23 September 2011
Supreme Court
Download

STATE OF PUNJAB Vs STATE OF HARYANA & ORS.

Bench: J.M. PANCHAL,H.L. GOKHALE
Case number: Original Suite 1 of 2007


1

Non-Reportable

IN THE SUPREME COURT OF INDIA

CIVIL ORIGINAL JURISDICTION

INTERLOCUTORY APPLICATION NO. 7 OF 2011

IN

ORIGINAL SUIT NO. 1 OF 2007

State of Punjab … Plaintiff

Versus

State of Haryana and others     … Defendants

O R D E R

J.M. Panchal, J.

The State of Punjab has filed Suit No. 1 of 2007  

on July 11, 2007 in this Court under Article 131 of the  

Constitution  read  with  Order  XLVII  of  the  Supreme  

Court Rules, 1966 and claimed a decree of perpetual  

injunction  restraining  the  State  of  Haryana  from

2

further  proceeding  with  the  digging  of  channel  and  

construction  of  an  embankment  under  the  project  

named Hansi Branch – Bhutana Branch Multipurpose  

Channel project by puncturing the Bhakra Main Line  

Canal.  The said State has also prayed for a decree of  

mandatory injunction directing the State of Haryana to  

dismantle the embankment of the project named Hansi  

Branch  –  Bhutana  Branch  Multipurpose  Channel  

Project  between  the  points  X  and  Y  in  the  map  

appended to the plaint as Annexure ‘A’.  The State of  

Punjab has further  prayed for  a decree of  perpetual  

injunction restraining the Union of India, its agents or  

departments from granting any clearance to the project  

named Hansi Branch – Bhutana Branch Multipurpose  

Channel Project in the absence of the concurrence of  

the State of Punjab as contemplated and mandated by  

Article  13  of  the  Bhakra  Nangal  Agreement  entered  

into between the erstwhile State of Punjab and State of  

Rajasthan.

2. The Original Suit No. 1 of 2007 along with I.A.  

No.  1  of  2007  was  placed  before  this  Court  for  

2

3

preliminary  hearing  on  August  17,  2007  and  after  

hearing the learned counsel for the parties, following  

order was passed by the Court: -

“Defendants have appeared.

List the Suit along with this application  on 05th September, 2007.

Written statement and the objections to  this I.A. may be filed in the meantime.

The defendant-State  is  restrained from  rupturing  the  Bhakra  Main  Line  Canal  connecting  the  proposed  Hansi  Branch  –  Bhutana  Branch  Multipurpose  Channel  till  then.”

After pleadings were complete, the Court had framed  

five issues for determination by order dated August 26,  

2008.  Thereafter, pursuant to directions given by the  

Court from time to time the evidence is being recorded  

in the Suit.

3. During the pendency of the above numbered Suit,  

the State of Punjab has filed present interlocutory  

application,  and  prayed  to  grant  ad  interim  

injunction  restraining  the  Defendant-State  of  

Haryana  from  further  proceeding  with  the  

3

4

construction  of  a  concrete  toe  wall/providing  

concrete  lining  on  the  outer  slope  of  the  left  

embankment  between  RD 45000  and  57000  of  

the  Hansi  Branch  –  Bhutana  Branch  

Multipurpose Link Channel (MPCL).  On service  

of a copy of the interlocutory application the State  

of Haryana has filed detailed reply to which the  

State of Punjab has filed rejoinder.   

4. This application was heard at great length and in  

great  detail  on  different  dates  as  indicated  in  

order-sheets.   On August  26,  2011 Mr.  Mohan  

Jain,  the  learned  Additional  Solicitor  General,  

had submitted  a copy of  “Brief  Note  on BML –  

Hansi  Branch  –  Bhutana  Branch  Multipurpose  

Link Channel (MPCL) Haryana” prepared in July,  

2011.  A copy of the said Brief Note was taken on  

record  and  the  plaintiff  as  well  as  defendants  

were granted time to enable them to file response  

to the report submitted by the learned Additional  

Solicitor  General.   In  order  to  support  oral  

arguments  the  learned  counsel  for  the  parties  

4

5

were  also  permitted  to  file  written  submissions  

and  accordingly  the  learned  counsel  for  the  

parties have filed written submissions.

5. The  State  of  Punjab  has  taken out  this  I.A.  to  

restrain  the  construction  of  a  concrete  toe-wall  

providing concrete lining on the outer slope of the  

left embankment.  The case of the Plaintiff-State  

of  Punjab  is  that  this  strengthening  will  result  

into an increased collection of back water and the  

sheet  flow  towards  the  State  of  Punjab.   This  

assertion is made on the footing that because of  

heavy rains in July-August, 2010 and flooding of  

the river Ghaggar,  which flows on the northern  

since of the stretch RD 45,000 to RD 57,000 of  

this canal, such water-clogging did take place in  

Punjab, in spite of a breach of the canal at point  

RD  53,000,  and  whereby  some  15  villages  

suffered  and  severe  damage  and  nuisance  of  

various kinds over an area of around 5000 acres  

had taken place.   The breach has already been  

attended  by  the  State  of  Haryana,  to  which  

5

6

Punjab  did  not  object.   It  is  objecting  to  this  

strengthening work which is being done to avoid  

any such breach in the future.  It is stated that  

the  strengthening  work  undertaken  by  the  

Defendant-State  of  Haryana  is  likely  to  cause  

further  serious  nuisance.   According  to  the  

Plaintiff-State  of  Punjab,  the  principle  of  

cooperative federalism and territorial integrity of  

the  State  of  Punjab  do  not  permit  the  

Government  of  Haryana  to  construct  a  toe-

wall/providing concrete lining on the outer slope  

of left embankment as the proposed construction  

has propensity of causing serious damage to lives  

and properties situated within the territory of the  

State  of  Punjab.   It  is  also  claimed  that  the  

construction undertaken by the State of Haryana,  

if allowed to complete, will cause in the event of  

heavy  rains  and  flooding  of  River  Ghaggar,  in  

future  an  adverse  impact  on  the  population  of  

Punjab  in  more  than  70  villages  and  would  

inevitably  result  in  prolonged  and  perpetual  

6

7

submergence  of  thousands of  acres of  lands in  

more than 32 villages.  The State of Punjab has  

mentioned that the protective measures sought to  

be undertaken by the State of Haryana are in the  

very area in which breach had taken place during  

the floods  of  2010 and but for  the  breach,  the  

floods  would  have  completely  inundated  and  

annihilated 70 villages in Punjab territory if sheer  

pressure  of  the  waters  had not  resulted  in  the  

canal being breached.  Under the circumstances,  

the  State  of  Punjab  has  filed  the  present  

application  and  claimed  the  relief  to  which  

reference is made earlier.  It may be mentioned  

that the prayer made by the State of Punjab is  

supported by the State of Rajasthan.

6. Before  this  Court  deals  with  the  submissions  

advanced at the Bar by the learned counsel for  

the parties, it is absolutely necessary to note and  

explain  the  topography  of  the  region  where  

construction  of  concrete  toe  wall/providing  

concrete  lining  on  the  outer  slope  of  the  left  

7

8

embankment  is  undertaken  by  the  State  of  

Haryana.   

7. The  Bhakra  Main  Line  Canal  runs  from  the  

Bhakra  Dam through  the  State  of  Punjab  and  

goes  to  the  State  of  Haryana  and then  further  

goes towards the State of Rajasthan.  The State of  

Haryana  was  carved  out  from  the  then  bigger  

State  of  Punjab  and  it  came  into  existence  on  

November 1, 1996.  There are two rivers which  

flow in this particular region.  One is known as  

the Patiala Nadi.  It runs almost parallel to the  

Bhakra  Main  Line  Canal  from  north  to  south-

west.   There  is  another  river  named  Ghaggar  

which runs from north-east to south-west.  The  

plateau of Punjab and Haryana is a flat plateau,  

which  slopes  towards  the  State  of  Haryana.  

There is a Bandh which has been constructed on  

the  south  of  Ghaggar  River.   The  Bandh  runs  

from north-east to south-west.  This Bandh was  

constructed way back in the year 1950 when the  

State  of  Haryana  was  not  even  created.   The  

8

9

Bandh was constructed  so  that  when the  river  

gets flooded during monsoon, its water would not  

further  overflow towards  the southern side.   In  

the year 1970,  the State of  Punjab constructed  

what is known as the Mirapur Drain, which runs  

from a point to the north-east of river Ghaggar in  

the  State  of  Punjab  and  joins  into  this  river  

somewhere to the  west  of  the  point  RD 45000.  

The Court was informed that this drain is 30 feet  

wide  and  10  feet  deep.   It  was  basically  

constructed to drain the excess water.   

8. It is pointed out on behalf of State of Haryana in  

its reply that though the injunction, as prayed for  

by the State of Punjab in I.A. No. 1 of 2007, was  

granted,  the  construction  of  the  canal  was  not  

restrained and it was completed by the year 2008  

at the risk of State of Haryana.  It is also stated in  

the reply that due to injunction granted by this  

Court, no water has been flowing in this canal.  It  

is common ground between the parties that at the  

stretch  between point  RD 45000 to  57000,  the  

9

10

canal and the Ghaggar River run parallel to each  

other  for  a  distance  of  about  three  and  a  half  

kilometres  within  the  territory  of  State  of  

Haryana.   The  Bandh,  however,  is  towards  the  

Punjab side and it is not disputed that the work  

which the State of Haryana is presently carrying  

out  is  at  the  bottom  of  the  Bandh  and  

particularly on the northern side, but up to the  

surface level a little above so that there should be  

no seepage of water and the Bandh does not get  

weakened.

9. It is pointed out by the State of Punjab that there  

was so much heavy rain and overflow of water in  

July/ August, 2010 that it led to a breach at the  

point  RD  53000  (almost  at  the  centre  of  this  

stretch RD 45000 to 57000), yet because of the  

Bandh and the canal there was huge back water  

formation in the territory of Punjab, which led to  

inundation of 15 villages in the State of Punjab.  

It  is  claimed  by  the  State  of  Punjab  that  the  

breach  has  been  attended  to  by  the  State  of  

10

11

Haryana  to  which  the  State  of  Punjab  did  not  

object.  According to the State of Punjab, what is  

being objected to  is  the  present work and it  is  

asserted that if that is permitted, in the event of  

heavy  rain  fall  and  excessive  water  in  river  

Ghaggar, the water will not flow towards the State  

of  Haryana,  but  the  back  water  will  spill  into  

larger  territory  of  the  State  of  Punjab.   It  is  

stressed that for protection the population of one  

State,  problem  cannot  be  created  in  another  

State.

10. On behalf of the State of Haryana, however, it is  

pointed  out  that  all  the  15  villages,  which  the  

State  of  Punjab  has  pointed  out  as  having  

suffered, are to the north of the Mirapur Drain  

and are quite far off.  Only four of those villages  

are somewhat near on the northern side of this  

Mirapur Drain.  It is, therefore, contended that if  

there is heavy rain waters from the northern side  

of Mirapur Drain, it would get collected into that  

drain and go down into Ghaggar River to a point  

11

12

to the west of RD 45000.  According to the State  

of Haryana, if there are heavy rains, the water in  

the  area  between  the  Mirapur  Drain  and  the  

Ghaggar River will go into the Ghaggar River or  

spill over into the Punjab territory because of the  

Bandh, but that has always been so, and if the  

Bandh  is  not  strengthened  and  more  breaches  

take place, water will flow down towards Haryana  

definitely  affecting  19 villages  in  the  immediate  

vicinity.  The State of Haryana has claimed that  

this is what had happened in July, 2010 when as  

against  some  5765  acres  of  land  getting  

submerged  in  the  State  of  Punjab,  more  than  

12,036 acres of land had got submerged in the  

State of Haryana affecting the population of some  

19 villages.  It is pointed out by the Defendant-

State of Haryana that earlier way-back in the year  

1993 this Bandh had breached and the State of  

Haryana  had  attended  it  at  that  very  point.  

According to the State of Haryana, the canal did  

not exist at that point of time and, therefore, the  

12

13

Bandh,  which was very much there,  had to  be  

repaired.  The State of Haryana has asserted that  

the  Bandh  was  created  when  the  State  of  

Haryana was not in existence and creation of the  

Bandh was with a view to preventing the damage  

basically  arising  out  of  heavy  flow  of  water  

towards villages to the south of the Bandh, which  

are  now  in  Haryana.   Explaining  further,  it  is  

pointed that the State of  Haryana had repaired  

this Bandh in the year 1993 and subsequently in  

the  year  2010 and that  the  Defendant-State  of  

Haryana should be permitted to strengthen the  

basement of the Bandh to avoid the recurrence of  

such an event.  What is asserted by the State of  

Haryana  is  that  the  breach  which  had  taken  

place in the year 2010 was attended to, and to  

avoid the recurrence the foundation of the Bandh  

is  being  strengthened  to  stop  the  seepage  of  

water.   What  is  mentioned  by  the  State  of  

Haryana is that the work, which is being carried  

out, is not in the canal but is at the bottom of the  

13

14

Bandh, which is towards the Punjab side.  It is  

further stated that the work is up to the surface  

level and it is only to avoid the seepage of water  

therein.   Thus,  the  State  of  Haryana  prays  to  

dismiss the I.A. No. 7 of 2011 filed by the State of  

Punjab.

11. It is necessary to notice that the State of Haryana  

has relied upon the report of the Central Water  

Commission.  The State of Punjab has objected to  

the reliance thereof on the ground that when the  

engineers  of  Central  Water  Commission  visited  

the  particular  area,  the  Punjab  engineers  were  

not  informed  and  it  is  a  one-sided  report.  

However,  it  is  material  to  note  that  the  report  

clearly  states  that  the  strengthening  of  the  

basement of the canal is not going to cause any  

serious  prejudice  as  is  claimed by the  State  of  

Punjab on the Punjab side of the Bandh.  It is  

also  mentioned  in  the  report  that  there  are  

already siphons provided for water to flow under  

the canal, which is, of course, at a height of ten  

14

15

to  twelve  feet  above  the  surface  level.   In  the  

stretch between RD 45000 to 57000, this Court is  

not much concerned with canal or its height, but  

with  the  strengthening  of  the  basement  of  the  

Bandh.

12. As noticed earlier, the Bandh was constructed at  

a time when the State of Haryana was not carved  

out.  The State of Haryana has a duty to protect  

the  lives  and  property  of  the  citizens  residing  

within its territory and a right to carry out the  

work within its territory to protect its people.  It is  

true  that  the  State  of  Punjab  has  produced  

photographs  and  other  materials  to  show  the  

flooding  in  the  area  to  the  north  of  Ghaggar  

Bandh  at  the  stretch  between  RD  45000  to  

57000.  However, in view of what is stated earlier,  

it  is  not  possible  to  hold  that  the  previous  

flooding except for a limited area in Punjab was  

caused basically because of Ghaggar Bandh.

15

16

13. As  against  that,  this  Court  finds  that  the  very  

purpose  of  the  Bandh has been to  prevent  the  

flooding of the areas on the southern side of the  

Bandh,  which  is  in  Haryana.   The  particulars  

supplied by the State of  Haryana to this  Court  

would show that extensive damage was caused to  

the 19 villages of the State of Haryana, which was  

obviously due to breach of this Bandh/canal at  

the point RD 53000.   

14. It is relevant to mention that the Professors of IIT,  

Roorkee,  who  visited  the  site,  had  suggested  

remedial  measures  in  their  report  stating  that  

“seepage might be one of the causes of breach of  

Hansi-Bhutana  Branch  MPLC….  Necessity  of  

proving  a  barrier  on  both  banks  of  breached  

reach of canal and on the left bank only in similar  

weak  reaches  of  canal  to  be  identified  by  

department.  This could be done by way of steel  

sheet  pile  or  RCC wall  or  steel  sheet  pile  with  

RCC cap”.

16

17

15. In fact the State of Punjab’s own expert has also  

admitted the need to strengthen the Bandh.  He  

had made another suggestion in his report of July  

13, 2011.  The suggestion made is as under: -

“It  is  a  well  understood  knowledge  that  a  deep vertical cut-off or a sheet pile is better  suited for seepage control as compared to a  toe wall and, ……….. toe walls are generally  shallower  in  comparison  and  are  usually  required in order to provide support for slope  protection measures such as stone pitching.”

Further,  paragraph 10.1 of the CWC Report  of  July,  

2011 mentions following relevant facts: -

“The  RCC  toe  wall/protection  wall  is  being  constructed with a RCC CAP whose top has  been  shown  to  be  flush  with  NSL.   This  implies that the top of the toe wall will be at  or slightly above or below NSL.  Therefore the  toe wall will not act as an obstruction for flow  of water.”

xxx xxx xxx

“Construction of the toe wall is a part of the  embankment,  with  its  top  at  NSL,  and  its  construction  will  not  interfere  with  the  existing drainage system in a very significant  manner.” (NSL = Natural Surface Level)

17

18

16. (i) An  assertion  is  made  by  the  State  of  

Haryana that in fact State of Haryana had relied  

on the principle of cooperative federalism against  

the  State  of  Punjab  during  the  course  of  

arguments in its Suit No. 6 of 1996 relating to the  

construction  of  the  Satluj  Yamuna  Link  Canal  

and other schemes and that the State of Punjab  

is not entitled to invoke the said principle against  

the State of Haryana because of its conduct.  We  

do not think it appropriate to go into this issue in  

the present application.  Similarly, the argument  

advanced on behalf  of  the State of  Punjab that  

after  having  repaired  the  breach  in  2010,  the  

current  strengthening  work  by  Haryana  is  

nothing  but  political  posturing  need  not  be  

examined by this Court because in reply to this  

contention, it is argued by the learned counsel for  

the  State  of  Haryana  that  in  fact  I.A.  No.  7  of  

2011  is  nothing  but  political  posturing  on  the  

part of State of Punjab and the application has  

been motivated by internal politics in Punjab just  

18

19

prior to impending elections late this year/early  

next year.  Such an issue cannot be decided on  

the  basis  of  allegations  and  counter-allegations  

made by the parties and appropriate evidence will  

have to be led by the parties to enable the Court  

to decide the same.   

(ii) The apprehensions expressed by the State of  

Punjab in paragraph 16 of the I.A. No. 7 of 2011 are  

based on hypothesis.  We are informed by the State of  

Punjab that the cunnette capacity of Mirapur Drain is  

829  cs.  after  its  widening  in  2003-2004  and  is  not  

sufficient  to  drain  all  the  flood  water.   We  are  also  

informed that  the  ground level  of  the  villages  varies  

between 778 to 784 ft.  The highest flood level of River  

Ghaggar is of the order of about 794 ft. as mentioned  

in  the  2008  report  of  CWC.   It  was,  therefore,  

submitted  that  if  the  water  level  in  the  area  of  the  

north of the canal goes up by 2 ft., the flooding in the  

villages will be to the extent of 8 ft. (792.4 – 784).  As of  

now itself, it is difficult to accept that the flooding in  

the areas to the north of Mirapur Drain was caused  

19

20

due to the flooding in River Ghaggar, where 4 villages  

are situated somewhat nearby to the north of Mirapur  

Drain.  Assuming to be so, the other 11 villages are  

much further to the north and nearer to the Patiala  

Nadi.  If there are heavy showers because of monsoon  

and  the  rivers  and  nalas  get  flooded  that  will  be  

because of heavy rains all over the areas.  Heavy rains  

will be in those areas also and it is difficult to accept  

that the areas in the 15 villages got flooded because of  

the  Ghaggar  Bandh,  despite  the  breach therein.   In  

any case it  is  very clear  that  the  damage in  the  19  

villages in Haryana which are on the southern side of  

River Ghaggar is clearly attributable to the over flowing  

waters  of  River  Ghaggar  as  well  as  water  flowing  

through  the  breach.   The  relief  claimed  in  the  

interlocutory application cannot, therefore, be granted  

on the basis of a hypothesis, that the strengthening of  

the  Bandh  will  cause  flooding  in  70  villages.   The  

submission made on behalf of the State of Punjab that  

strengthening  of  Ghaggar  Bandh  would  cause  

backwater formation in Punjab and thus, exacerbate  

20

21

the nuisance of submerging of villages in Punjab to the  

north of the Ghaggar Bandh, is not correct because the  

Ghaggar Bandh was constructed by the erstwhile State  

of Punjab in 1950s for the purpose of preventing flood  

waters, entering and submerging areas to the south of  

the Bandh.  It  was constructed neither to guide the  

course  of  River  Ghaggar  nor  was  it  designed  to  be  

deliberately weak enough to give way in heavy floods.  

It was constructed to hold backwaters in the heaviest  

of floods to prevent flood waters from ever submerging  

the villages to the south.  The Bandh performed the  

function  for  which  it  was  designed  until  the  first  

breach occurred in 1993.  Though the breach which  

had occurred in 1993 was repaired and stone-pitching  

was  applied  to  the  outer  slope  to  make  the  Bandh  

stronger,  the  flood  of  2010  resulted  into  another  

breach  in  the  same  area  causing  serious  and  

widespread damage.  The case of State of Punjab rests  

on the premise that the breach repaired area should be  

allowed to remain as it is without strengthening it so  

that it can breach again if there is flood once again,  

21

22

and  this  area  can  act  as  a  pressure  release  valve,  

which would cause less damage to the State of Punjab.  

This assertion of right is contrary to the rights of the  

Defendant-State  of  Haryana,  which  is  entitled  to  

protect  its  inhabitants  from floods  just  as  erstwhile  

State of Punjab was entitled to protect its inhabitants  

to the south of the Bandh.  The State of Haryana is  

only ensuring that after the two disastrous breaches of  

1993 and 2010, a breach does not occur in the future.  

This Court is of the opinion that the State of Punjab  

cannot reasonably object to this course of action.   

17. As is evident, a concrete toe-wall or a vertical cut-

off  below  the  ground  from  the  natural  surface  

level  is  intended  to  prevent  slippage  of  the  

concrete lining and also prevent seepage of water  

below the ground level  because it  is  such high  

level  of  seepage  continuing  throughout  the  

monsoon  that  erodes  the  base  of  the  

Bandh/embankment and by a sliding movement  

makes the  Bandh weak and unstable.   Such a  

weak and unstable Bandh is unable to withstand  

22

23

the  pressure  of  the  flood  water  above  ground  

level.  The concrete lining proposed on the outer  

slope is to strengthen the Bandh for withstanding  

flood water  pressure  above  ground level  and to  

prevent  slippage  of  the  lining.   Both  these  

measures have only one object, i.e., to prevent a  

breach of the Bandh.  The toe-wall would prevent  

seepage  below  ground  and  also  prevent  the  

weakening of the base of the Bandh, whereas the  

concrete lining of  the outer slope of  the Bandh  

above ground level would enable it to withstand  

the pressure of flood water.

18. Before we conclude, we must note that although  

both the  States  are  canvassing  the  principle  of  

inter-State  cooperation,  yet  there  is  this  

unfortunate  controversy.   The  Central  

Government has not taken any stand whatsoever.  

Whether  the  dispute  should  be  referred  to  the  

Inter-State River Water Disputes Tribunal, is one  

of the issues to be decided in the suit.  We are,  

however,  required  to  decide  the  interim  

23

24

application on the basis of  data which is made  

available to us.

19. Hence, in view of the larger damage, which was  

caused in Haryana in the year 2010, and which is  

likely to be caused in Haryana, if  the Bandh is  

not properly repaired as undertaken, the balance  

of convenience is in favour of the Defendant-State  

of Haryana.  It is rightly pointed out by the State  

of  Haryana  that  if  the  relief,  as  prayed  for,  is  

granted  to  the  State  of  Punjab,  it  is  State  of  

Haryana,  which  will  suffer  greater  loss  and  

irreparable  injury.   It  cannot as well  be denied  

that State of Haryana has the right to carry out  

the necessary work in its territory and also the  

duty to its citizens.

20. For  the  foregoing  reasons,  it  is  not  possible  to  

entertain  this  Interlocutory  Application.   The  

same is, therefore, rejected.

………………………………J.

24

25

                  (J.M. PANCHAL)

……………………………….J.  (H.L. GOKHALE)

New Delhi; September 23, 2011.

25