RASHTRIYA ISPAT NIGAM LTD. Vs M/S. PRATHYUSHA RESOURCES & INFRA PRIVATE LIMITED
Bench: PINAKI CHANDRA GHOSE,R.K. AGRAWAL
Case number: C.A. No.-003699-003699 / 2006
Diary number: 5509 / 2006
Advocates: K J JOHN AND CO Vs
SRIDHAR POTARAJU
Page 1
1
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3699 OF 2006
RASHTRIYA ISPAT NIGAM LTD. APPELLANT(S)
VERSUS
M/S. PRATHYUSHA RESOURCES & INFRA PRIVATE LIMITED AND ANR. RESPONDENT(S)
O R D E R
1. The present appeal is filed by the appellant challenging the
judgment and order dated 16.12.2005 passed by the Division
Bench of the High Court of Judicature for Andhra Pradesh at
Hyderabad, whereby the order dated 6.7.2004, passed by the
learned District Judge, Vishakhapatnam, was set aside and the
arbitration award was confirmed.
2. The appellant - Rashtriya Ispat Nigam Ltd., which is
popularly known as Visakhapatnam Steel Plant, is a
Government of India Undertaking, inter alia, engaged in
manufacture and sale of steel products and pig iron in the
domestic and export markets. Respondent No.1 is a transporter,
Page 2
2
stevedoring, clearing & forwarding agent at Visakhapatnam. The
appellant floated a tender vide Notification dated 31.03.1992 for
transportation of pig iron etc. from its Visakhapatnam Steel
Plant to the Visakhapatnam Port area. Respondent No.1 being
the successful bidder, was awarded the work order on
28.07.1992. An Agreement was entered into between the
appellant and respondent No.1 on 24.02.1993 which was to
expire on 31.03.1993. But owing to circumstances, the work was
extended several times and the contract was finally completed
on 23.10.1997. Issues arose as to the rate of escalation based on
the base year 1992 or 1994. Respondent No.1 submitted final
bill having three annexures out of which first two were admitted,
however, the appellant rejected the third one which was as to
deciding the base year for calculating escalation.
3. The Arbitration Tribunal (consisting of a retired Judge of
the High Court) decided the five issues framed in favour of the
respondent/claimant whereby the base year was adjudged as
1992, the bar of limitation was negated and the calculations
made by the Claimant were upheld. The appellant challenged
the said award under Section 34 of the Arbitration Act, 1996
Page 3
3
before the Ld. District Court which set aside the award as the
relief was barred by limitation. Upon appeal under Section 37 of
the Act by the respondent/claimant, the High Court set aside
the order of the District Judge and upheld the award of the
Arbitrator.
4. The appellant/ Employer herein have challenged the said
Order of the High Court. The bone of contention in this appeal is
the question of relief being barred by the law of limitation. The
appellant submits that the High Court has arrived at a wrong
conclusion by invoking Article 137 of the Limitation Act, 1963,
and since the contract was in the nature of work contract,
Article 18 would apply. This Article would thereby provide that
the right to sue accrued when the contract was completed i.e.
23.10.1997 and hence notice for arbitration was beyond the
period of limitation. The respondent/claimant also argued that
the dispute as to determination of base year for calculating
escalation arose vide letter dated 15.7.1996 and hence the
notice for arbitration was issued beyond the period of limitation.
Either ways the cause of action in favour of the
respondent/claimant accrued, if any, is an imperfect right.
Page 4
4
5. We shall now consider the settled law on the subject. This
Court in a catena of judgments has laid down that the cause of
action arises when the real dispute arises i.e. when one party
asserts and the other party denies any right. The cause of action
in the present case is the claim of the respondent/claimant to
the determination of base year for the purposes of escalation and
the calculation made thereon, and the refusal of the appellant to
pay as per the calculations.
6. We find that the view taken by the High Court is correct as
to when the real dispute arose between the parties to be
adjudicated by the Arbitrator. It is nobody's case that the
contract came to an end on 23.10.1997, but the difference on
determination of base year first arose in the letter dated
15.7.1996. The said letter is already controverted as the service
of the same was seriously contested before in Arbitration.
However, the said letter was there even before completion of the
work and prior to that the respondent/claimant had reserved his
right to claim money later since the contract was still subsisting
then. In light of the above reservation by the
respondent/claimant, bills were raised in 1998 vide letter dated
Page 5
5
4.9.1998, which actually resulted into exchange of letters which
formed the base of dispute between the parties. It is an admitted
fact that the bills were not finalized as could be seen from the
letters dated 7.2.2000 and 9.5.2000. Therefore, we find that the
findings of the learned Arbitrator and concurrently affirmed by
the High Court are correct on the point that the cause of action
arose on or after 4.9.1998. Hence, the said letter by the
respondent/claimant to the appellant to initiate arbitration was
not barred by the law of limitation.
7. Accordingly, the civil appeal is dismissed with no order as
to costs.
….....................................J (Pinaki Chandra Ghose)
……..................................J (R.K. Agrawal)
New Delhi; February 12, 2016.
Page 6
6
ITEM NO.1C COURT NO.10 SECTION XIIA (For judgment) S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
Civil Appeal No(s). 3699/2006 RASHTRIYA ISPAT NIGAM LTD. Appellant(s) VERSUS M/S. PRATHYUSHA RESOURCES & INFRA PRIVATE LIMITED & ANR. Respondent(s)
Date : 12/02/2016 This appeal was called on for pronouncement of judgment today.
For Appellant(s) Mr. Pratap Venugopal, Adv. Ms. Surekha Raman, Adv. Mr. Anuj Sarma, Adv. Ms. Niharika, Adv.
For M/s. K. J. John & Co. For Respondent(s) Mr. Mohan Parasaran, Sr. Adv.
Mr. K. Raghavacharyulu, Adv. Mr. Sridhar Potaraju, AOR Mr. Kailash Pandey, Adv. Mr. Gaichangpou Gangmei, Adv. Mr. Arjun Singh, Adv. Mr. Mukunda Rao Angara, Adv. Mr. Ranjeet Singh, Adv.
***** Hon'ble Mr. Justice Pinaki Chandra Ghose pronounced the
reportable judgment of the Bench comprising His Lordship and Hon'ble Mr. Justice R.K. Agrawal.
The appeal is dismissed in terms of the signed reportable judgment.
(R.NATARAJAN) (MADHU NARULA) Court Master Court Master
(Signed reportable judgment is placed on the file)