MUNICIPAL CORP.OF GREATER BOMBAY Vs YESHWANT JAGANNATH VAITY .
Bench: V.S. SIRPURKAR,T.S. THAKUR, , ,
Case number: C.A. No.-002575-002575 / 2011
Diary number: 33058 / 2009
Advocates: SUCHITRA ATUL CHITALE Vs
DUA ASSOCIATES
“REPORTABLE”
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2575 OF 2011 [ARISING OUT OF SLP (C) NO. 31645 OF 2009]
The Municipal Corporation of Greater Bombay & Anr. …. Appellants
Versus
Yeshwant Jagannath Vaity & Ors. …. Respondents
J U D G M E N T
V.S. SIRPURKAR, J.
1. Leave granted.
2. Whether the High Court was right in directing the
appellant The Municipal Corporation of Greater Bombay
(hereinafter called “the MCGB” for short) to grant additional
transfer development rights (hereinafter called “TDR” for
short) and to issue further development rights certificate
(hereinafter called “DRC” for short) equivalent to 2646.14 sq.
metres (85 % of the area of a courtyard) developed by the
respondents in favour of the appellants is a question that
fall for consideration in this appeal.
3. By the impugned judgment, the Bombay High Court under
Clause 6 of Appendix VII to the Development Control Regulation
for Greater Bombay, 1991 (hereinafter called “the Regulations”
for short) has issued such a direction in a writ petition
filed by the respondents herein.
Factual panorama
4. The respondents herein owned 10,000 sq. yards of land
in Mulund village. A development plan was sanctioned for
Greater Bombay in the year 1957. Mulund comes within the area
of Greater Bombay. The said land was shown as reserved for
public purpose of construction of a godown. Ordinarily, such
land is acquired under the provisions of Land Acquisition Act,
1894. However, the respondents and the four other co-owners
entered into a private agreement to hand over possession of
10,000 sq. yards to the MCGB for the temporary use as a truck
terminal. The land was also to be used as a town duty office.
The possession was handed over on 18.9.1961. An agreement was
entered into between the respondents and the other co-owners
with the MCGB wherein it was agreed that the respondents and
the other co-owners would receive compensation of Rs.90,000/-.
The land, though, was given in possession much earlier and
there was an agreement dated 16.12.1967, it was not put to any
use much less for the public purpose for which it was intended
to be acquired. The land was not put to any other use also
right till November, 1998. Hence, the respondents filed a
writ petition No.3437 of 1988 inter alia praying therein for a
declaration that the land was not liable to be acquired. The
writ petitioners demanded back the possession of 10,000 sq.
yards. There was a compromise effected in this writ petition
by order dated 10.3.1992 between the parties. Under the same,
the MCGB agreed to acquire and retain the area of 3500 sq.
metres for the purpose of establishing and constructing an
export octroi office. The consent terms provided that
appellant Nos.1 and 2, namely, MCGB and its Chief Engineer
would hand over the remaining area to the respondents herein
and the respondents herein would refund the amount of
Rs.90,000/- with interest therein @ 10 % per annum from the
date of payment till the date of re-payment to the MCGB. It
was further provided in the consent terms that the respondents
herein would be entitled to TDR to the extent provided in the
Regulations in respect of 3500 sq. metres in lieu of the
payment of Rs.90,000/- with interest. It was further provided
in the consent terms that the MCGB would grant TDR in lieu of
the said land measuring 3500 sq. metres subject to the
compliance of various requirements by the petitioners as
required under Regulation 34, Appendix VII of the Regulations.
It was specifically provided by Clause 9 of the consent terms
that if the petitioners constructed and developed export
office for the MCGB on the aforementioned area of 3500 sq.
metres and handed over the premises to the MCGB free of cost,
the respondents would be entitled to the benefit of additional
transferable development rights as per Regulation 6 of
Appendix VII. The precise wordings of Clause 9 to the consent
terms are as under:
“9. The petitioners shall be entitled to the benefit of Additional Transferable Development Rights (hereinafter referred to as ‘ATDR’), if the petitioners are asked by the respondent No.1 to construct and develop the Export Office for the Corporation on the land so surrendered at their own costs and as per the plans and designs and specifications of the respondent No.1 and hand over the premises so constructed to the respondent No1 free of costs as per the sub-regulation 6 of Appendix VII of the Development Control Rules for Greater Bombay, 1991.”
5. A letter was addressed by the Constituted Attorney of
the respondents dated 18.4.1992 calling for a joint survey and
demarcation and the engineer of the MCGB was requested to
inform the details and specifications of the work which the
present respondents would have to carry on to claim the TDR as
per paragraph 4 of the consent terms and the additional TDR as
per paragraph 9 of the consent order quoted above. The
respondents were informed on 25.4.1992 that they would have to
carry out the work of leveling the plots, construction of
compound wall on three sides with gates, development of yard
with asphalting and the construction of an export office
building as per the specifications submitted by the Deputy
C.E.(P & D)/ Municipal Architect by his communication dated
20.9.1991. The Constituted Attorney was directed to approach
the concerned authority.
On 25.5.1992, the Architect of the respondents made an
application to the MCGB for grant of TDR in respect of 3500
sq. metres of area already surrendered by the respondents to
appellant No.1. The petitioners also paid the sum of Rs.3
lakh 15 thousand (principal amount of Rs.90,000/- and the
interest @ 10 % per annum) from the date of payment till the
date of re-payment as agreed to in the consent terms.
On 22.01.1993, the respondents addressed a letter to the
Assessor and Collector asking for further details relating to
the work to be carried out on the said 3500 sq. metres of
land. On 5.3.1993 the Assessor and Collector of the appellant
No. 1 herein addressed a letter to the respondents herein
enclosing a sketch plan of for the proposed export office
together with development of yard. It was informed in the
said letter that as per the directions of the Municipal
Commissioner, additional TDR in lieu of the development of
export yard and construction of office would be granted to the
respondents. The respondents were also requested to expedite
the work of construction of export office.
On 7.6.1993, a letter was addressed by Municipal
Architect to the respondents herein enclosing specifications
for asphalting. It was mentioned that this work to be carried
out under the supervision of Municipal engineer.
By a further letter dated 23.6.1993, the Chief
Engineer informed the petitioners that the development right
certificate would be issued after compliance with certain
additional requirements contained in the said letter. On
13.9.1993, the respondents herein wrote a letter to the
Assistant Engineer informing about the various compliances and
requesting for issue of development right certificate in
respect of 3500 sq. metres.
On 9.2.1994, it was informed by a letter that the
respondents’ right to grant development certificate would be
considered after they commence the work of construction of the
export office. Further on 22.2.1995, the Chief Engineer
addressed a consent letter to the respondents certifying his
no objection for constructing the export office building
subject to the terms and conditions mentioned in the said
letter. Condition Nos. 1 and 4 in the said letter are
relevant for the issued involved. They are as under:-
“1. That you will construct the Export Office building as per the plans & specifications of the Municipal Corporation enclosed herewith and the Municipal Corporation will grant the Transferable Development Rights equivalent to the builtup area of the Export Office.
4. That you will concrete/ asphalt the portion of the Export Office Yard around the Export Office building as per the specifications of MCGB and as given by the Chief Engineer (Roads & SWD) of the MCGB. The work will be carried out under the Municipal supervision and certified by the Competent Authority. The Municipal Corporation will grant the benefit of Transferable Development Right in respect of the concrete/asphalted surface area around the Export Office building as and when the quantum of such TDR is decided by the Municipal Commissioner.”
(emphasis supplied)
6. The petitioners constructed the export office and also
developed the surrounding area. The possession of the export
office and the courtyard was handed over to the the MCGB for which
a possession receipt was also issued. Possession receipt
mentioned the details of the constructed amenity as under:-
“CTS No.137A Export Office Gr.FI.293.13 sq. Electric of village & chowky for m. 1st FI.170.15 fittings Mulund (East) octroi Deptt. sq.m. Exit. Fixtures as office 27.88 sq. advised by E.E.(Mech) & Water cooler- Total 491.16.sq.m.
CTS No.137A Court yard of Area as shown by Electric of village Export office A B C D E F G H poles and Mulund (East) office I JK on the plan carriage duly certified by entrance to Roads Deptt. under plot & front No.DYCHE/1486/compound/ Rds.dt.23.2.96 wall.”
7. An application was made by the respondents’ Architect for
DRC. On 19.1.1999, DRC for TDR in respect of export office being
491.16 sq. metres equivalent of the 100 per cent of the built up
area of the export office was granted. However, insofar as the
additional transferable rights in lieu of the development of the
export courtyard surrounding the export office was concerned, the
same was restricted to 466.96 sq. metres being 15 per cent of the
built up area of the courtyard. This was the first flash point.
On 7.3.2000, the petitioners by their letter claimed that they
were entitled to the additional transferable rights to the extent
of 3113 sq. metres as against the development of the courtyard of
export office on which they had done the asphalting work. On
27.6.2000, the Chief Engineer refused to grant further additional
TDR contending therein that the TDR issued was in accordance with
the BMC policy. Once again, a demand was made by communication
dated 6.7.2000 for the balance area and also requested the MCGB
for the particulars of the alleged policy. It was informed herein
that there was a circular dated 9.12.1996 which formulated the
policy. The respondents were invited for discussion. A contempt
application was also filed by the respondents being Contempt
Petition No.116 of 2000, contending therein that the consent order
dated 10.3.1992 was violated. The said contempt petition was
dismissed holding that there was no willful disobedience. On
23.12.2003, the respondents again addressed a letter to the MCGB
calling them upon to grant further DRC for the remaining 85 per
cent of the area of the courtyard and since the demand was not
met, the writ petition came to be filed.
8. The writ petitioners-respondents mainly relied on the
consent terms dated 10.3.1992 and, more particularly, on Clause 9
and contended that they were entitled to the benefit of additional
TDRs as they had developed not only the export office of the MCGB
but also done the asphalting work of the surrounding area, more
particularly, in accordance with the Regulations. Appendix VII,
Sub-Clause 6 of Regulation 34 of the Regulations were also
reiterated in the letter issued by the Chief Engineer dated
22.12.1992. Further condition No. 4 provided that the MCGB will
grant benefit of transferable development rights in respect of the
agreed asphalted surface area, the export office building as and
when the quantum of such TDR is decided by the Municipal
Commissioner was also relied upon. They pointed out that the
Municipal Commissioner could not have relied on a subsequent
circular dated 9.12.1996 and had to go strictly by the language of
Clause 6 of Appendix VII of Regulation 34 of the Regulations under
which they were entitled for an area equivalent 100 per cent of
the area of the courtyard which they had developed. In short,
they pointed out that limiting that area only to 15 per cent and
granting DCR only in respect of that much of area was wholly
illegal.
9. On the other hand, it was contended on behalf of the
appellants herein that Regulations 33 and 34 of the Regulations
were only enabling provisions and did not create any legal right
to get additional TDR. The appellant also relied on the circular
dated 9.12.1996 and it was contended that as per this circular
various amenities were described where 100 per cent FSI was
admissible in respect of some amenities and in respect of others
only 15 per cent of additional development rights could be
admissible. It was mainly contended that the courtyard and the
development therein did not amount to an amenity within the
meaning of Section 2 (7) of the Regulations. The High Court
allowed the writ petition. It was held that the Regulations had
statutory force and Clause 6 of Appendix VII of Regulation 34 of
the Regulations provided for benefit to be enjoyed by a person who
constructed the amenity. Relying on the plain language of Clause
6, it was held that the respondents herein were entitled to 100
per cent DCR rights. The High Court also held that the
aforementioned circular dated 9.4.1996 was of no consequence vis-
à-vis the specific language of Clause 6 of Appendix VII Regulation
34 of the Regulations. The High Court also relied on the judgment
of this Court reported as Godrej & Boyce Manufacturing Co. Ltd.
v. State of Maharashtra & Ors. [2009 (5) SCC 24]. The High Court
came to the conclusion that the above mentioned decision of this
Court applied on all fours to the present matter.
10. Shri Uday Lalit, learned senior counsel appearing on
behalf of the appellants herein firstly contended that the above
mentioned decision was distinguishable. According to him, in that
decision the Court was considering whether a road constructed by
the owner would entitle the owner to additional TDR. He further
argued that the road was undoubtedly an amenity under Maharashtra
Regional and Town Planning Act (hereinafter called “the Act” for
short) as also under the Regulations. Learned counsel further
argued that in the present case the additional TDR was being
claimed on the basis of the work of asphalting of the courtyard
and, therefore, it could not be held to be an amenity entitling
the owner to the additional TDR.
11. It was further submitted that the circular dated 9.4.1996
had no bearing in Godrej & Boyce’s case (cited supra) since it was
issued after the land owners had surrendered their plot of land
after construction of the roads as required by the Municipal
Council while in the present case the said circular was issued
prior to the respondent Nos.1 and 3 completing the construction of
an export office and asphalting of the courtyard and handing over
the possession. The counsel further urged that the question
arising in the present case was different in the sense that in the
present case, the question was whether under sub-regulation 6 of
Appendix VII of Regulation 34, it was mandatory for the
Commissioner or the appropriate authority to grant 100 % TDR
equivalent to the entire area of the courtyard. Lastly, it was
contended that in Godrej & Boyce’s case, the difference between
Regulations 5 and 6 of Appendix VII was not noticed.
12. The learned senior counsel also urged that Clause 6
applied only to the developed or constructed amenity and
asphalting the courtyard could not be covered under the same. Our
attention was drawn to the definition of ‘amenity’ and it was
contended that the courtyard could not be covered under the same.
The learned senior counsel further urged that the High Court had
not properly interpreted the consent terms as also Clause 4 of the
letter dated 22.2.1995. It was urged that that unlike sub-
regulation 5, the wording in sub-regulation 6 confers a discretion
on the authority. Our attention was drawn to the difference in
language by contending that while in clause 5 the wording used is
“shall be equal to” and in clause 6, the same was “may be
granted”. Our attention was also drawn to the phraseology used in
the two clauses. While in clause 5, the wording used was “equal”,
in clause 6 it was “equivalent”. It was also urged that by
circular dated 9.4.1996, arbitrary exercise of discretion by the
Commissioner was avoided and that was the main purpose of bringing
in the circular. The same provided definite guidance in respect
of the extent of TDR that was to be granted by the Commissioner
/competent authority. Lastly, it was urged that asphalting of the
courtyard was a separate activity. It had got nothing to do with
the consent terms. As regards the letter dated 22.2.1995, and more
particularly, clause 4 therein, it was urged that under the same
the respondents had specifically agreed that the quantum of the
TDR to be granted was to be decided by the Municipal Commissioner
and, therefore, the respondents could not turn back and urge that
they would be entitled to the 100% TDR.
13. As against this, Shri Ashok H. Desai, learned senior
counsel appearing on behalf of the respondents pointed out that
the matter was fully covered by the decision in the aforementioned
case of Godrej & Boyce (cited supra). The learned senior counsel
pointed out that it was a misnomer to say that asphalting was not
an amenity. He pointed out that unless the asphalting was done,
the basic purpose of constructing the octroi duty office would
have been frustrated as there would be no place for the large
number of vehicles to be parked. The learned counsel also pointed
out, relying on the provisions of DCR, that the courtyard, though
was separately mentioned and explained in the Rules, the
asphalting therein would certainly be an amenity. The counsel
urged about the letter dated 22.2.1995, that even if it was the
discretion to decide about the quantum of grantable TDR, the said
discretion could not have been used in contravention of the
Regulations. He pointed out that on that date, the circular was
nowhere which came much later and as such it could not have been
made applicable with retrospective effect. The learned senior
counsel also urged that the interpretation put forward by the
appellants of Clauses 5 and 6 was incorrect and in fact there was
very little or no difference. The learned senior counsel stressed
the implication of Clause 6 and pointed out that there was no
scope for the interpretation tried to be put forward by the
appellant MCGB. Learned senior counsel wholly supported the High
Court judgment.
14. It will be our task to examine as to whether the
aforementioned ruling in Godrej & Boyce’s case (cited supra)
clinches the issue. The factual scenario in both the matters is
almost identical. The only difference is that in that case, the
land owners had developed the roads while in the present case, the
land owners have developed the courtyard by asphalting the same.
In Godrej & Boyce’s case (cited supra), the reliance was only on
the same circular dated 9.4.1996 issued by the Municipal
Commissioner of the MCGB. That was by far the only defence. In
that case, the State had argued that the law provides for the
grant of additional FSI or TDR commensurate to the value of the
amenity constructed by the landowner and the meaning of Para 6 of
Appendix VII to the Regulations would be clear by reading it
alongwith other provisions of the Regulations and the parent Act.
The State had argued that the said circular dated 9.4.1996 was
clarificatory and fully applied to the claims of the appellants in
that case which were even prior to the said circular being born.
After taking the full resume of the provisions of the Act as also
the Regulations, the Court went on to hold firstly that as per
Regulation 2(2) of the Regulations, any terms and expressions not
defined in the Regulations shall have the same meaning as in
Bombay Municipal Corporations Act, 1888 and the Rules and Bye-laws
framed thereunder, as the case may be, unless the context
otherwise required. The Court then went on to hold that the term
“amenity” which was defined under Regulation 3 Clause (7) was much
restricted than the one given under the Act, inasmuch as the sport
complex, parade grounds, gardens, markets, parking lots, primary
and secondary schools and colleges and polytechnics, clinics,
dispensaries and hospitals were not included in the definition of
“amenity”. The Court, however, found that the road was common to
definitions, both, under the Act and the Regulations and it was
defined in the widest possible terms in Clause (76) of Regulation
3.
15. After considering the concepts like “floor spare index
(FSI)”, “Additional FSI” and “TDRs”, the Court considered Appendix
VII referred to in Regulation 34 of the Regulations, the Court
then took the stock of the argument that the envisaged grant of
FSI or TDR was under two separate heads, one, for the land and the
other for the construction of the amenity for which the land was
designated in the development plan, at the cost of the owner. The
Court referred to Section 2(9-A), as also to Section 126(1)(b).
Taking note of Para 6 of Appendix VII of the Regulations, the
Court noted that the additional DR for construction of the amenity
for which the surrendered plot was designated in the development
plan at the owner’s cost provided for a further DR in the form of
FSI “equivalent to the area of the construction/development”. The
Court also noted the argument that this grant of additional DR
could not be on a sliding scale for construction/development of
different kinds of amenities on the surrendered land and thus, it
could not be reduced or curtailed. After taking into
consideration the circular dated 9.4.1996 and noting,
particularly, para 3 thereof, the Court also noted that in that
case, the earlier granted TDR @ 15% was increased to 25%. The
Court also noted the further argument that the Regulations framed
under the Act had statutory force as held in Pune Municipal
Corporation Vs. Promoters and Builders Assn. [2004 (10) SCC 796].
As against this, the circulars issued by the Municipal
Commissioner were simply executive instructions and thus could not
override or supersede the provisions of the Regulations. The
Court also noted the argument that since the Municipal authorities
were fully aware and conscious of this legal position, they had
requested to the State Government to suitably modify Para 6 of
Appendix VII of the Regulations. The non-retrospectivity of the
circular dated 9.4.1996 was also noted.
16. All these arguments were tried to be countered in that
case, basically on the ground that the grant of additional TDR for
construction of all different kinds of amenities equal to the area
of the construction was illogical, unreasonable and
discriminatory. It was also urged that the law contemplated grant
of further additional TDR commensurate to the value of the land
constructed/developed on the surrendered land. This argument was
specifically refuted. In the present case, Shri U.U. Lalit also
tried to argue the same aspect that as against the value or the
expenditure spent for asphalting, the claim for TDR over the area
would be an excessive claim if the values are to be compared. In
short, the argument was that the value of asphalting would be
nothing in comparison to the claim of 100% TDR for the whole
courtyard. The Court did not accept this proposition which was
accepted by the Bombay High Court in that case. Relying on the
language of Section 126(1)(b) and the use of the word “against”
therein in respect of the area of the land surrendered and the
further use of the word “against” in respect of the development or
construction of amenities of the surrendered land, the Court held
that what was contemplated by law was to recompense the landowner.
However, Para 5 of the Appendix VII to the Regulations used the
words “equal to the gross area of reserved plot”, and, therefore,
there was no difficulty insofar as the bare land was concerned.
The Court then went on to consider the effect of the words
“equivalent to the area of the construction/development” in Para 6
of the Appendix and noted in paragraph 58 of the judgment to the
effect that the argument on behalf of the Government, though not
without substance, had to be rejected as it was not in keeping
with the law as it stood and, therefore, the value of the
development/construction could only be made the basis for granting
additional FSI or TDR by making suitable amendments in the law and
not by an executive circular. In short, the Court came to the
conclusion that (1) construction of the road was undoubtedly an
“amenity”, (2) under the express language of Section 126(1)(b)
read with Para 6 of the Appendix VII, the use of the word
“equivalent” would entitle the owner of the building to 100% for
the construction of an amenity at owner’s cost, and (3) a
subsequent circular would be of no consequence and would not have
the effect of overriding the provisions of the Regulations as
envisaged in Appendix VII and clauses 5 and 6.
17. In view of this unequivocal declaration of law by this
Court in the aforementioned case of Godrej & Boyce (cited supra),
in fact, law seems to be fully settled against the appellants. It
is, however, argued that asphalting of the courtyard could not be
said to be an “amenity”. The argument must fail as the very
stance on the part of the MCGB to provide 15% of additional TDR
for asphalting the courtyard would contain an admission that
asphalting of the courtyard would amount to an amenity. Had it
not been so, the MCGB could have conveniently said that it would
not provide even 1% of additional TDR to the respondents herein.
Further, considering the definition of “amenity” under Regulation
3(7) of the Regulations, which includes open spaces, parks,
recreational grounds, play grounds etc., we have no difficulty in
holding that asphalting the courtyard would certainly amount to an
amenity. The building offered to be constructed by the
respondents herein was an export office. Considering the overall
situation prevailing in Mumbai, the asphalting of the whole
courtyard and thus providing parking lot would certainly amount to
an amenity. After all, the office, by its very nature, would
attract trucks and other vehicles. In the absence of an asphalted
large area, the office could possibly not be a feasible idea. On
this count, the argument of the appellants must fail.
18. Shri U.U. Lalit, learned senior counsel appearing on
behalf of the appellants then urged that the respondents herein
had specifically agreed in the letter dated 22.2.1995 and more
particularly in terms of para 4 thereof that the Municipal
Corporation will grant the benefit of TDR in respect of the
concrete/asphalted surface area around the Export Office building
as and when the quantum of such TDR is decided by the Municipal
Commissioner. It was very earnestly argued by the learned senior
counsel that thereby the respondents had compromised their rights
and had left it to the discretion of the Municipal Commissioner
and, therefore, they could not turn around and say that it was not
for the Municipal Commissioner then to decide the quantum as per
his own discretion. The argument is clearly incorrect for the
simple reason that on the day when this letter was signed, the
aforementioned circular dated 9.4.1996 was nowhere in existence.
The respondents, therefore, had no reason to believe that the
Municipal Commissioner would decide to scale down the entitlement
which they legitimately expected because of clauses 5 and 6 in
Appendix VII. The aforementioned letter merely provided that the
quantum could be decided in terms of the area of courtyard to be
developed and the grant of TDR would depend upon as to whether
that much area was fully developed as per the satisfaction of the
Municipal Commissioner. The scope of Para 4 could not be taken
beyond this.
19. Shri Lalit, learned senior counsel, relying on clause 15,
also argued that the land owner was to get the TDR only on the
land being levelled to the surrendering ground level and a 1.5
metres high compound wall was constructed with a gate, at the cost
of the owner. That may be so; however, in our view, the agreement
on the part of respondents to construct such a compound wall and
gate and to do the levelling of the land before handing over the
land admeasuring 3500 sq. metres, would be of no consequence
insofar as the present controversy is concerned. The further
argument of the learned senior counsel about the difference in the
phraseology in clauses 5 and 6 i.e. the word “equal” having been
used in clause 5 and the word “equivalent” having been used in
clause 6 would also be of no consequence as, in our opinion, the
same has been concluded by the aforementioned ruling of this Court
in Godrej & Boyce’s case (cited supra) against the appellants,
and, therefore, the argument that it gives a discretion to the
Municipal authorities to scale down the grantable TDR, does not
impress us.
20. That apart, in the aforementioned ruling in Godrej &
Boyce’s case (cited supra), the Court has clearly held that in a
circular, the Corporation could not have created divisions in the
total amenities in the sense that it could not have chosen to
grant 100% of additional TDR in favour of some amenities and 15%
in case of some others.
21. Shri Lalit, learned senior counsel has also reiterated the
argument regarding the value of construction vis-à-vis the grant
of TDR, which question, in our opinion, is not open in view of the
unequivocal finding given on that question in the aforementioned
ruling in Godrej & Boyce’s case (cited supra).
It was tried to be suggested that in asphalting of the
courtyard there was no element of development as, according to the
learned senior counsel, the term “development” meant building,
engineering, mining or other operations in, or over, or under land
or the making of any material change in any building or land. The
argument is wholly incorrect, as had this not been development,
the MCGB would not have agreed to provide even 15% of the TDR
therefor.
22. Lastly, Shri Lalit, learned senior counsel urged that the
ruling in Godrej & Boyce’s case (cited supra) was distinguishable
inasmuch as under the said ruling what was considered was the
construction of road which was not equivalent to asphalting of a
courtyard. We have already pointed out that the question was not
of the construction of a road or asphalting of a courtyard; the
question was whether it was an amenity. Once it is held as an
amenity, there will be no question of refusing the right of
equivalent TDR therefor. It was then urged that the circular
dated 9.4.1996 in Godrej & Boyce’s case (cited supra) was issued
after the land owners had surrendered their plot of land and
completed the construction of roads as required by the Municipal
Corporation, whereas in the present matter, the circular was
issued “prior to” completion of the construction of the export
office by respondents 1 to 3 and asphalting of the courtyard and
handing over of the possession by them. In our opinion, this
cannot be the distinguishable feature, as under any circumstance,
the circular dated 9.4.1996 was issued much after the compromise
in the writ petition and the issuance of letter of intent dated
22.2.1995.
23. No other point was urged before us.
24. We are, therefore, of the clear opinion that the High
Court was right in allowing the writ petition and granting 100%
TDR as against the development of courtyard by asphalting the
same. We find no merits in the appeal. The appeal is, therefore,
dismissed. No costs.
………………………………..J. (V.S. Sirpurkar)
………………………………..J. (T.S. Thakur)
New Delhi; March 17, 2011.