

Appeals filed by TISCO

82. The issue about refund of excess royalty paid by TISCO  

arises  only  for  the  period  from 10th August,  1998 when this  

Court delivered its judgment and order in SAIL.

83. The claim for refund has been rejected by the High Court  

in its judgment and order dated 23rd July, 2002 in the following  

words:-

“However,  in  view of  the fact  that  the State [of  Bihar]  has  been reorganized since 15th November, 2000, now in place of  ‘State of Bihar’, ‘State of Jharkhand’ will be charging royalty,  the appellant – TISCO shall not ask for refund of excess royalty  if deposited.”

84. A perusal of the above indicates that the High Court really  

gave no reason for denying the refund of the excess royalty  

paid by TISCO.  For the reasons given in respect of Tata Steel  

keeping in view the decision rendered in  Central Coalfields  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 46 of 50

                                                  

47

Page 47

Ltd., we hold that TISCO is entitled to refund of royalty paid  

from 10th August, 1998 to 25th September, 2000. However, this  

amount need not be physically refunded but should be adjusted  

pro rata against future payments of royalty by TISCO over the  

next one year. TISCO is not entitled to refund of royalty paid  

after 25th September, 2000.  The royalty paid by TISCO after  

25th September,  2000  was  correctly  paid  and  in  accordance  

with Rule 64B and Rule 64C of the MCR, which have not been  

challenged by TISCO.   

85. We make it clear that we have not adverted to the issue of  

consumption  of  coal  within  the  boundaries  of  the  leased  

premises since that question does not arise in these appeals.

86. No other contention was urged before us.

Conclusion

87. Our conclusions are as follows:-

(1)The decision rendered in SAIL is confined to its own facts  

and to the minerals dolomite and limestone.  The decision  

does not deal with removal of a mineral from the leased  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 47 of 50

                                                  

48

Page 48

area but deals with consumption within the leased area.

(2)The  unreported  decision  of  this  court  in  Central  

Coalfields Ltd. approves the law laid down by the Orissa  

High  Court  in  National  Coal  Development  

Corporation Ltd. to the effect that removal of coal from  

the seam in the mine and extracting it through the pit-

head to the surface satisfies the requirements of Section  

9 of the MMDR Act in order to give rise to a liability for  

royalty.  This view was earlier approved by this court in  

National Coal Development Corporation Ltd.  

(3)In view of the insertion of Rule 64B and Rule 64C on 25th  

September,  2000  in  the  Mineral  Concession  Rules,  the  

levy of royalty on coal has now been postponed from the  

pit-head  to  the  stage  of  removal  of  the  coal  (whether  

unprocessed or ROM coal or whether beneficiated coal).

(4)In view of the decision in  Central Coalfields Ltd. the  

entitlement of TISCO and Tata Steel to refund of royalty  

from  10th August,  1998  to  25th September,  2000  is  

recognized.   For the period from 25th September,  2000  

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 48 of 50

                                                  

49

Page 49

onwards, TISCO is obliged to pay royalty as per Rule 64B  

and Rule 64C of the Mineral Concession Rules.

(5)Tata Steel, like TISCO is liable to pay royalty on coal with  

effect from 25th September, 2000 in terms of Rule 64B  

and Rule 64C of the Mineral Concession Rules.

(6)The constitutional validity or the vires of Rule 64B and  

Rule 64C of the Mineral Concession Rules has not been  

adjudicated upon.  It is open to Tata Steel either to revive  

these appeals limited to this question or to challenge the  

constitutionality  and  vires  of  these  rules  through  a  

separate challenge.

88. The  appeals  are  disposed  of  as  above.   However,  the  

parties will bear their own costs.

                                     …..……………………CJI   (H.L. Dattu)

                                  …..……………………….J  (Madan B. Lokur)                                    

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 49 of 50

                                                  

50

Page 50

        ……………………………J  (A.K. Sikri)

New Delhi; March 17, 2015

C.A. Nos._______ /2015 (@ S.L.P. (C) Nos. 8972-8973 of 2014) etc.etc.Page 50 of 50