13 July 2018
Supreme Court
Download

NATIONAL HIGHWAYS AUTHORITY OF INDIA THROUGH DIRECTOR Vs M/S GWALIOR JHANSI EXPRESSWAY LIMITED THROUGH DIRECTOR

Bench: HON'BLE THE CHIEF JUSTICE, HON'BLE MR. JUSTICE A.M. KHANWILKAR, HON'BLE DR. JUSTICE D.Y. CHANDRACHUD
Judgment by: HON'BLE MR. JUSTICE A.M. KHANWILKAR
Case number: C.A. No.-003288-003288 / 2018
Diary number: 39281 / 2017
Advocates: ASTHA TYAGI Vs


1

1    

REPORTABLE  

IN THE SUPREME COURT OF INDIA  

CIVIL APPELLATE JURISDICTION   

 

CIVIL APPEAL NO. 3288  OF  2018    

NATIONAL HIGHWAYS AUTHORITY OF INDIA  …..Appellant(s)          

:Versus:    

GWALIOR JHANSI EXPRESSWAY LIMITED   ....Respondent(s)    

 

 

J U D G M E N T  

 

A.M. Khanwilkar, J.  

1. This appeal emanates from the decision of the High Court  

of Delhi at New Delhi dated 21st August, 2017 in Appeal ARB.A  

(Comm.) No.20 of 2017 whereby the appeal filed by the  

appellant under Section 37(2)(b) of the Arbitration and  

Conciliation Act, 1996 (for short, “the Act”) seeking to quash  

the order dated 24th May, 2017 passed by the Arbitral Tribunal  

under Section 17 of the Act came to be dismissed. The Arbitral  

Tribunal vide order dated 24th May, 2017 allowed the

2

2    

application preferred by the respondent (claimant) under  

Section 17 of the Act seeking a direction to the appellant to  

allow the respondent to exercise an option to match the lowest  

bid in terms of the order dated 23rd July, 2016 passed by the  

Arbitral Tribunal and including to exercise Right of First  

Refusal (“ROFR”) and for other consequential reliefs.   

  2. Shorn of unnecessary details, some of the relevant facts  

are that  the appellant (a body corporate, constituted under  

the National Highways Authority of India Act, 1988) entered  

into a Concession Agreement dated 17th December, 2006 with  

the respondent (a consortium comprising of Apollo Enterprises  

Limited and D.S. Construction Limited) for works of widening  

the existing two-lane portion of Km 16.000 to Km 96.127 on  

National Highway No.75 to four lanes in the States of Uttar  

Pradesh and Madhya Pradesh on the terms and conditions  

specified therein. The appellant asserts that the respondent  

failed to undertake the project work at the requisite pace, inter  

alia, due to inadequate deployment of machinery, plant,  

material and manpower. The respondent had merely achieved

3

3    

62% progress and eventually abandoned the project site in  

March, 2012.  The appellant, therefore, had to issue a Cure  

Period Notice dated 19th October, 2013 requiring the  

respondent to cure the breaches within 30 days from receipt of  

the notice, failing which the appellant may be forced to initiate  

further action to terminate the contract in terms of the  

Concession Agreement. The respondent denied the correctness  

of the stated notice by a written reply. The appellant then  

issued letters dated 27th February, 2014 and 7th March, 2014  

expressing its intention to issue termination notice of the  

Concession Agreement. The respondent immediately rushed to  

the court by filing a petition under Section 9 of the Act seeking  

stay of the Cure Period Notice dated 19th October, 2013 as well  

as the notice expressing the intention to issue termination  

notice.  The High Court of Delhi passed an interim stay on 12th  

March, 2014 restraining the appellant from taking any  

coercive action.  The petition under Section 9 of the Act was  

finally disposed of on 22nd April, 2015 with a direction to the  

Arbitral Tribunal, which was already constituted in the  

meantime,   that the interim order dated 12th March, 2014

4

4    

would continue during the pendency of the arbitral  

proceedings with liberty to the parties to seek its modification  

or revocation before the Arbitral Tribunal.   

 3. The appellant accordingly moved an application dated 8th  

April, 2016 under Section 17 of the Act before the Arbitral  

Tribunal seeking permission to complete the balance works of  

the project as it was causing huge distress due to traffic  

congestion, unsafe highway, increase in expenditures, higher  

wear and tear of the vehicles and, in particular, national loss  

to the public at large. The respondent also filed an application  

under Section 17 of the Act on 17th May, 2016 seeking interim  

directions against the appellant to pay Rs.400 crores to the  

respondent at the risk and costs of the respondent for  

completing the balance works of the project.  The reliefs  

claimed in the application filed by the respondent read thus:  

 “a) Allow the present application and as an interim  

measure direct the Respondent to pay a sum of Rs.400  Crores to the Claimant at the risk and cost of the Claimant  so as to complete balance/remnant works of the project;  

 b) In the alternative and strictly without prejudice to  

the prayer (a), as an interim measure permit the  Respondent to invite tender/bid for executing the

5

5    

balance work under the Concession Agreement on  Engineering Procurement and Construction basis subject  

to Claimant being granted the right of First Refusal for  matching the lowest bid and in the event the Claimant  

matches the said lowest bid permit the Claimant to  complete the said balance/remnant works on the terms  and conditions of the tender/bid invited on Engineering  

Procurement and Construction basis except for the  provision, if any, for furnishing Bank Guarantees;    

c) In alternative and strictly without prejudice to the  prayer (a) & (b), direct the Respondent to act in terms of their  

letter dated 19.01.2016 and the Circular dated 09.06.2015  in the event prior to the award of contract of the balance  work on Engineering Procurement and Construction basis  

the Project Lenders of the Claimant agree to provide first  charge to the Respondent;  

 d) Pass such further order and other relief(s) as this  Hon‟ble Tribunal may be deem fit, just, necessary and  

appropriate in the facts and circumstances of the case.”    

(emphasis supplied)  

 

4. During the pendency of the aforementioned proceedings  

before the Arbitral Tribunal, a meeting was held on 19th April,  

2016 in the Chamber of Member (P) at NHAI – HQ to discuss  

and conclude the issues of Gwalior-Jhansi project pursuant to   

Ministers‟ meeting dated 15th March, 2016 in order to get the  

work restarted  without further delay. Another meeting was  

convened on 27th April, 2016 before the said Authority, as a  

result of which the hearing of the matter was deferred till 18th

6

6    

May, 2016.  On the adjourned date,  the advocate appearing  

for the appellant placed reliance on the minutes of the  

meetings held on 19th April, 2016 and 27th April, 2016.  The  

hearing of the applications was then deferred till 29th May,  

2016, as the respondent submitted a construction-linked  

financial plan for completing the balance work within a  

maximum period of 24 months from the date of receipt of  

advance payment from the appellant. The appellant filed its  

response on 28th May, 2016 to the proposal submitted by the  

respondent.  The appellant asserted that the financial plan  

submitted by the respondent was not in accord with the NHAI  

Circular dated 19th June, 2015.  In the meantime, on 25th  

May, 2016, the respondent filed its reply to the application  

filed by the appellant under Section 17 of the Act. The  

appellant had stated that it was agreeable to infuse funds for  

completion of the project as per the policy with condition of  

first charge of NHAI, considering the larger public interest.   

The respondent accepted the offer given by the appellant  

including the conditions specified by the appellant.             

7

7    

The conditions suggested by the appellant have been noted by  

the Arbitral Tribunal as under:   

 

“(i) As the Respondent is a public body, in the event of the  lowest bidder being denied the work, it will require to be  compensated. For this purpose Claimant/Concessionaire  

shall pay to the authority a sum of Rs.2% of the bid amount,  out of which 75% shall be paid to the lowest bidder. This is  

on the lines agreed by the parties and provided in the  Concession Agreement based on Model Concession  Agreement (MCA).  

 (ii) The Respondent shall not pay any „Mobilization  

Advance‟ without Bank Guarantee being furnished for the  equivalent amount. The advance shall be at the interest at  the rate of 2% more than the prevailing bank interest.  

 (iii) The work shall be completed by the Claimant in a  period of 24 months from the date of LOA for the  

Construction Contract.    

(iv) The terms and conditions of the Construction  Agreement shall be in addition to and not in substitution of  any terms and condition of the Concession Agreement. In the  

event of any disparity the terms of the Concession Contract  shall prevail.    

(v) The specifications and quality of construction shall not  be lower than stipulated in the Concession Agreement.  

 (vi) The Respondent shall be free to bring forward  consequential additional claims for the expenses incurred  

and damages suffered.”      

 

The respondent, through counsel, informed the Arbitral  

Tribunal that the respondent would accept the  

aforementioned conditions except condition No.(ii).   

8

8    

 5. The arguments were heard by the Arbitral Tribunal  

on 28th May, 2016. Before the application filed by the  

parties under Section 17 of the Act could proceed further,  

the appellant filed an application under Section 23 of the  

Act for amendment of its reply dated 25th May, 2016 so  

as to withdraw its acceptance of prayer (b) for  

modification of procedure order No.9 dated 28th May,  

2016, for the reasons mentioned therein. Finally, the  

Arbitral Tribunal disposed of the applications by a  

common order dated 23rd July, 2016. It accepted the  

relief claimed by the respondent in terms of prayer clause  

(b) of its application, reproduced in paragraph 3 above.   

 6. The Arbitral Tribunal rejected the plea of the  

appellant to withdraw from its earlier offer noted in the  

reply affidavit. The Arbitral Tribunal inter alia observed  

thus:  

“ . . . . .  

NHAI had taken a specific stand before us that it would not  agree to prayer (a) made by the Claimant. Tribunal therefore  granted time to NHAI to examine and come out with concrete  

proposals in respect of prayer (b) and on the unilateral  conditions suggested by NHAI itself, an order to that effect

9

9    

was passed by the Tribunal on May 18, 2016. Conditions  stipulated by NHAI, it is seen, are more stringent than what  

were suggested by CCEA in its meeting held on May 13,  2015, particularly in the CCEA decision made on October  

14, 2015, where in CCEA stated that after the constructions,  loans can be recovered bi-annually through execution of a  tripartite agreement between NHAI, lender and  

concessionaire. Policy endorsed by CCEA takes note of the  comfort level of not only that of NHAI, citizens and travellers,  but also of the concessionaire. We have to take it, that it was  

after taking into consideration all those aspects including  the policy decisions taken by CCEA and the Claimant‟s  

eligibility for one time fund infusion in terms of the Circular  dated June 9, 2015, the NHAI suggested various conditions  and all those conditions were accepted by the Claimant  

including the furnishing, of Bank Guarantee for the  mobilization advance to be made by NHAI. We are of the view  

that by furnishing the unconditional Bank Guarantee, the  interest of NHAI is also protected.   We find that NHAI has no case that the Claimant has been  

blacklisted or that it is incapable of completing the balance  work. In our view, it would not be in public interest if the  remaining work is allotted to a third party and in the facts  

and circumstances, one cannot rule out the possibility of  passing the same order, even if NHAI is allowed to withdraw  

the unilateral conditions suggested by it.   The Tribunal in its order dated May 25, 2016, also made it  clear that only if the Claimant would agree to all the  

conditions stipulated by NHAI, the Claimant would be  granted permission to complete the balance work. The  Claimant has now filed an affidavit before the Tribunal that  

all the conditions stipulated by NHAI are acceptable to it,  that being the factual position, we find no reason to  

entertain the application preferred by NHAI under Section 23  of the Act seeking amendment in its reply dated May 25,  2016, to the Claimant‟s Sec 17 application, so as to  

withdraw the conditions unilaterally suggested by it.   We are also of the view that the reasons stated for  

modification of Procedural Order No.9 dated May 28, 2016,  cannot be sustained in the facts and circumstances of the  case and we find it difficult to accept the contention that the  

specific conditions stipulated by NHAI to the alternative  prayer (b) made by the Claimant in Sec 17 Application have  been made without application of mind or that the so called  

„higher management‟ was unaware of the pendency of this  arbitration proceedings as well as the pendency of the Sec 17

10

10    

applications filed by the parties and the various meetings  held in respect of this matter at HQ of NHAI and the  

participation of Lead Bank, the Claimant and the officials of  NHAI and the meaning and content of the policy laid down  

by CCEA. Sec 17 Application preferred by NHAI would  therefore stand dismissed and prayer (b) made by the  Claimant in its Sec 17 Application stands allowed subject to  

the conditions stipulated by NHAI.  NHAI is directed to take up follow up action on the basis of  this order, within two weeks from today and submit a report  

to that effect within a month. Claimant is directed to  scrupulously follow the conditions imposed by NHAI for  

accepting prayer (b). Claimant is further directed to submit  quarterly reports before the Tribunal of the progress of the  balance work undertaken by it on the basis of the order of  

this Tribunal. The Claimant is directed to furnish Bank  Guarantee from a nationalised bank on the mobilization  

advance to be made by NHAI within the time stipulated. Both  sec 17 Applications and the Application made by NHAI under  Sec 23 of the Act are disposed of as above, reserving all the  

contentions raised by the parties in the main matter.     

This order as well as the observations and findings recorded  

will have no bearing on the ultimate disposal of the main  matter.”  

 

 

7. The appellant acquiesced to the aforementioned  interim  

order passed by the Arbitral Tribunal and allowed it to attain  

finality.  For, the subject project was on Build Operate and  

Transfer  (“BOT”) basis, any amount incurred by the Authority  

with regard to the project or in relation to the completion of  

the balance work was liable to be reimbursed by the  

Concessionaire (respondent).   

11

11    

8. The appellant accordingly issued a tender for the balance  

work vide Notice dated 28th November, 2016 which fact was  

brought to the notice of the Arbitral Tribunal during the  

hearing on 10th December, 2016. The tender notice was placed  

in the public domain, as is done in the case of other tender  

process. Some of the pertinent clauses of the tender  

documents may be appositely reproduced for considering the  

matter in issue before us. In the bidding document, Volume I,  

regarding Invitation for Bids (“IFB”), it was noted that sealed  

bids were invited (technical and financial) from eligible bidders  

for the construction and completion of the balance work  

detailed in the table given in the said document. Clause (1)  

postulated that eligibility of bidders would be assessed on post  

qualification basis, amongst others. The financial bid in the  

second part would be opened of only those bidders whose  

technical bids were responsive to eligibility and qualification  

requirements as per the Request for Proposal (“RFP”).  Further,  

clause (7) of the IFB reads thus:  

“7. The Bidders may take notice of the following:    

Notwithstanding anything to the contrary contained in this  RFP, as per the direction of Hon‟ble Arbitral Tribunal, if the

12

12    

BOT-Annuity concessionaire (M/s Gwalior Jhansi  Expressway Ltd.) of Four lane project (Gwalior-Jhansi  

section of NH-75, is also a responsive bidder, the  Concessionaire shall have the option of matching the  

lowest bid in terms of the selection criteria, subject to  payment of 2% (two per cent) of the bid amount to the  Authority and thereupon becomes the selected Bidder.  

……………...”    

           (emphasis supplied)      

In Section I of the bid document providing for procedure  

for tender document of the Instructions to Bidders, the  

eligibility of bidders has been specified in clause (3)  

thereof which reads thus:   

“3. Eligible Bidders  3.1 Eligibility of bidders is based on bidder meeting the  

pass/fail criteria regarding their general and particular  experience, financial position, personnel and equipment  capabilities and other relevant information as demonstrated  

by the applicant‟s responses on the forms attached.  3.2. This invitation for bids is open to bidders meeting the  

following requirements:-    

a) xxx xxx xxx   

b) xxx xxx xxx   c) xxx xxx xxx    d) xxx xxx xxx  

  “(e) Notwithstanding anything to the contrary contained in  

this REP, as per the direction of Hon‟ble Arbitral Tribunal, if  the BOT-Annuity concessionaire (M/s Gwalior Jhansi  Expressway Ltd.) of Four lane project (Gwalior-Jhansi  

section of NH-75, is also a responsive bidder, the  Concessionaire shall have the option of matching the  

lowest bid in terms of the selection criteria, subject to  payment of 2% (two per cent) of the bid amount to the  Authority and thereupon becomes the selected Bidder. Out  

of the amount so received by the Authority (ILLEGIBLE) 5%

13

13    

of the amount shall be paid by the Authority to the lowest  bidder. For the avoidance of doubt, it is clarified that no  

claim for compensation, damages, loss of profits etc. by the  lowest bidder for unbecoming selected bidder, shall be  

admissible from the Authority.   (f) Notwithstanding anything to the contrary contained in  

this RFP, for the purposes of eligibility and qualification of  

the BOT-Annuity concessionaire (M/s Gwalior Jhansi  Expressway Ltd.), if it has participated in the bidding  process, it shall be deemed to fulfill all the requirements  

of Clauses 3 to 6 of the RFP, being the existing  concessionaire of the Four lane project (Gwalior-Jhansi  

section of NH-75.”    

           (emphasis supplied)    

 Again in clause 26, it is stated thus:  

   

“26. Examination of Technical Bids and Determination of  Responsiveness of Technical Bids  

  x x x      x x x  x x x  x x x       

26.8 Notwithstanding anything to the contrary contained in  this RFP, as per the direction of Hon‟ble Arbitral Tribunal, if  

the BOT-Annuity concessionaire (M/s Gwalior Jhansi  Expressway Ltd.) of Four Lane project (Gwalior-Jhansi  section of NH-75, is also a responsive bidder, the  

Concessionaire shall have the option of matching the  lowest bid in terms of the selection criteria, subject to  

payment of 2% (two per cent) of the bid amount to the  Authority and thereupon becomes the selected bidder, Out of  the amount so received by the Authority, 75% of the amount  

shall be paid by the Authority to the lowest bidder. For the  avoidance of doubt, it is clarified that no claim for  compensation, damages, loss of profits etc. by the lowest  

bidder for unbecoming selected bidder, shall be admissible  from the Authority.  

 26.9 Notwithstanding anything to the contrary contained in  this RFP, for the purposes of eligibility and qualification of  

the BOT-Annuity concessionaire (M/s Gwalior Jhansi  Expressway Ltd.), if it has participated in the bidding

14

14    

process, it shall be deemed to fulfill all the requirements  of Clauses 3 to 6 of the RFP, being the existing  

concessionaire of the Four lane project (Gwalior -Jhansi  section of NH-75).  

 27. Opening of Financial Bids.    

xxx  xxx  xxx  xxx     27.5 Notwithstanding anything to the contrary contained in  

this RFP, as per the direction of Hon‟ble Arbitral Tribunal, if  the BOT-Annuity concessionaire (M/s Gwalior Jhansi  

Expressway Ltd.) of Four lane project (Gwalior-Jhansi  section of NH-75, is also a responsive bidder, the  Concessionaire shall have the option of matching the  

lowest bid in terms of the selection criteria, subject to  payment of 2% (two per cent) of the bid amount to the  

Authority and thereupon becomes the selected Bidder. Out  of the amount so received by the Authority, 75% of the  amount shall be paid by the Authority to the lowest bidder.  

For the avoidance of doubt, it is clarified that no claim for  compensation, damages, loss of profits etc. by the lowest  bidder for unbecoming selected bidder admissible from the  

Authority.    

27.6 Notwithstanding anything to the contrary contained in  this RFP, for the purposes of eligibility and qualification of  the BOT-Annuity concessionaire (M/s Gwalior Jhansi  

Expressway Ltd.), if it has participated in the bidding  process, it shall be deemed to fulfill all the requirements of  Clauses 3 to 6 of the RFP, being the existing concessionaire  

of the Four lane project (Gwalior-Jhansi section of NH-75).”      

          (emphasis supplied)    

 

In clause 30, it is observed thus:   

 “30. Examination of Financial Bids and Determination of  

Responsiveness of Financial Bids    

xxx  xxx  xxx   xxx  

15

15    

30.4  Notwithstanding anything to the contrary contained in  this RFP, as per the direction of Hon‟ble Arbitral Tribunal, if  

the BOT-Annuity concessionaire (M/s Gwalior Jhansi  Expressway Ltd.) of Four lane project (Gwalior Jhansi  

section of NH-75, is also a responsive bidder, the  Concessionaire shall have the option of matching the lowest  bid in terms of the selection criteria, subject to payment of  

2% (two per cent) of the bid amount to the Authority and  thereupon becomes the selected Bidder. Out of the amount  so received by the Authority, 75% of the amount shall be  

paid by the Authority to the lowest bidder. For the avoidance  of doubt, it is clarified that no claim for compensation,  

damages, loss of profits etc. by the lowest bidder for  unbecoming selected bidder, shall be admissible from the  Authority.   

 30.5 Notwithstanding anything to the contrary contained in  

this RFP, for the purposes of eligibility and qualification of  the BOT-Annuity concessionaire (M/s Gwalior Jhansi  Expressway Ltd.), if it has participated in the bidding  

process, it shall be deemed to fulfill all the requirements  of Clauses 3 to 6 of the RFP, being the existing  concessionaire of the Four lane project (Gwalior-Jhansi  

section of NH-75).”    

             (emphasis supplied)             

9. In consonance with the tender documents as uploaded  

on E-Tender Portal 2016, technical bids were opened on 5th  

January, 2017 and financial bids were opened on 29th March,  

2017. It is only thereafter on 25th April, 2017, the respondent  

moved an application before the Arbitral Tribunal under  

Section 17 of the Act, seeking,  inter alia,  permission of the  

Arbitral Tribunal to complete the balance work at its risk and

16

16    

cost.  In the said application, it was asserted that the  

respondent verily believed that it would get an opportunity to  

exercise the option of ROFR and match the lowest bid, in  

terms of the order dated 23rd July, 2016.  However, to its utter  

shock, surprise and dismay, it was reliably learnt on the  

previous day (to the filing of the application)  that the  

appellant was proceeding to conclude the tender process by  

issuing LOI/LOA in favour of the L-1 bid behind the back of  

the respondent and in a highly surreptitious and opaque  

manner.  On the basis of the said  assertions, the respondent  

in its application filed under Section 17 of the Act prayed thus:  

 “a) Allow the present application and direct the  

respondent to grant first right of refusal to the claimant for  matching the lowest bid, in terms of the order dated  23.07.2016 passed by this Hon‟ble Tribunal;  

b) Pending hearing and disposal of the present  Application, pass an ex-parte ad-interim Order, directing the  

Respondent to not issue LoI/LoA or award the works or take  any further steps, in any manner, directly or indirectly, in  favour of any party, pursuant to the Notice Inviting Tender  

published by the Respondent on 28.11.2016;  c) Confirm prayer (b) upon issuance of notice;  d) Pass such further order and other relief(s) as this  

Hon‟ble Tribunal may be deemed fit, just, necessary and  appropriate in the facts and circumstances of the case.”  

  

17

17    

10. This application was resisted by the appellant by filing a  

reply affidavit. The appellant asserted that the respondent  

chose to remain silent during the entire period and only at the  

belated stage when the tender process was nearing  

completion, it has chosen to file the application with the  

intention of stalling the entire process. This approach cannot  

be countenanced. The appellant also asserted that it was  

unfathomable that the respondent would get the right to  

match the lowest bid without participating in the bidding   

process. Further, an application such as this would delay the  

progress of the main arbitration proceedings which was  

required to be completed within one year.  It was thus asserted  

by the appellant that the ROFR could be invoked by the  

respondent only if it had participated in the bidding process.   

The appellant adverted to the terms and conditions of the  

tender documents which unambiguously mandated the  

respondent to participate in the tender process, coupled with  

the fact that there was no express direction given by the  

Arbitral Tribunal so as to give any right or cause of action to  

the respondent to contend to the contrary. The appellant

18

18    

beseeched the Arbitral Tribunal to allow it to take the tender  

process to its logical end.   

 11. Admittedly, no rejoinder was filed by the respondent to  

the specific plea taken by the appellant in the reply affidavit  

that despite having knowledge of the condition in the tender  

documents requiring the respondent to participate in the  

tender process, it failed to do so for reasons best known to the  

respondent.   

 12. The Arbitral Tribunal vide order dated 24th May, 2017  

allowed the application preferred by the respondent by inter  

alia observing as follows:  

 

“The Tribunal while examining both the 17 Applications  

preferred by the parties specifically noticed that the  Claimant had completed more than 65% of the work though,  

NHAI took the stand that the physical progress was only  62.13%. Claimant took the stand that it had completed more  than 73% work. Considering the fact that so much of money  

and labour had been invested by the Claimant, and at the  same time safeguarding the interest of NHAI, the Tribunal  passed the order dated 23.7.2016 directing the Respondent  

to grant the Claimant the right of first refusal for matching  the lowest bid. The Tribunal also felt that involvement of  

third parties would also create more problems. The Tribunal,  therefore, ordered in the event Claimant matches the lowest  bid, Claimant be permitted to complete the balance work  

that too by periodically submitting reports before the  Tribunal so that the Tribunal can examine whether the

19

19    

Claimant is successfully completing the balance work to the  satisfaction of NHAI. In our view, the stand taken by the  

Respondent that the first right of refusal can be granted to  the Claimant only if it had participated in the bidding  

process cannot be sustained. Accordingly, reliefs sought for  by the Claimant in the Application dated 25.4.2017 are  granted”.  

 

 

13. Against this decision, the appellant filed an appeal under  

Section 37(2)(b) of the Act before the High Court of Delhi at  

New Delhi. The same was dismissed on 21st August, 2017. The  

High Court upheld the view taken by the Arbitral Tribunal by  

inter alia observing thus:  

“12. It is quite clear from a perusal of the earlier order  dated 23.07.2016 that the respondent was granted right of  first refusal by matching the lowest bid, and if it matched the  

bid the respondent was to be permitted to complete the  balance work as stated. There was no directions that the  

respondent was obliged to participate in the bid. They had  been given the right to match the lowest bidder, subject to  terms and conditions and in that eventuality of their  

matching the lowest bid, they were to be given the right to  carry out the balance work. The insistence of the appellant  that the respondent ought to have participated in the bid  

floated pursuant to the order of the learned Arbitral Tribunal  dated 23.07.2017 is misplaced.   

 13. Learned counsel for the appellant was, several times  asked as to what prejudice is caused by the respondent by  

not participating in the bid. The only reply made by the  learned counsel for the appellant was that in the absence of  

participation in the bid by the respondent, the appellant is  unable to ascertain whether the respondent was eligible to  be a bidder or not. In my opinion in the light of the orders of  

the Learned Arbitral Tribunal dated 23.07.2016 the

20

20    

appellant was not to participate in the bid. The apprehension  of the appellant are entirely misplaced.  

 14. No prejudice is caused to the appellant. It is manifest  

that other than insistence on compliance by the respondent  of a procedural requirement, there is no prejudice caused to  the appellant by non participation of the respondent in the  

bidding process. Further the impugned directions are passed  in accordance with the earlier orders of the Learned Arbitral  Tribunal dated 23.07.2016 which has not been challenged  

and attained finality. There is no merit in the present appeal  and the same is dismissed.”  

   14. The appellant has assailed  the decision of the Arbitral  

Tribunal dated 24th May, 2017 and of the High Court dated  

21st August, 2017 on the argument that the respondent  

cannot be permitted to exercise ROFR sans participating in  

the bidding process and in the teeth of the terms and  

conditions of the tender documents. According to the  

appellant, the Court cannot interfere with the tender process  

and in particular with the modalities adopted for re-tendering  

of the balance work of the project.  The process of evaluation  

of tender and awarding the contract are essentially commercial  

functions for which reason the Courts should refrain from  

exercising  judicial review, especially when the decision taken  

by the statutory authority is bona fide and taken in public  

interest. Further, the order of the Arbitral Tribunal dated 23rd

21

21    

July, 2016 in no way, much less expressly, exempts the  

respondent from participating in the bidding  process nor has  

any stipulation been placed on the appellant to refrain from  

incorporating a condition requiring the respondent to  

participate in the tender process along with others. In that  

case, all concerned including the respondent, were bound by  

the terms and conditions specified in the tender documents.  

The fact that the respondent was deemed to possess technical  

qualifications would not and does not do away with the  

essentiality of participating in the subject bidding process, the  

purpose whereof is to ensure a fair competition amongst the  

participants and, more particularly, to get a fair offer and the  

best value for money in a scientific and transparent manner,  

encouraging competition between the participants and also to  

give them equal opportunity. It is contended that the order of  

the Arbitral Tribunal, be it dated 23rd July, 2016 or dated 24th  

May, 2017, is in excess of jurisdiction as it transcends beyond  

the purport of  Section 17 of the Act.  For, it was not open to  

the Arbitral Tribunal to pass an interim order concerning a  

separate contract albeit facilitating completion of the

22

22    

unfinished and incomplete works of the project. It is  

contended that it is well settled position that the prerogative to  

formulate the terms and conditions of the tender document is  

that of the employer and the Court cannot sit in appeal over  

such conditions. Nor can the same be re-written or modified  

much less when it has not been challenged by the respondent.  

It is contended that the fact that the respondent qualified the  

technical bids in 2006, will not by itself qualify it for re-

tendering bid  process in 2016. Having failed to participate in  

the bid process in 2016, it was not possible to examine the  

eligibility and qualification of the respondent in the context of  

tender documents of 2016. Further, a person or entity who  

stands out of the tender process or fails to comply with the  

terms and conditions of the tender documents cannot acquire  

any right or interest much less actionable claim in respect of  

such tender process. According to the appellant, the  

respondent must take the consequences of non-participation  

in the subject tender process and cannot be allowed to  

interdict the same in absence of an express exemption granted  

by the competent forum/Authority to the respondent not to

23

23    

participate in the tender process and yet exercise ROFR. To  

buttress the aforesaid submission, reliance has been placed  

on the decision of the Delhi High Court in VHCPL-ADCC  

Pingalai Infrastructure Pvt. Ltd. & Anr. Vs. Union of India  

& Ors.1 and on the decision of the Appellate Tribunal for  

Electricity in M/s. Raj West Power Limited & Anr. Vs.  

Rajasthan Electricity Regulatory Commission & Ors.2     

  15. The respondent on the other hand, would contend that  

no interference in this appeal is  warranted in view of the  

concurrent view taken by the Arbitral Tribunal as well as the  

High Court that it was not necessary for the respondent to  

participate in the tender process to exercise ROFR. For, the  

order dated 23rd July, 2016 does not prescribe such a pre-

condition nor does it prohibit the respondent from exercising  

the ROFR without participation in the bidding process.  It is  

contended that the order dated 23rd July, 2016 is based on  

consent of the parties and has never been challenged by the  

appellant and as such, the appellant was obliged to comply  

                                                           1    2010 SCC Online Del 2687  

2    2013 SCC Online APTEL 46

24

24    

with the same in its letter and spirit. According to the  

respondent, having completed 78% work of the Project (which  

according to the appellant, is only around 62%) and having  

invested Rs.715 crores on the Project, by no stretch of  

imagination can the respondent be termed as a non-serious  

contender. According to the respondent, the appellant cannot  

be heard to challenge the order dated 23rd July, 2016, which  

confers ROFR, as it was based on consent of the parties and  

also attained finality. Further, the purpose of participating in  

the bidding process was only to ascertain as to whether the  

offer given by the bidder was a responsive offer. The  

respondent having already completed substantial work of the  

Project, by no stretch of imagination, can be said to be  

incapable of completing the balance work. This aspect had  

commended to the Arbitral Tribunal, as can be discerned from  

the order dated 23rd July, 2016. The Arbitral Tribunal in that  

order also unambiguously recorded that it was not the case of  

the appellant herein that the respondent had been black listed  

or was incapable of completing the balance work. Not only  

that, the Arbitral Tribunal went on to observe that it would not

25

25    

be in the public interest to allow a  third party to take over the  

balance work of the project. On that basis, direction was given  

to the appellant to allow the respondent to exercise ROFR,  

subject to certain conditions.  The order passed by the Arbitral  

Tribunal, in essence, was on the basis of consent of the  

respondent with unilateral conditions imposed by the  

appellant, which the appellant should not be allowed to resile.  

According to the respondent, it was impermissible for the  

appellant to incorporate conditions such as clauses 3, 26, 27  

and 30 in the tender documents, as the same are in the teeth  

of order dated 23rd July, 2016 passed by the Arbitral Tribunal  

and, more so, without seeking liberty from the Arbitral  

Tribunal in that behalf. It is contended that the purpose of the  

tender process is only to evoke responsive offers. There would  

be no logic or rationale for participation of the respondent in  

the backdrop of clause 3.2(f) which is a deeming provision  

virtually declaring the respondent as eligible and qualified for  

the work. The capability of the respondent to complete the  

balance work was never in doubt as has been recorded by the  

Arbitral Tribunal.  In any case, in the absence of liberty given

26

26    

by the Arbitral Tribunal, it was not open to the appellant to  

incorporate such a pre-condition in the tender document. It is  

contended that such pre-condition would require the  

respondent to furnish bid security amount in which case it  

would be a fait accompli situation for the respondent if it were  

to refuse or fail to match the lowest bid. For, it would result in  

forfeiture of its bid security and also entail in black listing. The  

order dated 23rd July, 2016, is one of ROFR and not for right  

to participate in the bidding process as such. Further, the  

submission of financial bid by the respondent was not to find  

out whether it is L-1. In that, all the bidders participating in  

the subject tender process pursuant to tender notice, were  

made fully aware in the bid document itself that the  

respondent had ROFR and L-1 would be compensated by the  

respondent as provided in the order dated 23rd July, 2016.   

Therefore, the respondent was not expected to bid with itself  

by submitting a financial bid and then matching the same.   

The respondent would contend that the appellant has wrongly  

asserted that the respondent was aware of the conditions  

prescribed in the tender documents and yet did not choose to

27

27    

participate in the bidding process. For, the bid documents  

were neither furnished to the respondent nor  placed on record  

before the Arbitral Tribunal. Thus, the conditions on which  

reliance has now been placed by the appellant were never  

pointed out to the respondent or to the Arbitral Tribunal at  

any point of time.  In any case, the appellant had completely  

failed to show as to what prejudice would be caused by  

allowing the respondent to exercise ROFR without  

participating in the tender process. The learned Single Judge  

of the High Court repeatedly made queries in that behalf  

which was not explained by the appellant, as is noted in the  

impugned judgment. Resultantly, the High Court rejected the  

plea of the appellant and held that it was not necessary for the  

respondent to participate in the bidding process in terms of  

order dated 23rd July, 2016, to exercise ROFR. The respondent  

has distinguished the two decisions relied upon by the  

appellant and would contend that the same do not lay down  

any legal principle that participation in the bidding process is  

a condition precedent for exercise of ROFR.  It is contended, in  

the present case, the ROFR, without condition of participation

28

28    

in the bid, was granted by the Arbitral Tribunal on the basis of  

consent of the parties. It is contended that in view of the  

concurrent view taken by the Arbitral Tribunal as also the  

High Court, this Court should be slow in entertaining this  

appeal.  

 16. We have heard Mr. K.K. Venugopal, learned Attorney  

General for India and Mr. Mukul Rohatgi, learned senior  

counsel appearing for the respondent.   

 

17. The issue involved in the present appeal ostensibly  

concerns the justness of the order passed by the Arbitral  

Tribunal and affirmed by the High Court on an application  

moved by the respondent (claimant) under Section 17 of the  

Act in the pending arbitral proceedings. However, in essence,  

the subject matter of the application under consideration  

relates to the rights and liabilities of the parties in respect of a  

tender process for awarding of a contract in relation to the  

unfinished and balance work of the Highway Project.   

29

29    

18. While considering the relief claimed by the respondent  

(claimant), the same should have been tested on the  

touchstone of the principle governing the tender process,  

especially when the validity of the tender document has not  

been put in issue or challenged before any competent forum.  

Going by the terms and conditions in the tender documents,  

as already alluded to in paragraph 8 above, there is no tittle of  

doubt that the right of the claimant (respondent) to match the  

bid of L-1 or to exercise ROFR would come into play only if the  

respondent was to participate in the tender process pursuant  

to the notice inviting tenders from the interested parties. The  

objective of tender process is not only to adhere to a  

transparent mechanism but to encourage competition and give  

equal opportunity to all tenderers with the end result of  

getting a fair offer or value for money. The plain wording of the  

eligibility clause in the tender documents and the incidental  

stipulations  make it explicit that the respondent was required  

to participate in the tender process by submitting its sealed  

bid (technical and financial).  The fact that a deeming clause  

has been provided in the tender document that if the

30

30    

respondent was to participate in the bidding process, it shall  

be deemed to fulfill all the requirements of the tender clauses  

3 to 6 of the RFP, being the existing concessionaire of the  

Project, does not exempt the respondent from participating in  

the tender process; rather the tenor of the terms of the  

documents made it obligatory for the respondent to participate  

in the tender process to be considered as a responsive bidder,  

along with others. Having failed to participate in the tender  

process and, more so, despite the express terms in the tender  

documents, validity whereof has not been challenged, the  

respondent cannot be heard to contend that it had acquired  

any right whatsoever. Only the entities who participate in the  

tender process pursuant to a tender notice can be allowed to  

make grievances about the non-fulfillment or breach of any of  

the terms and conditions of the concerned tender documents.  

The respondent who chose to stay away from the tender  

process, cannot be heard to whittle down, in any manner, the  

rights of the eligible bidders who had participated in the  

tender process on the basis of the written and express terms  

and conditions.  At the culmination of the tender process,  if

31

31    

the respondent had not participated, in law, the offer  

submitted by the eligible bidders is required to be considered  

on the basis of the stated terms and conditions. Thus, if the  

claim of the respondent was to be strictly adjudged on the  

basis of the terms and conditions specified in the subject  

tender document, the respondent has no case whatsoever.   

 19. The gravamen of the plea taken by the respondent is on  

the assumption that the interim order passed by the Arbitral  

Tribunal  on 23rd July, 2016 bestows unconditional right on  

the respondent to exercise ROFR, in the event tender process  

in respect of the balance work is resorted to. For that, we may  

straightway advert to the order dated 23rd July, 2016. That is  

an order granting prayer clause (b) in the application preferred  

by the respondent under Section 17 of the Act.  The same has  

been reproduced in paragraph 3 above. Notably, there is  

nothing in the entire application (filed by the respondent  

under Section 17 of the Act) to even remotely suggest that the  

respondent had prayed in clause (b) that it be exempted from  

participating in the proposed tender process as such, and

32

32    

could yet exercise ROFR before the letter of intent was to be  

issued to the lowest bidder.  The exemption in this regard  

cannot be inferred. It has to be an express exemption sought  

and so granted and disclosed in the tender documents. The  

respondent may be right in contending that the interim order  

passed by the Arbitral Tribunal dated 23rd July, 2016 neither  

prescribes that the respondent must participate in the bidding  

process as a condition precedent for exercise of ROFR nor does  

it prohibit the respondent from exercising  ROFR without  

participation in the bidding process. The order is, indeed,  

silent in that behalf. But, that will be of no avail to the  

respondent. For, such  exemption ought to have been prayed  

and expressly granted by the Court. In absence of such  

express exemption, the respondent was obliged to comply with  

the terms and conditions of the tender documents publicly  

notified by the appellant as per its understanding of the order  

of the High Court. Having failed to participate in the bidding  

process in consonance with such notified terms and  

conditions, the respondent lost the opportunity granted under  

the order dated 23rd July, 2016 to match the lowest bid or to

33

33    

exercise ROFR.  Any other view would fall foul of the  

fundamental policy of the Indian law and cannot be  

countenanced.   

 20. It is not the case of the respondent that an express  

exemption has been granted to the respondent, from  

participating in the bidding process.  In the matter of tender  

process, there can be no tacit or implied exemption from  

participating.  In the first place, whether such direction can be  

issued by the Arbitral Tribunal under Section 17 of the Act  

itself is debatable. However, since the order dated 23rd July,  

2016 has remained unchallenged, we do not wish to dilate on  

that aspect. Indeed, the appellant accepted the order with a  

sanguine hope that a proper tender process can be resorted to,  

wherein the respondent would also participate, for awarding  

the contract of unfinished and balance works of the subject  

Project.  For effectuating that order, tender documents were  

issued by the appellant on 28th November, 2016 which, as  

aforesaid, explicitly stipulated that the respondent was  

expected to submit its bid within the specified time.

34

34    

Admittedly, the fact that tender notice was issued, came to be  

disclosed before the Arbitral Tribunal on 10th December, 2016.   

Surprisingly, the respondent neither took any clue nor  

bothered to follow up the tender documents which were placed  

in public domain (as is done in respect of any other tender  

process). Further, the respondent waited till the opening of  

technical bids on 5th January, 2017 and financial bids on 29th  

March, 2017 and rushed to the Arbitral Tribunal by way of an  

application under Section 17 of the Act, only on 25th April,  

2017 stating that on the previous day, it had come to its   

notice that the appellant was likely to issue letter of intent to  

the lowest bidder, without giving opportunity to the  

respondent to match the lowest bid or exercise ROFR.  To  

oppose the said application, the appellant in the reply affidavit  

had asserted that the respondent was fully aware about the  

terms and conditions of the tender documents and yet  chose  

not to participate in the bidding process.  The respondent did  

not think it necessary to counter the said assertion by filing  

any rejoinder thereto. Notwithstanding that, the Arbitral  

Tribunal was impressed by the plea taken by the respondent

35

35    

and allowed the application of the respondent vide order dated  

24th May, 2017. The relevant extract of the said order has been  

reproduced in paragraph 12 above.  The Arbitral Tribunal was  

more impressed by the fact that the respondent had completed  

substantial works of the Project and it would be just and  

proper to allow the respondent to complete the balance work.  

The Arbitral Tribunal made no effort to ascertain as to whether  

the order dated 23rd July, 2016 was a blanket and  

unconditional order entitling the respondent to straightaway  

exercise ROFR without participating in the bidding process.   

The Arbitral Tribunal merely adverted to the objection of the  

appellant and rejected the same on the finding that  

involvement of a third party in the Project would create serious  

problems. It took the view that giving option to the respondent  

to match the lowest bid and to complete the balance work,  

with a condition to periodically submit the progress report to  

the Arbitral Tribunal for monitoring whether the balance work  

was successfully completed to the satisfaction of the NHAI,  

would be a proper and equitable arrangement. This approach

36

36    

is  not  in conformity with the fundamental policy of Indian  

law.   

 21. The approach of the High Court in the appeal preferred  

by the appellant was no different. The relevant extract of the  

High Court decision has been reproduced in paragraph 13  

above. The High Court did not find any error, much less  

manifest error, in the view taken by the Arbitral Tribunal.   

Further, it can be gleaned from the observations of the High  

Court in the impugned judgment that the High Court was  

more eager to know as to what prejudice would be caused to  

the appellant if the respondent had not participated in the  

bidding process. This query of the High Court is begging the  

question. For, that cannot be the primary basis to answer the  

relief claimed by the respondent in the application under  

Section 17 of the Act. An entity who stays away from the  

bidding process and fails to comply with the express terms  

and conditions of the tender documents cannot claim any  

right to match the lowest bid or exercise ROFR.  Only a  

responsive bidder could do so. The High Court has overlooked

37

37    

the fact that the appellant is a body corporate under the 1988  

Act. It has to act in a just and fair manner in the matter of  

allocation of contract albeit the balance and unfinished work  

of the Project. No express exemption has been granted to the  

respondent vide order of the Arbitral Tribunal dated 23rd July,  

2016 – to exercise ROFR or match the lowest bid without  

participating in the bidding process. The respondent had the  

option to participate in the bidding process which was not  

availed of for reasons best known to the respondent. The High  

Court also overlooked the fact that the tender process was not  

an empty formality and with the initiation of the same, third  

parties, who participated in the bidding process, were likely to  

be prejudiced by allowing the respondent to match the lowest  

bid or exercise ROFR, without participating in the bidding  

process despite the express stipulation in that behalf in the  

tender documents. Suffice it to observe that the High Court  

committed the same error as committed by the Arbitral  

Tribunal in not examining the core issues for grant or         

non-grant of the relief to the respondent, in conformity with  

the fundamental policy of Indian law.  

38

38    

 22. The argument of the respondent that the order dated 23rd  

July, 2016 passed by the Arbitral Tribunal was based on  

consent of the parties and was never challenged by the  

appellant, does not take the matter any further. The  

respondent on the one hand, contends that the said order was  

based on consent of the parties and also in the same breath  

contends that the respondent consented to the unilateral  

conditions stipulated by the appellant, which the appellant  

should not be allowed to resile as prayed by it. Be that as it  

may, on a fair reading of the order dated 23rd July, 2016, it is  

noticed that the same is the outcome of a contest and not  

founded on any concession. In any case, the order makes no  

express mention about granting of exemption to the  

respondent from participating in the proposed bidding  

process. The fact that the respondent has already invested a  

substantial amount in the subject Project and has also  

completed substantial work can be no basis to overlook the  

fundamental policy of Indian law regarding the subject of  

tender process and the rights and obligations of the parties

39

39    

involved. We are also not impressed by the argument of the   

respondent that the respondent was not expected to refuse to  

match its own bid or that if it had participated in the bidding  

process and exercised ROFR, then it would have resulted in  

consequence of black listing and forfeiture of bid security  

amount. The fact that the respondent would exercise ROFR  

would mean that the bid given by the respondent was not L-1.   

If it was not L-1, exercising ROFR would obviously neither  

entail in forfeiture of the bid security nor would visit the  

consequence of black listing.  This plea is obviously an  

argument of desperation and belated one to justify the failure  

to participate in the bidding process.   

 23. The appellant invited our attention to the dictum in  

VHCPL-ADCC Pingalai Infrastructure Pvt. Ltd., (supra). In  

that case, the Court considered the question whether the  

petitioner had preferential right to match the lowest bid  

without pre-qualifying  or participating  in the bidding process.  

In that case, Article 14.1(c) of the concession agreement  

stipulated that the respondent No.1 could invite proposals

40

40    

from eligible persons for capacity augmentation of the project  

which required the petitioner to give an option to submit its  

proposal. The Court after noticing the precedents on the  

relevant aspects, went on to observe that if the concessionaire  

chose not to submit its proposal, it did not have the right to  

match the preferred offer as would be the case of the  

respondent herein, in view of the express stipulation in the  

tender documents requiring the respondent to participate in  

the bidding process. The appellant has also placed reliance on  

the decision in M/s. Raj West Power Limited, (supra).  We  

agree with the respondent that this decision does not lay down  

any principle which may have any bearing on the case in  

hand.  

 24.  In view of the above, we have no hesitation in concluding  

that the decision of the Arbitral Tribunal  as confirmed by the  

High Court, falls foul of the fundamental policy of  Indian law  

and cannot be countenanced.    

 

25. Accordingly, the order passed by the Arbitral Tribunal  

dated 24th May, 2017 as also the order dated 21st August,

41

41    

2017 passed by the learned Single Judge of the High Court,  

deserve to be quashed and set aside and resultantly, the  

application preferred by the respondent under Section 17 of  

the Act dated 24th April, 2017 ought to be dismissed.  We  

order accordingly.    

 

26. The appeal is allowed in the above terms with  no order  

as to costs.         

  

.………………………….CJI.        (Dipak Misra)   

  

 

…………………………..….J.                (A.M. Khanwilkar)  

 

 

…………………………..….J.               (Dr. D.Y. Chandrachud)  

New Delhi;  

July 13, 2018.