13 July 2011
Supreme Court
Download

SHIPPING CORPORATION OF INDIA LTD. Vs MARE SHIPPING INC

Bench: ALTAMAS KABIR,A.K. PATNAIK, , ,
Case number: SLP(C) No.-019461-019461 / 2006
Diary number: 21076 / 2006


1

REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

SPECIAL LEAVE PETITION (C) No.19461 of 2006

SHIPPING CORPORATION OF INDIA LTD. … PETITIONER(s)  

VS.

MARE SHIPPING INC.  … RESPONDENT(s)

J U D G M E N T

ALTAMAS KABIR, J.

1. The Special Leave Petition arises out of the  

Judgment and Order dated 24.10.2005 passed by the  

learned Single Judge of the Bombay High Court in

2

A.P.No.531  of  2003  affirming  the  Award  of  the  

Arbitral Tribunal dated 8.9.2005, and the judgment  

and order dated 20.1.2006 passed by the Division  

Bench dismissing A.N.No.1158 of 2005 filed by the  

Petitioners herein.

2. On  9.11.1999  the  Petitioners  and  the  

Respondent(s)  entered  into  a  Charter  Party  in  

respect  of  the  Respondents’  vessel,  “m.t.  

Prestige”,  for  carriage  of  minimum  8150  metric  

tonnes of crude oil from the Egyptian Red Sea port  

of  Ras  Sukheir  to  one/two  safe  

anchorage(s)/lighterage  points/SBM(s)/one/two  safe  

port(s)one/two  safe  berth(s)  anywhere  in  India.  

The  vessel  was  described  in  Clause  41  of  the  

Charter Party as being fitted with “AK Tongue Type  

Bow Chain Stopper of min SWL 2000 Mts.”

3. Clause  9  of  the  Charter  Party  provided  for  

settlement  of  all  disputes  arising  out  of  the  

2

3

Charter Party by arbitration under the Arbitration  

&  Conciliation  Act,  1996,  and  the  Maritime  

Arbitration  Rules  of  the  Indian  Council  of  

Arbitration (ICA).   

4. The vessel arrived at Ras Sukheir at 4.00 a.m.  

on  19.11.1999  and  tendered  Notice  of  Readiness  

(NOR).  The  loading  commenced  at  10  p.m.  on  

20.11.1999  and  was  completed  by  3.15  p.m.  on  

21.11.1999.   The  total  lay  time  provided  for  

loading  and  discharge  of  cargo  was  72  running  

hours.  Out of the said lay time hours, the lay  

time  used  at  Ras  Sukheir  was  37  hours  and  30  

minutes.   On  account  of  a  mishap  involving  the  

vessel’s anchor and the submarine pipe-lines, the  

vessel was delayed at Ras Sukheir for fourteen days  

and could leave the port only on 4.12.1999.  On  

6.12.1999  while  the  vessel  was  sailing,  the  

Respondents nominated Vadinar Single Berth Mooring  

(SBM)  for  discharge  of  the  cargo.   Port  of  

3

4

discharge  had  not  been  nominated  earlier.   The  

vessel arrived at Vadinar and the Master tendered  

NOR at 8 p.m. on 15.12.1999.  Since the vessel had  

only one chain stopper/Bow Panama Chock, which had  

been  specified  in  the  Charter  Party,  the  vessel  

could  not  be  safely  moored  at  the  SBM  and  the  

Master  was  asked  by  the  Receiver,  Indian  Oil  

Corporation on 21.12.1999 to take away the vessel  

from the Vadinar SBM.   

5. On  21.12.1999  a  message  was  sent  to  the  

Petitioners’ Agents, M/s. J.M. Baxi & Co. by the  

Manager of the Respondents drawing attention to the  

fact that the vessel could not be berthed at the  

SBM and requesting that immediate steps be taken to  

berth the vessel.  In the absence of any positive  

response  to  the  said  letter,  the  Respondents’  

lawyer, Mr. Prashant Pratap, sent a legal notice to  

the Petitioners on 24.12.1999 indicating that the  

vessel  continued  to  await  discharge  incurring  

4

5

demurrage  for  which  the  Petitioners  were  held  

responsible.  The Petitioners were also informed  

that on account of the detention of the vessel at  

Vadinar,  there  was  a  serious  possibility  of  the  

vessel missing its next engagement.

6. Finally a decision was arrived at on 28.12.1999  

and  Addendum  No.1  to  the  Charter  Party  dated  

9.11.1999 was drawn up and signed by the Owners and  

the  Charterers  containing  the  following  further  

conditions agreed upon, namely,  

a) m.t.  Prestige  will  be  diverted  by  the  

Charterers from Vadinar to L.P.O. Mumbai for  

discharge.   

b) Charterers  will  pay  freight  basis  Ras  

Sukheir/LPO  Mumbai  where  cargo  will  be  

discharged  into  a  daughter  vessel  and  

Charterers will pay all the expenses of the  

daughter vessel, M.T. Maharaja Agrasen.

5

6

(c) Charterers will bear the cost of deviation  

of m.t. Prestige basis Ras Sukheir/LPO Mumbai  

v/s  Ras  Sukheir/Vadinar/LOP  Mumbai  which  

included time at the demurrage rate.

d) The extra cost of bunkers incurred as a  

result of the deviation will be on Charterers’  

account,  subject  to  the  Owners  submitting  

documentary evidence.

(e) All direct expenses incurred by the Owners  

at Vadinar towards pilotage, tugs and other  

port expenses and Agency fees, will be settled  

by the Charterers.

(f) Demurrage  to  be  settled  as  per  Charter  

Party terms.   

7. Pursuant  to  the  above  arrangement,  m.t.  

Prestige  sailed  from  Vadinar  at  1  a.m.  on  

29.12.1999 and arrived at Mumbai Lighterage point  

6

7

on 30.12.1999 at 2 p.m.  The vessel tendered Notice  

of Readiness at 2 p.m. on 30.12.1999 and completed  

discharge  at  3.30  p.m.  on  1.1.2000.  The  

Respondents/Owners submitted their demurrage claims  

along with supporting documents to the Charterers  

on  3.2.2000.   As  the  said  claim  was  disputed,  

arbitration was invoked by the parties under the  

provisions of the Arbitration & Conciliation Act,  

1996, hereinafter referred to as “the 1996 Act”.  

Both the parties appointed their Arbitrators and  

the  two  Arbitrators  appointed  a  third  as  the  

Presiding  Arbitrator.   The  Arbitrators  made  and  

published their Award dated 26.8.2003 by which they  

allowed the Respondents’ demurrage claim in full.  

Certain other amounts payable under the Addendum  

dated 28.12.1999 were also awarded in favour of the  

Claimants/Respondents.   

8. The  said  Award  was  challenged  by  the  

Petitioners/Charterers in the Bombay High Court on  

7

8

the ground that the Respondents had not proved that  

the  Notice  of  Readiness  had  been  tendered  at  

Vadinar and consequently the Respondents were not  

entitled  to  demurrage  for  the  period  that  m.t.  

Prestige  was  detained  at  Vadinar.   The  learned  

Single  Judge  of  the  High  Court  accepted  the  

submission made on the Petitioners’ behalf and by  

his order dated 25.4.2005 remitted the matter to  

the  Arbitration  for  a  proper  finding  in  this  

regard,  with  leave  to  the  Respondents/owners  to  

lead  evidence  to  prove  tender  of  the  Notice  of  

Readiness to the Petitioners/Charterers.

9. After  remand,  the  Arbitrators  passed  another  

Award on 8.9.2005 after admitting fresh evidence,  

including  documentary  evidence,  holding  that  the  

service of the Notice of Readiness by the Master of  

the  vessel  on  the  Agents  of  the  Petitioners  at  

Jamnagar  had  been  duly  proved  in  view  of  the  

evidence  of  the  Petitioners’  witness,  Mr.  Sunil  

8

9

D’Souza that he had asked Captain Jude D’Souza for  

a  copy  of  the  Notice  of  Readiness  sent  by  the  

Master to the Petitioners’ Agents at Jamnagar.  The  

said  fact  was  also  confirmed  by  Mr.  S.J.  Joshi  

during  his  evidence  before  the  Tribunal.   The  

Arbitrators  also  noted  that  no  attempt  had  been  

made by the Charterers to rebut Mr. Sunil D’Souza’s  

evidence by producing Captain Jude D’Souza.

10. The  Tribunal  accordingly  held  that  the  

Respondents/Owners  were  entitled  to  receive  

demurrage  in  the  amount  of  U.S.  $220376.48,  

together with interest and costs, as awarded in the  

earlier Award of 26.8.2003.

11. On  receiving  a  copy  of  the  Award  of  the  

Tribunal  dated  8.9.2005,  the  Petitioners  applied  

for amendment of the Petition under Section 34 of  

the 1996 Act.  However, by order dated 24.10.2005  

the learned Single Judge dismissed the Arbitration  

9

10

Petition No.531 of 2003.  An appeal, being No.1158  

of 2005, was filed by the Petitioners before the  

Division  Bench  of  the  Bombay  High  Court  which  

dismissed the same on 20.1.2006.

12. The  present  Special  Leave  Petition  has  been  

filed  against  the  said  Award  of  the  Arbitration  

dated 8.9.2005, as well as the judgments and orders  

dated  24.10.2005  and  20.1.2006  passed  by  the  

learned Single Judge and the Division Bench of the  

Bombay High Court confirming the Award.

13. Mr. Bhaskar Gupta, learned Senior Advocate, who  

appeared  for  the  Petitioners,  focused  his  

submissions  on  the  sustainability  of  the  

Respondents’ claim for demurrage.  Urging that a  

claim for demurrage can only arise after the expiry  

of the “lay days”, namely, the time specified for  

loading or discharging the cargo from the vessel,  

Mr. Gupta submitted that the all-important question  

10

11

in respect of such a claim is when do the lay days  

commence and when are they used up.  Mr. Gupta  

submitted that the commencement of lay days depends  

on three factors :-

a) Firstly, the ship must be an “arrived  

ship”  in  order  to  give  Notice  of  

Readiness.

b) Secondly,  she  must  have  given  the  

prescribed  notice  to  load  or  

discharge, as the case may be.

c) Thirdly, she must be ready to load or  

discharge, as the case may be.

14. Mr. Gupta submitted that whether the ship is an  

“arrived  ship”  or  not  depends  on  the  point  

designated  as  the  destination  in  the  mutual  

understanding of the parties in the Charter Party  

itself  or  the  terms  thereof  –  the  degree  of  

precision being a matter of agreement between the  

11

12

parties.  Mr. Gupta urged that in practice, the  

destination is usually a part or a specified area  

within the port such as a basin, a dock, or a buoy  

at a certain distance from the shore or a river.  A  

still more precise point would be where the loading  

or discharge is to take place, e.g., a particular  

quay, pier, wharf or mooring.  Mr. Gupta submitted  

that a ship is said to be an “arrived ship” only  

when she has reached the particular point and has  

moored  there.   Mr.  Gupta  urged  that  the  said  

propositions  are  well-established  and  have  been  

laid down in (1) Leonis Steamship Company Ltd. Vs.  

Rank Limited (1908) 1 K.B. 499; (2) Armament Adolf  

Deppe Vs.  John Robinson & Company Ltd. [1917]  2  

K.B. 204; and (3) Owners of S.S. Plata Vs. Ford &  

Co. (1917) 2 K.B. 593.  We shall have recourse to  

refer  to  the  aforesaid  decisions  later  in  this  

judgment.

12

13

15. Mr.  Gupta  submitted  that  Clause  ‘D’  of  the  

Charter  Party  dated  9.11.1999,  specifies  

“discharging  port”  as  one/two  safe  

anchorage(s)/lighterage  point(s)/SBM(s),  1/2  safe  

Ports, 1/2 safe Berth(s) and full India.  Mr. Gupta  

also submitted that the Charter Party provides that  

on arrival of the vessel for discharge at Vadinar,  

the vessel was to maintain 70% of her deadweight on  

board for safe mooring at a SBM.

16. Mr. Gupta urged that by a communication dated  

6.12.1999,  the  Petitioners/Charterers  designated  

Vadinar SBM as the destination and not a ‘Port’.  

The destination was, therefore, a specific point  

and not a large area like a Port.  Vadinar SBM,  

therefore,  became  the  destination  as  if  

incorporated  in  the  Charter  Party  itself.   Mr.  

Gupta submitted that inspite of the best efforts of  

the Terminal Authorities, IOC, who were also the  

receivers of the cargo, m.t. Prestige was unable to  

13

14

moor at the Vadinar Single Berth Mooring (SBM) on  

account of the fact that it had only one bow chain.  

It may be of interest to note that Vadinar is the  

only SBM in the whole of India.  Mr. Gupta urged  

that inspite of the various attempts of the Port  

Authorities, the vessel could not be berthed at the  

Vadinar SBM and was asked to move away.  Mr. Gupta  

contended that since the vessel could not be moored  

at Vadinar, it was not an “arrived vessel’ and “lay  

time” could not be said to have commenced running  

on 15.12.1999.  The Notice of Readiness given by  

the Petitioners could not, therefore, be treated as  

valid and the period spent at Vadinar could not be  

taken into consideration while computing the number  

of lay days utilized.

17. In  support  of  his  aforesaid  contention,  Mr.  

Gupta referred to and relied on the decision of the  

House of Lords in the case of  Johanna Oldendorff,  

(1973) 11 LLR 285, in which Viscount Dilhorne laid  

14

15

down ten tests for determining when a ship is an  

arrived ship.  Mr. Gupta referred to the first and  

fifth tests as being relevant in the context of  

this case and the same are extracted hereinbelow :

(i) That under a port Charter Party to  

be an “arrived ship”, that is to say  

a  ship  at  a  place  where  a  valid  

Notice  of  Readiness  to  load  or  

discharge  can  be  given,  she  must  

have ended her voyage at the port  

named; and

(ii) A vessel has not reached her port of  

destination  until  it  has  ended  its  

voyage within the port, either in its  

legal,  or  if  it  differs,  in  its  

commercial sense.  If it is refused  

permission  and  ordered  to  wait  

outside  the  port  by  the  Port  

15

16

Authority,  it  is  not  an  “arrived  

ship”.

18. Mr. Gupta submitted that the mere fact that the  

vessel had arrived near the SBM and had anchored  

there would not make the vessel an “arrived ship”,  

because the destination was the SBM and not the  

port and the vessel could end her voyage only when  

she was moored at the SBM, which the vessel was  

unable  to  do.   Mr.  Gupta  submitted  that  the  

decision  in  Johanna  Oldendorff’s  case  was  an  

affirmation of the Kings Bench decision in the case  

of  Leonis Steamship Company Ltd. Vs.  Rank Limited  

(1908) 1 K.B. 499.  Mr. Gupta urged that not having  

been allowed to berth at the SBM, the vessel could  

not be categorized as an “arrived ship” for the  

purpose of issuing Notice of Readiness, which Mr.  

Gupta  submitted  had  not  been  served  on  the  

Petitioners in the first place.   

16

17

19. By way of an alternative argument, Mr. Gupta  

submitted  that  under  Clause  6  Part  II  of  the  

Charter Party, the delay at Vadinar could not be  

counted as lay time, because it was the receivers  

(I.O.C.) and not the Charterers who declared that  

safe  berthing  of  the  vessel  at  Vadinar  was  not  

possible  because  of  infra-structural  deficiencies  

and  not  because  of  any  fault  on  behalf  of  the  

Petitioners since the Petitioners had no control  

over the situation.  Accordingly, the entire time  

from  the  tender  of  the  Notice  of  Readiness  on  

15.12.1999,  if  at  all  tendered,  till  the  vessel  

started discharge in Bombay, had to be excluded in  

calculating lay time.

20. Mr. Gupta submitted that service of the Notice  

of Readiness had not been proved even after remand,  

as the only evidence tendered was that of Sunil  

D’Souza which, in any event, did not prove anything  

beyond the fact that he had been asked to get a  

17

18

copy of the Notice of Readiness from the Agent.  

Furthermore, the entire evidence of Sunil D’Souza  

was hearsay.

21. On  the  question  of  Safe  Port  Warranty,  Mr.  

Gupta contended that only after all attempts had  

been made to berth the vessel at the SBM that it  

was  asked  to  move  away  from  the  mooring.  

Consequently,  even  if  the  finding  of  the  

Arbitrators  that  the  Petitioners  had  failed  to  

designate a safe port was accepted, at best the  

ship owners could be entitled to damages and not  

demurrage  and  would  be  subject  to  the  ordinary  

rules  as  to  remoteness,  mitigation  etc.,  as  

available  under  Section  73  of  the  Contract  Act.  

Mr.  Gupta  submitted  that  the  Respondents  had  

claimed damages before the learned Arbitrators who,  

however, allowed demurrage in their Award on the  

ground that demurrage is a genuine pre-estimate of  

damages.  Mr. Gupta submitted that even if there  

18

19

was a breach of warranty on the Petitioners’ part,  

the same would give rise to a claim for damages and  

not demurrage within the scope of Sections 73 and  

74 of the Contract Act.   

22. Mr. Gupta submitted that in the Addendum dated  

28.12.1999  to  the  Charter  Party  dated  9.11.1999  

since the Charterers had agreed to bear the cost of  

deviation  basis  Ras  Sukheir/LPO  Mumbai  vs  Ras  

Sukheir/Vadinar/LPO Mumbai, which included time at  

the demurrage rate, there could not be a separate  

claim for demurrage as that would amount to double  

jeopardy.  Mr. Gupta submitted that it is the said  

provision contained in Clause (f) of the aforesaid  

Addendum which has given rise to this arbitration.  

Mr.  Gupta  submitted  that  although  the  Award  has  

relied on Clause 4(1) of Part II of the Charter  

Party, which provides that extra expenses incurred  

in  connection  with  any  change  in  loading  or  

discharging  ports,  has  to  be  paid  by  the  

19

20

Charterers, and any time thereby lost to the vessel  

shall count as used lay time, the said clause would  

have to be read in the context of Clauses 4(a) and  

4(b)  where  certain  ports,  other  than  any  Indian  

Port, have been named.

23. On the question of mitigation of damages, Mr.  

Gupta urged that the Petitioners/Owners had done  

everything in its power to safely berth the vessel  

at the SBM Vadinar, which was perhaps the only SBM  

in operation in India at the relevant point of time  

and would otherwise have been ideal for discharge  

of the cargo of crude oil.  Mr. Gupta contended  

that it was IOC, the receiver, who had taken almost  

two weeks to decide to redirect the vessel from  

Vadinar to Mumbai. Mr. Gupta submitted that it was,  

in effect, the Respondents who did not take any  

steps to mitigate the damages.

20

21

24. On the quantum of demurrage or damages, Mr.  

Gupta submitted that since the demurrage rate was  

fixed at US $16000 per day and the same has really  

a  genuine  pre-estimate  of  damages,  the  Tribunal  

should have awarded damages at a reasonable rate,  

instead of making its Award on the consideration of  

damage as fixed in the Charter Party.  Mr. Gupta  

urged that the Tribunal had gone completely wrong  

in giving a go-bye to the provisions of Sections 73  

and 74 of the Contract Act in awarding compensation  

in keeping with the provisions for fixed demurrage  

in the Charter Party, particularly when all the lay  

days had not been used up.

25. Mr.  Gupta  submitted  that  the  scope  of  a  

petition under Section 34 of the 1996 Act had been  

considered by this Court in detail in Oil & Natural  

Gas Corporation Ltd. Vs. Saw Pipes Ltd. [(2003) 5  

SCC 705], and it was indicated therein that if the  

Award passed by the Arbitral Tribunal was contrary  

21

22

to  any  of  the  provisions  of  the  Act  or  the  

substantive  law  governing  the  parties  or  was  

against the terms of the contract, the same could  

be set aside.  Mr. Gupta urged that even in the  

instant case, the law had been misapplied by the  

Arbitrators  who  had  missed  considering  the  all-

important issue that no valid Notice of Readiness  

could have been tendered by a ship which was not an  

“arrived  ship”.   In  such  circumstances,  the  

petition  under  Section  34  of  the  1996  Act  was  

clearly not maintainable.   

26. In conclusion, Mr. Gupta drew our attention to  

the wording of Clause 6 of the Charter Party which  

deals with Notice of Readiness and in particular,  

to the last sentence thereof where delay in getting  

a  berth  for  a  vessel  after  giving  Notice  of  

Readiness, for any reason over which the Charterer  

has no control, shall not count as used lay time.  

Mr.  Gupta  submitted  that  the  facts  of  the  case  

22

23

would clearly indicate that the Arbitral Tribunal  

failed  to  take  into  consideration  the  facts  in  

their true sequence and ended up in a “cart before  

the horse” situation, since no demurrage, which is  

the consequence of using up all the lay time, could  

have been awarded without a correct computation of  

the used “lay time”.    

27. Going to the heart of the matter, Mr. Prashant  

Pratap, learned Advocate, submitted that the case  

of  the  Petitioners/Charterers  of  the  vessel  

depended primarily on the terms and conditions of  

the Charter Party on the basis whereof the Arbitral  

Tribunal  had  awarded  demurrage  to  the  

Respondents/Owners of the vessel.  As was also done  

by  Mr.  Gupta,  special  emphasis  was  laid  by  Mr.  

Prashant Pratap on Clause 6 of the Charter Party  

relating to Notice of Readiness.  Learned counsel  

emphasized  the  fact  that  in  terms  of  the  said  

clause, the Master of the vessel or his Agent would  

23

24

give the Charterer or his Agent notice by letter,  

telegraph, wireless or telephone that the vessel is  

ready  to  load  or  discharge  cargo,  berth  or  no  

berth,  and  lay  time  would  commence  upon  the  

expiration of six hours from receipt of such notice  

or upon the vessel’s arrival in berth, which would  

mean  finished  mooring  when  at  a  sea  loading  or  

discharging terminal and all fast when loading or  

discharging  alongside  a  wharf  whichever  first  occurs.   Then  follows  the  rider  that,  however,  where the delay is caused to the vessel getting  

into berth after giving Notice of Readiness for any  

reason over which the Charterer has no control, the  

delay caused could not be counted as used lay time.

28. Mr. Prashant Pratap referred to Clauses 8 and 9  

of  the  Charter  Party  dealing  with  Demurrage  and  

Safe Berthing Shifting.  Clause 8 provides that the  

Charterer shall pay demurrage per running hour and  

pro rata for a part thereof at the rate specified  

24

25

in Part I for all the time taken for loading and  

discharging when the time taken for discharging the  

cargo exceeds the allowed lay time specified.  If,  

however, delay in discharge of the cargo is caused  

at the port of loading and/or discharge by reason  

of  fire  or  other  unavoidable  circumstances,  the  

rate of demurrage would be reduced to one-half of  

the amount stated in Part I per running hour or pro  

rata for part of an hour for demurrage so incurred.  

It was also stipulated that the Charterer would not  

be liable for demurrage for delay caused by strike,  

lockout,  stoppage  or  restraint  of  labour  for  

master, officers and crew of the vessel or tugboat  

or pilots.  Mr. Prashant Pratap also pointed out  

that Clause 9 of the Charter Party which provides  

for  Safe  Berthing  Shifting  indicates  that  the  

vessel shall load and discharge at any safe place  

or wharf, or alongside vessels or lighterage point  

reachable on her arrival, which shall be designated  

25

26

and procured by the Charterer, provided the vessel  

could proceed thereto, lie at and depart therefrom  

always safely afloat.  Clause 9 also enables the  

Charterer to shift the vessel at ports of loading  

and/or discharge from one safe berth to another on  

payment of towage and pilotage for shifting to the  

next berth and other expenses and the time consumed  

on account of such shifting would count as used lay  

time, except as otherwise provided in Clause 15.

29. Mr.  Prashant  Pratap  then  contended  that  the  

question as to whether M/s. m.t. Prestige was an  

“arrived ship” or not at port Vadinar, had never  

been raised either before the learned Single Judge  

or the Division Bench of the High Court, nor was it  

taken as a ground in the Special Leave Petition.  

Learned  counsel  submitted  that  even  the  ground  

taken with regard to the Notice of Readiness being  

invalid, as the vessel was allegedly not ready in  

all respects to discharge its cargo, was neither  

26

27

argued  before  the  learned  Single  Judge  or  the  

Division  Bench  nor  was  the  ground  taken  in  the  

Special Leave Petition before this Court.

30. Coming to the question as to what constitutes  

an “arrived ship”, Mr. Prashant Pratap submitted  

that the said question was extensively considered  

by  the  House  of  Lords  in  the  case  of  Johanna  

Oldendorff (supra), which was also relied upon by  

Mr. Gupta, where the House of Lords was of the view  

that the vessel should have reached a position in  

the  port  where  she  is  at  the  immediate  and  

effective  disposition  of  the  Charterers  and  for  

practical  purposes  it  is  so  much  easier  to  

establish that if the ship is at the usual waiting  

place within the port where waiting vessels would  

normally  lie  before  proceeding  to  the  berth  

nominated by the Charterers for discharge of cargo.  

If the vessel is at such a place, then the vessel  

is considered to be an “arrived ship”.  It is only  

27

28

thereafter  that  the  vessel  can  tender  Notice  of  

Readiness.   Furthermore,  if  the  Charter  Party  

provides for the location where the vessel should  

arrive and tender Notice of Readiness, then if the  

vessel  has  reached  that  location,  the  vessel  is  

considered to be an “arrived ship”.  Mr. Prashant  

Pratap submitted that in the present Charter Party,  

the parties have expressly agreed in Clause 6 for  

the  vessel  to  arrive  at  customary  anchorage  (emphasis  supplied)  at  the  port  of  loading  or  

discharge  and  tender  Notice  of  Readiness.  

Accordingly, once the vessel arrived at anchorage  

at Vadinar, it became an arrived ship in terms of  

Clause 6 of the Charter Party and was entitled to  

tender Notice of Readiness.

31. Mr. Prashant Pratap submitted that it was not  

disputed that M/s. m.t. Presitge was at customary  

anchorage at Vadinar Port when Notice of Readiness  

was  tendered.   Mr.  Prashant  Pratap  also  placed  

28

29

emphasis  on  the  expression  “berth  or  no  berth”,  

included in Clause 6 of the Charter Party which  

meant that even if a berth was not available or the  

vessel had not reached the berth, the vessel is  

entitled  to  tender  Notice  of  Readiness.   Mr.  

Prashant Pratap submitted that the term had been  

explained in the case of the NOTOs where dealing  

with a clause identical to Clause 6 of the Charter  

Party, it was held that the meaning of the said  

words indicated that the Notice of Readiness could  

be given upon arrival at the customary anchorage  

and could take effect whether or not a berth was  

then available or not for the vessel.   

32. Mr.  Prashant  Pratap  then  argued  that  the  

submission  made  on  behalf  of  the  

Petitioners/Charterers  that  since  the  destination  

in the Charter Party had been shown as “SBM” and  

the vessel had failed to be moored at the SBM, no  

demurrage could be claimed, was wholly erroneous on  

29

30

account  of  the  fact  that  such  notice  could  be  

tendered  on  the  arrival  of  the  vessel  at  the  

customary anchorage.  The vessel is not, therefore,  

required to be at the destination within the port  

for the purpose of becoming an “arrived ship” and  

for tendering of Notice of Readiness.

33. Referring to Mr. Gupta’s submissions that for  

the purpose of tendering Notice of Readiness, the  

vessel must be an arrived ship, Mr. Prashant Pratap  

submitted that the vessel, therefore, must be at  

the effective disposal of the Charterers who would  

have  unrestricted  access  to  the  vessel’s  cargo  

tanks and the vessel pumps must be in working order  

to  pump  out  the  cargo  upon  the  hoses  being  

connected, provided that the Charterers were ready  

to receive the cargo.  In this regard, Mr. Prashant  

Pratap  referred  to  the  decision  in  the  Leonis  

Steamship Co. Ltd. (supra), where it was observed  

by  Lord  Justice  Kennedy  that  “the  ship’s  

30

31

obligations, therefore, under such a Charter Party  

the  performance  of  which  much  precede  the  

commencement of the lay days (as the fixed loading  

period is commonly termed) are three : Firstly, the  

ship must have arrived at her destination and so be  

within the designation of an arrived ship.  Till  

then  she  is  not  entitled  to  give  a  Notice  of  

Readiness to load.  Secondly, she must have given  

the  prescribed  Notice  of  Readiness  to  load.  

Thirdly, she must, in fact, be so far as she is  

concerned, ready to load.  The ship owner cannot  

claim against the Charterer that the lay days begin  

to count until the ship is an arrived ship; ……………”  

Mr. Prashant Pratap submitted that the aforesaid  

passage made it clear that the vessel has to be  

ready to load or discharge, as the case may be.  

The  Tribunal’s  findings  are  that  the  vessel  was  

ready, but the terminal was not.  The Tribunal held  

that the vessel was at the immediate and effective  

31

32

disposition  of  the  Charterers  when  Notice  of  

Readiness was given.   

34. Mr. Prashant Pratap then urged that from the  

Charter  Party  it  is  quite  clear  that  the  

responsibility  of  providing  a  berth  where  the  

vessel could moor safely was that of the Charterers  

and the same would be clear from the use of the  

word “safe” in Clause D of Part I of the Charter  

Party  which  precedes  the  words  

“Ahchorage/Lighterage Points/SBM”.  Even in terms  

of Clause 9 of the Charter Party, the place of  

discharge must be safe and has to be designated and  

procured by the Charterers.  Mr. Prashant Pratap  

referred to various other judgments such as the Sea  

Queen [(1988) Vol.1 KKR 500] and  Fjordaas [(1988)  

Vol.1 LLR 336].  In the later case, it has been  

indicated that “reachable” or “arrival” are well-

known  expressions  and  mean  precisely  what  they  

say.  It was further observed that if the berth  

32

33

cannot  be  reached  on  arrival,  the  warranty  is  

broken, unless there is some relevant protecting  

exception.  Such berth, in its term, is required to  

have two characteristics: it has to be safe and it  

also has to be reachable on arrival.  By nominating  

SBM at Vadinar as the destination of the vessel and  

also the place for discharge of the cargo, it was  

the responsibility of the Charterers to ascertain  

as  to  whether  the  vessel  could  be  moored  there  

safely and be in a position to discharge the cargo  

safely.   

35. Apart  from  the  aforesaid  questions  regarding  

the  vessel  being  an  arrived  ship,  Mr.  Prashant  

Pratap  urged  that  service  of  the  Notice  of  

Readiness  by  the  Master  on  the  Agents  of  the  

Charterers have been duly proved and is a finding  

based  on  appreciation  of  evidence  by  the  

Arbitrators, which has been upheld by the learned  

33

34

Single Judge and the Division Bench, whose orders  

were under challenge in the Special Leave Petition.  

36. Mr. Prashant Pratap urged that if the Notice of  

Readiness was valid, as had been found not only by  

the  Arbitral  Tribunal  but  also  by  the  learned  

Single Judge and the Division Bench of the Bombay  

High Court, then lay time commenced six hours after  

the tender of Notice of Readiness.  Accordingly,  

lay time expired on 17.12.1999, and, thereafter,  

the vessel was on demurrage all throughout, till  

discharge of the cargo was completed.   Since in  

the  instant  case,  the  Charterers  had  failed  to  

nominate a safe berth at which the vessel could  

safely lie and discharge the cargo and failing to  

provide a berth which was reachable upon arrival of  

the  vessel  at  Vadinar,  the  consequent  delay  in  

berthing  and  discharge  of  the  cargo,  was  the  

responsibility  of  the  Charterers  for  which  

demurrage was payable by them.  Mr. Prashant Pratap  

34

35

pointed out that at no stage did the Charterers  

question the validity of the Notice of Readiness  

tendered at Vadinar either on the ground that the  

vessel was not an arrived ship, or on the ground  

that  the  vessel  was  not  ready  to  discharge  the  

cargo.  On the contrary, the Charterers signed the  

Addendum dated 28.12.1999 by which they agreed to  

bear all the expenses incurred by the vessel at  

Vadinar and also agreed to pay additional freight  

charges  for  discharge  of  cargo  at  Mumbai.  

Significantly, the Charterers also agreed that the  

time taken for the vessel to proceed from Vadinar  

to  Mumbai  would  count  as  demurrage  time.   Mr.  

Prashant Pratap urged that the Charterers would not  

have  agreed  to  the  terms  and  conditions  of  the  

Addendum if it was their contention that the vessel  

was  not  an  arrived  ship  or  that  the  Notice  of  

Readiness was invalid.   

35

36

37. Mr.  Prashant  Pratap  then  submitted  that  the  

only requirement as far as the vessel was concerned  

was that it had to maintain 70% of the dead weight  

on board for safe mooring at the SBM at Vadinar and  

it is nobody’s case that the vessel did not conform  

to such condition.

38. On the question of designation of the SBM as  

the destination point within Vadinar Port by the  

Charterers, Mr. Prashant Pratap contended that the  

Charterers  had  been  put  on  notice  regarding  the  

berthing arrangement both in the Charter Party as  

well  as  in  the  questionnaire  setting  out  the  

vessel’s  mooring  arrangements  provided  to  the  

Charterers.  Learned counsel submitted that it was  

for the Charterers to check the vessel equipment  

vis-à-vis  facilities  available  at  the  Port  of  

loading and discharge, before nominating the same.  

Since the Charterers had failed to undertake such  

an exercise, there was a resultant problem faced at  

36

37

Vadinar whereby the vessel could not discharge its  

cargo at Vadinar but had to be diverted to Mumbai.  

Mr. Prashant Pratap also pointed out that while the  

entire  Indian  coastline  was  available  to  the  

Charterers to nominate a safe port for discharge of  

the cargo, it made a conscious decision to nominate  

the SBM at Vadinar which ultimately turned out to  

be  unsafe  for  mooring  of  the  vessel,  given  the  

equipment available on board the ship.  

39. Mr. Prashant Pratap submitted that it had been  

agreed on behalf of the Charterers that demurrage  

is a genuine pre-estimate of damages and even if  

the Charterers’ argument is to be accepted that the  

owners are entitled to damages and not demurrage,  

the calculation of such damages would have to be  

the demurrage rate in the facts and circumstances  

of the case.   

37

38

40. Mr.  Prashant  Pratap,  accordingly,   submitted  

that the award of the Arbitral Tribunal, as upheld  

both by the learned Single Judge and the Division  

Bench of the Bombay High Court, did not warrant any  

interference  and  the  Special  Leave  Petition  was  

liable to be dismissed with appropriate costs.

41. Having  gone  through  the  submissions  made  on  

behalf of the respective parties in the background  

of the facts as disclosed, it is clear that we are  

required to consider two basic questions for the  

purpose  of  deciding  the  present  Special  Leave  

Petition, namely :-

(a) Whether on arriving at anchorage point at Port  

Vadinar,  despite  the  destination  point  being  

the SBM mooring, it could be said that it was  

an arrived ship which was competent under the  

Charter Party dated 9.11.1999, to issue Notice  

of Readiness of discharge of its cargo?

38

39

(b) If the finding of the Arbitral Tribunal that  

the vessel was an arrived ship at Port Vadinar,  

as upheld by the learned Single Judge and the  

Division  Bench  of  the  Bombay  High  Court  is  

accepted, would the Respondents/Owners of the  

vessel be entitled to damages or demurrage?

42. Various ancillary questions connected with the  

aforesaid  two  questions  also  crop  up,  which  we  

shall consider shortly.   

43. From the undisputed facts, the position that  

emerges is as follows :-

(i) The  Charter  Party  dated  9.11.1999  was  in  

respect of a transaction which provided for  

carriage of crude oil from Ras Sukheir to a  

safe  port  on  the  Indian  coastline.    The  

Charterers  were  given  the  choice  of  

39

40

nominating  such  port  for  discharge  of  the  

aforesaid cargo of crude oil.

(ii) In  the  absence  of  any  named  port  of  

destination in the Charter Party itself, it  

was only after the vessel left Ras Sukheir  

that  an  intimation  was  given  by  the  

Charterers for discharge of the cargo at the  

SBM at Port Vadinar in Gujarat.

(iii) That  the  aforesaid  nomination  was  a  

conscious  decision  on  the  part  of  the  

Charterers, despite having knowledge of the  

equipment available on board the vessel for  

mooring at a SBM, and in keeping with such  

decision m.t. Prestige set its course from  

Ras Sukheir to Vadinar.

(iv) The fiasco at Vadinar was occasioned by the  

fact that no prior checking had been done to  

see  whether  with  the  mooring  equipment  on  

40

41

board, the vessel would be able to safely  

berth at the SBM for discharge of its cargo.

(v) Who was responsible for the detention of the  

vessel at Vadinar since its arrival at the  

anchorage point and its final departure from  

the  said  Port?   Whether  there  was  

contributory negligence on the part of both  

the parties in the cause of such delay?

44. The  concept  of  an  arrived  ship  in  shipping  

terminology requires that a vessel should reach a  

destination in a port where she could be safely  

berthed and thereupon be ready to either discharge  

or load cargo from and on to the vessel.  That is a  

general concept, but the Charterers and the Owners  

of the vessel could in the Charter Party agree to a  

specific destination point within the port area for  

discharging or loading of cargo.  Once the vessel  

arrived at the said spot and was ready to discharge  

41

42

its cargo, it could be described as an “arrived  

ship” with the authority to issue and tender Notice  

of Readiness. In the instant case, the nominated  

port  for  the  arrival  of  the  vessel  was  Vadinar  

Port, but the destination point was the SBM where  

the vessel was to be moored and was to discharge  

its cargo of crude oil. In fact, in the Charter  

Party  dated  9.11.1999,  Clause  6  specifically  

provided for arrival of the vessel at the port of  

loading or discharge and cast an obligation upon  

the Master or his Agent to give the Charterer or  

his  Agent  Notice  of  Readiness  in  relation  to  

discharge of the cargo.  Since the decision in this  

case  will  to  a  large  extent  depend  on  the  

interpretation of Clause 6, the same is extracted  

hereinbelow :

“Clause 6 Notice of Readiness :

Upon  arrival  at  customary  anchorage  at  each  port  of  loading  or  discharge,  the  Master  or  his  Agent  shall  give  the  

42

43

charterer or his Agent notice by letter,  telegraph, wireless or telephone that the  vessel is ready to load or discharge cargo  berth  or  no  berth  and  lay  time  as  hereinafter  provided  shall  commence  upon  the  expiration  of  six  (6)  hours  after  receipt of such notice or upon the vessel  arrival in berth – finished mooring when  at a sea loading or discharging terminal  and all fast when loading or discharging  alongside a wharf which ever first occurs.  However, where delay is caused to vessel  getting  –  berth  after  giving  notice  of  readiness  for  any  reason  over  which  charterer has no control, such delay shall  not count as used lay time.”    

45. As will be evident from the above clause, the  

Master of the vessel was under an obligation to  

give  Notice  of  Readiness  on  arrival  at  the  

customary anchorage at the port of discharge.  It  

is a possibility that since no specific port in the  

Indian coastline had been mentioned in the Charter  

Party, the Master of the vessel or his Agent was  

required  to  give  Notice  of  Readiness  upon  the  

vessel arriving at customary anchorage.  It is only  

after the vessel sailed from Ras Sukheir that the  

receiver, IOC, nominated Vadinar to be the port of  

43

44

discharge with the specific destination point being  

the SBM within the port.  In giving such Notice of  

Readiness upon arrival at the customary anchorage  

at Vadinar, the Master of the Vessel duly complied  

with  the  conditions  of  Clause  6  of  the  Charter  

Party  and  in  terms  of  the  aforesaid  clause  

irrespective of whether a berth was available or  

not,  lay  time  commenced  upon  the  expiry  of  six  

hours  after  receipt  of  such  notice.   That  the  

vessel  could  not  be  moored  at  the  SBM  is  a  

different facet of the story.  The Charterers had  

full  knowledge  of  the  equipment  on  board  m.t.  

Prestige through the questionnaire provided by the  

Respondents/Owners  to  the  Petitioners/Charterers.  

It could not be denied that despite having such  

knowledge  the  IOC  nominated  the  SBM  as  the  

destination  point  for  discharge  of  the  cargo.  

Obviously, the parties to the Charter Party had not  

made  any  attempt  to  verify  as  to  whether  the  

44

45

equipment on board the vessel was sufficient for  

her to be safely moored at the SBM and to discharge  

her cargo safely.  As it turned out later on, the  

vessel  was  not  so  equipped  and  could  not,  

therefore,  be  moored  at  the  SBM  and  had  to  be  

requested  to  move  away  therefrom.   Although,  an  

attempt has been made on behalf of the Charterers  

to convince us that it was really the duty and  

responsibility of the Owner of the vessel to check  

whether the vessel could be safely moored at the  

SBM in Vadinar, we are unable to convince ourselves  

that such a duty was that of the Owners of the  

vessel and not the Charterers which had a choice of  

all the ports in India for discharge of the cargo,  

as was subsequently done in Mumbai port.  As has  

been held by the Arbitral Tribunal and subsequently  

affirmed both by the learned Single Judge and the  

Division  Bench  of  the  Bombay  High  Court,  the  

responsibility for the failure of the ship to moor  

45

46

at the SBM in Vadinar must lie squarely with the  

Charterers and the receiver as it was they who had  

nominated  the  SBM  for  the  safe  mooring  of  the  

vessel.  The lay time must, therefore, be held to  

have recommenced after the expiry of six hours from  

the tendering of the Notice of Readiness upon the  

vessel’s  arrival  at  the  customary  anchorage  at  

Vadinar  on  15.12.1999  in  keeping  with  the  

provisions of Clause 6 of the Charter Party. It was  

not the case of the Charterers that the failure of  

the vessel to discharge its cargo at the SBM at  

Vadinar was for reasons beyond their control.  It  

cannot also be said that the owners of the vessel  

contributed in any way to such failure since the  

equipment on board the vessel had been made known  

to  the  Charterers  when  the  Charter  Party  was  

signed.

46. In  the  face  of  the  specific  conditions  

indicated in Clause 6 of the Charter Party, the  

46

47

theoretical  and/or  academic  exercise  of  what  

constitutes  an  “arrived  ship”  loses  much  of  its  

relevance.  The  terms  of  the  Charter  Party  were  

agreed upon by the parties with their eyes wide  

open.  What is also significant and cuts at the  

root of the submissions advanced on behalf of the  

Charterers is that even after the vessel was denied  

mooring  at  the  SBM  for  safety  reasons  on  

21.12.1999, no steps were taken on behalf of the  

Petitioners to either arrange for an alternate safe  

berthing in Vadinar or to give instructions as to  

where the cargo was to be discharged.  In fact, on  

behalf of the Respondents/Owners a legal notice was  

addressed to the Petitioners on 24.12.1999 pointing  

out that the vessel continued to await discharge  

incurring demurrage.  It is only thereafter that  

Addendum No.I to the Charter Party was drawn up and  

signed  on  28.12.1999  by  the  Owners  and  the  

Charterers, whereby m.t. Prestige was diverted by  

47

48

the Charterers from Vadinar to a Lighterage point  

at  Mumbai  port  for  discharge  and  it  was  

specifically agreed that the Charterers would bear  

all  the  costs  of  discharge,  including  freight  

charges and the expenses of the daughter vessel,  

m.t. Maharaja Agrasen.  It was also agreed that  

demurrage would be settled as per the terms of the  

Charter Party.  In our view, the various decisions  

cited on behalf of the Petitioners/Charterers do  

not help them in the facts of this case.  We do  

not, therefore, think it necessary to consider all  

the  decisions  cited  on  behalf  of  the  respective  

parties  and  those  referred  to  hereinbefore  are  

sufficient for our purpose. The decisions relied  

upon by the parties lay down certain propositions  

of law which are well-established and with which  

there  cannot  be  any  disagreement,  but  for  the  

purposes of this case they are basically academic.  

48

49

47. Once we have affirmed the finding that m.t.  

Prestige  was  an  arrived  ship  on  reaching  the  

customary  anchorage  at  Vadinar  port  and  once  we  

have  also  held  that  it  was  the  Charterers  who  

having the choice of a safe port, had selected the  

SBM  at  Vadinar  as  the  discharge  point,  the  

suggestion made on behalf of the Charterers that it  

was the responsibility of the Owners of the vessel  

to check whether the ship could be safely moored at  

the SBM, is untenable.  The responsibility of the  

Owners of the vessel ended with the declaration of  

the equipment available on board for mooring and  

berthing for the purpose of discharge of its cargo.  

Consequently, all the other ancillary issues which  

arise  have  to  be  answered  in  favour  of  the  

Respondents herein.  As indicated hereinbefore, the  

fiasco at Vadinar was occasioned by the fact that  

no prior checking had been done by the Charterers  

to  ascertain  as  to  whether  with  the  mooring  

49

50

equipment on board the vessel she would be able to  

moor safely at the SBM for discharge of her cargo.  

Even the subsequent deviation of the vessel from  

Vadinar to Mumbai was not on account of any laches  

on the part of the Owners of the vessel who were  

awaiting  instructions  once  the  vessel  had  been  

asked to move away from the SBM.  In fact, it took  

a notice from the Owners of the vessel and a week  

for  the  Charterers  to  galvanize  themselves  into  

action, which ultimately resulted in the Addendum  

No.1 dated 28.12.1999.

48. Read with Clause 6 of the Charter Party, the  

Addendum dated 28.12.1999 makes it abundantly clear  

that the Charterers had accepted the responsibility  

for  the  failure  of  the  vessel  to  discharge  her  

cargo at Vadinar and had agreed to bear all the  

expenses for the delay in diversion of the vessel  

from Vadinar to Mumbai, including the time spent at  

50

51

Vadinar  port  and  the  expenses  incurred  towards  

pilotage, tugs and other port expenses.

49. Apart from the above, Clause 4(1) of Part II of  

the Charter Party specifically provides that extra  

expenses  incurred  on  account  of  any  change  in  

loading or discharging ports, has to be paid by the  

Charterers, and any time thereby lost to the vessel  

shall count as used lay time. We are not inclined  

to accept Mr. Gupta’s submission that the aforesaid  

clause has to be read in the context of Clauses  

4(a)  and  4(b)  which  refer  to  ports  other  than  

Indian Ports in a different context.

50. We, therefore, see no reason to interfere with  

the  Award  of  the  Arbitral  Tribunal  and  the  

decisions, both of the learned Single Judge and the  

Division  Bench,  confirming  the  Award  of  the  

Arbitral  Tribunal  and,  accordingly,  dismiss  the  

Special Leave Petition.  In the facts of the case,  

51

52

the parties shall bear their own costs as far as  

these proceedings are concerned.               

      

…………………………………………J. (ALTAMAS KABIR)

…………………………………………J. (A.K. PATNAIK)

NEW DELHI DATED:JULY 13, 2011

52