05 August 2013
Supreme Court
Download

ORISSA POWER TRANSMISSION CORP.LTD. Vs ASIAN SCHOOL OF BUSINESS MGMT.TRUST &ORS

Bench: G.S. SINGHVI,V. GOPALA GOWDA
Case number: C.A. No.-006257-006257 / 2013
Diary number: 1266 / 2013
Advocates: RAJ KUMAR MEHTA Vs SANTOSH KUMAR - I


1

Page 1

        NON-REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.   6257         OF 2013 (Arising from SLP(C) No.8168 of 2013)

Orissa Power Transmission Corporation Limited and others ..Appellants

versus

Asian School of Business Management  Trust and others         ..Respondents

J U D G M E N T

G.S. SINGHVI, J.

1. Leave granted.

2. In  exercise  of  the  power  vested  in  it  under  Section  29  of  the  

Electricity (Supply) Act, 1948 (for short, ‘the Act’),  Orissa State Electricity  

Board (for short, ‘the Board’) (predecessor of appellant No.1) framed about  

50 transmission schemes, which were notified on 30.05.1991 to enable the  

licensees  and  other  interested  persons  to  make  representations.  The  

1

2

Page 2

notification was published in official gazette dated 20.7.1991. For the sake  

of reference, the relevant portions of the notification are extracted below:

“The Orissa Gazette

EXTRAORDINARY PUBLISHED BY AUTHORITY No.857 CUTTACK, SATURDAY JULY 20, 1991 /  

ASADHA 29, 1913

ORISSA    STATE   ELECTRICITY    BOARD BHUBANESWAR

NOTIFICATION The 30th May 1991

No.4459- In  accordance  with  Section-29  of  Electricity  (Supply) Act, 1948, the following transmission schemes which  the  Orissa  State  Electricity  Board  intends  to  undertake  for  execution,  are  published  for  general  information.  It  is  also  notified  in  the  interest  of  general  public  that  any  person  interested in making representation regarding the execution of  the above schemes, may submit such representation in writing  so  as  to  reach  the  Secretary,  Orissa  State  Electricity  Board,  Bhubaneswar-751007 within 2 (two) months from the date of  publication.  Full details of the schemes and the plan may be  seen in the Office of the Chief Engineer (Planning, Monitoring  and Coordination), Orissa State Electricity Board, Bhubaneswar  on any working day during office hours.

(A) 220 KV LINES

Sl.  No.

Name of the Scheme (Rs.In lakhs)

(1) (2) (3) 2 220  KV  DC  line  from  

Meramundali  to  Bhubaneswar  (Chandaka) 150 Kms @  

2170.50

2

3

Page 3

14.47 lakhs/Km.

        (emphasis supplied)

3. Some of the aforesaid schemes were modified vide notification dated  

30.01.1996, which was also published in Official Gazette dated 15.2.1996.  

That notification reads as under:

“The Orissa Gazette

EXTRAORDINARY PUBLISHED BY AUTHORITY No.177 CUTTACK, THURSDAY FEBRUARY 15,  

1996 / MEGHA 26, 1917

ORISSA   STATE   ELECTRICITY   BOARD BHUBANESWAR

                        NOTIFICATION                                    The 30th January, 1996

No. 589 - PL.II-PFC-18/95 - In partial modification of Schemes  against Sl.No. 2 of Gazette Notification No. 857, dated the 20th  July,  1991  and in  accordance  with  Section  29 of  Electricity  (Supply) Act, 1948, the following transmission schemes which  the  Orissa  State  Electricity  Board  intends  to  undertake  for  execution,  are  published  for  general  information.  It  is  also  notified  in  the  interest  of  general  public  that  any  person  interested in making representation regarding the execution of  the above schemes, may submit such representation in writing  so  as  to  reach  the  Secretary,  Orissa  State  Electricity  Board,  Bhubaneswar  -751007  within  two  months  from  the  date  of  publication. Full details of the scheme and the plan may be seen  in  the  office  of  the  Chief  Engineer  (Transmission  Project),  O.S.E.B.,  Bidyut  Bhawan,  Sahidnagar,  Bhubaneswar-751007  on any working day during office hours.

3

4

Page 4

Name of the Scheme :- Strengthening of transmission network  in  and around  Chandaka  Command area  (Bhubaneswar)  and  Bidanasi  (Cuttack)  Command  area  as  per  the  detail  scope  furnished below:

Necessity of the Scheme :-(i) To transmit power from the main  pooling  centre  at  Meramundali  to  Chandaka/Mendhasai  Command area.

Establishment of new 220 KV network at Bidanasi (Cuttack). Improve  the  reliability  of  power  supply  in  Chandaka  (Bhubaneswar) Command area.

Improvement of voltage profile in Bhubaneswar, Cuttack, Puri,  Khurda, Jagatsinghpur Transmission System

Scope of Work

Sl Sl.No.

Scope of Scheme Approximate  estimated  cost  in  lakhs of rupees

12 3 11.Meramundali-Chandaka/Mendhasal  (bhubaneswar) 400 KV DC line. ( 110  Kms. ) with 220 KV bay extension at  Chandaka and IVIeramundali.

5,918.00

2Chandaka(Bhubaneswar)-Bidanasi  (Cuttack) 220 KV DC line with bay  Extension(25 Kms.).

990.00

3Construction of 2 x 100 MVA, 220/132  KV substation at Bidanasif Cuttack).

1,368.00

4Bidanasi (Cuttack)-Nuapada (Cuttack)  132 KVDC link line with bay Extension  (13.6 Kms.)

880.00

Total 9,156.00 lakhs

        (emphasis supplied)

4

5

Page 5

4. None of the licensees/other interested persons are shown to have made  

representation against any of the schemes including the one mentioned at  

item No.2  of  notification  dated  30.5.1991  and  item No.1  of  notification  

dated 30.1.1996 and the Board executed the same without any objection.

5. After 14 years and 6 months of publication of the schemes, Human  

Resources  Development  and  Management  Trust  of  India  (for  short,  ‘the  

Trust’) (predecessor of respondent No.1), who had purchased some parcels  

of land in Mauza  Andharua, Tahsil Bhubaneswar, District Khurda vide sale  

deed  dated  30.10.2005  raised  objection  against  execution  of  the  scheme  

mentioned at item No.2 of notification dated 30.5.1991 on the ground that  

two  of  the  transmission  towers  proposed  to  be  erected  would  cross  the  

building constructed by it.  The Trust also requested appellant No.1 to shift  

the transmission towers and line to an alternative site.  

6. Appellant  No.1  and  its  officers  did  not  accept  the  

objection/representation of the Trust,  who then filed Civil  Suit  No. 72 of  

2006 in the Court of Civil Judge (Junior Division), Bhubaneswar and prayed  

for grant of the following relief:

“The plaintiff  therefore humbly prays that this Hon'ble Court  may graciously be pleased to pass a decree declaring that the  defendant has no right to enter into the suit schedule property  and  also  pass  decree  of  permanent  injunction  permanently  

5

6

Page 6

injunction the defendants from erecting/ constructing any tower  on the suit schedule property and decree the suit with cost to the  plaintiff.”

7. The Trust also filed an application for temporary injunction. The trial  

Court passed ad-interim order dated 9.3.2006 and directed that status quo  

regarding construction be maintained.   That  order  was made absolute  on  

26.4.2006 and the appellants were restrained from entering the suit land and  

constructing any tower.   That  order  was  set  aside by Ad-hoc Additional  

District  Judge,  Bhubaneswar  in  FAO  (Misc.  Appeal)  No.40/33  of  2006  

decided on 4.10.2008.   The Additional  District  Judge noted that  all  the  

towers had already been erected on both sides of  the disputed land and,  

therefore, it is not possible for the appellant to erect any tower leaving the  

suit land and thereby compromise the public interest.  In the opinion of the  

learned Additional District Judge, the Trust could be compensated by the  

competent authority.   

8. The  Trust  challenged  the  appellate  order  in  Writ  Petition  (C)  

No.14806 of 2008, the prayer clause of which reads as under:

“The petitioner therefore, humbly prays that this Hon'ble Court  may graciously be pleased to admit the writ application and call  for  the  records  from  the  court  below  and  upon  hearing  the  parties be pleased to issue a writ in nature of Certiorari or any  other  appropriate  writ(s),  direction(s)  quashing the  impugned  order dtd. 04.10.2008 passed by the learned Adhoc Additional  

6

7

Page 7

District  Judge,  F.T.C.  No.  3,  Bhubaneswar  in  F.A.O.  (Misc.  appeal ) No. 40/33 of  2006 under Annexure - 9 and restrain the  opp.  parties  from entering  the  suit  schedule  property  of  the  petitioner  and  from  erecting/constructing  any  tower  on  suit  schedule property, pending adjudication of the writ petition.

And may pass such other order(s) as deemed just and proper.”

9. The  learned  Single  Judge  of  the  High  Court  dismissed  the  writ  

petition  vide  order  dated  21.11.2008,  the  relevant  portions  of  which  are  

extracted below:

“17. As per the affidavit filed today, the entire work on either  side  on  the  suit  land  was  completed  and,  therefore,  the  argument of the learned counsel for the respondent was that the  petitioner  is  not  entitled  to  any order  of  injunction  as  every  work sought to be injuncted was already completed.  

18. Further  when once no objection  was raised  within  the  statutory period, the subsequent belated correspondence by any  officer of Respondent may not act as an estoppel against them  because such officer is not entitled to forgo the statutory period  of prescribed for receiving objections or to extend it or even to  waive  it.  Moreover,  after  having  purchased  the  land  in  December, 2005, the building was constructed below the power  line by petitioner only in July 2006, after knowing fully well  that negotiation with officers of respondent failed.

19. In  these  circumstances,  even  assuming  for  argument  sake, that there is some illegality in the Scheme, then what is  provided in  Section  12 of  the  Indian  Electricity  Act  is  only  compensation  and  not  dismantling  of  the  entire  line  of  numerous towers erected at  the heavy cost  of  public  money.  Moreover,  the scheme involves public interest.  When private  interest  is  at  stake  and  especially  when  compensation  is  awardable,  no  injunction  could  be  granted  especially  when  

7

8

Page 8

work  sought  to  be  injuncted  has  already  been  completed.  Viewed in this angle, I am not able to entertain the writ petition  and I  find no error  in  the effect of  the order  of  the lower  appellate court.”

10. After  about  one year,  respondent  No.1  filed Writ  Petition  (C)  No.  

20659 of 2009 and prayed for grant of the following substantive reliefs:

“(I) Directing the Opposite Parties No.1 to 3 not to make any  construction of the transmission tower/line-within the premises  of the petitioner;

(II) Directing the Opposite Parties No.1to 3 to take a final  decision regarding re-routing/re-alignment of the 220/132 KV  Mendhasal  – Bidanasi  over head line within a stipulate  time  after completion of the profile survey by the petitioner.”

11. The learned Single Judge noticed the prayer made in the civil suit, the  

orders passed by the trial  Court,  the lower appellate Court  and the High  

Court  in  Writ  Petition  No.14806/2008,  referred  to  the  judgments  of  this  

Court in K.S. Rashid and Son v. Income Tax Investigation Commission and  

others,  AIR  1954  SC  207,  Bombay  Metropolitan  Region  Development  

Authority,  Bombay v.  Gokak Patel  Volkart  Limited  and  others  (1995)  1  

SCC 642, Jai Singh v. Union of India and others, AIR 1977 SC 898 and held  

that the writ petition was not maintainable because the civil suit was pending  

before  the  competent  Court.   The  learned  Single  Judge  then  considered  

whether the second writ petition was barred by  res judicata and answered  

8

9

Page 9

the same in the affirmative by observing that the cause of action for filing  

the two petitions  was the  same and identical  reliefs  had been sought  by  

respondent No.1.  The learned Single Judge relied upon the judgments in  

Naresh Shridhar Mirajkar v. State of Maharashtra and another, AIR 1967 SC  

1, State of Karnataka and another v. All India Manufacturers Organization  

and others (2006) 4 SCC 683, Direct Recruit Class-II Engineering Officers’  

Association  v.  State  of  Maharashtra  and  others  (1990)  2  SCC  715  and  

Forward Construction Co. and others v. Prabhat Mandal (Regd.), Andheri  

and others AIR 1986 SC 391 and held that the prayer made in the second  

writ petition does not merit consideration.  The learned Single Judge also  

adverted to the issue of public interest and observed:

“The paramount public interest in this case cannot be lost sight  of. On one hand, the larger interest of the State involving lakhs  of  electricity  consumers  spreading  over  several  districts  of  Orissa and on the other hand the purported inconvenience of a  few hundred of students. Time and again, the apex Court has  deprecated the practice of the educational institutions acting in  violation of law and committing irregular and illegal acts and  thereafter, taking plea of career of the students. I am shocked  that  in  the  case  at  hand  even  the  threat  of  law  and  order  situation by the students has been argued. Plight of the students  is  apparently due to  improper action of  the petitioner.  If  the  career of the students is at stake,  the petitioner is solely and  wholly responsible for it.”

12. Having failed to convince the learned Single Judge to entertain its  

prayer, respondent No.1 filed Writ Appeal No. 393 of 2010.  During the  

9

10

Page 10

pendency of the appeal, respondent No.1 filed an application in the name of  

the Trust for withdrawal of the suit.  The trial Court allowed the application  

vide order dated 16.3.2011, which reads as under:

“The  case  record  is  put  up  today  being  advanced  by  the  Plaintiff.  Advocate for the Plaintiff files a petition supported by  an  affidavit  praying  withdraw  the  suit  on  the  ground  stated  therein. Copy served. No objection the petition is raised by the  defendants.  Heard the learned counsels for the parties on the  petition for withdrawal of the suit. Since the plaintiff does not  want  to  proceed with the suit,  the petition for  withdrawal  is  allowed and the suit is dismissed as withdrawn.”

13. The Division Bench of the High Court reversed the findings recorded  

by  the  learned  Single  Judge  on  the  issue  of  maintainability  of  the  writ  

petition by observing that the reliefs claimed in the two writ petitions were  

different.  The Division Bench then referred to Sections 28 and 29 of the Act  

and held that notifications dated 30.05.1991 and 30.01.1996 were ultra vires  

the provisions of those sections because the procedure prescribed in those  

sections had not been followed and concurrence of the competent authority  

had not been obtained. The Division Bench also referred to interlocutory  

orders passed by it for production of full details of the scheme and held that  

the  documents  produced  on  behalf  of  the  appellants  herein  were  not  

sufficient to prove that the scheme had been framed, published and modified  

10

11

Page 11

in  accordance  with the provisions  of  the Act  and that  in  the  absence  of  

approval of the Central Government, the scheme cannot be implemented.

14. Shri P.P. Rao, learned senior counsel for the appellants argued that the  

impugned judgment is liable to be set aside because the view expressed by  

the Division Bench of the High Court on the validity of the scheme is ex-

facie erroneous and is untenable.  Learned senior counsel pointed out that  

notifications dated 30.5.1991 and 30.1.1996 were issued in accordance with  

Section 29 of the Act and both the notifications contained a clear stipulation  

that full details of the scheme and the plan can be seen in the office of the  

Chief Engineer (Planning, Monitoring and Coordination) and argued that a  

person who had purchased land after more than 14 years of the issue of first  

notification and raised construction after the scheme had been substantially  

executed  could  not  have  challenged  the  same  on  the  ground  of  lack  of  

particulars/details or any error in the notifications because the landowner(s)  

had  neither  made  any  representation  nor  filed  objections.  Shri  Rao  

emphasized that the approval of the Central Government was not necessary  

because cost of the scheme was less than rupees hundred crores and as per  

notification  dated  28.12.1995  issued  by  the  Government  of  India,  

concurrence of the Central Electricity Authority was required only if the cost  

of the scheme was more than hundred crores.     Learned senior counsel then  

11

12

Page 12

argued that the second writ petition filed by respondent No.1 should have  

been dismissed by the High Court by invoking the doctrine of  res judicata  

because similar prayer had been rejected in the earlier round of litigation.  

Learned  senior  counsel  referred  to  affidavits  filed  by  Shri  Amar  Nath  

Mohanty, Assistant General Manager, EHT(Construction) before the High  

Court  to show that  none of  the three alternative proposals  were feasible.  

Shri  Rao  also  invited  the  Court’s  attention  to  additional  affidavit  dated  

26.4.2013 of Shri Amar Nath Mohanty to show that height of the two towers  

LOC 36 and LOC 37 has been so raised that the line will be 4.58 meters  

(14.56 feet) above the existing line and there will be a clearance of 9 meters  

(28.62 feet) between the highest point of existing three storey building in the  

campus of respondent No.1 and the proposed line as against the requirement  

of 5.4 meters (17.17 feet) in terms of Rule 80 of the Indian Electricity Rules,  

1956.  From  the  affidavit  of  Shri  Amar  Nath  Monhanty,  Shri  Rao  also  

pointed out that tower Nos. LOC 1 to 35 and LOC 40 to 117 have already  

been  erected  over  a  length  of  31.124  kilometers  by  spending  Rs.14.31  

crores.  In the end, the learned senior counsel submitted that even if there  

was any mistake in the description of the scheme, the High Court should not  

have interfered with the same because appellant No.1 had already erected  

12

13

Page 13

towers by spending huge amount and it would not be in public interest to  

change the route of the line by shifting/dismantling the existing towers.

15. Dr.  Abhishek  Manu  Singhvi,  learned  senior  counsel  appearing  for  

respondent  No.1  supported  the  impugned  judgment  and  argued  that  the  

Division Bench of the High Court did not commit any error by directing  

appellant No.1 to re-align the transmission line by shifting the transmission  

towers  to  some  other  area  because  construction  thereof  will  be  highly  

detrimental to the people including the students living in the Campus. Dr.  

Singhvi  further  argued  that  the  scheme  framed  by  the  Board  cannot  be  

executed because the same was not framed after following the procedure  

prescribed under Sections 28 and 29 of the Act.   Learned senior counsel  

pointed out that the scheme mentioned at item No.2 of notification dated  

30.5.1991 and at item No.1 of notification dated 30.1.1996 does not relate to  

the area in which the land of respondent No.1 is situated and, therefore, the  

appellants  cannot  erect  transmission  towers  over  the  existing  buildings.  

Learned senior  counsel  then argued that  the Division Bench of  the High  

Court rightly refused to apply the doctrine of res judicata because the reliefs  

claimed in the two proceedings were entirely different.  In support of this  

argument,  Dr.  Singhvi  relied  upon  the  judgment  of  this  Court  in  S.J.S.  

Business Enterprises (P) Ltd. v. State of Bihar (2004) 7 SCC 166.

13

14

Page 14

16. We have considered the respective arguments. Sections 28 and 29 of  

the Act, which have bearing on the decision of this appeal read as under:

“28.  Preparation  and sanctioning  of  scheme.—(1)  For  the  efficient performance of its duties under this Act, the Board or a  Generating Company, as the case may be, may prepare one or  more schemes,  relating to the establishment or acquisition of  generating stations, tie-lines, sub-stations or transmission lines,  as are referred to in clause (e) of section 18 or clause (c) of sub- section (1) of section 18A, as the case may be.

(2) The  Board  or,  as  the  case  may  be,  the  Generating  Company  which  has  prepared  a  scheme  may,  sanction  such  scheme either generally or  in respect  of  any part  of the area  specified  in  the  scheme  and  where  a  scheme  has  been  sanctioned in respect of any part of the area, such scheme may  subsequently be sanctioned in respect of any other part of that  area:

Provided that where the scheme is of the nature referred to in  subsection (1) of section 29, the scheme shall not be sanctioned  (generally or for part of an area) by the Board or the Generating  Company  except  with  the  previous  concurrence  of  the  Authority.

(2A)  The  Board  or,  as  the  case  may  be,  the  Generating  Company shall, as soon as may be after it has sanctioned any  scheme which is  not  of  the nature referred to  in  section  29,  forward the  scheme to  the  Authority  and,  if  required by the  Authority  so  to  do,  supply  to  the  Authority  any information  incidental or supplementary to the scheme within such period as  may be specified by the Authority.

(3) Every  scheme  sanctioned  under  this  section  shall  be  published in the Official Gazette and in such local newspapers  as the Board or, as the case may be, the Generating Company  may consider necessary.

14

15

Page 15

29.  Submission  of  schemes  for  concurrence  of  Authority,  etc.—  (1)  Every  scheme  estimated  to  involve  a  capital  expenditure  exceeding  such  sum,  as  may  be  fixed  by  the  Central Government, from time to time, by notification in the  Official Gazette, shall, as soon as may be after it is prepared, be  submitted to the Authority for its concurrence.

(2) Before finalisation of any scheme of the nature referred  to in sub-section (1) and the submission thereof to the Authority  for  concurrence,  the  Board  or,  as  the  case  may  be,  the  Generating Company shall  cause such scheme,  which among  other  things  shall  contain  the  estimates  of  the  capital  expenditure involved, salient features thereof and the benefits  that  may  accrue  therefrom,  to  be  published  in  the  Official  Gazette of the State concerned and in such local newspapers as  the Board or the Generating Company may consider necessary  along with a notice of the date, not being less than two months  after the date of such publication, before which licensees and  other  persons  interested  may  make  representations  on  such  scheme.

(3) The  Board  or,  as  the  case  may  be,  the  Generating  Company may, after considering the representations, if any, that  may have been received by it and after making such inquiries as  it  thinks  fit,  modify  the  scheme  and  the  scheme  so  finally  prepared (with or without modifications) shall be submitted by  it to the Authority along with the representations.

(4) A copy of the scheme finally prepared by the Board or,  as the case may be, the Generating Company under sub-section  (3)  shall  be  forwarded  to  the  State  Government  or  State  Governments concerned:

Provided  that  where  the  scheme  has  been  prepared  by  a  Generating  Company  in  relation  to  which  the  Central  Government  is  the  competent  government  or  one  of  the  competent governments, a copy of the scheme finally prepared  shall be forwarded also to the Central Government.

15

16

Page 16

(5) The Authority may give such directions as to the form  and contents of a scheme and the procedure to be followed in,  and any other  matter  relating to,  the  preparation,  submission  and approval of such scheme, as it may think fit.

(6) In respect of any scheme submitted to the Authority for  its concurrence under sub-section (1), the Board or, as the case  may  be,  the  Generating  Company  shall,  if  required  by  the  Authority  so  to  do,  supply  any  information  incidental  or  supplementary  to  the  scheme  within  such  period, being  not  less  than  one  month,  as  may  be  specified  by  the  Authority.”

17. An analysis of the above reproduced provisions makes it clear that the  

Board or the Generating Company can prepare one or  more schemes for  

efficient performance of its duties under the Act.  Such schemes may relate  

to the establishment or acquisition of the generating stations, tie-lines, sub-

stations or transmission lines.  By notification dated 28.12.1995 issued by  

the  Government  of  India  in  the  context  of  Section  29(1)  of  the  Act,  

concurrence of the Central Electricity Authority was made mandatory for the  

schemes  involving  capital  expenditure  of  hundred crores.   Therefore,  no  

scheme involving capital expenditure of rupees hundred crores or more can  

be sanctioned by the Board or Generating Company except with the previous  

concurrence of the Central Electricity Authority.  In terms of Section 28(3),  

the scheme is required to be published in the Official Gazette and in the  

local newspapers. Section 29(2) requires that every scheme shall contain the  

16

17

Page 17

estimates of the capital expenditure involved, salient features thereof and the  

benefits likely to accrue therefrom.  The scheme is required to be published  

giving the licensees  and other interested persons an opportunity to make  

representation. Section 29(3) postulated consideration of representation by  

the Board or the Generating Company, as the case may be, before finalizing  

the scheme.  In terms of Section 29(5), the competent authority can give  

appropriate direction in the matter of preparation of scheme or call upon the  

Board  or  the  Generating  Company  to  supply  information  incidental  or  

supplementary to the scheme.   

18. A  reading  of  notification  dated  30.5.1991  makes  it  clear  that  the  

Board  had  notified  almost  50  schemes  and  invited  representations  from  

interested  persons.  Some of  the schemes  were  subsequently  modified  by  

notification dated 30.1.1996.  In both the notifications, it was specifically  

mentioned that full details of the schemes and the plans can be seen in the  

office  of  the  Chief  Engineer  (Planning,  Monitoring  and  Coordination)  /  

Chief Engineer (Transmission Project).  The landowner(s) from whom the  

Trust purchased the land vide sale deed dated 30.10.2005 neither made any  

representation nor filed objection against the scheme.  Indeed, it is not even  

the  pleaded  case  of  respondent  No.1  that  anyone  else  had  made  

representation  or  filed  objection  against  any  of  the  schemes.  Therefore,  

17

18

Page 18

neither the Trust nor respondent No.1, who constructed buildings knowing  

fully well that the Board had already framed scheme for the area in which its  

land was situated could object to erection of the remaining two towers or  

seek  shifting  of  the  scheme  and  the  officers  of  appellant  No.1  did  not  

commit any illegality by refusing to entertain the request of respondent No.1  

for shifting of the transmission towers by diverting 220 KV line from the  

existing alignment.  

19. Unfortunately,  the  Division  Bench  of  the  High  Court  completely  

overlooked the fact that respondent No.1 had stepped into the shoes of a  

person who had no grievance against the scheme framed by the Board or  

execution thereof by appellant No.1 and proceeded to decide the matter as if  

execution of the scheme has commenced after construction of buildings by  

respondent No.1.  This is the first fatal flaw in the approach adopted by the  

Division Bench of the High Court.  

20. The  exercise  undertaken  by  the  High  Court  for  ascertaining  the  

availability of alternative route through which the transmission line could be  

routed  was  totally  unwarranted  and  half  waked  consideration  of  the  

affidavits filed on behalf  of  the appellants  has resulted in miscarriage of  

justice.   As noted above, the scheme was notified on 30.5.1991 and was  

18

19

Page 19

modified on 30.1.1996.  During this  period,  respondent  No.1 was not  in  

picture.  Admittedly, the Trust had purchased the land after more than 14  

years and 6 months of initial publication of the scheme.  Therefore, neither  

the Trust nor respondent No.1 had the locus to seek a mandamus for re-

alignment of the route and the Division Bench of the High Court committed  

serious error by ordaining appellant No.1 to shift the transmission towers  

from their present site completely ignoring the fact that almost 150 towers  

had already been erected by appellant No.1 by spending more than rupees  

fourteen crores.  In paragraphs 8 to 15 of the additional affidavit filed by him  

in  Writ  Appeal  No.393/2010,  Shri  Amar  Nath  Mohanty  spelt  out  the  

following  reasons  for  not  accepting  three  alternatives  suggested  by  

respondent No.1:

“That in its sketch map produced in the Hon'ble Court on 18.02.2011  during hearing, the ASBM Trust has proposed three alternatives to  (a) divert/realign the now operating 220 KV Mendhasal-Chandaka  line and (b) divert /realign the ongoing 220 KV Mendhasal-Bidanasi  line in question to outside his premises identified in that sketch as:-

1- Alternative-1

2- Alternative-2

3- Common to both Alternatives

1 -Alternative-1 line identified in the sketch as = A, IB, 1C

This diversion suggests to link the Bidanasi end at Point-A of  ongoing  220  KV  Mendhasal-Bidanasi  line  with  the  existing  

19

20

Page 20

operating 220 KV Mendhasal-Chandaka line towards Chandaka  end at Point-IC.

2 -Alternative-2 line identified in the sketch as = A 2B, 2C, 2D

This diversion suggests to link the Bidanasi end at Point-A of  the  on-  going  220  KV  Mendhasat-Bidanasi  line  with  the  existing  operating  220  KV  Mendhasal-Chandaka  line  at  its  Mendhasal end at Point-2D.

3- Line Common to both Alternatives identified in the sketch  as= 1,2,3

This diversion suggests  to link the Mendhasal  end at  one of  existing tower location,  of  the on-going 220 KV Mendhasak  Bidanasi line through Point- 1 & 2 with the existing operating  220  KV  Mendhasal  -Chandaka  line  at  its  Chandaka  end  at  Point-3.

9.  That  all  three  proposals  i.e  Alternative  1(A,  1B,1C),  Alternative 2 (A,2B,2C,2D) and Common to both Alternative  (1,2 & 3) proposed by the ASBM Trust are not feasible to be  carried out.

(a) As per the proposal Alternative which is Common to both  Alternatives along with Alternative 2, if executed, will divert  the existing 220 KV Mendhasal-Chandaka line as well as the  220 KV Mendhasal-Bidanasi line in question from the premises  of ASBM. Any one such alternative can not divert either line. If  this  proposal  i.e  Common  Alternative  with  Alternative  2  is  worked out, it will involve erection of 7 Nos. of new towers  along with the transmission line in the proposed route and eight  Nos.  of  towers  already  constructed  have  to  be  dismantled/abandoned. The cost of such diversion will involve  around Rs. 1 Crore excluding the amount of compensation payable  to the land owners over whose land the line and towers are to be  erected.

(b) As per the proposal  the Alternative Common to both the  proposals can not be treated as a full-fledged Alternative unless  this is worked out along with the proposed Alternative 1. This  proposal will involve erection of six (6) new towers along with  

20

21

Page 21

the transmission line and 5 Nos. of constructed towers have to  be  abandoned/dismantled.  The  approximate  cost  of  this  diversion will be little less than Rs.l crore besides compensation  payable to owners.

10.That the proposal as suggested by the Appellant if executed,  will  pass  over  many  private  lands  and  buildings  under  construction and also over jungle lands and some Anabadi lands  of  the State  Government  as  would be  evident  from the land  particulars filed herewith as Annexure J/1 series which has been  obtained by the Opp. Parties from the office of the Revenue  Inspector, Chandaka, Dist- Khurda. On further verification it is  found that all the towers, transmission line including corridor  will  pass  through  series  of  private  plots  for  which  it  is  not  possible to re-route the line as suggested.

11.That as against the towers to be constructed on the land of  the  ASBM,  the  diversion  as  proposed  if  worked  out,  compensation payable will be much more since there will be  large  number  of  owners  as  against  the  single  owner  ASBM  Trust.

12. That  besides  payment  of  compensation  the  proposed  diversion  will  also  create  series  of  Right  of  Way  (ROW)  problems  in  view  of  the  constructions  and  multistoried  buildings coming up over the route which will not be possible  in law without publishing fresh scheme in accordance with law.  This is highly impractical and hence not feasible.

13.That  besides  the  above  if  the  diversion  of  the  line  as  proposed  in  any  Alternatives  are  accepted  then  necessary  statutory  notification  has  to  be  published  afresh  in  the  state  gazette as well as in the local News Papers inviting objections  from  the  general  public  and  in  that  event  any  person  may  approach  the  Court  of  law  and  seek  redressal  of  grievance  including any order of injunction. This will further inordinately  delay  the  already  delayed  construction  of  transmission  line  which is very vital for power supply to Bhubaneswar, Cuttack,  Puri, Khurda, Jagatsingpur Command Areas.

21

22

Page 22

14.That to complete the existing line only two (2) towers are to  be constructed, one tower within the area of ASBM and another  partly  in  area  of  ASBM out  of  which stub  setting  has  been  completed in respect of one tower, of which two (2) legs are  inside the compound wall of ASBM and the other two (2) legs  are  outside  the  compound  wall  of  ASBM.  There  is  no  construction on the land on which these two (2) towers are to be  built. It is also submitted that the construction of those two (2)  towers will not endanger the life and property of the Institution  since ft has been proposed to maintain the vertical clearance at  a much more height than specified in Rule 79 & 80 of Indian  Electricity Rule,  1956 which provides a vertical  clearance of  5.4  Mtrs.  for  220  KV  line  above  the  top  of  the  building.  Accordingly in the instant case the vertical clearance will be 10  Mtrs. above the top of the existing structure of ASBM.

15.That the photographs filed herewith as Annexure K/l series  would  show  that  the  220  KV  Mendhasal-Chandaka  transmission  line  has  passed  through  the  compound  of  the  Appellant ASBM long since which is existing and ASBM has later  constructed its building and structures near the line.”

21. The reasons assigned by the concerned officer of appellant No.1 for  

not accepting the alternatives suggested by respondent No.1 were germane  

to the inability of appellant No.1 to change the alignment of the route and  

shift  the  transmission  towers  and  the  Division Bench  of  the  High Court  

committed  serious  error  by  entertaining  the  prayer  made  by  respondent  

No.1.

22. A  somewhat  similar  question  was  considered  by  this  Court  in  

Ramakrishna Poultry (P) Limited v. R. Chellappan (2009) 16 SCC 743.  The  

appellant in that case had purchased land in June, 2004/November, 2004.  At  

22

23

Page 23

about the same time, the Power Grid Corporation of India Ltd. took up the  

work of  construction of  400 KV Perambalur-Pugalur D/C line as  part  of  

Neyveli  Thermal  Station  Expansion  Project  for  evacuation  of  electricity  

generated  therein.  This  required  installation  of  transmission  towers  at  

various  locations,  some  of  which  were  private  lands  including  the  land  

belonging to the appellant.  In the first round of litigation, the High Court  

directed District Magistrate to hear the parties and decide the representation  

to  be  made  by  the  appellant.  The  District  Magistrate  directed  the  

Corporation to re-align the transmission line in such a way that it did not  

pass above the poultry sheds constructed by the appellant.  This affected the  

respondent,  who filed  writ  petition  before  the  High  Court.   The  learned  

Single Judge dismissed the writ petition. The Division Bench held that the  

District Magistrate did not have any power to direct change of alignment.  

This Court took cognizance of the fact that the Corporation had agreed to  

raise the height of the transmission lines and observed:   

“38.  Keeping  aside  the  technical  aspect  of  the  matter  as  to  whether  the  order  passed  by  the  District  Collector  was  one  under Section 16 or Section 17 of the Telegraph Act, 1885, in  order to arrive at a practical solution to the problem, the Power  Grid  Corporation  accepted  the  alternate  suggestion  made  on  behalf of the appellant Company and raised the height of the  lowest point of sag of the transmission lines between the two  towers  on  either  side  of  the  poultry  sheds  of  the  appellant  Company from 46.5 m to 52 m, which in practical terms means  

23

24

Page 24

a clearance of 30 ft between the lowest point of the sag and the  highest  point  of  the  poultry  shed.  Of  course,  it  has  been  contended by Mr Ganesh that  according to  the report  of  the  experts, even if the height of the tower was raised to 100 m, the  electro-magnetic  field  created  by  the  transmission  of  high  voltage electricity would still encompass the poultry sheds and  adversely  affect  the  reproductive  system  not  only  of  the  chickens but of all living things within that zone.

39.  However,  what  goes  against  the  case  of  the  appellant  Company is the fact that the purchases of the land for starting  the poultry business and the erection of the poultry sheds were  effected at a point of time when the process of identifying the  route  of  the  transmission  lines  was  already  in  progress  and  survey  work  was  being  undertaken.  We  find  it  difficult  to  accept that the appellant Company did not have knowledge of  the ongoing project, which is for the benefit of a large number  of  people  of  the  area  as  against  the  interest  of  a  single  individual.

40.  In  view  of  the  objections  on  behalf  of  the  Power  Grid  Corporation  that  the  deviation  in  the  transmission  lines,  as  suggested  on behalf  of  the appellant  Company,  could not  be  practically achieved, we are left with the next best solution i.e.  to increase the clearance between the lowest point of the sag of  the  transmission  cable  and  the  topmost  portion  of  the  appellant’s poultry sheds. It should not also be forgotten that  from  the  point  of  the  sag  on  both  sides  the  cable  moves  upwards and the clearance becomes even greater on both sides  of  the  lowest  spot.  During  the  hearing  we  had  asked  Mr  Tripathi  to  confirm  with  the  engineers  of  the  Power  Grid  Corporation to explore the possibility of raising the height of  the towers even further to lessen the damage, if any, that may  be  caused  to  the  egg-laying  capacity  of  the  layers  in  the  appellant’s poultry farm.”

(emphasis supplied)

24

25

Page 25

23. We also agree with Shri P. P. Rao that the learned Single Judge of the  

High Court had rightly refused to entertain the second writ petition and the  

Division Bench committed an error by setting aside the order passed by him.  

A careful reading of the relief clauses of the two writ petitions makes it clear  

that substantially similar prayer had been made in both the cases.  The first  

petition  which  could  be  treated  as  one  filed  under  Article  227  of  the  

Constitution was dismissed by the High Court by assigning detailed reasons  

including  the  one  that  larger  public  interest  outweighed  the  individual  

interest of respondent No.1. However, while deciding the writ appeal filed  

against the order passed in Writ Petition No.20659/2009, the Division Bench  

overlooked this vital factor and ordered shifting of the transmission line.   

24. In Ramchandra Dagdu Sonavane v. Vithu Hira Mahar (2009) 10 SCC  

273, this Court discussed the doctrine of  res judicata embodied in Section  

11 of the Code of Civil Procedure and held:

“It is well known that the doctrine of res judicata is codified in  Section 11 of the Code of Civil Procedure. Section 11 generally  comes into play in relation to civil  suits.  But  apart  from the  codified law, the doctrine of res judicata or the principle of res  judicata has been applied since long in various other kinds of  proceedings  and  situations  by  courts  in  England,  India  and  other  countries.  The  rule  of  constructive  res  judicata  is  engrafted in Explanation IV of Section 11 of the Code of Civil  Procedure and in many other situations also principles not only  of direct res judicata but of constructive res judicata are also  

25

26

Page 26

applied, if  by any judgment or order any matter in issue has  been directly and explicitly decided, the decision operates as res  judicata and bars the trial of an identical issue in a subsequent  proceedings between the same parties.

The principle of res judicata comes into play when by judgment  and order a decision of a particular issue is implicit in it, that is,  it  must  be  deemed  to  have  been  necessarily  decided  by  implications even then the principle of res judicata on that issue  is directly applicable. When any matter which might and ought  to have been made a ground of defence or attack in a former  proceeding but was not so made, then such a matter in the eye  of the law, to avoid multiplicity of litigation and to bring about  finality in it, is deemed to have been constructively in issue and,  therefore, is taken as decided.”

25. The facts brought on record show that in the suit filed by the Trust,  

the trial Court had granted an injunction, which was vacated by the lower  

appellate Court and the petition filed against the order of the lower appellate  

Court was dismissed by the High Court on the premise that respondent No.1  

had  purchased  the  land  only  in  December,  2005  and  the  building  was  

constructed  in  July,  2006  knowing  fully  well  that  negotiations  with  the  

officers  of  appellant  No.1  had  failed.  The  learned  Single  Judge  further  

observed that it would be against public interest to pass an order which may  

necessitate  dismantling  of  the  entire  line  of  numerous  towers  erected  by  

spending  public  money.  Even  after  dismissal  of  the  petition  filed  under  

Article  227  of  the  Constitution  and  its  failure  to  persuade  the  Court  to  

sustain the order of injunction passed by the trial Court, respondent No.1  

26

27

Page 27

kept the suit pending and, at the same time, filed the second writ petition.  

This was a clear case of abuse of the process of the Court. It is a different  

thing that even in the second round, respondent No.1 could not persuade the  

learned Single Judge to entertain its prayer. The suit was withdrawn only  

after  the writ  appeal  was entertained by the Division Bench of  the High  

Court. This shows that respondent No.1 had availed parallel remedies and  

gave up its pursuit before the Civil Court only after the Division Bench of  

the High Court indicated its willingness to hear the writ appeal on merits.  

26. The judgment in S.J.S. Business Enterprises (P) Ltd. v. State of Bihar  

(supra), on which strong reliance has been placed by Dr. Singhvi, is clearly  

distinguishable. The facts of that case were the appellant had filed suit on  

4.4.2002 in the Court of Sub-Judge, Patna challenging the action taken by  

Bihar State Industrial Credit and Investment Corporation Ltd. under Section  

29 of the State Financial Corporations Act, 1951 for sale of its assets. On the  

very next day a writ petition was filed by the appellant for the same relief.  

While the Civil Court did not pass an interim order in terms of the prayer  

made by the appellant, the learned Single of the Patna High Court granted  

the prayer for stay of the auction proceedings subject to the condition of  

payment of Rs.10 lakhs. However, when the pendency of suit was brought to  

the notice of  the learned Single  Judge,  he dismissed the writ  petition by  

27

28

Page 28

holding  that  the  appellant  had  suppressed  the  factum  of  civil  suit.  The  

Division Bench of  the High Court  dismissed the appeal  filed against  the  

order of the learned Single Judge. A two Judge Bench of this Court referred  

to R. v. General Commissioner for the purposes of the Income Tax Act for  

the District of Kensington (1917) 1 KB 486 and State of Haryana v. Karnal  

Distillery Co. Ltd. (1977) 2 SCC 431 and observed:

“Assuming that the explanation given by the appellant that the  suit  had been filed by one of  the Directors  of  the Company  without  the  knowledge  of  the  Director  who  almost  simultaneously approached the High Court under Article 226 is  unbelievable (sic), the question still remains whether the filing  of the suit can be said to be a fact material to the disposal of the  writ  petition  on  merits.  We  think  not.  The  existence  of  an  adequate or suitable alternative remedy available to a litigant is  merely a factor which a court entertaining an application under  Article 226 will consider for exercising the discretion to issue a  writ  under  Article  226  [A.N.  Venkateswaran  v.  Ramchand  Sobhraj Wadhwani AIR 1961 SC 1506]. But the existence of  such remedy does not impinge upon the jurisdiction of the High  Court to deal with the matter itself if it is in a position to do so  on the  basis  of  the  affidavits  filed.  If,  however,  a  party  has  already availed  of  the alternative remedy while  invoking the  jurisdiction under Article 226, it would not be appropriate for  the court  to  entertain the writ  petition.  The rule  is  based on  public  policy  but  the  motivating  factor  is  the  existence  of  a  parallel  jurisdiction in another court.  But this Court  has also  held in Chandra Bhan Gosain v. State of Orissa (1964) 2 SCR  879 that even when an alternative remedy has been availed of  by  a  party  but  not  pursued  that  the  party  could  prosecute  proceedings under Article 226 for the same relief. This Court  has also held that when a party has already moved the High  Court  under  Article  226 and failed  to  obtain  relief  and then  moved an application under Article 32 before this Court for the  

28

29

Page 29

same  relief,  normally  the  Court  will  not  entertain  the  application  under  Article  32.  But  where  in  the  parallel  jurisdiction, the order is not a speaking one or the matter has  been disposed of  on some other ground, this Court  has,  in a  suitable  case,  entertained  the  application  under  Article  32  [Tilokchand Motichand v.  H.B.  Munshi  (1969)  1 SCC 110].  Instead of dismissing the writ petition on the ground that the  alternative remedy had been availed of, the Court may call upon  the party to elect whether it will proceed with the alternative  remedy or with the application under Article 226 [K.S. Rashid  and Son v. Income Tax Investigation Commission AIR 1954  SC 207]. Therefore, the fact that a suit had already been filed  by the appellant was not such a fact the suppression of which  could have affected the final  disposal  of the writ  petition on  merits.

In this case,  admittedly, the appellant has withdrawn the suit  two weeks after  the suit  had been filed.  In  other  words,  the  appellant elected to pursue its remedies only under Article 226.  The pleadings were also complete before the High Court. No  doubt, the interim order which was passed by the High Court  was obtained when the suit was pending. But by the time the  writ petition was heard the suit had already been withdrawn a  year  earlier.  Although  the  appellant  could  not,  on  the  High  Court’s reasoning, take advantage of the interim order, it was  not correct in rejecting the writ petition itself when the suit had  admittedly  been  withdrawn,  especially  when  the  matter  was  ripe for hearing and all the facts necessary for determining the  writ  petition on merits  were before the Court,  and when the  Court was not of the view that the writ petition was otherwise  not maintainable.”

27. The ratio of the above extracted observations is that the Court will not  

allow a party to pursue two remedies simultaneously.  The proposition laid  

down by this Court does not help the cause of respondent No.1.  Instead, the  

same can be relied upon for holding that the Division Bench of the High  

29

30

Page 30

Court committed an error by setting aside the order of the learned Single  

Judge who had non-suited respondent No.1 on the ground that it had not  

only availed parallel remedies but pursued the same till the writ appeal filed  

against the order of the learned Single Judge was entertained.

28. The finding recorded by the Division Bench of the High Court that the  

scheme was not in consonance with Sections 28 and 29 of the Act is also  

erroneous. In  response  to  the  observation  made  by  the  High  Court  on  

25.3.2011, Shri Amar Nath Mohanty filed further affidavit dated 29.3.2011,  

paragraphs 3 to 6 of which are extracted below:

“3. That the nomenclature of the schemes like Chandaka-Bidanasi- Mendhasal are only indicative in nature for internal project planning,  while  actual  construction takes place after survey of  the line  and  alignment and tower spotting are finalized in accordance with the  notified scheme. These details are kept in the office. In the instant  case, the land schedule etc., are not available but the profile of the  said portion is available which is enclosed herewith as Annexure-M/l  .

4. That there are several examples where the name of sub-station is  different from its specific site locations. For example the Chandaka  Grid Sub-station is in Patia Mouza written in brackets as Chandaka  Industrial Estate, the "Bargarh Grid Sub-station" in Bhubaneswar is  in  Kesura  Village  and  Jharsuguda  Grid  Sub-station  is  in  Village  sarasmala.

5. That the line work has been completed from both Mendhasal and  Bidanasi end; except this small portion which is left out; the line  alignment is already fixed with two remaining towers coming in the  area of ASBM. So further change cannot be made.

30

31

Page 31

6. That the Appellants in course of arguments have also produced a  Map before this Hon'ble Court which has also been annexed by the  Respondents  as  Annexure-H/1  to  the  Affidavit  filed  by  the  Respondents on 25.03.2011 and the said Map clearly discloses that  two towers are to be erected on the land of ASBM.”

29. In our view, the explanation given for not incorporating full details of  

the scheme in the notifications should have been accepted by the High Court  

and there was no justification to direct re-routing of the transmission line on  

the specious ground of non-compliance of the two provisions.

30. In the result, the appeal is allowed, the impugned judgment is set aside  

and Writ  Petition No.20659/2009 filed  by respondent  No.1  is  dismissed.  

Respondent No.1 shall pay cost of Rs.10 lakhs to appellant No.1 because  

implementation of the scheme was frustrated due to unwarranted litigation  

by the Trust and respondent No.1.  The cost shall be paid to appellant No.1  

within a period of three months from today.

................................................J. (G.S. SINGHVI)

................................................J. (V. GOPALA GOWDA)

New Delhi; August 5, 2013.

31