STATE OF BIHAR (NOW ST.OF JHARKHAND) THROUGH THE SUB DIVISIONAL OFFICER Vs TATA IRON AND STEEL CO. LTD.
Bench: HON'BLE MR. JUSTICE L. NAGESWARA RAO, HON'BLE MR. JUSTICE M.R. SHAH
Judgment by: HON'BLE MR. JUSTICE L. NAGESWARA RAO
Case number: C.A. No.-003861-003861 / 2014
Diary number: 9215 / 2008
Advocates: ANIL K. JHA Vs
KARANJAWALA & CO.
Non - Reportable
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No . 3861 of 2014
State of Bihar (Now State of Jharkhand) Through the Sub Divisional Officer .... Appellant
Versus
Tata Iron & Steel Co. Ltd. …. Respondent
J U D G M E N T
L. NAGESWARA RAO, J.
1. The Certificate Officer, Jamshedpur issued a notice for
recovery of a sum of Rs.5,97,97,527.92/- towards interest on
arrears of rent payable by the Respondent on 10.05.1994.
The objection raised by the Respondent was rejected by an
order dated 23.01.1996. The Respondent filed a Writ Petition
challenging the demand and the order dated 23.01.1996 of
the Certificate Officer in the High Court of Bihar at the Ranchi
Bench (now Jharkhand), which was allowed. This Appeal
arises out of the said judgment of the High Court.
1
2. Land was acquired and conveyed to the Respondent
between the years 1912-1929 under the Land Acquisition
Act, 1894 for setting up an industry. The Respondent
established an integrated steel plant, allied manufacturing
units, township, civic amenities for its staff, hospitals,
schools, parks, etc. The entire township came up gradually
which was renamed as Jamshedpur.
3. The Bihar Land Reforms Act was enacted in the year
1950 (for short “the BLR Act”) and by a Notification dated
01.01.1956 all lands of the Respondent Company stood
vested in the State Government. Section 2B was inserted in
the BLR Act in the year 19611 exempting the lands which
were acquired for an industrial undertaking from the
application of the BLR Act. By virtue of the said amendment,
the Respondent’s lands were exempted from vesting under
the BLR Act. Thereafter, Section 2B of the BLR Act was
deleted in the year 1972 vide the Bihar Land Reforms
(Amendment) Act, 19722 (for short “Amendment Act, 1972”).
Consequently, the lands of the Respondent again stood
vested in the State. Amendment Act, 1972 was assailed by
1 Vide Bihar Land Reforms (Amendment) Act, 1960, Act 02 of 1961. 2 Act No.5 of 1972
2
the Respondent by way of a writ petition in this Court. The
implementation of the Amendment Act, 1972 against the
Respondent was stayed by this Court. Later, the Writ Petition
was withdrawn by the Respondent and the State of Bihar
amended the BLR Act in the year 1982 by enacting the Bihar
Land Reforms (Amendment) Act, 1982 (for short
“Amendment Act, 1982”). Sections 7D and Section 7E of the
BLR Act were substituted by the Amendment Act, 1982 and
the Respondent was treated as the deemed lessee of the
State Government for the lands held by it subject to the
payment of fair and equitable rent which was to be
determined by the State Government.
4. An Agreement for lease was entered into between the
Appellant and the Respondent on 01.08.1984. It was agreed
that the lands together with the buildings and structures as
were being used for the purposes of factories or mills or
godowns by the Respondent were saved to the company
under Section 7 of the BLR Act on payment of rent at the rate
of Rs.200/- per acre per year effective from 01.01.1956.
Clause (xii) of the Agreement provided that all rents and
dues from the Respondent company to the State
3
Government for the period from 01.01.1956 to 31.03.1984
particularly in respect of clauses (i), (ii), (iii), (v), (vi), (ix) and
(x) therein shall be paid in three equal annual installments
with interest. The first installment had to be paid on or
before 31.12.1984 and the interest would be calculated at
the rate of 9.5% from 01.01.1956 to 31.12.1974 and at the
rate of 13% from 01.01.1975 to 31.03.1984. According to
Clause (xv), the existing hats, Melas, Bazaars, Jalkars,
fisheries and other Sairats were to be settled by the State
Government with the Respondent company on a fixed jama
for a period of five years at a time and the Respondent had
to carry on the management and administration thereof on
payment of the entire amount of the fixed jama to the State
Government. The entire amount realized towards the above
mentioned items by the Respondent for the period between
01.01.1956 and 31.03.1984 was agreed to be paid by the
Respondent to the State Government in three equal
installments with the first of such installment due on or
before 31.12.1984. The interest on such dues was to be paid
at the rate of 9.5% per annum for the period between
4
01.01.1956 and 31.12.1974 and at the rate of 13% per
annum for the period between 01.01.1975 and 31.03.1984.
5. A formal lease deed was executed on 01.08.1985
incorporating the terms of the Agreement for Lease dated
01.08.1984 (for short “Lease Deed”). A demand was raised
by the State Government for payment of Rs.1.95 Crores as
rent along with interest as per Clause (xii) of the Lease Deed
on 11.09.1985. A further demand of Rs.2.19 Crores was
made on 18.10.1985 towards rent coupled with interest in
terms of Clause (xv) of the Lease Deed. The Respondent
complied with the demand and made the payments.
6. On 29.10.1993, a letter was written by the Secretary,
Department of Revenue and Land Reform, Bihar (for short
“the Secretary”) to the Deputy Commissioner, Jamshedpur in
which it was stated that the Government was suffering heavy
losses due to the absence of the words “per annum” for
calculation of interest in Clause (xii) of the Lease Deed. After
obtaining legal opinion, the Secretary directed the Deputy
Commissioner, Jamshedpur to re-calculate the interest on the
arrears of rent payable under Clause (xii) of the Lease Deed
5
on a yearly basis in the same manner as done for the rent on
the lands under Clause (xv) and realize the same from the
Respondent. A certificate proceeding was issued by the
District Collector, Jamshedpur under the Bihar and Orissa
Public Demands Recovery Act, 1914 (for short “Public
Demands Act”) by which the Respondent was directed to pay
Rs.5.97 Crores towards interest calculated on per annum
basis in respect of the lands under Clause (xii) of the Lease
Deed. The Respondent filed a Writ Petition against the said
demand before the High Court of Bihar, Ranchi Bench (now
Jharkhand). The contention raised on behalf of the
Respondent that the demand cannot be said to be a public
demand under the Public Demands Act was rejected by the
learned Single Judge of the High Court. The learned Single
Judge observed that the demand for the payment of interest
on rent payable under the Lease Deed entered into pursuant
to the BLR Act would certainly fall within the sweep of Item
(vii) of Schedule I read with Section 6(3) of the Public
Demands Act. Writ Petition No. 2761 of 1994 was dismissed
as being not maintainable but liberty was granted to the
Respondent to raise all objections relating to their liability to
6
pay in accordance with the provisions of Section 9 of the
Public Demands Act. The Certificate Officer was directed to
consider the objections notwithstanding any delay in filing
the same without being influenced by the observations made
by the High Court. The judgment of the learned Single Judge
was affirmed by the Division Bench in the LPA No.276 of
1995 (R) filed by the Respondent.
7. On 23.01.1996, the Certificate Officer rejected the
objections that were filed by the Respondent. Questioning
the legality and validity of the demand and the Order of the
Certificate Officer by which the objections were rejected, the
Respondent filed a Writ Petition before the High Court of
Bihar, Ranchi Bench (now Jharkhand). The High Court stayed
the execution of the demand subject to the Respondent
depositing Rupees One Crore before 30.03.1996 and
furnishing a Bank Guarantee for the remaining amount. In
compliance of the interim order of the High Court, we are
informed by the learned Senior Counsel for the Respondent
that an amount of Rupees One Crore was deposited in the
High Court on 28.03.1996. The High Court by the impugned
7
judgment allowed the Writ Petition filed by the Respondent
and concluded as follows:
“48 (i)The wording contained in clause (xii) and clause (xv) would clearly convey the meaning that clauses (xii) would indicate that interest in respect of the said clause can be calculated only on “lump sum” basis and not “per annum” basis as there is no use of words “per annum” in clause (xii) like that of clause (xv) and therefore, the impugned demand for interest “per annum” in respect of clause (xii) is illegal.
(ii) The impugned demand is not a “public demand” within the meaning of section 3(6) of the Bihar and Orissa Public Demands Recovery Act, 1914 as the demand in question is concerned with the interpretation of clause (xii) and hence the demand is not realizable in certificate proceedings.”
8. Guided by the decisions of this Court on the
interpretation of contracts in Delhi Development
Authority v. Durga Chand,3 Provash Chandra Dalui v.
Biswanath Banerjee,4 20th Century Finance
Corporation Ltd. v. State of Maharashtra,5 and Union of
India v. Shiv Dayal Soin & Sons (P) Ltd.,6 the High Court
3 (1973) 2 SCC 815 : AIR 1973 SC 2609 ¶19 and 21 4 (1989) 1 SCC Suppl. 487: AIR 1989 SC 1834 5 (2000) 6 SCC 12 ¶ 12 6 (2003) 4 SCC 695
8
was of the opinion that the contract must be construed as a
whole and that the meaning of the words contained in the
contract has to be formed on the facts and circumstances of
each case in the light of the terms and conditions of the
contract. According to the High Court, the words expressly
mentioned in one place but not in another place must be
taken to have been deliberately omitted on the well settled
principle of Expressio Unius Est Exclusio Alterius. The High
Court found that Clause (xii) and Clause (xv) pertain to two
different types of lands. Clause (xii) relates to properties
falling in Clauses (i), (ii), (iii), (v), (vi), (ix) and (x) of the
Lease Deed wherein the Respondent developed the lands by
setting up industries, buildings, structures, roads, civic
amenities, hospitals, etc. whereas Clause (xv) dealt with the
lands settled by the Government on a fixed jama on a period
of five years at a time. Lands covered in Clause (xv) were
being utilized for hats, bazaars, melas, Jalkars, fisheries and
other Sairats from which the Respondent was earning money.
Taking into account the difference in the nature of the lands
and their utility, the High Court held that the word “per
annum” was intentionally included in Clause (xv) of the
9
Lease Deed and excluded from Clause (xii) of the Lease
Deed. The High Court observed that the State cannot travel
beyond the terms and conditions of the Lease Deed and
issue a demand for payment of interest under Clause (xii) by
calculating the same on a yearly basis.
9. The High Court accepted the submission made on
behalf of the Respondent that the demand that was made by
the Certificate Officer was not a public demand within the
meaning of Section 3(6) of the Public Demands Act. The
High Court remarked that Sections 7D and 7E of the BLR Act
did not provide for payment of interest and the interest
charged by the State of Bihar was pursuant to an agreement.
As the demand was purely contractual, it cannot be termed
as a “public demand”, according to the High Court.
10. The judgment of the High Court was criticized by the
learned Senior Counsel for the Appellant, Mr. Sunil Kumar, on
more than one count. Being aware of the earlier judgment of
the High Court wherein the very same demand was held to
be a public demand under the Public Demands Act by
another Division Bench of the same High Court, a different
10
view could not have been taken by the Division Bench. If the
Division Bench was not in agreement with the judgment of
the earlier Division Bench the only course open to it was to
refer the matter to a larger Bench. The learned Senior
Counsel for the State further submitted that the word “rent”
has not been defined in the BLR Act. He submitted that the
words and expressions used in the BLR Act but not defined
thereunder would have the same meaning as per the
definitions in the Bihar Tenancy Act, 1885 or the Chota
Nagpur Tenancy Act, 19087. As the Chota Nagpur Tenancy
Act, 1908 was applicable to the lands in question, the word
“rent” as defined in Section 3(xxviii) of the Chota Nagpur
Tenancy Act, 1908 would apply to the facts of the case.
“Rent” as defined in the said Act includes any rent lawfully
payable by a tenant to his landlord on account of the use or
occupation of the land held by the tenant and includes all
dues (other than personal services) which were recoverable
under any enactment for the time being in force as if they
were rent. The learned Senior Counsel contended that in
view of the definition of “rent” in the Chota Nagpur Tenancy
Act, 1908 which includes all dues recoverable under any
7 Section 2(t), BLR Act
11
enactment, it cannot be said that the demand made by the
State of Bihar was not a public demand. On the
interpretation of Clauses (xii) and (xv) of the Lease Deed, he
stated that the mere omission of the words “per annum” in
Clause (xii) would not make any difference and the
Government committed an inadvertent error in the
calculation of interest payable under Clause (xii) in the year
1985 which was corrected later.
11. Mr. Gopal Jain, learned Senior Counsel for the
Respondent, argued that the High Court was right in its
interpretation of Clause (xii) and Clause (xv) of the Lease
Deed by taking into account the intention of the parties. He
submitted that the revised demand made in the year 1994
was a unilateral decision of the Government contrary to the
terms of the Lease Deed. The demand made by reading the
words “per annum” into Clause (xii) of the Lease Deed is
wholly impermissible.
12. The well known rule of interpretation of Contracts is
that the deed ought to be read as a whole in order to
ascertain the true meaning of its several clauses and a word
12
of each Clause should be so interpreted as to bring it into
harmony with the other provisions of the deed, if that
interpretation does no violence to the meaning of which they
are naturally susceptible.8
13. Lord Hope speaking for the Supreme Court of the United
Kingdom stated the principles of interpretation as follows9:
“The court’s task is to ascertain the intention of the parties by examining the words they used and giving them their ordinary meaning in their contractual context. It must start with what it is given by the parties themselves when it is conducting this exercise. Effect is to be given to every word, so far as possible, in the order in which they appear in the clauses in question. Words should not be added which are not there, and words which are there should not be changed, taken out or moved from the place in the clause where they have been put by the parties. It may be necessary to do some of these things at a later stage to make sense of the language. But this should not be done until it has become clear that the language the parties actually used creates an ambiguity which cannot be solved otherwise.”
8 Chamber Colliery Ltd. v. Twyerould (Note) (1893) (1915) 1 Ch. 268, per Lord Watson 9 Multi-Link Leisure Developments Limited v. North Lanarkshire Council (Scotland) [2010] UKSC 47
13
14. The well known principles of interpretation of a contract
were correctly appreciated by the High Court. The question
that falls for our consideration in this case is whether the
demand of interest made by the Certificate Officer for the
arrears of rent payable under Clause (xii) of the Lease Deed
was valid or not.
15. It is relevant to refer to Section 7D and Section 7E of
the BLR Act.10 The Agreement dated 01.08.1984 and the
10 7D.Land and buildings etc. acquired for an industrial undertaking and utilized for providing civic amenities, namely, health, housing, welfare, power house and educational facilities to be deemed settled with it by the State –(1) If any land has been acquired for an industrial undertaking under the Land Acquisition Act, 1894 (Act 1 of 1894) so much of such land and buildings and structures thereon in possession of the industrial undertaking as are being utilized for providing civil amenities, namely, health, housing, welfare, power house and education facilities to its employees and so much of the remaining portion of such land and building and structures thereon as are found essential on enquiry by the State Government for production processes of the industrial undertaking shall be deemed to have been leased out by the State Government with the owner of the industrial undertaking for period as determined by the State Government subject to payment of such fair and equitable rent as determined by the State Government.
(2) The provisions of sub-section (1) shall have effect notwithstanding anything contained in section 4(a) and shall be without prejudice to the exemptions granted or concession given to intermediaries under Sections 5, 6, 7, 7A, 7B and 7C.
(3) If the claim of the industrial undertaking as to possession over the lands, buildings and structures thereon, referred to in sub-section (1) or to the extent of such lands, buildings and structure is disputed by any person within three months of the commencement of the Bihar Land Reforms (Amendment) Act, 1972, the Collector shall make such inquiries in the matter as he deems fit and pass orders as may appear to him as just and fair.
(4) The provisions of sub-section (1) shall be deemed to have been inserted in this Act from the commencement thereof.
7E. Land and building, etc., acquired for an industrial undertaking and leased out by it to another industrial undertaking for its expansion by establishing new industry or to an individual to be deemed as leased with it by State Government on same terms. -[If any portion out of the land acquired for an industrial undertaking under the Land Acquisition Act, 1894 (Act I of 1894) has been leased out by the industrial undertaking before the 22nd June, 1970 to another industrial undertaking for establishment of a new industry or its expansion or to any individual or society or association for residential, commercial or for such other purpose, the whole of such land, buildings or structures covered by such lease shall with effect from the commencement of this Act, be deemed to be leased to the industrial undertaking for such period as may be determined by the State Government subject to payment of
14
Lease Deed dated 01.8.1985 was entered into pursuant to
the abovementioned provisions of the BLR Act. Clause (xii)
of the Lease Deed pertains to lands which have been
developed by the Respondent by establishing industries and
other civic amenities whereas Clause (xv) relates to lands
which were being used for commercial purposes. The
Respondent was making money from the use of lands that
were covered under Clause (xv) for which reason the “jama”
was also fixed for the lands falling under Clause (xv) for five
years at a time. Interest being calculated on a yearly basis
as per Clause (xv) is clearly due to the lands being used for
commercial purposes wherefrom the Respondent was getting
returns. The exclusion of the words “per annum” in Clause
(xii) was intentional and the Appellant cannot be permitted
to read those words into Clause (xii) for the purpose of
issuing a demand of additional amount towards interest. A
plain reading of the Lease Deed as a whole would make it
fair and equitable rent as determined by the State Government and the other industrial undertaking, individual, society or association to whom lease has been granted by the industrial undertaking shall be deemed to be the sub-lessee of the original industrial undertaking and the provisions of clauses (G) and (H) of Section 4 shall not be effective with respect to such land or buildings or structures thereon.
The terms and conditions of the lease granted under sub-section(1), shall be determined by the State Government: Provided that if the period of sub-lease expires before the expiry of the lease granted under sub-section (1) then in that condition at the time of renewal of the sublease, the State Government shall have power to revise the amount of rent payable to State Government by the lessee.
15
clear that the payment of interest on rent chargeable under
Clause (xii) is essentially different from that under Clause
(xv). The principle of Expressio Unius Est Exclusio Alterius is
squarely applicable to the facts of this case. For the above
reasons, we are in agreement with the finding of the High
Court that the District Collector, Jamshedpur was not right in
issuing a demand for payment of Rs.5.97 Crores towards
interest on the arrears of rent for the lands covered under
Clause (xii) of the Lease Deed.
16. However, the conclusion of the High Court that the
demand does not fall within the sweep of the Public
Demands Act is not correct. Being aware of the earlier
decision of the High Court on this point, an error was
committed by the High Court in taking a completely different
view. If the High Court was not in agreement with the earlier
decision, the only course open to it was to refer the matter to
a larger Bench. That apart, in Clause (xx) of the Lease Deed,
the Respondent and the Appellant agreed that recoveries of
arrears of rent may be affected under the Public Demands
Act. It is not open to the Respondent to contend that the
demand made for payment of interest under the Lease Deed
16
as not a public demand in view of Clause (xx) of the Lease
Deed. “Public demand” has been defined in Section 3(6) of
the Public Demands Act as under:
“3. Definitions. … …
(6) “Public demand’ means any arrear or money mentioned or referred to in Schedule I, and includes any interest which may, by law, be chargeable thereon upto the date on which a certificate is signed under Part II.”
Item No.7 of Schedule I of the Public Demands Act is as
follows:
“Any demand payable to the Collector by a person holding any interest in land, pasturage, forest-rights, fisheries or the like, whether such demand is or is not transferable, when such demand is a condition of the use and enjoyment of such land, pasturage, forest right, fisheries or other things.”
17. Item No.7 of Schedule I covers any demand payable by
a person holding any interest in land. Therefore, interest on
rent payable for the lands would, in our opinion, be
recoverable under Item No.7 of Schedule I read with Section
3(6) of the Public Demands Act.
18. The judgment of the High Court is upheld though we are
not approving the conclusion of the High Court that the
demand is not a public demand under the Public Demands
Act. The amount of Rupees One Crore deposited by the
17
respondent in the High Court on 28.03.1996 pursuant to the
interim order shall be returned to the respondent.
19. For the aforementioned reasons, the Appeal is
dismissed.
.................................J. [L. NAGESWARA RAO]
..................................J. [M.R.SHAH]
New Delhi, May 09, 2019.
18