27 August 2013
Supreme Court
Download

RAMACHANDRA NARAYAN NAYAK Vs KARNATAKA NEERAVARI NIGAM LTD. .

Bench: CHANDRAMAULI KR. PRASAD,V. GOPALA GOWDA
Case number: C.A. No.-000077-000084 / 2004
Diary number: 19170 / 2003
Advocates: E. C. VIDYA SAGAR Vs ANITHA SHENOY


1

Page 1

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS. 77-84 OF 2004

RAMACHANDRA  NARAYAN  NAYAK         … APPELLANT VS.

KARNATAKA NEERAVARI NIGAM LTD. & ORS.   … RESPONDENTS

J U D G M E N T

V. Gopala Gowda, J.

The appellant has filed these appeals being  

aggrieved  by  the  impugned  common  judgment  and  

decree dated 12th June, 2003 passed in RFA nos.

2

Page 2

C.A. Nos.77-84 of 2004

593-600/2000 by the High Court of Karnataka urging  

various  relevant  facts  and  legal  grounds  for  

setting aside the same and restoring the common  

judgment  and  decrees  dated  30th November,  1999  

passed in O.S. no. 35/97 to 42/97 by the Civil  

Judge (Senior Division) Gadag.   

2.  The brief facts are stated hereunder for the  purpose of the rival factual and legal contentions  

that are urged by the learned counsel on behalf of  

the  parties.For  the  sake  of  convenience,  the  

parties are referred to in this judgment as per  

the ranking assigned to them in the plaints before  

the trial court.  

 The plaintiff, the appellant herein, is a  

Class I contractor.  He undertakes the contract of  

construction of irrigation canals and other major  

works  on  a  large  scale.  The  plaintiff  has  

constructed  an  irrigation  dam  across  the  

Malaprabha  river  near  Soundatti  in  Belgaum  

District.  The water from the said reservoir is to  

2

3

Page 3

C.A. Nos.77-84 of 2004

be supplied to agricultural lands of the farmers  

in Dharwad and Belgaum Districts, through canals  

to be excavated and constructed for that purpose.  

For the construction of such canals in Ron taluka  

in Dharwad District, a Division is established at  

Ron  headed  by  an  Executive  Engineer.  A  Chief  

Engineer  was  appointed  to  supervise  work  whose  

office was established at Belgaum.

3.  The plaintiff submitted his tenders upon an  invitation  from the  defendants, the  respondents  

herein,  for  execution  of  the  balance  work  of  

canals and his offer of bid was accepted.  He has  

deposited the earnest money in the form of bank  

guarantee.   On accepting the bid amount offered  

by the plaintiff, parties entered into a contract  

for execution of Alur combined branch and work of  

canal at K.M. no.1-6 and Malaprabha right bank  

canal works K.M. 97 and 102, as per the terms and  

conditions  agreed  between  them  and  more  

particularly as stipulated in the tender notice.

3

4

Page 4

C.A. Nos.77-84 of 2004

4.   Accordingly,  the  defendant  no.4,  Executive  Engineer, Irrigation Department issued work orders  

to the plaintiff relating to various canals on  

9.11.1988, 10.3.1989 and 16.3.1989 respectively.  

As per clause 2 of the agreement, the execution of  

work was to be completed within a period of 15  

months from the date of handing over the site to  

the plaintiff excluding the monsoon season from  

15th June to 15th September of the relevant years.

5.  It is the case of the plaintiff that he was  able to complete his part of the work such as  

canal excavation, embankment, morum lining/casing  

etc. within a short period deploying his staff and  

machinery. Upon progress of execution of work, the  

plaintiff wrote several letters dated 25.5.1990,  

8.6.1990,  10.6.1990,  27.3.1991,  9.5.1991  and  

14.10.1992 (Exs. P-45, P-32, P-46, P-30, P-42 and  

P-19) addressed to defendant no. 4 requesting him  

to supply cement, RCC templates and PCC slabs for  

4

5

Page 5

C.A. Nos.77-84 of 2004

putting them to the bed of canal and for other  

uses.

6.  It is the further case of the plaintiff that  as  per  the  meeting  which  was  held  between  the  

plaintiff  and  defendant  no.4,  the  proceedings  

which are marked as Ex. P-20, revealed that the  

cement and cement materials were in stock and were  

available  with  defendant  no.4,  but  he  had  

purposely delayed the supply of cement and cement  

materials  and  he  also  did  not  authorize  the  

plaintiff to procure cement from the open market  

and made certain false accusations against him.  

The plaintiff placed reliance upon clause 30 of  

the tender agreement wherein it is stated that the  

decision of the Chief Engineer in relation to the  

dispute is final.   

7.   It is the case of the plaintiff that despite  repeated requests and demands made by him vide his  

letters  referred  to  supra,  the  defendant  no.4  

5

6

Page 6

C.A. Nos.77-84 of 2004

failed  to  supply  cement  and  cement  materials  

required by the plaintiff to complete the work,  

therefore he had no option but to terminate the  

contract with the defendants.  The plaintiff vide  

his aforesaid letter dated 9.5.1991 to defendant  

no.4, marked as Ex. P-42, asked to finalise the  

bill regarding the execution of work by him and to  

terminate  the  contracts  without  imposing  any  

penalty.    

8.    It is the further case of the plaintiff that  on 12.10.1994, vide Ex.D-41, defendant no.3 passed  

an  order  rescinding  the  contract  and  levied  

penalty  on  the  plaintiff,  which  order  was  

communicated to the plaintiff by defendant no.4  

vide letter dated 24.10.1994 marked as Ex.D-42.  

Before  rescinding  the  contract,  defendant  no.3  

neither issued notice nor heard the plaintiff, as  

required  under  clause  3(d)  of  the  agreement,  

though  the  contract  is  rescinded  by  invoking  

clause 3(d) of the agreement by him.

6

7

Page 7

C.A. Nos.77-84 of 2004

9.   The  plaintiff,  being  aggrieved  by  the  rescinding of the contract and failure on the part  

of the defendants to make payments for the work  

done  and  return  of  earnest  money  and  security  

deposit amount, filed eight original suit nos. 35  

to 42 of 1997 against the defendants before the  

Civil Judge (Senior Division) Gadag seeking for  

grant  of  declaratory  relief  that  the  order  of  

rescinding the contract passed by defendant no. 3  

in respect of works of canal is illegal and not  

binding on him.  Further, the plaintiff sought  

decrees  of permanent  injunction restraining  the  

defendants from either forfeiting or adjusting the  

earnest money and security deposit amount made by  

him and for payment of bill amount in respect of  

the work executed by him and also to restrain the  

defendants from recovering the alleged risk and  

cost amount from him from out of the amount due  

from  the  works  executed  by  him  in  any  other  

Division or Department (Exs. P-1 to P-6 produced  

7

8

Page 8

C.A. Nos.77-84 of 2004

in the Original Suits) of Alur combined branch and  

work  of  canal  at  K.M.  no.  97  and  102  and  

Malaprabha  right  bank  canal.   He  had  further  

prayed  for  settlement  of  final  bill  amount  in  

relation to the execution of work and return of  

earnest money and security deposit amount along  

with 18% interest and also on the withheld amount  

along with damages, costs and other reliefs.   

10.  Defendant  no.  4  filed  written  statement  opposing the prayers made in the original suits  

and  denied  various  allegations  made  in  the  

plaints,  except  admitting  the  execution  of  the  

contract with the plaintiff for execution of the  

canal  work  to  complete  the  balance  work  of  

construction  of  the  canal  in  relation  to  the  

project in Dharwad district.   The same is adopted  

by defendant nos. 1 to 3 accepting the execution  

of the contract with the plaintiff.  It is further  

admitted by defendant no.4 that plaintiff has done  

some work and the defendant’s Department was to  

8

9

Page 9

C.A. Nos.77-84 of 2004

supply cement after the raw materials, i.e. metal,  

sand etc. required was collected for bed concrete  

and slab lining, but the excavated canal was not  

trimmed  and  dressed  to  the  required  section.  

Therefore, the defendant no. 4 was not bound to  

supply cement and cement materials, in fact the  

plaintiff  was  even  requested  to  make  his  own  

arrangements for procuring cement from the open  

market  as  per  para  7   of  Schedule  'A'  of  the  

agreement.  

11.   It  is  further  pleaded  in  the  written  statement that the plaintiff without following the  

terms  and  conditions  of  the  contract,  with  an  

illegitimate  motive, purposely  stopped the  work  

and abandoned it in the middle, knowing fully well  

that the balance work will be completed at his  

cost as per the tender clauses and he requested to  

terminate  the  work  without  any  penalty  to  be  

imposed against him as per the contract agreement.  

Defendant no.4 further pleaded that the plaintiff  

9

10

Page 10

C.A. Nos.77-84 of 2004

was at fault and did not resume the work when he  

was  requested  to  complete  the  work  as  per  the  

agreement.  As  such,  considering  the  facts  and  

circumstances of the case, defendant no. 4 was  

directed to take action against the plaintiff as  

per the tender conditions of contract work and  

accordingly the contract was rescinded and he was  

informed of the action taken by the Chief Engineer  

by  imposing  maximum  penalty  upon  him  and  

forfeiture of earnest money and security deposit  

amount.   Defendant  no.4  denied  the  various  

allegations made by the plaintiff against him and  

prayed for dismissal of the suits both on merits  

as well as on the question of limitation, besides  

declaratory relief and other reliefs sought for by  

the plaintiff.

12.  The trial court has framed nearly nine issues  for its determination. The suits went for trial.  

Common evidence is recorded in all the original  

suits.  The  plaintiff  examined  himself  and  got  

10

11

Page 11

C.A. Nos.77-84 of 2004

marked  73  documents  as  exhibits  and  defendants  

examined  eight  witnesses  and  got  marked  136  

documents in support of their case.  After hearing  

the  arguments,  the  learned  trial  judge  decided  

issue nos. 1 to 5 in the affirmative, issue nos. 6  

to  8  in  negative  and  issue  no.  9  in  the  

affirmative and the suits of the plaintiffs were  

decreed in part by recording reasons in the common  

judgment.

13. The correctness of the common judgment of  the trial court and decrees passed in the original  

suits  of  the  plaintiff  was  challenged  by  the  

defendants  before  the  High  Court  of  Karnataka  

urging various legal contentions questioning the  

correctness of the findings and reasons recorded  

on the aforesaid contentious issues and requested  

the High Court to set aside the impugned common  

judgment and decrees as the same are erroneous and  

suffer from error in law.   The High Court, after  

adverting  to  the  relevant  necessary  facts,  

11

12

Page 12

C.A. Nos.77-84 of 2004

formulated the points for its consideration and  

answered the same in favour of the defendants and  

against  the  plaintiff  by  recording  its  reasons  

holding  that  the  finding  of  fact  and  reasons  

recorded by the trial court on the contentious  

issues  are  vitiated  on  account  of  erroneous  

reasoning  for non-consideration  of the  material  

evidence on record in favour of the defendants and  

in  the  absence  of  evidence  in  favour  of  the  

plaintiff, the same are answered in affirmative  

and therefore it has reversed the common judgment  

and  decrees  by  allowing  the  appeals.   The  

correctness of the same is challenged in all these  

civil appeals by urging the following questions of  

law:

1) Whether the order dated 12.10.1994 passed  

by defendant no.3 rescinding the contract,  

communicated by defendant no.4 vide letter  

dated 24.10.1994, is valid and justified  

12

13

Page 13

C.A. Nos.77-84 of 2004

in  the  facts  and  circumstances  of  the  

case?

2) Whether  the  High  Court  is  justified  in  

setting aside the judgment and decrees of  

the  trial  court  without  giving  cogent  

reasons?

3) Whether  the  plaintiff  is  entitled  to  

recover the cost of the work executed by  

him in respect of the disputed contract?

4) Whether the defendant no.3 is justified in  

imposing  penalty,  forfeiture  of  earnest  

money,  security  deposit  and  withholding  

bill amount and the same is in accordance  

with  the  terms  and  conditions  of  the  

contract?

5) Whether  the  High  Court  is  justified  in  

taking hyper technical view in the regular  

first appeals without justification?

14. It is contended by Mr. Kirti S. Javali,  the learned counsel on behalf of the plaintiff  

13

14

Page 14

C.A. Nos.77-84 of 2004

that  the  impugned  judgment  passed  by  the  High  

Court is unwarranted and uncalled for as it has  

ignored the admissible evidence adduced on record  

by the plaintiff which is accepted by the learned  

trial judge on proper appreciation of pleadings  

and  evidence  and  has  accorded  the  reliefs  as  

prayed  for  in  the  original  suits  by  assigning  

valid and cogent reasons on the contentious issues  

framed  by  him.  The  High  Court  has  ignored  the  

evidence  adduced  by  the  plaintiff  and  the  

defendants, particularly, the DWs 1 to 6 and 8,  

whose  evidence  unimpeachably  and  conclusively  

proves  the  case  of  the  unilateral  breach  of  

contract by the defendants besides that they have  

acted most irresponsibly as a result of which it  

was impossible for the plaintiff to complete the  

contract work.  Further, it is urged that the High  

Court has completely ignored the admission made by  

the  witnesses  of  the  defendants,  wherein  the  

plaintiff also adduced positive evidence to show  

that  the  defendants  had  committed  breach  of  

14

15

Page 15

C.A. Nos.77-84 of 2004

contract. Therefore, it is urged that the High  

Court has committed an error of jurisdiction and  

the impugned judgment is liable to be set aside.   

15. It  is  further  contended  that  the  High  Court has failed to consider the important and  

admitted fact that the defendants, after the earth  

work excavated by the plaintiff, were required to  

supply cement, RCC templates and PCC slabs for  

putting them to bed of canal and for other use.  

It is also admitted by the defendants that the  

cement  was  in  stock  and  the  plaintiff  was  not  

informed to procure the same from the open market  

after obtaining due permission and further it is  

also an admitted fact that the defendants never  

informed the plaintiff that there was no stock of  

the said materials much less supplying the same as  

and when required.  Further, it is contended that  

it  is  evident  from  the  facts  pleaded  and  the  

evidence on record that the defendants are guilty  

of breach of contract without any fault of the  

15

16

Page 16

C.A. Nos.77-84 of 2004

plaintiff and they forfeited the earnest money and  

security deposits.   Therefore, the findings and  

reasons recorded on the contentious points by the  

High Court in the impugned judgment are contrary  

to the legal evidence on record. Hence, the said  

findings recorded on contentious points framed by  

the High Court are erroneous in law and the same  

are liable to be set aside.

16. Further,  it  is  submitted  that  the  High  Court  has  failed  to  consider  the  findings  and  

reasons recorded in paras 16,17,18 and 18A of the  

trial court judgment.  However, it has accepted  

the  excuses  given  by  the  defendants  that  the  

plaintiff should not have demanded cement before  

collecting sand and metal.  In this regard, the  

High Court has ignored the pleadings and evidence  

placed on record with regard to collecting the  

sand and metal for execution of work.

16

17

Page 17

C.A. Nos.77-84 of 2004

17. It  is  further  submitted  that  it  was  nothing but high handedness on the part of the  

defendants that they have not only caused undue  

harassment to the plaintiff but also caused great  

loss to him by committing breach of the terms and  

conditions  of  the  contract.  Further,  the  High  

Court has failed to consider the evidence of the  

defendants who have supported the claim of the  

plaintiff which is referred to in para 19 of the  

judgment of the trial court.   Further, the High  

Court  erred  in  re-appreciating  the  evidence  

elicited  from  the  defendants’  witnesses  during  

their  cross  examination,  wherein  they  have  

admitted that plaintiff has carried out all the  

earth work as per specifications. When he demanded  cement and cement materials from defendant no.4  

for execution of further work, the same were not  

supplied to him.  Therefore, it is very clear that  

in  spite  of  repeated  demands  made  by  the  

plaintiff, cement and cement materials were not  

supplied to him by defendant no. 4.  Therefore,  

17

18

Page 18

C.A. Nos.77-84 of 2004

the impugned common judgment of the High Court is  

contrary  to  the  facts  and  legal  evidence  on  

record.   Hence, the same is not sustainable in  

the eye of law and is liable to be set aside.  

18. Further, it is contended by Mr. Kirit S.  Javali,  the  learned  counsel  for  the  plaintiff  

that the High Court has failed to appreciate the  

evidence of defence witnesses who themselves have  

admitted in their evidence that as they did not  

supply  cement  and  cement  materials,  the  

gradation  test  also  could  not  be  carried  out.  

The  plea  that  since  sand  and  metal  were  not  

collected by the plaintiff and defendant no. 4  

did  not  supply  cement  and  cement  materials  by  

giving lame excuses and therefore the same could  

not  have  been  accepted  by  the  High  Court  to  

reverse the finding of fact recorded by the trial  

court on the contentious issues in favour of the  

plaintiff.  The  High  Court  has  accepted  the  

grounds  pleaded  by  the  defendants  in  their  

18

19

Page 19

C.A. Nos.77-84 of 2004

appeals, that, the plaintiff did not construct  

any shed or make provision for storing the cement  

at the work site and this stand was taken up by  

them  for  the  first  time  only  at  the  time  of  

adducing  evidence  and  there  is  no  pleading  to  

this effect in their written statement. Further,  

the ground of appeals urged by them is that the  

evidence of DW 8 with regard to non supply of  

cement was that the plaintiff did not submit the  

construction programme to enable the defendants  

to  supply  the  required  quantity  of  cement  and  

cement materials, this evidence is without there  

being any pleading  in this regard, and further,  

he has stated that the defendants  also did not  

supply cement as the plaintiff had not trimmed  

the canal and had not collected  the sand and  

metal for conducting gradation test.  Therefore,  

it is contended by the learned counsel on behalf  

of  the  plaintiff  that  the  common  judgment  and  

order of the High Court is contrary to the facts  

and evidence on record.

19

20

Page 20

C.A. Nos.77-84 of 2004

19.    Ms. Hetu Arora Sethi, the learned counsel  appearing  on  behalf  of  the  defendants  in  these  

appeals  has  sought  to  justify  the  findings  and  

reasons recorded on the contentious points answered  

by the High Court contending that the High Court  

being the appellate authority, the appeals being in  

continuation  of  original  proceedings,  has  

reappraised the oral and documentary evidence and  

found fault with the findings of fact recorded by  

the trial court on the contentious issues framed by  

it and the same are erroneous and therefore must be  

set  aside.    It  is  further  contended  that  the  

plaintiff  has  not  fulfilled  his  contractual  

obligations as he has not executed the contract work  

and  therefore,  the  Chief  Engineer  has  rightly  

rescinded the contract and levied the penalty and  

forfeited earnest money and security deposit amount  

and withheld the final bill amount and therefore,  

the  impugned  judgment  in  these  appeals  at  the  

instance of the plaintiff need not be interfered  

20

21

Page 21

C.A. Nos.77-84 of 2004

with by this Court in exercise of its jurisdiction  

under Article 136 of the Constitution.

20.   It was further contended on behalf of the  plaintiff  that  the  defendants  had  not  even  

informed  the  plaintiff  the  reasons  for  not  

supplying  the  cement  and  cement  materials,  the  

High Court has failed to take into consideration  

the  evidence  of  the  defendants  witnesses,  with  

regard to the meeting held on 23.3.1992 in the  

Chambers  of  Chief  Engineer,  Belgaum,  the  

proceedings of the meeting are marked as ex. P-20,  

the plaintiff, defendant no. 4 and other officers  

of  the  Department  were  present  in  the  said  

meeting, and the work of construction of canal for  

8 kms. was discussed  and it was found that the  

defendant no. 4 had purposely delayed the supply  

of cement to the plaintiff on untenable grounds.  

Further, DW1, the Executive Engineer, admitted in  

his  evidence  that  on  the  basis  of  proceedings  

drawn  in  the  Chief  Engineer's  chambers  that  

21

22

Page 22

C.A. Nos.77-84 of 2004

departmental  action  was  also  proposed  against  

defendant no. 4 and the subsequent action proposed  

against him would support the contention of the  

plaintiff  that  it  is  due  to  the  fault  of  the  

Department, more particularly of the defendant no.  

4, the contract work had to be stopped in the  

middle by the plaintiff.    The Ex. P-20 puts  

blame on defendant no. 4 for stoppage of work by  

the  plaintiff.   Even  in  the  letter  dated  

11.12.1992 issued by the Government of Karnataka,  

marked  as  Ex.  P-23,  it  is  observed  that  the  

concerned Executive Engineer has come in the way  

of contract by not supplying the cement in time to  

the  plaintiff  and  the  action  of  the  Executive  

Engineer  in  terminating  two  contracts  is  not  

approved.  The aforesaid important aspects of the  

matter has not been considered by the High Court  

in reversing the judgment of the trial court by  

passing the impugned judgment and it is contrary  

to the facts and evidence on record.  Therefore,  

the  same  is  liable  to  be  set  aside  and  the  

22

23

Page 23

C.A. Nos.77-84 of 2004

judgment and decrees of the trial court are to be  

restored.

21.  It was further contended that the High Court  has failed to appreciate that the defendants were  

not supplying cement free of cost but for charges  

which were to be deducted from the final bill of  

the  plaintiff.   The  plaintiff  had  requested  

defendant no.4 for the supply of cement and it was  

for him to decide as to how he could have stored  

the  cement  or  made  provision  for  the  same.  

Further, the High Court should have noticed that  

non-completion of the work by the plaintiff is due  

to non supply of cement by defendant no. 4 and, he  

also did not supply even the templates and lugs  

required for putting bed concrete in the excavated  

canal.    The  High  Court  further  should  have  

noticed that the defendants have not adduced any  

evidence to show that there was no stock of cement  

which was required to be supplied in terms of the  

contract to the plaintiff.   The High Court ought  

23

24

Page 24

C.A. Nos.77-84 of 2004

to have considered the entire evidence on record  

particularly that the plaintiff is not at fault  

for non-completion of work as per the contract.  

Therefore,  the  impugned  judgment  and  order  is  

contrary  to  the  facts  and  legal  evidence  on  

record.   Hence,  the  same  is  liable  to  be  set  

aside.

22.  With reference to the aforesaid rival factual  and legal contentions, the  following points would  

arise for our consideration:-

1. Whether the findings and reasons of the  

High Court in reversing the findings recorded  

by the trial court on contentious issue nos.  

1 to 3 and 6 and dismissing the suits of the  

plaintiff by answering the point nos.1 and 2  

in the affirmative by passing the impugned  

judgment are correct?

2. Whether the findings and reasons recorded  

by the High Court on the contentious point  

24

25

Page 25

C.A. Nos.77-84 of 2004

nos.1 and 2, in favour of the defendants in  

the impugned judgment are legal and valid?

3. Whether the High Court is justified in  

holding that the rescission of the contract  

of the plaintiff by reversing the finding on  

issue no. 4 and answering the point nos. 3  

and 4 in the affirmative is valid and the  

action taken by the Department in imposing  

penalty  and  forfeiting  of  earnest  money,  

security deposit and withholding bill amount  

of the plaintiff is justified?

4. What order is to be passed?

23. Answers to point nos. 1 and 2 : The first and  second points are answered together, as they are  

interrelated,  in  favour  of  the  plaintiff  by  

assigning the following reasons:  

  We have carefully perused the pleadings and  

evidence of the parties on record and considered  

the rival factual and legal submissions made on  

their  behalf  and  the  findings  recorded  by  the  

25

26

Page 26

C.A. Nos.77-84 of 2004

trial court in its judgment on the contentious  

issue nos. 1 to 3 and 6 and point nos. 1 and 2 by  

the High Court to answer the aforesaid points.  

The trial court in its judgment while answering  

the   contentious  issues  nos.  1  to  5  in  the  

affirmative and issue nos. 6 to 8 in the negative  

in  favour  of  the  plaintiff,  has  elaborately  

referred to the pleadings and evidence on record,  

particularly  the  evidence  elicited  from  the  

defendants’ witnesses by the plaintiff's counsel  

in  the  cross  examination,  viz.  from  DW  1  the  

Executive Engineer, MRBC Ron, DW 2 the retired  

Executive  Engineer,  MRBC  Division  no.5  Sub  

division no.18 in Mallapur,  DW 4 the Assistant  

Executive  Engineer,  MRBC,  Division  no.5,  Sub-

division no.18, Mallapur and DW 5 the Assistant  

Engineer,   MRBC,  Division  no.  5,  Sub-division  

no.18  Mallapur,  and  also  referred  to  the  

documentary  evidence,  namely  the  letters  

correspondence  made  by  the  plaintiff  with  the  

Executive Engineer Defendant no.4  requesting him  

26

27

Page 27

C.A. Nos.77-84 of 2004

to supply the cement and cement materials for the  

purpose of  execution of the work as agreed upon  

in  the  contract.  The  learned  trial  judge  has  

recorded the findings of fact on the contentious  

issue nos. 1 & 2 in the affirmative holding that  

the plaintiff has proved that defendant no.4 did  

not  supply  cement  and  cement  articles  for  

completion of the work though he had requested  

him on several occasions by his letters, which  

are marked as Exs. P-30, P-32, P-41, P-42, P-45  

and P- 46 referred to supra and also referred to  

the admission made in the cross examination of  

the defendant witnesses namely DWs 1, 2, 4 and 5.  

The trial court has rightly further held that the  

plaintiff  had  proved  the  fact  that  due  to  non  

supply  of  cement  and  cement  materials  by  the  

defendant no.4 as agreed upon in the contract,  

the progress of the work could not be carried out  

by him and therefore it was held that he was not  

at fault for non completion of the agreed work.  

The  findings  of  fact  recorded  by  the  learned  

27

28

Page 28

C.A. Nos.77-84 of 2004

trial judge on the aforesaid contentious issues  

are  in  the  affirmative  after  referring  to  the  

pleadings  and  evidence  of  the  plaintiff  and  

defence  witnesses  and  also  considering  the  

submissions made by the learned counsel on behalf  

of the plaintiff, that there is no condition in  

the  tender  agreement  to  collect  the  sand  and  

metal before making a demand for the supply of  

cement and cement materials from defendant no.4.  

It was further held by the learned trial judge  

that  according  to  the  case  of  the  defendants,  

collection of the sand and metals is required for  

conducting gradation test, and even to carry out  

such a gradation test cement is required and it  

is an undisputed fact that the defendant no.4 has  

neither supplied nor authorized the plaintiff to  

procure the cement and cement materials from the  

open market and on account of non supply of the  

same  the  plaintiff  had  to  keep  his  men  and  

machinery  idle  for  months  together,  which  has  

resulted  in  heavy  losses  for  him  and  after  

28

29

Page 29

C.A. Nos.77-84 of 2004

informing the defendant no.4, the plaintiff had  

moved his men and machinery from the work site.  

Further, the proceedings held in the meeting on  

23.3.1992 in the Chamber of the Chief Engineer,  

Belgaum, which document is marked as exhibit P-20  

has been referred to by the learned trial judge  

wherein it is observed that due to injudicious  

act of defendant no.4 in not supplying cement and  

cement materials to the plaintiff, the contract  

work  had  to  be  stopped  by  him  and  further  

departmental action was also proposed against him  

for  his  inaction  in  supplying  the  cement  and  

cement  materials  to  the  plaintiff.   Therefore,  

learned trial judge has rightly arrived at the  

conclusion on facts and evidence on record and  

recorded the findings of fact and held that the  

plaintiff has proved that the contract work could  

not  be  completed  due  to  the  fault  of  the  

Department  itself  and  its  officer  i.e.  the  

defendant  no.4,   and  the  plaintiff  cannot  be  

blamed.   The  learned  trial  judge  has  also  

29

30

Page 30

C.A. Nos.77-84 of 2004

considered legal submission made on behalf of the  

defendants  that  the  plaintiff  did  not  seek  

permission from the defendant no.4 for procuring  

cement  from  the  open  market  and  the  further  

contention urged on behalf of the defendants was  

that delay in taking possession of the work site  

shows  that  plaintiff  had  no  real  intention  of  

completing the work within the time limit and the  

trial  court  has  rightly  rejected  the  same  by  

recording  valid  reasons.   The  plaintiff  had  

demanded supply of cement for the entire 8 k.ms.  

of work,  which comes to about 22 to 23 thousand  

bags of cement but he had not made any provision  

for  storing  such  cement  and  the  same  perishes  

faster  than  sand  and  metal.  He  had  not  even  

collected sand and metal required for conducting  

gradation  test.  The  further  contention  that  in  

spite of the request made by defendant no.4 to  

the plaintiff to resume the work and complete the  

same, he had not completed the work, though he  

knew  fully  well  the  consequences  of  abandoning  

30

31

Page 31

C.A. Nos.77-84 of 2004

work in the middle without any reasonable cause  

would  entail  serious  civil  consequences  and  

therefore, the fault lies with the plaintiff and  

not with the defendants.  The above said factual  

submissions made by the learned counsel on behalf  

of  the  defendants  were  examined  by  the  trial  

judge  with  reference  to  the  pleadings  and  

evidence  on  record  and  the  same  were  rightly  

answered  against  the  defendants.   The  learned  

trial judge in his judgment at paragraphs 16, 17,  

18 and 18A adverted to the evidence elicited in  

the cross examination of DWs 1, 2, 3 and 4 and  

recorded the positive finding on the contentious  

issues nos. 1 and 2, in the affirmative. DW 1 has  

admitted in his cross examination that there was  

no condition in the tender agreement to collect  

sand and metal before demanding cement from the  

Department  and  further  admitted  that  after  

completing the earth work, the plaintiff demanded  

cement by his letter dated 25.5.1990, which is  

marked as Ex. P- 45. He further admitted in his  

31

32

Page 32

C.A. Nos.77-84 of 2004

cross examination  that the plaintiff had written  

letter  to  the  defendant  no.4  stating  that  he  

would commence the bed concrete work next week,  

if 2731 bags of cement is supplied to him.  Such  

quantity of cement is required for 1 k.m. work  

and further the evidence elicited in his cross  

examination shows that cement, template and the  

lugs were not supplied by defendant no.4 to the  

plaintiff and he could not complete the work. He  

has further admitted that defendant no.4 had to  

give  authorization  to  the  plaintiff  to  procure  

cement from the open market and since he did not  

inform the plaintiff regarding the grant of such  

authorization, he could not procure cement from  

the open market for want of such authorization.  

Since the cement, templates and the lugs were not  

supplied  for  all  the  kilometers  of  work  by  

defendant no.4, the plaintiff could not complete  

the  work.   The  plaintiff  had  also  written  a  

letter to defendant no.4 to conclude the contract  

for the reason that he could not finish the same  

32

33

Page 33

C.A. Nos.77-84 of 2004

for non supply of cement, template and lugs.  DW  

1 further admitted in his cross examination that  

they were not required to supply cement free of  

charge to the plaintiff but the defendants would  

deduct  the  cost  of  cement  in  the  bill  amount  

payable to him. It was further admitted in his  

cross examination that defendant no.4 asked the  

plaintiff to resume the work, as stated  in the  

evidence  of  DW  1,  as  the  labour  charges  and  

material  charges  were  already  increased  and  

therefore,  the  plaintiff  did  not  agree  for  

resuming the work for executing the same at old  

rates.  

 

24.  Further,  the  evidence  elicited  by  the  plaintiff's  counsel  from  DW  2,  the  retired  

Executive Engineer, is extensively referred to by  

the learned trial judge in his judgment wherein he  

has stated that for bed concrete, trimming work  

fixing templates and lugs, cement is required.  He  

further  admitted  in  his  evidence  that  for  

33

34

Page 34

C.A. Nos.77-84 of 2004

execution  of  the  above  said  works  mixing  of  

cement, sand and metal, gradation test was to be  

conducted to ascertain their proportion and if,  

the defendants do not supply the cement, gradation  

test  cannot  be  conducted.   He  also  further  

admitted that the defendants did not inform the  

plaintiff  that  they  have  sufficient  stock  of  

cement and he could collect sand and metal for  

execution of work. The Department did not supply  

cement and the plaintiff had informed the superior  

officers of the Department stating that the work  

is halted for non supply of cement and further  

stated in his evidence to the effect that if mud  

mixes  with  sand  and  metal,  it  cannot  be  used  

without washing and for such washing more expenses  

will  have  to  be  incurred  by  the  plaintiff.  

Further, he had admitted in his cross examination  

that authorization was required for the plaintiff  

to procure cement from open market.  DW-4 also has  

deposed to the same effect, which supports the  

case of the plaintiff.

34

35

Page 35

C.A. Nos.77-84 of 2004

25. DW-4,  the  Asstt.  Executive  Engineer  in  MRBC, Division 5, Sub-division no.18, DW-5 who was  

working as Asstt. Engineer in the same Division  

and DW-7 who was working as Jr. Engineer at the  

relevant point of time of work have also admitted  

in their cross examination that they did not ask  

the  plaintiff  to  procure  cement  from  the  open  

market and in spite of repeated requests made by  

the plaintiff, the defendant no. 4 did not supply  

the cement.  DW-8, the then Executive Engineer  

also admitted in his cross examination that though  

plaintiff had written several letters to defendant  

no.4 for supply of cement, the Department did not  

supply cement and he had admitted that due to non  

supply of cement, the plaintiff had to stop the  

work and due to stoppage of work the plaintiff's  

men and machineries had to suffer loss on that  

count.

35

36

Page 36

C.A. Nos.77-84 of 2004

26. After adverting to the evidence elicited  in  the  cross  examination  of  the  aforesaid  

defendant witnesses the trial judge has analyzed  

and appreciated the same properly and came to the  

right conclusion and recorded the findings of fact  

at paragraph 18 of the trial court judgment on the  

contentious issue nos. 1 to 3 in the affirmative.  

Further, the defence taken by the defendants at  

the time of adducing the evidence without pleading  

in their written statement, regarding non supply  

of cement, is that the plaintiff had not submitted  

the  construction  programme  to  them  to  enable  

defendant no.4 to supply the required quantity of  

cement and the cement materials.   The learned  

trial  judge  rightly  made  observation  on  the  

relevant issue in his judgment that defendant no.4  

was not supposed to supply cement at free of cost  

to the plaintiff but charges for the same were to  

be deducted at the time of disbursement of amount  

in the final bill.  Therefore, when the request  

was made by the plaintiff with defendant no.4 for  

36

37

Page 37

C.A. Nos.77-84 of 2004

supply of cement, it was for him to see how to  

store cement safely and how to make best use of  

the  same  for  the  purpose  of  completing  the  

contract work.  The trial judge further recorded  

the finding of fact and held that the defendants  

neither supplied cement though it was in stock nor  

authorized  the  plaintiff  to  procure  the  cement  

from  the  open  market.   Defendant  no.4  did  not  

inform the plaintiff regarding refusal to supply  

the cement. It would have made no difference to  

the Department if it had supplied cement earlier  

or later. The DW 1 has admitted the same in his  

evidence on the basis of the proceedings recorded  

in the meeting held on 23.3.1992, which is marked  

as Ex. P-20. In the said proceedings blame was put  

on defendant no.4 for stoppage of work and the  

following facts were noticed and recorded:

“ a) Instead of putting the blame on the  

contractor for not collecting sand, jelly  

etc., the contractor might have allowed to  

37

38

Page 38

C.A. Nos.77-84 of 2004

procure the cement from the open market as  

per clauses of the agreement;

b)  Cement  was  available  with  department  

when the contractor had placed his demand  

for cement;

c) Instead of issuing cement as demanded  

by the contractor the then EE prolonged  

the issue and had insisted to collect the  

sand, jelly etc before issue of cement.”

Further, in the letter Ex. P-23  written by the  

Government of Karnataka to the Chief Engineer it  

is observed that the concerned Executive Engineer  

has come in the way of the plaintiff to execute  

the  contract  work  for  non  supply  of  cement  in  

time  to  him  and  the  proposed  action  of  

terminating two contracts is not approved by it.  

Therefore,  the  learned  trial  judge  after  

adverting to the oral evidence of the defendant  

witnesses referred to supra and the documentary  

evidence  Ex.  P-20  and  Ex.  P-23  and  other  

38

39

Page 39

C.A. Nos.77-84 of 2004

documentary evidence, has rightly arrived at the  

conclusion on facts and held that the plaintiff  

could not complete the work due to non supply of  

cement and cement materials by defendant no.4 and  

he  also  did  not  supply  templates  and  lugs  

required  for  putting  bed  concrete  in  the  

excavated canal. The plaintiff had requested the  

defendants  to  conclude  his  contract  and  return  

the  earnest  money,  security  deposit  and  other  

amounts  withheld  by  them.   Reference  was  also  

made  to the letter dated 13.1.1993, marked as  

Ex.  P-21 of  the  defendant  no.4,  asking  the  

plaintiff  to  continue  the  contract  work  and  

furnish his clear consent regarding the same. The  

plaintiff did not accept the same for the reason  

that his men and machinery were moved from the  

work site and the contract has come to an end.  

Therefore,  learned  trial  judge  has  rightly  

answered the contentious issue nos. 1 and 2 in  

the  affirmative.  The  same  was  erroneously  set  

aside by the High Court by recording its findings  

39

40

Page 40

C.A. Nos.77-84 of 2004

on  fact  without  proper  analysis  and  re-

appreciation  of  evidence  on  record  and  wrongly  

applied the terms and conditions of the contract  

to the fact situation of the case in hand and  

accepted the case of the defendants and  has set  

aside the findings in the relevant issues without  

noticing the fact that it is the defendants, who  

had  committed  breach  of  contract  and  therefore  

the plaintiff could not complete the agreed work  

under the contract.

27.   The findings of fact recorded by the learned  trial judge in his judgment have been reversed by  

the High Court, ignoring the pleadings and legal  

evidence on record and therefore we have to hold  

that the findings of the High Court are erroneous.  

We have very carefully examined that portion of  

the impugned judgment to answer the point nos. 1  

and  2  framed  by  us  in  these  appeals  for  our  

consideration.  The learned Division Bench of the  

High Court has adverted to the relevant clause 11  

40

41

Page 41

C.A. Nos.77-84 of 2004

at para 15 of its judgment regarding supply of  

materials to the plaintiff that may be required  

from  time  to  time  to  be  used  by  him  for  the  

purpose of execution of works as agreed in the  

contract and clause 11(A)(i), which provides that  

the contractor shall see that only the required  

quantities  of  materials  are  indented  with  the  

Junior  Engineer  of  the  Department  and  the  same  

shall be supplied to him.  The said condition of  

the agreement as provided in the above clause is  

not complied with by the plaintiff is the finding  

recorded  by  the  High  Court.  As  per  the  said  

clause, the plaintiff was required to be supplied  

with cement and cement materials by defendant no.  

4,  from time to time on presentation of indents  

signed by him or his authorized representative and  

counter signed by the Department officers, and in  

this regard, the High Court has referred to both  

oral and documentary evidence and held that the  

plaintiff had not presented any indent signed by  

him  or  his  authorized  representative  to  the  

41

42

Page 42

C.A. Nos.77-84 of 2004

Department  for  supply  of  cement  to  the  Junior  

Engineer, who in turn sent it to the Assistant  

Executive Engineer by recommending the same who in  

turn was required to send it to the Divisional  

office for supply of the same. The further finding  

is that the evidence adduced by the defendants in  

this regard is unchallenged by the plaintiff and  

undisputedly,  neither  indent  nor  proof  for  

submitting the same to the defendants is placed  

before the Court by the plaintiff to show that he  

had presented any indent with the Department for  

supply of cement and cement materials and the High  

Court has referred to para 18 of the trial court  

judgment and also to Exs. P - 31, 37, 45, 59, 65  

and 70 the same are marked as  Exs. D- 28, 62, 76,  

102,  116  and  132  respectively  and  reversed  the  

findings recorded on the above contentious issues  

1 to 3, 5 and 6 by the trial court by recording  

its reasons. The correctness of the said findings  

and reasons are examined by us to find out whether  

the same is tenable on facts and in law. Further,  

42

43

Page 43

C.A. Nos.77-84 of 2004

the High Court has stated in the impugned judgment  

by  reversing  finding  of  fact  recorded  on  the  

contentious issues referred to supra by the trial  

court by answering the contentious points formed  

by it and held that nowhere in the said letters it  

is mentioned that any indent had been prepared or  

presented  by  either  the  plaintiff  or  his  

authorized  representative  to  the  defendants  in  

connection with request to supply cement and other  

materials to him.  Therefore, it has held that  

there is non compliance of the condition nos. 2.05  

and 2.06 of the agreement referred to above by the  

plaintiff and further it is not the case of the  

plaintiff  that  in  the  tender  contract  he  was  

required  to  be  supplied  with  cement  and  cement  

materials without any indent made as such. In this  

regard, we record our findings as under.  

28.   After the plaintiff took possession of the  site of the works for execution of work, he wrote  

several letters as per exhibits referred to supra  

43

44

Page 44

C.A. Nos.77-84 of 2004

with a request to the defendants for supply of  

cement and cement materials and the said letters  

are  very  important  for  the  reason  that  the  

plaintiff  has  been  persistently  demanding  

defendant  no.4  for  supply  of  cement  and  cement  

materials  as  agreed  to  be  supplied  to  him  for  

execution of work.  The aforesaid findings of the  

High Court adverted to in the preceding paragraph  

are erroneous in law for the reason that the High  

Court has placed reliance on the evidence of DW-8  

regarding  non  submission  of  indents  by  the  

plaintiff as per the terms of the contract and  

general conditions of the tender, which evidence  

is wholly inadmissible in law, as the same was  

allowed to be placed on record by the trial court  

without pleading in their written statement. Apart  

from  the  said  reason,  the  defendants  in  their  

cross-examination have categorically admitted that  

the cement and cement materials were not supplied  

to the plaintiff for execution of work and in fact  

in the various letters written by the plaintiff  

44

45

Page 45

C.A. Nos.77-84 of 2004

marked  as  exhibits  referred  to  supra  he  has  

specifically demanded for supply of cement  and  

cement materials, the same were accepted by the  

defendants but they did not insist the plaintiff  

to submit indents and construction programme and  

therefore the said letters must be construed as  

such. Ignoring the substantive evidence on record,  

the High Court has reversed the findings of fact  

on the contentious issues referred to supra, which  

are wholly unsustainable in law.     

29.  In view of the aforesaid specific conditions  and clauses in the agreement, the request of the  

plaintiff with the Department to supply cement in  

entirety within a week, even in the absence of  

indents the demand of the plaintiff for supply of  

cement and other materials as per his requirement  

from time to time to use the same in the execution  

of contract work was very much there by writing  

number of letters which are exhibited and the same  

was  not  met  by  the  defendants  by  pleading  and  

45

46

Page 46

C.A. Nos.77-84 of 2004

adducing  evidence.   The  fact  remains  that  

defendants have neither supplied the cement and  

cement materials to the plaintiff as requested by  

the plaintiff through his series of letters marked  

as  exhibits  referred  to  supra  nor  have  they  

replied to him asking him to submit the indents.  

In view of these admitted facts, the High Court  

should  not  have  placed  reliance  upon  the  

inadmissible evidence of DW 8, to set aside the  

findings of fact recorded by the trial court on  

the aforesaid contentious issues. Further, para 22  

of the impugned judgment refers to the Department  

asking the plaintiff to furnish the construction  

programme  as  contemplated  in  general  condition  

no.1.10 of the tender document. This is clear from  

the  letters  dated  26.6.1990,  28.6.1990  and  

30.6.1990 placing reliance upon evidence of DW-8  

Gangareddy,  by  the  High  Court  to  come  to  its  

conclusion to reverse the findings of the trial  

court recorded on contentious issue nos. 1 to 3, 5  

& 6, as he has stated in his evidence that as per  

46

47

Page 47

C.A. Nos.77-84 of 2004

tender agreement, the plaintiff-contractor should  

have  submitted  construction  programme  for  the  

contract period of 15 months to the defendants,  

but he has not submitted it to them and therefore  

it has found fault with the finding of the trial  

court in holding that the defendant no.4 has not  

supplied  cement  and  cement  materials  to  the  

plaintiff for execution of work and set aside the  

same.  It is further erroneously observed by the  

High  Court  in  the  impugned  judgment  that  the  

evidence  of  DW-8  remained  unchallenged  by  the  

plaintiff,  as  it  has  accepted  the  inadmissible  

evidence regarding non submission of construction  

programme by the plaintiff, the said evidence of  

DW-8 is without pleading of the defendants and  

therefore it should not have relied upon the same  

and reversed the findings of the trial court on  

the contentious issues.  In view of the foregoing  

reasons,  the  High  Court’s  conclusion  and  its  

finding in holding that the plaintiff had failed  

to comply with the said general conditions of the  

47

48

Page 48

C.A. Nos.77-84 of 2004

tender  and  he  committed  breach  of  contract  is  

wholly untenable in law. Further, its reference  

and reliance to clause 44(b) of the agreement and  

non supply of the cement and its materials, that  

the Government shall not be, in any way, liable on  

account of any delay in supply of such material  

also cannot be accepted by this Court in view of  

the observations made by the Chief Engineer in the  

proceedings drawn in the meeting held on 23.3.1992  

which  document  is  marked  as  Ex.  P-20.   After  

placing strong reliance upon the said clause for  

non  submission  of  letter  of  indent  by  the  

plaintiff, though demand has been made as per the  

letters referred to supra by the plaintiff, and  

letters of the defendants referred to supra, and  

that payment of bill amount is being made to the  

plaintiff and therefore the question of concluding  

contract by defendant no.3 does not arise.  The  

defendant no.4 had requested him to bear with the  

Department.  By the time the letters were written  

to the plaintiff by defendant no. 4, the plaintiff  

48

49

Page 49

C.A. Nos.77-84 of 2004

had already shifted his men and machinery from the  

site and accordingly informed the Department about  

the same.  The High Court has erroneously held  

that the plaintiff could not have relied solely on  

the evidence of DW-8 regarding non furnishing of  

construction programme for supply of cement and  

cement materials to him and he had abandoned the  

tender  work  in  the  middle,  and  recorded  its  

finding  by  reversing  the  finding  of  the  trial  

court. The said finding of the High Court that the  

Executive Engineer has stated in his evidence that  

plaintiff did not take permission from defendant  

no.4 to procure cement and cement material as per  

his  evidence  is  contrary  to  the  terms  of  the  

contract.  So also the evidence of DWs 3 and 4 in  

this regard could not have been placed reliance  

upon by the High Court to set aside the finding of  

the trial court. For the reasons stated supra and  

evidence of DWs 2, 3, 4 and 5, reliance was placed  

upon the evidence of  DW-8 by the High Court, as  

he stated in his evidence that the plaintiff did  

49

50

Page 50

C.A. Nos.77-84 of 2004

not do canal dressing, trimming work and concrete  

work, which is wholly erroneous as the same is  

contrary  to  the  terms  and  conditions  of  the  

contract  and  substantive  evidence  on  record  in  

favour of the plaintiff.  

30.  Further, the trial court has referred to the  evidence of DWs 3, 4, 5, 7 and 8 and held that the  

plaintiff  had  done  canal  work  and  canal  bund,  

murrom  lining  embankment  work,  however  for  the  

gradation test required to be done as stated by  

DW-8,  the same could not be done without cement,  

according to the evidence of DWs 2, 3 and 4, as  

cement was necessary for plaintiff to do the bed  

concrete and trimming work.  The finding of the  

High Court was that only a certain quantity of  

cement was required by the plaintiff but he had  

requested for supply of entire quantity of cement  

from the Department and not the required quantity  

for execution of the said works, which were to be  

attended at that stage of request made by him is  

50

51

Page 51

C.A. Nos.77-84 of 2004

once again erroneous in law and cannot be allowed  

to sustain in law.  Further, it has erroneously  

observed that the plaintiff had not constructed  

any godown for storing the cement at the work site  

and he had not stored sufficient sand and metal,  

in  this  regard,  the  trial  court  has  placed  

reliance upon the evidence of DWs.2, 3, 4, 7 and 8  

and recorded the finding holding that non supply  

of cement and cement materials to the plaintiff is  

contrary  to  the  terms  and  conditions  of  the  

agreement. The High Court has found fault with the  

above  findings  of  the  trial  Court  on  the  

contentious issue nos. 1 and 2 and held that the  

trial  court  has  arrived  at  erroneous  finding,  

therefore, it has answered the point Nos. 1 and 2  

framed by it against the plaintiff and set aside  

the  findings  recorded  by  the  trial  court  on  

contentious issue nos. 1 and 2 in its judgment.  

Consequently, the first appeals of the defendants  

were allowed.

51

52

Page 52

C.A. Nos.77-84 of 2004

31.  It is needless to observe that the conclusion  and findings arrived at by the High Court on the  

basis of re-appreciation of evidence is contrary  

to the pleadings and evidence on record, the trial  

judge being the fact finding authority has duly  

considered  the  entire  evidence  after  proper  

analysis and it has recorded the finding of fact  

on the contentious issue nos. 1,2,3,5 and 6 in  

favour of the plaintiff.   

32.  Answer to point no.3 - The High Court, on the  issue  of  rescission  of  the  contract  with  the  

plaintiff  by  defendant  no.3,  vide  order  dated  

12.10.1994,  which  order  was  communicated  by  

defendant no.4 to the plaintiff, has relied on  

letters sent by the defendants to the plaintiff,  

wherein he was requested to resume and complete  

the work and all the items of tender as agreed  

upon  by  him.  The  High  Court  has  erroneously  

recorded  the  finding  of  fact  stating  that  no  

infirmity can be found in the action taken by the  

52

53

Page 53

C.A. Nos.77-84 of 2004

Department in rescinding the agreement and levying  

of  penalty  and  forfeiture  of  earnest  money,  

security  deposit  and  withholding  of  final  bill  

amount,  as the plaintiff did not resume work nor  

had he shown his willingness to resume or complete  

the work as per the terms and conditions of the  

agreement, nor did he request for any fresh terms  

and conditions to complete the same, and so the  

Department was left with no option but to rescind  

the tender agreement. We find the above findings  

of the High Court in reversing the finding of the  

trial court on issue nos. 4, 5 and 7 are wholly  

untenable both on facts and in law and we have to  

hold  that  the  rescinding  of  the  contract  by  

defendant  no.3  is  illegal,  and  penalty  imposed  

upon  the  plaintiff  and  forfeiture  of  earnest  

money, security deposit and withholding of bill  

amount after rescinding the contract is not legal  

and valid as the plaintiff himself has requested  

the defendants to conclude the contract without  

any  penalty  or  the  risk  and  cost  amount.  

53

54

Page 54

C.A. Nos.77-84 of 2004

Defendant no. 3 passed the order of rescinding the  

contract, without issuing any show cause notice or  

holding an enquiry, as required under clause 3(d)  

of the contract and therefore the learned trial  

judge has rightly recorded the findings on the  

aforesaid  contentious  issues  in  favour  of  the  

plaintiff and rightly held that the rescinding of  

the  contract  was  not  justified.  The  unilateral  

rescission of the contract of the plaintiff by  

defendant No. 3 is arbitrary and unreasonable. The  

action  of  defendant  no.3  in  rescinding  the  

contract  has  resulted  in  serious  civil  

consequences  of  imposition  of  penalty  and  

forfeiture of the earnest money deposit amount,  

security deposit and withholding the bill amount  

in relation to the execution of the work by the  

plaintiff.  Therefore,  defendant  no.  3  before  

rescinding  the  contract,  by  invoking  his  power  

under clause 3(d) of the agreement, should have  

complied with the conditions mentioned in the said  

clause as the same is mandatory. The rescinding of  

54

55

Page 55

C.A. Nos.77-84 of 2004

the  contract  is  also  bad  in  law  for  one  more  

reason that the State Government has  accorded  

permission to defendant no.3- the Chief Engineer,  

Irrigation  (North),  Belgaum  to  rescind  the  

contract  as  per  terms  and  conditions  of  the  

agreement  vide  letter  dated  29.8.1994,  which  

document is marked as Ex. D-40. The Chief Engineer  

directed  the  Superintending  Engineer,  M.R.B.C.  

Circle, Dharwad to levy penalty and rescinded the  

contract  vide  letter  dated  12.10.1994,  which  

document  is  marked  as  Ex.  D-41,  the  relevant  

portions of this letter is extracted below :

“(ii) to rescind the contract and to take up  the balance work at the risk and cost of the  contract as per clause-3 of Agreement.

In addition to the above, the expenditure  incurred towards the work charged establishment  if any, beyond the tender period till the date  of rescinding the agreement may be recovered,  duly  observing  all  the  formalities  of  the  agreement.  The  Superintending  Engineer  is  requested to call for tenders for the balance  works.”

We  have  to  infer  from  the  last  unnumbered  

paragraph of the said letter, that the contract of  

55

56

Page 56

C.A. Nos.77-84 of 2004

the plaintiff is rescinded.  Thus, we have to hold  

that defendant no.3 rescinded the contract, which  

order  is  communicated  by  defendant  no.4  vide  

letter 24.10.1994 which document is marked as Ex.  

D-42. The reliance placed by defendant no.3 and  

the Superintending Engineer upon the approval of  

the  Government  in  its  letter  Ex.D-40  for  

rescinding of the contract with the plaintiff is  

fallacious,  as  the  Government  has  very  clearly  

stated in its letter referred to supra, that the  

contract of the plaintiff has to be rescinded and  

penalty be imposed as per the conditions of the  

agreement. Therefore, the finding recorded by the  

High  Court  on  this  contentious  point  in  the  

impugned  judgment  is  liable  to  be  set  aside.  

Accordingly, we set aside the same by answering  

the point no.3 in favour of the plaintiff.

33.   For the foregoing reasons, we are of the  view that the findings and reasons recorded by the  

High Court on the contentious points framed by it  

56

57

Page 57

C.A. Nos.77-84 of 2004

are totally erroneous both on facts and in law and  

therefore the same are required to be interfered  

with  by  this  Court  and  hence  the  appeals  must  

succeed.   In  view  of  the  findings  and  reasons  

recorded by this Court on point nos. 1, 2 and 3 in  

favour of the plaintiff, point no.4 is accordingly  

answered in favour of the plaintiff.  Hence, we  

set aside the impugned judgment and decrees dated  

12th June,  2003  passed  by  the  High  Court  of  

Karnataka in RFA nos. 593-600/2000 and we restore  

the common judgment and decrees of the trial court  

in the original suits, except modification with  

regard to rate of interest from 18% to 9%.   

    

34.  The  defendants  are  directed  to  repay  the  earnest money and security deposit amount and also  

finalize the bill of the plaintiff for the work  

executed by the plaintiff and pay the same with  

interest @ 9% per annum within six weeks from the  

date  of  receipt  of  the  copy  of  this  judgment.  

57

58

Page 58

C.A. Nos.77-84 of 2004

Accordingly,  the  appeals  are  allowed,  with  no  

order as to costs.

……………………………………………………………J.                    [CHANDRAMAULI KR. PRASAD]

…………………………………………………………J.                               [V. GOPALA GOWDA]

New Delhi, August 27, 2013.   

58