16 February 2012
Supreme Court
Download

NTPC LIMITED Vs ANSALDO CALDAIE BOILERS INDIA P.LD.

Bench: ALTAMAS KABIR,J. CHELAMESWAR
Case number: C.A. No.-002134-002134 / 2012
Diary number: 8052 / 2011
Advocates: SHAILENDRA SWARUP Vs AP & J CHAMBERS


1

REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO.2134 OF 2012

(Arising out of SLP(C)No.7807 of 2011)

NTPC LIMITED   … APPELLANT   

              Vs.

ANSALDO CALDAIE BOILERS  INDIA P. LTD. & ANR.   … RESPONDENTS

J U D G M E N T

ALTAMAS KABIR, J.

1. Leave granted.

2. Following international competitive bidding procedures,  

the  Appellant  had  invited  bids  for  the  supply  and  

installation of Steam Generator package for captive coal-

2

based Thermal Power Projects in different areas. The bid of  

the Respondent No.1 was rejected by the Appellant by its  

letter dated 5th January, 2011, as the same did not meet the  

minimum  qualifying  requirements  set  out  in  the  Bid  

documents.  Furthermore,  the  Qualified  Steam  Generator  

Manufacturer, Ansaldo Caldaie, Italy, proposed by the said  

Respondent,  did  not  have  the  necessary  minimum  

qualification,  as  was  required  in  terms  of  the  Bid  

documents.  

3. The main issue which arises for consideration in this  

Appeal is whether Ansaldo Caldaie, Italy, can be said to be  

a  Qualified  Steam  Generator  Manufacturer  within  the  

definition set out in the detailed Invitation for Bids.  The  

said invitation for bid contained the qualifying requirement  

for Bidders in Clause 7 of the Tender Document. Clause 7.1.0  

provided  that  the  Bidder  should  meet  the  qualifying  

requirements of any one of the qualifying routes stipulated  

under Clause 1.1.0 or 1.2.0 or 1.3.0 or 1.4.0 or 1.5.0.  In  

addition,  the  Bidder  was  also  required  to  meet  the

3

requirements  stipulated  under  Clause  7.6.0  and  7.7.0,  

together with the requirements stipulated under Section ITB.

4. Route 1 permits a Qualified Steam Generator Manufacturer  

to join the bidding process provided that it should meet the  

qualifying  requirements  of  any  of  the  qualifying  routes  

indicated in Clause 7 of the tender documents.  In Clause 7  

of  the  tender  documents,  five  different  routes  have  been  

enumerated which could be taken by the tenderers, namely :-

(i) as a Qualified Steam Generator Manufacturer; or

(ii) as an Indian Steam Generator Manufacturer; or

(iii) as an Indian subsidiary company of a Qualified Steam  Generator Manufacturer; or

(iv) as an Indian Joint Venture Company for manufacturing  Super Critical Steam Generators in India between an  Indian  Company  and  a  Qualified  Steam  Generator  Manufacturer; or  

(v) as an Indian Joint Venture Promoter holding at least  51%  stake  in  a  Joint  Venture  Company  for  manufacturing  Super  Critical  Steam  Generators  in

4

India  between  an  Indian  Company  and  a  Qualified  Steam Generator Manufacturer.

5. Indisputably, none of the parties which responded to the  

invitation adopted Routes 1 or 3.  Bharat Heavy Electricals  

Ltd. adopted Route 2, while Route 4 found favour with Larsen  

& Toubro, MHI and the Appellant, while BGR took recourse to  

Route  5.   Route  4  contained  in  Clause  7.4.0  relates  to  

Indian Joint Venture Companies for manufacturing of Super  

Critical Steam Generators in India between an Indian Company  

and a Qualified Steam Generator Manufacturer. For the sake  

of reference, Clauses 7.4.1 and 7.4.2 which formed part of  

Route 4 are extracted hereinbelow :-

“7.4.0 Route 4 : Indian Joint Venture (JV) Company  for  manufacturing  of  Super  Critical  Steam  Generator in India between an Indian Company  and a Qualified Steam Generator Manufac-turer

7.4.1 The  Bidder  shall  be  a  Joint  Venture  (JV)  Company  incorporated  in  India  under  the  Companies Act 1956 of India, as on the date  of techno-commercial bid opening, promoted by  (i)  an  Indian  Company  registered  in  India  under  the  Companies  Act  1956  of  India  and  (ii) a Qualified Steam Generator Manufacturer  meeting requirements of clause 7.1.1, created  for  the  purpose  of  manufacturing  in  India  supercritical  steam  generator  sets  covering

5

the type, size and rating specified.  If the  JV  Company  is  incorporated  as  a  public  limited Company then it should have obtained  certificate for Commencement of Business in  India as on the date of techno-commercial bid  opening.

The  Qualified  Steam  Generator  Manu-facturer  shall maintain a minimum equity participation  of 26% in the JV Company for a lock-in period  of 7 years from the date of incorporation of  JV  Company  or  up  to  the  end  of  defect  liability period of the contract whichever is  later.   

One  of  the  promoters  shall  be  a  majority  stakeholder  who  shall  maintain  a  minimum  equity  partici-pation  of  51%  in  the  JV  Company for a lock in period of 7 years from  the date of incorporation of JV Company or up  to the end of defect liability period of the  contract whichever is later.

In the event that the majority stake holder  in the JV Company is an entity other than the  Qualified  Steam  Generator  Manufacturer,  it  should be an Indian Company and should have  executed,  in  the  last  10  years,  large  industrial  projects  on  EPC  basis  (with  or  without civil works) in the area of power,  steel, oil & gas, petrochemical, fertilizer  and/or  any  other  process  industry  with  the  total  value  of  such  projects  being  Rs.10,000/- million or more. At least one of  such projects should have a contract value of  Rs.4,000/- million or more.  These projects  shall be in successful operation for a period  of not less than one year as on the date of  techno-commercial bid opening.  

6

7.4.2 The Bidder shall furnish a DJU executed by  him,  the  Qualified  Steam  Generator  Manufacturer and other JV promoter having 25%  or  higher  equity  participation  in  the  JV  Company, in which all the executants of DJU  shall be jointly and severally liable to the  Employer  for  successful  performance  of  contract as per the format enclosed in the  bidding  documents.   The  joint  deed  of  undertaking  shall  be  submitted  along  with  techno-commercial  bid,  failing  which  the  Bidder  shall  be  disqualified  and  his  bid  shall be rejected.

In case of award, each promoter having 25% or  higher equity participation in the JV Company  will be required to furnish an on demand bank  guarantee for an amount of 0.5% of the total  contract price of the Steam Generator Package  in  addition  to  the  contract  performance  security to be furnished by the Bidder.”  

6. As  mentioned  hereinbefore,  the  bid  filed  by  the  

Respondent No.1 was rejected by the Appellant by its letter  

dated  5th January,  2011,  as  the  same  did  not  fulfil  the  

qualifying requirements of Route 4, extracted hereinabove.  

7. Appearing  for  the  Appellant,  the  learned  Attorney  

General,  Mr.  Goolam  E.  Vahanvati,  submitted  that  Clause  

7.1.1  prescribes  the  basic  qualifying  requirements  for  a  

Qualified  Steam  Generator  Manufacturer  and  the  same  is

7

applicable  to  all  the  routes  permitted  under  the  bidding  

documents, irrespective of the route which the Bidder would  

opt  for,  for  seeking  qualification.  For  the  sake  of  

convenience, Clause 7.1.1 is reproduced hereinbelow :-

“7.1.1 The  Bidder  should  have  designed,  engineered  ,   manufactured/got  manufactured,  erected/supervised  erection,  commissioned/  supervised commissioning of at least one (1) number  of coal fired supercritical Steam Generator having  rated capacity of 1500 tonnes of steam per hour or  above.  Further, such Steam generator should be of  the type specified, i.e. single pass (tower type) or  two pass type using either spiral wound (inclined)  or vertical plain or vertical rifled type water wall  tubing, and should be in successful operation for a  period of not less than one (1) year as on the date  of Techno-commercial bid opening.  In addition, the  above Steam Generator should have been provided with  evaporator suitable for variable pressure operation  (sub-critical  and  supercritical  pressure  ranges).  The  Bidder  shall  offer  only  the  type  of  Steam  Generator and type of water wall tubing for which he  is qualified.”   

8. The learned Attorney General submitted that Clause 7.1.1  

is identical to Clause 1.1.2 of Item No.4 of Section III of  

the  Tender  Documents  and  under  Clause  1.4.1  it  has  been  

clearly mentioned that the requirements of Clause 1.1.1 had  

to be met.  The learned Attorney General urged that in view

8

of  Clause  7.1.1,  the  Bidder  must  have  “designed”  and  

“engineered” the entire Steam Generator himself and the same  

could not be outsourced.  Accordingly, once it is submitted  

that a Steam Generator is to be designed by the Qualified  

Steam Generator Manufacturer itself, all the integral parts  

of  the  Steam  Generator  like  the  furnace  (evaporator),  

Superheaters  1,  2  and  3,  Reheaters  1  and  2,  connecting  

piping etc., have to be designed and engineered by the said  

manufacturer  himself.  The  learned  Attorney  General  also  

urged that Clause 7.1.1, however, permitted the manufacture,  

erection or commissioning to be outsourced by the Qualified  

Steam  Generator  Manufacturer,  in  view  of  the  expressions  

used, such as, “got manufactured”, “supervised erection” and  

“supervised commissioning”.   

9. The learned Attorney General also contended that Clause  

7.1.1  also  categorically  states  that  the  Steam  Generator  

would have to be provided with an evaporator suitable for  

variable  pressure  operation  (emphasis  added).  It  was  submitted that an evaporator is an integral and one of the  

most critical parts of any Supercritical Steam Generator. It

9

was further urged that if the evaporator was not designed  

for variable pressure operation, conditions in Note 5 of the  

Notes in Clause 1.0.0 of the Bid documents would have to be  

complied  with.  For  the  sake  of  reference,  Note  5  is  

reproduced hereinbelow :-

“Steam Generator Manufacturer with Technology Tie-up  for Variable Pressure Design In case a supercritical Steam Generator manufacturer  meets all the requirements as specified in clause  no. 1.1.1 above except that the evaporator in the  reference  steam  generator  is  not  designed  for  variable  pressure  operation  and  is  designed  for  constant  pressure  (Universal  Pressure)  operation  only,  in  such  case,  the  Supercritical  Steam  Generator  Manufacturer  has  an  ongoing  license  agreement (which covers technology transfer), as on  the date of Techno-commercial bid opening, with the  original  Technology  Owner  (Licensor)  for  design,  manufacture,  sell,  use,  service  of  once  through  variable  pressure  supercritical  steam  generator  technology  (with  evaporator  suitable  for  variable  pressure operation in sub-critical pressure ranges).

i. The  licensor  should  have  experience  of  providing such variable pressure design steam  generator technology for at lease one (1) no.  of coal fired supercritical steam generator for  a  1500  T/hr  or  higher  capacity  using  either  spiral  wound  (inclined)  or  vertical  plain  or  vertical rifled type water wall tubing with the  evaporator  suitable  for  variable  pressure  operation  in  sub-critical  and  super-critical  pressure  ranges  and  which  should  be  in

10

successful operation for a period of not less  than one (1) year as on the date of bid opening.

ii. The Bidder shall offer only the type of steam  generator i.e. single pass (tower type) or two  pass type for which the Bidder is qualified and  shall offer only the type of water wall tubing  (either  spiral  wound  (inclined)  or  vertical  plain or vertical rifled type) for which his  licensor is qualified.

iii.In such an event, the Bidder shall furnish a    Deed of Joint Undertaking executed between the  Bidder  and  the  supercritical  steam  generator  manufac-turer  (as  the  case  may  be)  and  its  Technology Owner (Licensor), as per the format  enclosed in the Bidding Documents towards the  Bidder  and  the  licensor  being  jointly  and  severally liable to the Employer for successful  performance of the Steam Generator along with  an extended warranty of at least one (1) year  over and above what is required as per tender  documents.  

iv. In case of award, Technology Owner (Licensor)  will be required to furnish an on demand bank  guarantee for an amount of 0.1% of the total  contract price of the Steam Generator Package  in  addition  to  the  contract  perfor-mance  security to be furnished by the Bidder.”       

10. In addition to the above, the learned Attorney General  

submitted that in the event the provisions of Note 5 were to  

be followed, it would be necessary for the Bidder to provide  

a  Deed  of  Joint  Undertaking  to  be  executed  between  the  

Bidder, the proposed Qualified Steam Generator Manufacturer,

11

who possessed the experience of designing and engineering a  

Steam  Generator  with  evaporator  suitable  for  constant  

pressure operation. The very reason for the furnishing of a  

Deed of Joint Undertaking was to make the technology owner  

responsible for the successful operation of the plant along  

with the Bidder.  It was submitted that only when such an  

undertaking  was  given  by  the  licensor  and  the  Qualified  

Steam  Generator  Manufacturer  that  the  Bidder  would  be  

eligible  for  being  considered  as  being  qualified  to  

participate  in  the  bidding  process.  The  learned  Attorney  

General submitted that despite the fact that the Respondent  

No.1 had taken recourse to Note No.5 and the bid of the  

Respondent was non-responsive, no Deed of Joint Undertaking  

had been furnished by the Respondent. On the other hand, in  

the  bid  submitted  by  the  Respondent  No.1,  it  had  been  

mentioned  in  Clause  1.2.0  that  the  evaporator  in  the  

reference Steam Generator, which was supplied to Enel, was  

for variable pressure operation.  The Respondent claimed to  

have designed and engineered the reference Steam Generator,  

but when it came to the actual confirmation in reference to

12

the experience, it was indicated as follows :-

1.5.0  We, confirm that M/s ANSALDO CALDAIE S.p.A.  (Qualified Steam Generator Manufacturer)  meets  all the requirement as per 1.1.1 of BDS except  that the evaporator indicated in the reference  steam  generator  is  not  designed  for  variable  pressure operation and is designed for constant  pressure  (Universal  Pressure)  operation  only  and  seeking  qualification  along  with  the  original technology owner (Licensor) from which  he  has  an  ongoing  license  agreement  (which  covers technology transfer), as on the date of  Techno-commercial  bid  opening, for  design,  manufacture, sell, use, service of once through  variable pressure supercritical steam generator  technology  (with  evaporator  suitable  for  variable pressure operation in sub-critical and  supercritical pressure ranges).

Further  we  confirm  that  original  technology  owner  (Licensor)  had  experience  of  providing  variable  pressure  design  steam  generator  technology  for  at  least  one  (1)  no.  of  coal  fired supercritical steam generator technology  for  at  least  one  (1)  no.  of  coal  fired  supercritical steam generator for a 1500 T/hr  or  higher  capacity  using  either  spiral  wound  (inclined) or vertical plain or vertical rifled  typed  water  wall  tubing  with  the  evaporator  suitable  for  variable  pressure  operation  in  sub-critical and super-critical pressure ranges  and which should be in successful operation for  a period of not less than one (1) year as on  the date of techno commercial bid opening.  The  detail  of  Licensor  and  his  experience  detail  are as follows:”

13

11. The  learned  Attorney  General  submitted  that  it  was,  

therefore,  clear  that  the  evaporator  for  the  Steam  

Generator, which the Respondent No.1 had agreed to provide,  

had not been designed for variable pressure operation and,  

accordingly, the experience of the licensor was relied upon.  

Furthermore, the Deed of Joint Undertaking referred to in  

Clause  1.01.00  was  left  blank,  and  Clause  1.6.0  which  

included the reference to the Deed of Joint Undertaking was  

expressly and consciously scored off.  It was submitted that  

the failure to furnish the said undertaking made the bid of  

the Respondent No.1 completely non-responsive.   

12. In  support  of  his  aforesaid  submissions,  the  learned  

Attorney General submitted that the crucial aspects of the  

case are :-

(i) Did the tender contemplate that the Evaporator is  something separate from the Steam Generator?

(ii) Is the Evaporator not an integral part of the Steam  Generator?

14

(iii) Could  the  Evaporator,  if  the  tender  contemplated  that the Evaporator could be manufactured by a third  party, be manufactured by a third party?

(iv) Did  Ansaldo  Caldaie  indicate  that  the  Evaporator  would be supplied by it after having it manufactured  by a third party?

13. The learned Attorney General submitted that as far as  

the first two questions are concerned, the Evaporator was  

very much an integral part of the Steam Generator and as far  

as  the  third  and  fourth  questions  are  concerned,  the  

Attorney  General  submitted  that  the  answer  was  in  the  

negative.  

14. Learned Attorney General contended that the Respondent  

No.1 was ineligible to compete in the bid, since it did not  

satisfy  one  of  the  critical  conditions  of  the  tender  

document. It was submitted that in order to be eligible, a  

Bidder  had  to  satisfy  the  conditions  contained  in  Clause  

7.1.1  of  the  Memorandum  of  Understanding,  hereinafter  

referred to as ‘MOU’. Although, manufacturing, erection or  

commissioning of the Steam Generator could be outsourced,

15

the “designing” and “engineering” of the Steam Generator had  

to  be  done  by  the  Bidder  himself.  The  learned  Attorney  

General submitted that if the party proposed as Qualified  

Steam Generator Manufacturer by the Bidder had not designed  

or engineered the Steam Generator himself, he could not be  

said to have met the qualifying requirements stipulated for  

a Qualified Steam Generator Manufacturer and consequently,  

the Bidder could not also be said to have fulfilled the  

requirements relating to meeting the minimum qualification  

requirements  for  his  bid  to  be  accepted.   The  learned  

Attorney  General  submitted  that  the  evidence  on  record  

clearly indicated that the Respondent No.1 had not designed  

or  engineered  the  entire  Steam  Generator  and  that  it  

transpired  that  in  response  to  queries  raised  by  the  

Appellant to Enel, the reference station owner had indicated  

that the work had been split up between the Respondent No.1  

and BHK, but executed the contract for the reference station  

as part of a consortium. The detailed break-up which was  

provided, indicated that the Respondent No.1 had not done  

the designing and engineering of the boiler walls furnace.

16

It was submitted that the failure to design and/or engineer  

the  critical  parts  of  the  Steam  Generator  was  fatal  for  

qualification  as  a  Qualified  Steam  Generator  Manufacturer  

and hence the bid submitted by the Respondent No.1 had to be  

rejected.  

15. The learned Attorney General submitted that there were  

various  contradictions  and  inconsistencies  in  the  bid  

submitted by the Respondent No.1 and while, on the one hand,  

it  was  mentioned  that  the  reference  Steam  Generator  was  

provided  with  evaporator  suitable  for  variable  pressure  

operation  within  sub-critical  and  super  critical  pressure  

ranges, it was also indicated in another part of the Tender  

Documents  that  the  evaporator  indicated  in  the  reference  

Steam  Generator  was  not  designed  for  variable  pressure  

operation,  but  for  constant  pressure  operation.   It  was  

submitted  that  the  said  condition  being  one  of  the  

fundamental conditions of the bid, it could not be held to  

be substantially responsive.

17

16. The  learned  Attorney  General  submitted  that  the  High  

Court had not applied itself to these aspects of the matter,  

which  were  essential  in  nature  and  had  proceeded  on  the  

assumption that the bid of the Respondent No.1 was in order  

and that the rejection of the bid of the Respondent No.1 was  

liable to be quashed.  

17. On behalf of the Respondent No.1 it was submitted by Mr.  

Mukul Rohatgi, learned Senior Advocate, that the Respondent  

No.1 Company is an Indian Company jointly promoted by Gammon  

India  Limited  and  Ansaldo  Caldaie  S.p.A.,  Italy,  who  has  

been in the business of manufacturing, designing, erecting  

and  commissioning  of  boilers  since  1853  and  is  a  world  

leader in the manufacture of Supercritical Steam Generators  

and  had  engineered,  designed  and  manufactured  24  

Supercritical boilers with capacity of 1500 Tonnes of Steam  

per  hour  and  above.   Mr.  Rohatgi  submitted  that  the  

Respondent  No.1  Company  had  installed  boilers  of  various  

types  all  over  the  world  and  it  also  has  a  significant  

presence  in  India  since  1960.  Included  amongst  its  major  

projects within India, are :-

18

(i) 3 x 200 MW for NTPC at Ramagundam, Andhra Pradesh,  

which was installed in 1980 and has been operating  

successfully since its installation;

(ii) 2 x 500 MW for NTPC, Farakkha in West Bengal, which  

has been in operation since 1992;

(iii) 230 MW at Smalkot for BSES, which was commissioned  

in 1999; and

(iv) 2 x 210 MW at Neyvelli Lignite Corporation at Tamil  

Nadu, which was the first of its kind in the State.

It  was  submitted  that  the  consortium,  of  which  the  

Respondent No.1 was a part, has the distinction of being the  

second  largest  company  involved  in  the  installation  of  

boilers in India after Bharat Heavy Electricals Ltd. (BHEL).

18. Mr. Rohatgi submitted that the Respondent No.1 has vast  

experience in working with Steam Generators and was fully  

eligible to compete in the bids relating to Clause 7.4 of  

the detailed information for bids, which stipulated that the  

qualification of the Qualified Steam Generator Manufacturer  

would be considered if it owned at least 26% of the equity

19

of the Bidder as per Clause 7.1.1.  Accordingly, Respondent  

No.1  submitted  its  performance  certificate.  Mr.  Rohatgi  

submitted that the Respondent No.1 submitted the Performance  

Certificate  issued  to  Ansaldo  Caldaie  by  Anel  Tower  for  

Torranvaldaliga  Nord  Power  Plant,  to  the  Appellant  to  

support its eligibility for participating in the Bid.   

19. Mr.  Rohatgi  submitted  that  there  were  four  Bidders,  

including the Respondent No.1, but ultimately on 5th January,  

2011, the Respondent No.1 was informed that his technical  

bid had been rejected on the ground that it did not meet the  

qualification criteria. The Bank Guarantee furnished by the  

Respondent No.1 was returned to him. In the meantime, the  

Writ Petition filed by the Respondent, (WP (C) No.296 of  

2011), came up for hearing on 17th January, 2011, when it was  

withdrawn with liberty to file a fresh petition based on the  

fact that the Respondent No.1 had in the interregnum period  

received the rejection letter dated 5th January, 2011, issued  

by the Appellant.   

20

20. Mr. Rohatgi submitted that Clause 7.1.1 and Clause 7.4  

clearly reflected the mind of the Bidder. Learned counsel  

urged that the use of the expression “provided” in dealing  

with  the  capability  of  the  Bidder  to  deal  with  variable  

pressures  merely  indicated  that  the  Steam  Generator  

Manufacturer  would  have  to  provide  technical  tie-up  for  

variable pressure design and in the absence of the same, the  

bid submitted would still qualify for being considered. It  

was urged that the use of the expression “provided” would  

have to be read along with the phrase “designed, engineered,  

manufactured/got manufactured” etc. The further usage of the  

words “in addition” indicated that the stipulation regarding  

the  provision  of  an  evaporator  suitable  for  variable  

pressure  operation  was  an  additional,  ancillary  and  

peripheral requirement and not integral to the type of Steam  

Generator  contemplated.   Mr.  Rohatgi  urged  that  the  

submission made on behalf of the Appellant to the contrary  

was  incorrect  since  it  had  been  in  no  uncertain  terms  

submitted  that  in  the  bid  document  and  in  the  pleadings  

before  the  High  Court  and  this  Court  noted  that  the

21

evaporator  provided  with  the  Steam  Generator  at  the  

reference plant at TNP was suitable for variable pressure  

operation.  

21. It was submitted that the entire basis of the case made  

out by the Appellant was, therefore, non-est and the High  

Court did not commit any error in allowing the Writ Petition  

filed by the Respondents.  

22. There is no dispute that the Respondent No.1 chose Route  

4 while submitting its Tender Bid, in its capacity as an  

Indian  Joint  Venture  Company  for  manufacturing  Super-

Critical Steam Generator in India between an Indian Company  

and a Qualified Steam Generator Manufacturer. The crucial  

condition for a Bidder of the said category to be considered  

is contained in Clause 7.1.1 of the Tender Documents, which  

has been extracted hereinbefore and provides that the Bidder  

should  have  designed,  engineered,  manufactured/got  

manufactured,  erected/  supervised  direction,  

commissioned/supervised commissioning of at least one Steam  

Generator having rated capacity of 1500 Tonnes of Steam per

22

hour  or  above  and  that  it  should  be  provided  with  an  

Evaporator  suitable  for  variable  pressure  operations  for  

special category and supercritical pressure ranges.   

23. The  controversy  which  led  to  the  rejection  of  the  

Technical Bid of the Respondent No.1 was with regard to the  

question  as  to  whether  in  the  case  of  a  Joint  Venture  

Undertaking  it  was  essential  that  the  Qualified  Steam  

Generator Manufacturer also had to be the manufacturer of  

the  evaporator  or  whether  it  could  function  as  a  

facilitator.  Furthermore, what appears to have weighed with  

the  Appellant  in  rejecting  the  Technical  Bid  of  the  

Respondent  No.1  was  that  the  Steam  Generator  had  been  

designed for constant pressure and not variable pressure, as  

required by the Appellant.  

24. Admittedly, the evaporator is an integral part of the  

Steam Generator.  The question is whether the same could not  

be  manufactured  by  a  third  party  and  supplied  to  the  

Qualified  Steam  Generator  Manufacturer  for  use  in  the  

boiler.   Although,  the  said  proposition  has  been  hotly

23

contested on behalf of the Respondent, an attempt was also  

made to show that the evaporator was in fact designed for  

variable pressure, but such a submission was contrary to the  

confirmation given by the Respondent No.1 which indicated  

that the evaporator had been designed for Constant Pressure  

(Universal  Pressure)  operation  only.  The  MOU,  while  

permitting manufacturing, erection or commissioning of the  

Steam Generator, provided that the same could be outsourced,  

but the “designing” and “engineering” of the Steam Generator  

had  to  be  done  by  the  Bidder  himself  and  if  the  party  

proposed as Qualified Steam Generator Manufacturer and the  

Bidder had not designed and engineered the Steam Generator  

itself,  it  could  not  be  said  that  the  qualifying  

requirements for such manufacturer had been satisfied.   

25. From the terms and conditions contained in the MOU, it  

appears to us that it was the intention of the Appellant  

that the Qualified Steam Generator Manufacturer would have  

to be the manufacturer of the evaporator itself and could  

not  have  outsourced  the  manufacture  thereof  to  a  third  

party, since the evaporator controlling the pressure of the

24

Steam  generated  is  a  vital  and  crucial  component  of  the  

Steam Generator itself.  The Appellant, which will be the  

ultimate  user  of  the  Generator,  must  be  presumed  to  be  

conscious of the competence of the tenderer to “provide” the  

evaporator in keeping with the required specifications.

26. In the aforesaid context, we are unable to uphold the  

decision  of  the  Division  Bench  of  the  Delhi  High  Court  

quashing the letter dated 5th January, 2011, issued by the  

Appellant  herein,  informing  the  Respondent  No.1  that  its  

Techno-commercial Bid had been rejected on the ground that  

it did not meet the minimum requirement set forth in item  

No.4 of Section III of the Tender Documents. The High Court  

while  interpreting  the  provisions  of  Clause  7.1.1  of  the  

Tender Documents was influenced by the use of the phrase  

“manufactured/got manufactured” while considering the fact  

that although, Ansaldo Caldaie, Italy, was being projected  

as the Qualified Steam Generator Manufacturer, Siemens A.G.  

was shown as the technology owner/licensor of the evaporator  

which was offered by the Respondent No.1.  In other words,  

the evaporator being offered by the Respondent No.1 was one

25

which  had  been  manufactured  not  by  the  Qualified  Steam  

Generator Manufacturer, but by a third party, which was not  

contemplated  in  the  aforesaid  condition  of  the  Tender  

Documents.  

27. The importance of the above condition is manifested in  

the functioning of the Steam Generator which handles High  

Pressure Steam for the purpose of turning the turbines for  

generating electricity.  The design and engineering of the  

evaporator  and  the  boiler  itself  has  to  be  such  as  to  

withstand  the  very  high  temperatures  and  pressures  

generated.  The  importance  of  the  variable  pressure  

operations is of great importance as far as generation and  

wastage  of  energy  is  concerned.   The  importance  of  the  

evaporator in controlling pressure during operations is to  

automatically  regulate  the  flow  of  water,  generation  of  

pressure and temperature of the steam to the desired level.  

28. In that view of the matter, we allow the Appeal and set  

aside the impugned judgment of the Division Bench of the  

High  Court  allowing  the  Writ  Petition  filed  by  the

26

Respondent No.1. The Writ Petition filed by the Respondent  

No.1, therefore, stands dismissed.   

29. There shall, however, be no order as to costs.  

                            ………………………………………………J.    (ALTAMAS KABIR)

New Delhi                  ………………………………………………J. Dated: 16.02.2012        (J. CHELAMESWAR)