18 October 2016
Supreme Court
Download

TAMILNADU GENERATION AND DISTRIBUTION CORPORATION LTD. (TANGEDCO), REP. BY ITS CHAIRMAN AND MANAGING Vs CSEPDI - TRISHE CONSORTIUM, REP. BY ITS MANAGING DIRECTOR

Bench: DIPAK MISRA,SHIVA KIRTI SINGH
Case number: C.A. No.-010182-010183 / 2016
Diary number: 32211 / 2015
Advocates: B. BALAJI Vs


1

Page 1

1

Reportable

SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS. 10182-10183 OF 2016 (@ SLP(C) Nos. 28959-28960 of 2015)

Tamil Nadu Generation and Distribution …Appellant(s) Corporation Ltd. (TANGEDCO) Rep. By Its Chairman & Managing Director  and Anr. Etc.   

Versus

CSEPDI – Trishe Consortium, Rep. By its …Respondent(s) Managing Director & Anr.   

WITH

CIVIL APPEAL NOS. 10184-10185 OF 2016 (@ SLP Nos. 30098-30099 of 2015)

J U D G M E N T Dipak Misra, J.

Leave granted.

2. The appellant, Tamil Nadu Generation and Distribution

Corporation Ltd (for short ‘the Corporation’)  vide notification

dated 06.05.2013 floated a tender for setting up of two units of

2

Page 2

2

660 MW Ennore SEZ Supercricitcal Thermal Power Project at

Ash Dyke of NCTPS, Chennai wherein four bidders including

the respondents herein participated. However, two bidders out

of  four  were  disqualified  as  they  failed  to  meet  the  Bid

Qualification Requirements (BQR) as a result of which bids of

Consortium of  Trishe  Energy Infrastructure  Services Private

Limited (CSEPDI) and Bharat Heavy Electrical Ltd (BHEL) were

taken up for consideration. Prior to the opening of the price

bid, CSEPDI and BHEL submitted supplementary price bids

on 05.02.2014. Price bids were opened on 05.02.2014 by the

appellant  in  the  presence  of  the  representatives  of  the

respondents, the qualified bidders.

3. The  uncurtaining  of  facts  would  depict  that  the

1strespondent sent series of representations dated 16.06.2014,

17.06.2014,  01.07.2014  and  08.07.2014  to  the  appellant

highlighting various aspects of  the bid and the relevance of

para (viii) of Clause 29.0 of the “Instructions to Bidders” (ITB)

which  also  deals  with  the  rejection  of  bids  of  the  tenderer

whose  past  performance/vendor  rating  is  not  satisfactory.

3

Page 3

3

Since the appellant paid no heed to the request made by the

respondent No.1, it filed W.P. No. 19247 of 2014 seeking issue

of a writ of mandamus to direct the appellant to consider the

representations and comply with Tamil Nadu Transparency In

Tenders Act, 1998 (for short, “the TTIT Act”).  An undertaking

was  given  before  the  learned  Single  Judge  by  the  learned

Advocate General that post-bid representations submitted by

the respondent No.1 will  be duly considered while finalizing

the  tenders  and  appropriate  orders  will  be  passed  in

accordance  with  the  tender  specifications  and the  TTIT  Act

and  rules  framed  thereunder  and  in  terms  of  the  said

undertaking,  learned  Single  Judge  vide  order  dated

31.07.2014 directed the appellant to consider and pass orders

on the representations of the appellant herein after affording

them an opportunity of personal hearing and directed that till

such orders are passed, the tender should not be finalised.  

4. Being aggrieved by the said order, the appellant filed writ

appeal  W.A.  No.  1065  of  2014  before  the  Division  Bench

which,  by judgment and order dated 19.08.2014, disposed of

4

Page 4

4

the writ appeal by modifying the order of the learned Single

Judge  only  to  the  extent  that  affording  of  opportunity  of

personal hearing to the person was impermissible having not

contemplated  under  the  Rules  (for  short,  “the  rules”)  and

further permitted the  respondent No.1 to submit additional

documents  raising  all  its  objections  and  the  appellant  was

directed to pass an order and communicate the same to the

respondents,  CSEPDI  and  BHEL.   However,  the  Division

Bench did not modify the direction of the learned Single Judge

which  was  to  the  effect  that  till  a  decision  was  taken  on

representations  of  the  1st respondent,  the  bid  shall  not  be

finalised.  

5. After the disposal of the writ appeal, the respondent No.1

sent  its  representation on 25.08.2014 along with  necessary

documents  which  was  rejected  by  the  appellant  vide  its

communication dated 27.09.2014.  The legal propriety of the

said rejection was called in question by way of writ petition

W.P. No. 26762 of 2014 seeking quashment of the same and

further restraining the owner from taking steps to finalise the

5

Page 5

5

tender.  During the hearing of the writ petition, a copy of letter

dated 27.09.2014 awarding the contract to BHEL, respondent

No. 2 herein, was brought on record.  It was mentioned therein

with regard to price negotiation meetings with the respondent

No. 2.   The respondent No. 1 sent a letter dated 1.10.2014 to

the  appellant,  highlighting  the  arbitrariness,  anomalies  and

inconsistencies in its reasoning and the mala-fide intent in the

matter of evaluation of the bid submitted by it. However, the

appellant  by  letter  dated  10.10.2014,  informed  the  1st

respondent  that  the  subject  tender  had  been  finalised  and

awarded to BHEL.  

6. The  letter  dated  27.9.2014  awarding  the  contract  to

respondent No. 2 and letter dated 10.10.2014 were assailed by

the  respondent  No.1  by  filing  W.P.  No.  27529  of  2014  for

annulments of the letters and further for issue of directions to

the Corporation to determine the award of the tender strictly

in terms of the Tender/Bid document and taking into account

the bid of respondent No.1 and that of BHEL, the respondent

No.2 herein.

6

Page 6

6

7. The  learned  Single  Judge  dismissed  the  writ  petition

primarily based on the perusal of notes in the files containing

the  Consultant  Report  dated 30.05.2014 and on that  basis

opined that the conduct of process of evaluation of the tenders

did not appear to be arbitrary, capricious or unfair; and that

price  bids  of  the  bidders  had  been  evaluated  as  per  the

parameters  indicated  in  the  tender  notification  by  an

independent  consultant  who was selected as per  the Board

Resolution that was within the knowledge of both the bidders.

The reasoning of the learned Single Judge basically hinged on

the  Consultant’s  Report  that  had  determined  that  the

respondent No.2 herein was L1 and, therefore, the decision of

the  Corporation  in  treating  BHEL  as  L1  and  awarding  the

contract was neither arbitrary nor malafide.  

8. Aggrieved by the order of the learned Single Judge, the

respondent  No.1  preferred  writ  appeals  before  the  Division

Bench.   The Division Bench took note  of  the  various pleas

raised  by  the  respondent  No.1  including  violation  of  the

statutory  provisions,  arbitrariness,  adoption  of  unfair  and

7

Page 7

7

non-transparent  procedure,  erroneous  delineation  of  the

consultant’s  report  by  the  learned  Single  Judge  and

non-consideration of public interest.   

9. The  Corporation,  in  its  turn,  contended  before  the

Division Bench that there was no violation of procedure and

the award of the contract was not amenable to judicial review

in  the  obtaining  factual  matrix  and any  interference  would

only delay the execution of the work.  It was also urged that

Tender  Accepting  Authority  (TAA)  had  accepted  the  lowest

tender  and  negotiations  were  held  only  with  lowest  bidder;

that Clause 25.4 of the Instruction to Bidders did not permit

the bidder to change the substance of the bids after the bids

were  opened;  that  though the  respondent  No.1  had  offered

lower rate on interest, the original interest rate offered was not

in accordance with tender terms, for as per clause 14.0(d)(5)

the  rate  of  interest  quoted  should  be  fixed,  whereas  the

CSEPDI had not specified the fixed rate of interest; that there

was no perversity or arbitrariness in the decision taken as per

the terms of the tender, prevalent banking practice and the

8

Page 8

8

Term  Sheet  given  by  the  lender;  that  the  Consultant  was

appointed pursuant to the Board Resolution dated 28.01.2012

who participated in all pre-bid and post-bid meetings and the

minutes had been signed by all the parties and the consultant

and, therefore, CSEPDI was very much aware of appointment

of  the  consultant  and  the  role  played  by  consultant  could

neither be criticised nor ignored.

10. The  2nd Respondent  herein  contended  that  respondent

No.1 lacked credibility to make any allegation against it; that

design was the core area of leader of the consortium and they

have no experience in India insofar as supercritical Thermal

Power Projects are concerned; and that the work was under

progress and they had expended substantial amount.

11. After  hearing the rival  contentions,  the Division Bench

placed reliance on Jagdish Mandal v. State of Orissa1 and

observed that  the approach of  the owner was unfair  in the

tendering process.  It further analysed the scheme of Section

1

 (2007) 14 SCC 517

9

Page 9

9

10  of  the  TTIT  Act  and  held  that  the  Tender  Accepting

Authority (TAA) has a role to cause objective evaluation of the

tenders.  Referring to Section 10(6) of the TTIT Act, it held that

the Corporation had not complied with the said provision and

it was a case of procedural impropriety, unfair approach and

arbitrariness.  The appellate Bench referred to the authority in

Star  Enterprises  v.  City  and  Industrial  Development

Corporation of Maharashtra Ltd.2  and declined to accept

the  stand  of  the  Corporation  by  opining  that  reasons  for

rejection  of  1st respondent’s  representations  could  not  be

treated  as  reasons  for  rejection  of  its  bid  and  hence,  the

decision making process was flawed and in breach of Section

10(7) of the Act.  It further held that in the “Tender Bulletin”,

absence of reasons for acceptance of tender, no statement of

evaluation of tenders and no comparative statement of tenders

received and,  decision thereon was in clear  violation of  the

requirements of Section 6(1) read with Section 10 of the TTIT

Act  and  Rule  30(3)  of  the  TTIT  Rules.   On  the  interest

2

 (1990) 3 SCC 280

10

Page 10

10

component and commitment fee, the Division Bench held that

the approach was wholly arbitrary and the intention was to

oust the respondent No.1, for the evaluation process adopted

was meant to suit one and reject the other. It further held that

the process adopted and the decision taken by the owner was

arbitrary, unfair, irrational, biased and mala fide and did not

serve the larger public interest.  In view of the said analysis,

the  Division  Bench  allowed  the  appeals  and  directed  the

Corporation to evaluate the price bid of the respondents in the

light of its findings and taking into consideration all relevant

parameters  including  the  representations/documents

submitted by respondent No. 1 and to record detailed reasons

for the decision and communicate the same to the respondent

No.1 so as to comply with the requirement of the provisions of

the  TTIT  Act  and  TTIT  Rules  and  various  decisions  of  this

Court.  

12. Being  aggrieved  by  the  aforesaid  judgment,  the

corporation and the successful bidder, by way of special leave,

have preferred separate appeals.

11

Page 11

11

13. We  have  heard  Mr.  Mukul  Rohatgi,  learned  Attorney

General and Mr. Parag P. Tripathi, learned senior counsel for

the  appellant-BHEL and  Mr.  Subramonium Prasad,  learned

senior  counsel  for  the  appellant-Corporation,  and Mr.  Kapil

Sibal,  learned  senior  counsel  for  respondent  No.1  and  Mr.

Sriram  Panchu,  learned  senior  counsel  for  the  respondent

No. 2.

14. It is apposite to note that in course of hearing it has been

opined that the singular issue that is required to be addressed

is “whether the Evaluation Report dated 30th May, 2014 by the

Consultant,  is  prima facie  erroneous,  requiring  interference

within  the  parameters  of  judicial  review”.  Such  a  singular

point  was  required  to  be  focused  as  Mr.  Mukul  Rohatgi,

learned  Attorney  General  appearing  for  BHEL  and  Mr.

Subramonium Prasad learned senior counsel appearing for the

Corporation had submitted as the subsequent offers either by

BHEL or by the 1st respondent need not be considered.  At that

juncture, Mr. Kapil Sibal learned senior counsel appearing for

the 1st respondent, the contesting party, had submitted that

12

Page 12

12

the  Consultant’s  Report  would  graphically  exposit  that  the

respondent No.1 was entitled to be declared as L-1 even if it is

scrutinized  within  the  limited  parameters  of  the  judicial

review.  The  Court  had  directed  for  handing  over  the

Consultant’s Report to the learned counsel appearing for the

1st respondent.  In  view  of  the  aforesaid  submission,  the

opinion expressed on other issues by the learned Single Judge

or by the Division Bench need not be adverted to.  

15. On a perusal of the facts brought on record, it is manifest

that  the  Corporation in  its  meeting  held  on 30.1.2014 had

decided  to  open  the  price  bids  on  both  the  bidders  and

thereafter  the supplementary price  bids were obtained from

both  the  parties  for  the  additional  implications  items  in

respect  of  technical  deviation  quoted  by  both  parties  and

thereafter the price bids were opened on 05.2.2014.  As the

factual matrix would reveal, the price bids were evaluated by

the  Consultant.  The  learned  Single  Judge  has  adverted  to

price evaluation report submitted by the Consultant.  Certain

13

Page 13

13

paragraphs  from  the  report  of  the  Consultant  that  were

reproduced by him are as follows:-

“4.0 Evaluation

4.1 BHEL

BHEL has arranged finance from M/s. Power Finance Corporation of India.

They are arranged to finance 75% of the total cost as debt at an interest rate of 12.25% p.a.

Attached Annexures 1 to 5 indicate the methodology adopted  in  calculating  the  various  components required  for  evaluation  like  IDC-Debt,  IDC-Equity, IDC-UF Fess, Debt Repayment Schedule etc.

4.2 CSEPDI – TRISHE

CSEPDI-TRISHE  has  arranged  finance  from  M/s. ICBC, China.

They have arranged a finance 85% of the total cost as debt at an interest rate of 7.2% p.a.

Attached Annexures 6 to 12 indicate the methodology adopted  in  calculating  the  various  components required  for  evaluation  like  IDC-Debt,  IDC-Equity, IDC-UF Fess, Debt Repayment Schedule etc.

5.0 Evaluated Lower Cost

BHEL CSEPDI-TR ISHE

All  figures in  Rs. (Crores)

All  figures in  Rs. (Crores)

Capacity 1320 MW 1320 MW

14

Page 14

14

A Total EPC cost excluding VAT

7762.977 9207.264

B EPC Debt 75% 5822.233 7826.174 C EPC Equity 25% 1940.744 1381.090 D IDC Debt 12.25% 1295.079 1228.378 E EPC  Debt

Including  IDC (B + D)

7117.311 9054.552

F Upfront  Fees Including Interest

8.925 801.180

G Total  Debt  (E + F)

7126.237 9855.732

H Interest  on Equity

14% 509.597 456.606

I Total  Equity (C + H)

2450.341 1837.695

J Total  Project Cost (G + I)

9576.578 11693.427

K Total Cost per MW

7.255 8.859

L PV – Debt 7553.364 8464.318 M PV – Equity 2809.403 2106.984 N Total PV 10362.767 10271.302 O PV  Cost  per

MW ` 7.851 7.781

P Loading  for Deficiency

10.287 173.229

Q Total (N+P) 10373.054 10444.531 R Evaluated  Bid

Price per MW 7.858 7.913

Paragraphs  4.0  and  5.0  of  the  “Price  Evaluation Report”  submitted  by  the  Consultant,  which  I  have extracted above, show that the Consultant took into account only the interest rate of 12.25% per annum for the debt component arranged by BHEL from the Power Finance Corporation of India.  The Consultant did not take note of the reduced rate namely 12.15,

15

Page 15

15

subsequently  offered  by  BHEL,  for  arriving  at  the conclusion that the “Evaluated Bid Price” of BHEL was the lowest.”

16. There  is  no  dispute  that  as  per  the  Price  Evaluation

Report by the Consultant, the EPC price of the respondent No.

1 was Rs.9207.264 crores and respondent No.2 to whom the

contract  was  awarded  was  Rs.7762.977  crores.   Thus,  the

difference between the two EPC price is Rs.1444.287 crores.

The 1st respondent disputed the Price Evaluation Report by the

Consultant  on  the  ground  that  it  wrongly  loaded  the  sum

towards (a) the commitment fee, (b) interest on management

fee during IDC period; and (c) interest of guarantee fee during

IDC period in its bid amount which had led to the evaluation

of quoted financial charges with interest to Rs.801.18 crores.  

17. As regards the commitment fee, learned counsel for the

appellant submits that the contention of the respondent No.1

that since commitment fee was the fee to be charged on the

unutilised amount of the loan meaning thereby if the appellant

failed to draw the loan amount as undertaken, then only the

commitment  fee  would  be  charged  and,  therefore,  the

16

Page 16

16

determination  after  addition  of  the  same  was  without  any

rationale  as  the  respondent  No.1  had  quoted  in  the

‘Calculation Sheet for Financial Cost’ in the supplementary bid

commitment fee to the tune of Rs.164.72 crores which was to

be  charged  @  1%  p.a.  on  accrued  drawals  and  if  no

commitment fee was required to be paid, the respondent No.1

should have mentioned the same to be nil or zero.  To show

that the commitment fee  is  a part  of  the financial  charges,

learned senior counsel has drawn our attention to clause 14(d)

6 of the Instruction to Bidders under the tender, which reads

as follows:-

“6. Financing Charges : All financing charges of any nomenclature  relating  to  financing  of  the  project including  but  not  limited  to  Finders  Fees, Commitment  Fees,  Arrangement  Fees,  Management Fees,  Up  Front  Fees,  Syndication  Fees,  Service Charges, Guarantee Charges, Other Fees and Taxes, if any should be clearly outlined in the Financing Term Sheet.  No variation in Financing Charges is permitted during the tenor of loan.

3.37 “Financing Cost” means all financing charges of any nomenclature relating to financing of the project including but not limited to Finders Fees, Arranger’s Fees, Commitment Fees, Management Fees, Up Front

17

Page 17

17

Fees,  Syndication Fees,  Service  Charges,  Guarantee Charges, Other Fees and Taxes, if any.”

18. At  this  juncture  we  may  also  refer  to  clause  3.37  of

Section 2 that deals with the General Terms and Conditions of

the Contract.  It defines the “Financing Cost” as follows:-

“Financing Cost” means all financing charges of any nomenclature  relating  to  financing  of  the  project including but not limited to Finders Fees, Arranger’s Fees, Commitment Fees, Management Fees, Up Front Fees,  Syndication Fees,  Service  Charges,  Guarantee Charges, Other Fees and Taxes, if any”.

19. Clause 14 that  deals with the conditions for  a Binding

Debt Financing Term Sheet, which needs to be reproduced in

entirety.  It reads as follows:-

“14.0  Conditions  for  a  Binding  Debt  Financing Term Sheet Bidder  shall  enter  into  a  Memorandum  of Understanding  (MoU)  with  the  Lender  for  the  Debt Financing  agreeing  to  provide  Financing  for  the Project and making payments directly to the Bidder based  on  bills  certified  by  TANGEDCO  as  per  the terms of payment clause. The MoU shall be submitted by the Bidder along with their offer for signing of the loan agreement. The  Bidder  shall  be  responsible  for  arranging  the required financing and achieving Financial Closure of the project within 4 (Four months) from the date of Letter of Intent (LoI).

18

Page 18

18

a.  The  Bidder  and  Lender  shall  furnish  a  joint undertaking  to  fulfill  the  commitment  made  in  the offer for Debt Financing arrangement from the Lender subject to due diligence. TANGEDCO will  furnish the following documents to the  lender  for  processing  of  Debt  Financing  to  the successful bidder. 1. Profile of TANGEDCO 2. Audited Balance Sheet of TANGEDCO for the last three financial years 3.  MOU entered  between  TANGEDCO &  MMTC for long term supply of coal of this project. 4. Tariff order for sale of power. 5. Copy of DPR b.  It  shall  be  understood  that  the  Financing  Term Sheet shall be based on preliminary appraisal of the project jointly by the Bidder and the Lender satisfying themselves on the project financial viability. c. It shall be understood that the Award of Contract to the  Bidder  is  contingent  upon  successful  Financial Closure based on the Terms and Conditions provided in the Financing Term Sheet and in the event of the Financial Closure does not materialize due to reasons attributable  to  the  Bidder  or  the  Lender  or  in  the event of  withdrawal by the Lender from the Project, the Bidder will forfeit the security deposit.

d. The Term Sheet should be full and complete with all  material  terms  of  financing  including  but  not limited to: 1. Loan Amount : At least 75% of the Total EPC Cost + 100% of Interest during construction and Financing Cost. 2. Currency of Loan: INR/USD/Euro or a combination thereof.

19

Page 19

19

3. Tenor of the Loan : From the date of first drawal of the Loan upto 6 months from COD of the 1st or 2nd unit whichever is later and 15 years thereafter. 4. Rate of Interest. 5.  Fixed Rate of  Interest  till  the entire  tenor  of  the loan after taking into account the hedged cost. 6. Financing Charges :  All  financing charges of  any nomenclature  relating  to  financing  of  the  project including  but  not  limited  to  Finders  Fees, Commitment  Fees,  Arrangement  Fees,  Management Fees,  Up  Front  Fees,  Syndication  Fees,  Service Charges, Guarantee Charges, Other Fees and Taxes, if any should be clearly outlined in the Financing Term Sheet. No variation in Financing Charges is permitted during the tenor of loan. 7. Terms and conditions for draw down schedule. 8. Moratorium for Repayment of Installment, Interest and Financing Charges:  All cash outflow obligation of TANGEDCO  towards  repayment  of  Installment, Interest  and  Financing  Charges  should  be  in  INR (fully hedged) for the entire tenure of the loan and the repayment  will  commence  only  after  6months  from the date of COD of later unit. 9.  Repayment  Period:  15  years  post  IDC  and moratorium in 60 equated quarterly installments 10. Project Cash Flows and Installment Repayments statement should be submitted and will form part of the  Financing  proposal.   The  Bidder  shall  indicate Draw Down Schedule of finance to match the supply and erection schedule of project activities. 11. Equity requirements and related covenants. 12.  Security:  Against  Security  the  following  can  be made available by TANGEDCO a. Hypothecation of all 100% Project Assets b. Government Guarantee for the repayment of loan

20

Page 20

20

13.  Validity  period  of  the  Term  Sheet  will  be co-terminus with the validity of the bid.”

20. The stand of the respondent as regards the interpretation

of Clause 14(d) 6 is that it only outlines all fees, but it does not

mean that every such fee is to be loaded for evaluating the bid

to  determine  L1 and no commitment  fee  can be  loaded for

such evaluation.   It  is  also  put  forth that  there can be  no

question of loading interest on commitment fee.

21. As  has  been  stated  earlier,  the  issue  pertaining  to

correctness  of  Consultant’s  report  has  to  be  adjudged  and

scrutinized within the scope of limited power of judicial review

in  the  obtaining  factual  score.   The  Division  Bench  in  the

impugned  judgment  has  taken  exception  to  the  process

adopted in the identification of L1.  It has referred to its order

dated 19.8.2014 wherein the 1st respondent was granted the

time to submit  additional  documents.   The impugned order

takes  note  of  the  fact  that  at  that  point  of  time,  the

Corporation had never averred that tender had been finalized.

It has referred to the earlier order of the Division Bench that

representations were  to  be  considered and till  then the  bid

21

Page 21

21

should not  be finalized.   It  has referred to the letter  of  the

Chairman-cum-Managing  Director  of  the  Corporation  dated

20.7.2014 and opined that it appears to be a misstatement of

fact.   

22. Be  it  stated  that  the  Division  Bench  has  posed  two

questions:-

“(i) Whether interest offered by appellant is vague; and (ii)  Whether  the  reduction  of  interest  from 7.2% to 6.2% should be accepted.”

23. While dealing with the said issue, the Division Bench has

referred to the publication in the tender bulletin stating about

the decision on tender:-

“1. Name of the Tender: Chief Engineer/Civil/Projects &  Environment,  Inviting  Officer,  3rd Floor,  NPKRR Maaligai, 144, Anna Salai, Chennai – 600 002.

2. a) Name of the Project/Detail of Purchase & Works: Establishment of coal based 2 x 660 MW Ennore SEZ Supercritical Thermal Power Project in the ash dyke of existing NCTPS under Single EPC cum Debt Finance basis.  Vayalurvillage,  Thiruvallur  District,  Tamil Nadu.

22

Page 22

22

Sl. No

Details Tender Value

Decision  on Tender

1

2

M/s. Bharat Heavy Electricals Limited, BHEL House, Sirifort, New  Delhi – 110 049

Consortium of  Central Southern China Electric Power Design  – Ms.  Trishe, 668,  Minz Road, Ughan, China – 430 071

7840.08 7 Crores & Lender: Power Finance Corporat ion Limited Rate  of Interest: 12.25%

9716.59 74 Crores & Lender: Industri al  & Commer ce  Bank of China Rate  of Interest: 7.2% (USD  @ Rs. 59.26  at SBI  Bill selling rate)

Out  of  four  bids received  for  this work  and  among the  qualified  two bidders, negotiation  was called  for  &  held with  the  lowest bidder  viz M/s.BHEL.  After negotiation, tender  value  of Rs.  7788  Crores, Rate of Interest at 12.15%  was accepted  by  the Chief Engineer/Projects and  order  for acceptance of the tender  issued vide  this  office issue Lr.No.CE/P/SE/ M/EE-10/E/File. 2x660MW Ennore SEZ STPP/D.No.60/dt .27.09.2014

23

Page 23

23

Finally,  M/s.  BHEL/New  Delhi  offered  bid  for  Rs. 7788  Crores  was  accepted  by  the  Chief Engineer/Projects/Chennai and order for acceptance of  the  tender  was  issued  vide  this  officer Lr.No.CE/P/SE/M/EE-10/  E/File.2x660MW  Ennore SEZ STPP/D.No.60/dt. 27.09.2014.”

24. Thereafter, the Division Bench has recorded as follows:-

“31.3 While it is the plea of the appellant that fixed rate  of  7.2-7.5% per  annum or  LIBOR floating rate has been quoted by them, it is the case of the learned Advocate General that Clause 12.1 of the Instructions to Bidders stated that interest is to be quoted at fixed rate  and it  is  not  subject  to change,  and since the interest  quoted  is  variable,  it  is  not  possible  to evaluate the bid.

31.4 It is seen from the records, that subsequently, based  on  a  query  from  the  first  respondent,  the appellant had confirmed that it would be fixed rate of interest at 7.2%.  the same was also confirmed in the Repayment  Schedule  and  the  same  rate  of  interest was taken into consideration by the Consultant in his report dated 30.5.2014.  He did not find fault with the rate of interest.  It is to be noted that the Term Sheet was  submitted  during  July,  2013  and  tender  was evaluated  in  the  year  2014.   The  contention  of vagueness in rate of interest does not appeal to us. When  the  Consultant’s  report  dated  30.5.2014  is accepted  by  TANGEDCO  for  the  purpose  of evaluation,  it  has  to  be  accepted  for  all  purposes, though  we  have  reservation  on  the  Consultant’s report  dated  30.5.2014.  There  is,  therefore,  no vagueness in the rate of interest quoted at 7.2%.

31.5 The second issue relates to the reduction of rate of interest.  It is not in dispute that various meetings were held between the appellant and the TANGEDCO.

24

Page 24

24

The  learned  Advocate  General  states  that  the Consultant  was  appointed  based on the  21st Board Meeting  on  28.1.2012  and  the  Consultant participated in all pre-bid and post-bid meetings and minutes were signed by all  parties,  including BHEL and the appellant.  He stated that the appellant was aware of the Consultant’s appointment and his role. This only fortifies the fact that there have been series of consultation between both the bidders.  The finding of the learned Single Judge that the appellant acted on inside information is demolished by the stand of the  learned  Advocate  General  as  above.   The insinuation has no basis.

31.6  Coming  to  the  issue  of  reduction  of  rate  of interest,  taking  into  consideration  the  prevailing market rate, the appellant offered to reduce the rate of interest from 7.2% to 6.2% on 5.6.2014, even prior to any form of litigation.  When such an offer was given by the appellant the tender was not accepted in terms of Section 10(6) of the Act.  To recapitulate, what has happened earlier is that the writ petition in W.P. No. 19247 of 2014 was filed on 17.7.2014, subsequent to the offer made on 5.6.2014.  The first interim order was passed on 18.7.2014.  The second interim order was passed on 31.7.2014.  The Division Bench passed an order on 19.8.2014.  At that point of time, there was never a statement by the TANGEDCO that L1 was identified and discussion was going on.  We have also clearly  stated  that  the  statement  of  the Chairman-cum-Managing Director of TANGEDCO that the  representations  of  the  appellant  will  be  duly considered by the Board of Directors while finalizing the  tender  and  appropriate  orders  will  be  passed strictly  in  accordance with the tender  specifications and by following the provisions of TTIT Act and TTIT Rules.

25

Page 25

25

31.7 Therefore, the issue relating to reduction of rate of  interest  should  have  been  considered.   This reasoning of ours is also based on the fact that we have clearly held that the third respondent could not be  ascertained  as  L1  on  2.6.2014  as  per  the statement of TANGEDCO or on 30.5.2014 as per the finding of the learned Single Judge.  Once there is no identification of L1, TANGEDCO is bound to consider the reduction in rate of interest of both the appellant in  their  offer  dated  5.6.2014  and  that  of  the  third respondent  dated  27.6.2014,  reducing  the  rate  of interest from 12.25% to 12.15%.

31.8  Even  otherwise,  by  virtue  of  the  power  under Clause  25.3  of  the  Instructions  to  bidders,  which states that “The Purchaser reserves the right to relax or waive any of the conditions of this Specification in the best interests of the TANGEDCO”, the TANGEDCO could have considered such reduced rate of interest offered by the appellant and the third respondent.”

25. With  regard  to  commitment  fee,  the  analysis  of  the

Division Bench is worth referring to:-

“It clearly states that Commitment Fee is only on the cancelled portion of the loan.  That apart, even as per the Drawdown Schedule, the fee is to be paid only if the loan amount is not drawn by the 18th,  30th and 42nd month.   Moreover,  the  appellant  in  the  letters dated  13.6.2014,16.6.2014  and  17.6.2014,  clarified that  Commitment Fee is  only  on the unused credit line and that there shall be no Commitment Fee if the loan amount  is  fully  utilized  as  per  the  Drawdown Schedule.   All  these  representations  sent  by  the appellant were not considered by TANGEDCO, despite there being a specific direction by the Division Bench of this Court to consider the same.  It is a clear case

26

Page 26

26

of arbitrariness in approach and intended to oust the appellant.  This act of the TANGEDCO is nothing but a case of malafide in evaluation process to suit one and reject the other.”

26. While dealing with the consultant’s report, the Division

Bench has proceeded to state thus:-

“33.3  Even  as  per  the  Consultant’s  Report  the difference between the bid of  the appellant  and the third respondent is around Rs.71 Crores.  That being the case, if either the Commitment Fee of Rs.156.184 Crores  or  the  interest  on  Management  Fee  and Guarantee Fee for the 36 month construction period is not loaded on the appellant, it will have a bearing on deciding which one of the two is the lowest bid. Assuming  the  Consultant’s  report  is  of  any  value, such report without considering the relevant material is  of  no  use.   The  approach  to  add  these  figures without  taking  note  of  the  representations  and additional  particulars/documents  is,  therefore, arbitrary and tainted in bias.  This is in violation of the Division Bench judgment as well as the orders of the  learned  Single  Judge  in  the  first  round  of litigation.”

27. And again:-

“The financial implication in respect of two tenderers has been specified by the Consultant.  The issue is what factors mean and how it impacts the bid.  We find that the Repayment Schedule submitted by the appellant with regard to interest on management fee and guarantee fee during IDC period is an accepted document by the Consultant.  If nothing more is to be paid beyond that and that is clarified in the course of representation in clear terms, we fail to understand as

27

Page 27

27

to  how  this  amount  could  be  included  in  the  cost when there is no implication.  The Consultant, as we have held, did not have the benefit of considering the representation and other documents on the financial implications in this issue.  His opinion is therefore not based on relevant document/representation.  This we have held is not in conformity with the order of the learned Single Judge in the first round of litigation, which  was  confirmed  by  the  Division  Bench. Withholding such a factor and to obtain an evaluation from the Consultant loading the bid of the appellant is clearly a case of bias.  It is an unreasonable approach and an unfair  gesture which crumbles the spirit  of transparent tender.”

“33.6 We, therefore, have no hesitation to hold that the  first  respondent  had erroneously  added interest on Management Fee and Guarantee Fee when there is none and there is no ambiguity or vagueness. Once the appellant has indicated in the representation, in clear terms, as to how it should be treated, in the light of the order of the Division Bench, which TANGEDCO accepted to consider the bid of the appellant, the first respondent ought not to have loaded this amount on the basis of the Consultant’s Report.  In all fairness, the Tender Accepting Authority of the first respondent should have excluded this amount, if both the bidders are to be treated on the touchstone of fairness and on the  doctrine  of  level-playing  field.   This  becomes necessary because the entire tender is tested on the larger  public  interest,  that  is  to  say,  the implementation of the project in a time bound manner where  cost  is  another  important  factor  to  be considered  in  the  decision  making.   In  a  Welfare State,  public  authority  cannot  decide  arbitrarily  to throw  away  such  an  offer  which  they  agreed  to consider in the course of judicial proceedings, which we  have  referred  to  above.   These  factors,  namely,

28

Page 28

28

adding interest  on Management  Fee  and Guarantee Fee,  have  to  be  eschewed  for  the  purpose  of considering the bid of the appellant, otherwise, it will suffer  from  the  vice  of  unreasonableness  and irrationality.”

28. Eventually, it was directed as follows:-

“The  TANGEDCO  is  directed  to  evaluate  the appellant’s price bid along with the bid of the third respondent, in the light of our findings as above and also  taking  into  consideration  in  all  required parameters  and  the  clarifications  submitted  by  the appellant  in  its  various representations,  as  directed by the Single Judge in the order dated 31.7.2014 and that  of  the  Division  Bench  in  its  order  dated 19.8.2014, afresh, at the earliest.”

29.  Before this Court, the consultant’s report is criticized by

the 1st respondent stating thus:-

“2.3 The Consultant has made the following errors in the  calculation  of  the  said  ‘Upfront  Fees  Including Interest’ in respect of CSEPDI’s bid:

Error 1 : Included Commitment Fees

Error  2  :  Calculated  and  loaded  interest  on  (a.) Guarantee  Fee,  (b.)  Management  Fee  and  (c.) Commitment Fee during the construction period of 36 months, i.e., IDC (Interest During Construction)

2.4 In 5.0 Item F – ‘Upfront Fees Including Interest’, the  Consultant  has  loaded  BHEL  with  Rs.8.925 Crores  and CSEPDI  with Rs.  801.180 Crores.   The break-up  of  this  Rs.  801.180  Crores  in  the Consultant’s Report is as follows:

29

Page 29

29

a. Guarantee Fee : Rs. 371.743 Crores b. Management Fee : Rs. 117.393 Crores c. Commitment Fee : Rs. 156.184 Crores d. Interest for 36 months  

           on a,b,c (Rs. 127.613 Crores) e. Interest from 37th to 42nd month: Rs.155.860 Crores on a,b, & c (Rs. 28.247 Crores)

Total :      Rs. 801.180 Crores 2.4.1 There is no issue on entries a. and b. above 2.4.2  The  issue is  with  regard  to  entries  c.  and d. above. 2.4.3.  As  regards  c., no  Commitment  Fee  can  be loaded, for the reasons explained below.

2.4.4 As regards d., no interest can be loaded for the construction period of 36 months on Guarantee Fee and  Management  Fee,  for  the  reasons  explained below.  The question of interest on Commitment Fee does not arise at all because no Commitment Fee can be loaded in the first place for evaluation of CSEPDI’s bid.

2.4.5 e. above will stand reduced as it depends on c. and d.

2.5 If  the  Consultant  had  correctly  evaluated CSEPDI’s price bid by not including Commitment Fee and Interest on Guarantee Fee, Management Fee and Commitment  Fee  for  the  construction  period  of  36 months,  then CSEPDI would be L1 by Rs.  171.600 Crores. Neither TANGEDCO nor BHEL have disputed this fact.

x x x x x x

2.7  The  Consultant  has  confused  Commitment  Fee with  an  Upfront  Fee.   Commitment  Fee,  as  stated

30

Page 30

30

above, is a contingency fee payable if the scheduled drawal does not take place.  An Upfront Fee is levied by  the  lender  as  a  definite  fee  without  any contingency.   This  is  made  clear  by  PFC  (BHEL’s lender) letter dated 30-04-2015 showing Commitment Fee  and  Upfront  Fee  as  distinct  alternatives.   The Consultant has loaded BHEL with Upfront Fee.  The Consultant has erroneously treated Commitment Fee as an Upfront Fee for CSEPDI and has in fact applied the label Upfront Fee in Item F”.

30. With  regard  to  the  commitment  fee,  various  financial

nuances have been stated.  We think it apt to reproduce some

of them:-

“2.8.3 When the earmarked funds are drawn, the interest  agreed  is  payable.   When  the  earmarked funds are not drawn, the interest is not payable but instead the Commitment Fee has to be paid on the amount not drawn.

2.8.4 CSEPDI’s Term Sheet clearly mentions that the  Commitment  Fee  is  payable  on  the  cancelled portion of the loan.

2.8.5 The  term  ‘Accrued  Drawal’  refers  to  the amount  accured  and  available  for  drawal,  but  not drawn.

2.8.6 Commitment  Fee  is  therefore  only  a contingent fee leviable if the funds are not drawn as per the Drawdown Schedule.  It is more in the nature of a penalty in the event of a default by the borrower TANGEDCO  and  is  payable  by  TANGEDCO.   This cannot be added to the project cost for evaluation of the price bid.

x x x x x x

31

Page 31

31

2.8.8 The  Repayment  Schedule  sets  out  the entire amount to be paid by TANGEDCO in the form of  48 Equated Quarterly  Installments (EQI)  starting from the 43rd months of the date of financial closure for 12 years.  If there is one document to be termed as most  important  to  evaluate the Price  Bid,  it  is  this Repayment  Schedule.   The  Repayment  Schedule  is part of  the Price Bid and is absolutely crucial as it caps the amount TANGEDCO has to pay.  Not a single rupee needs to be paid over and above the amounts mentioned in the Repayment Schedule.

2.8.9 The  EQI  in  the  Repayment  Schedule  is based on the figure of Rs. 15,038.2914 Crores, which comprises of  interest  Rs.  5,025.3628 Crores on the Net  Loan  amount  of  Rs.  10,012.9286 Crores.   The components of this Net Loan amount are:

a.  Loan amount (85% of Total EPC  Cost of 9709.3822 Crores) : Rs. 8252.9748/-

b. Interest at 7.2% p.a. on the  above loan amount during  the Construction Period of 36 : Rs. 896.2032/- months

c. Guarantee Fee : Rs. 392.0163/-

d. Management Fee : Rs. 123.7946/-

Moratorium Period interest  for 37th to 42nd month (interest at 7.2% p.a. for  6 months on the total of  a,b,c and d. above) : Rs. 347.9396/- Total         : Rs.10,012.9286/-*

32

Page 32

32

*The  Price  Bid  submitted  by  CSEPDI  was  Rs. 9709.3822 Crores and the above calculations were on that basis.  However the admitted position is that of this  sum,  Rs.  509.339  Crores  was  disallowed  by TANGEDCO  and  the  Price  Bid  was  arrived  at Rs.9207.264  Crores.   The  Consultant  has  also evaluated CSEPDI’s bid at Rs. 9207.264 Crores”.

31. With  regard  to  no  interest  on  guarantee  fee  and

management fee during the construction period of 36 months

and  no  interest  on  Commitment  fee,  the  stand  of  the  1st

respondent has been put forth in various compartments.  We

think it apt to reproduce the relevant grounds:-

“2.9.1  The  Consultant  ought  not  to  have  loaded interest  on  Guarantee  Fee  and  Management  Fee during the construction period of 36 months, for the evaluation of CSEPDI’s Price Bid.

2.9.2 The very same Repayment Schedule calculation set out above shows that no interest is being charged on Guarantee Fee and Management  Fee during the construction period of 36 months and does not form part of the amount which TANGEDCO has to repay. Not a single rupee needs to be paid over and above the amounts mentioned in the Repayment Schedule.

2.9.3  The  only  interest  payable  during  the construction  period  of  36  months  is  interest calculated  at  7.2%  p.a.  on  the  basic  loan  amount (85% of the EPC cost) and not on any other amount like  Guarantee  Fee  and  Management  Fee.   This  is made  clear  in  the  specific  calculation  sheet  for

33

Page 33

33

Interest During Construction submitted by CSEPDI in its Price Bid.

2.9.4 The Term Sheet submitted by CSEPDI outlines the fees required to be paid by TANGEDCO and the circumstances in which they are payable.  In the very nature of this contract, the items chargeable have to be  mentioned,  not  the  items  not  chargeable.   The contract requires to be evaluated based on what the bidder is charging TANGEDCO.

2.9.5  In CSEPDI’s  Term Sheet,  mention is  made of Management  Fee  and  SINOSURE  Re-insurance (Guarantee Fee).  No mention is made of interest on Management  Fee  and  Guarantee  Fee  for  the construction period of 36 months.

2.9.6  As  far  as  interest  on  Commitment  Fee  is concerned, the same does not arise as Commitment Fee itself  cannot be loaded for  evaluating CSEPDI’s bid.”

32. The 1st respondent has also put forth that the Consultant

was  not  right  in  loading  on  CSEPDI  bid  the  values  for

Commitment  Fee  and  interest  thereon  and  Interest  on

Guarantee Fee and Management Fee during the construction

period of 36 months, because that Clause 14.d.6 only states

that  details  of  the  Financing  Charges  should  be  clearly

outlined in the Financing Term Sheet and does not state that

it  should  be  included  in  the  price  evaluation;  that  the

34

Page 34

34

reference  to  Commitment  Fee  in  the  Term  Sheet  clearly

indicates that it is only on the cancelled portion of the loan;

that the fee is to be paid only if the loan amount is not drawn

by  the  18th,  30th and  42nd months  in  accordance  with  the

Drawdown  Schedule;  that  Clause  12.1  and  Clause  32.1.1

makes no mention of interest on Financing Charges (i.e., on

Management Fee and Guarantee Fee) during the IDC period;

that the words ‘Interest and Financing Charges’ cannot mean

interest  on  financing  charges;  that  there  is  absolutely  no

variance  between the  Term Sheet  and Repayment  Schedule

submitted  by  CSEPDI;  that  the  Term Sheet  and  the  entire

Financial  Proposal/Price  Bid,  including  the  Repayment

Schedule,  are  to  be  read together;  that  the  CSEPDI’s  Term

Sheet only mentions that a Management Fee is to be paid but

does not mention any interest on Management Fee for the 36

month  construction  period  (IDC  period)  and  that  the

Consultant ought not to have loaded the disputed amounts for

evaluating the price bid of CSEPDI. It is also the stand that on

a perusal of the Comparison Sheet filed would indicate that

35

Page 35

35

CSEPDI is L1 by Rs.171.600 crores if the evaluation is done

correctly.  That  apart,  the  1st respondent  has  raised  other

grounds which we need not refer to in detail.

33. The Corporation in support  of  the Consultant’s  Report

has stated that the stand of the 1st respondent that Net Loan

Amount  in  the  repayment  schedule  provided by  respondent

No.1  gives  no  break  up  of  how  the  said  figure  has  been

reached; that one cannot find out from a bare perusal of the

said Repayment Schedule as to whether the respondent No.1

has factored the component  of  Commitment  Fee in  the Net

Loan Amount; that the respondent having not been declared

as  L1  bidder  as  a  post  facto  contention,  now  say  that

Commitment Fee shall not be taken for evaluation in spite of

the fact that they themselves have quoted Commitment Fees

for Rs.164.702 crores with split up details in the price bid and

the above post facto contention is against all tenets of fairness

and justice;  that  had the respondent No.1 become L1,  they

would have insisted that Commitment Fee being a financial

charge forms part of the loan and therefore is payable by the

36

Page 36

36

borrower i.e., the Corporation as per their price bids submitted

by respondent No.1; that since the respondent No.1 had not

been  evaluated  as  L1,  a  contention  is  advanced  that

Commitment  Fee  should  not  be  taken  for  evaluation  citing

universal definition.

34. On interest on management and guarantee fee, the stand

of the Corporation is that the CSEPDI-TRISHE CONSROTIUM

have quoted Rs. 123.9746 crores as Management fees and Rs.

392.0163 crores as Guarantee fee in their Price bid.  There is

no dispute on the quantum of fees. The Consultant during the

evaluation have worked out interest @ 7.2 per annum on the

above  fees  as  per  the  term  sheet  of  the  Industrial  and

Commercial Bank of China Limited from the date on which

they fall due since the above fees form part of the debt to be

repaid  by  the  appellant;  that  it  is  clear  from  the  Tender

Conditions as well as the Term Sheet provided by Industrial

and Commercial Bank of China Limited and the clarification

dated 21.10.2013 (issued by Industrial and Commercial Bank

of China Limited) that appellant herein would be bound to pay

37

Page 37

37

the interest on the whole loan amount which will include the

financial charges.  

35. The Corporation has quoted the relevant tender conditions

from the Term Sheet submitted by Industrial and Commercial

Bank of China Limited which are reproduced below:-

 “Clause  14(d)1  of  the Instruction to Bidders under  the  Tender defines  the  “Loan Amount” to include at least 75% of the total EPC  cost  +  100%  of interest  during construction  and Financing   Cost.  As per  clause  14(d)  6  of the  Instruction  to Bidders  under  the Tender  management fee  and guarantee  fee is part of the financial charges/financial cost.

 Under  the  term  relating  to  “Interest rate”  in  term  sheet  submitted  by Industrial  and  Commercial  Bank  of China  it  is  clearly  provided  that  the Borrower will pay interest on the full loan  amount  at  a  fixed  rate  per annum.

 Under  the  terms  defined  as “management  fee”  in  the  term sheet

38

Page 38

38

submitted  by  Industrial  and Commercial Bank of China Limited it is  specified  that  Management  fee  of 1.5% flat on the Loan Amount will be payable to the lender within a period of 60 days from the date of financial closure.  Six months is the time given for financial closure and so 8 months in case of management fee in view of outer limit of 60 days.

 Similarly, under the terms relating to “Conditions Precedent”,  the condition (d)  the  term  sheet  specifies  that petitioners will  be charged guarantee fee (termed as Insurance Policy in the term sheet) at the rate of 5% on 95% of the loan amount and the same will be  payable  from  the  end  of  the  6th month.

 According  to  the  term  sheet  the amounts get debited to the Petitioners account at the end of  the 8th month and 6th month respectively.

 All  financial  costs  form  part  of  the debt  taken  from  the  Industrial  and Commercial  Bank  of  China  Limited. As  per  the  clarification  dated 21.10.2013 issued  by  Industrial  and Commercial  Bank  of  China  Limited which  is  the  Lender  institution  for Respondent  no.1  all  costs  and  fee charged by ICBC will form part of the debt financing”.

39

Page 39

39

36. From the aforesaid, it  is vivid that the Consultant has

analysed the offers regard being had to the tender conditions.

Be it ingeminated that the analysis and determination made

by the financial consultant has been carried out before receipt

of any additional document from either side.  The documents

were called for by the owner from both the qualifying bidders

in a transparent manner and the same have been considered

at the time of evaluation by the Consultant.  Submission of

Mr. Sibal is that the evaluation is ex facie defective inasmuch

as  the  Consultant  has  loaded  certain  charges  as  a

consequence of  which the price has gone up.   Mr. Rohatgi,

learned Attorney General appearing for BHEL and Mr. Prasad,

learned senior  counsel  appearing for  the Corporation would

submit  that  the  evaluation  is  founded  on  definities  leaving

nothing to any kind of contingency.  They have referred to the

Term Sheet and what is put up by Industrial and Commercial

Bank of China Limited. At this juncture we are obliged to say

that in a complex fiscal evaluation the Court has to apply the

doctrine of restraint.  Several aspects, clauses, contingencies,

40

Page 40

40

etc. have to be factored.  These calculations are best left to

experts and those who have knowledge and skills in the field.

The financial computation involved, the capacity and efficiency

of the bidder and the perception of feasibility of completion of

the  project  have  to  be  left  to  the  wisdom  of  the  financial

experts and consultants.  The courts cannot really enter into

the  said  realm  in  exercise  of  power  of  judicial  review.  We

cannot  sit  in  appeal  over  the  financial  consultant’s

assessment.  Suffice it to say, it is neither ex facie erroneous

nor can we perceive as flawed for being perverse or absurd.

37.  Before parting with the case we are constrained to add

something.  We do so with immense pain.   The respondent,

before  finalization  of  the  financial  bid  submitted  series  of

representations and seeing the silence of the owner it knocked

at the doors of the writ court which directed for consideration

of the representations.  We are disposed to think that the High

Court  at  that  stage  should  have  exercised  caution.  If  the

courts  would  exercise  power  of  judicial  review  in  such  a

manner it  is  most  likely  to  cause confusion and also bring

41

Page 41

41

jeopardy in public interest. An aggrieved party can approach

the  Court  at  the  appropriate  stage,  not  when  the  bids  are

being considered. We do not intend to specify. It is appreciable

the  owner  in  certain  kind  of  tenders  call  the  bidders  for

negotiations to show fairness transparently. But the present

case  is  not  a  one  of  such  nature.  Once  the  price  bid  was

opened, a bidder could not have submitted representations on

his own and seek a mandamus from the Court to take certain

aspects into consideration.  We have stressed this aspect only

to  highlight  the  role  of  the  Court  keeping  in  mind  the

established principle of restraint.  

38. In view of our preceding analysis we are of the considered

opinion that the Division Bench through the delineation has

adopted the approach of an appellate forum or authority and

extended the  principle  of  judicial  review to  certain areas  to

which  it  could  not  have  and,  therefore,  the  judgment  and

order  of  the  Division  Bench  followed  the  path  of  error  in

continuum.  Consequently,  the  inevitable  conclusion  is

unsettlement of the impugned order and we so direct. In the

42

Page 42

42

ultimate eventual the appeals stand allowed. There shall be no

order as to costs.  

..............................J. (Dipak Misra)

..............................J.                            (Shiva Kirti Singh) New Delhi; October 18, 2016.