MANTRI TECHNOZE PVT. LTD. Vs FORWARD FOUNDATION .
Bench: HON'BLE MR. JUSTICE A.K. SIKRI, HON'BLE MR. JUSTICE S. ABDUL NAZEER, HON'BLE MR. JUSTICE M.R. SHAH
Judgment by: HON'BLE MR. JUSTICE S. ABDUL NAZEER
Case number: C.A. No.-005016-005016 / 2016
Diary number: 16740 / 2016
Advocates: DEVASA & CO. Vs
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5016 OF 2016 MANTRI TECHZONE PVT. LTD. … APPELLANTS
VERSUS FORWARD FOUNDATION AND ORS. … RESPONDENTS
WITH
CIVIL APPEAL NOS.8002-8003 OF 2016
CIVIL APPEAL NO.12326 OF 2016
CIVIL APPEAL NO.9227 OF 2016
CIVIL APPEAL NO.1343 OF 2017
CIVIL APPEAL NO.10995 OF 2016
CIVIL APPEAL NO.10993 OF 2016
CIVIL APPEAL NO.10994 OF 2016
CIVIL APPEAL NO.2246 OF 2018
CIVIL APPEAL NO.10992 OF 2016
CIVIL APPEAL NO.12157 OF 2016
CIVIL APPEAL NO.12152 OF 2016
CIVIL APPEAL NO.12156 OF 2016
CIVIL APPEAL NO.12158 OF 2016
CIVIL APPEAL NO.12160 OF 2016
CIVIL APPEAL NO.12159 OF 2016
2
CIVIL APPEAL NOS.4923-4924 OF 2017
CIVIL APPEAL NO.14966 OF 2017
J U D G M E N T
S.ABDUL NAZEER, J.
1. These appeals have been preferred under Section 22 of the
National Green Tribunal Act, 2010 (for brevity 'NGT Act')
challenging the judgment and order dated 07.05.2015 and
04.05.2016 respectively passed by the Principal Bench of the
National Green Tribunal, New Delhi (for short 'the Tribunal').
2. The appellants in Civil Appeal Nos. 5016 of 2016 and 8002-
8003 of 2016 are respondent Nos. 9 and 10 in the Original
Application No. 222 of 2014 (hereinafter referred to as 'the
respondent Nos. 9 and 10'). The said Application was filed by
respondent Nos.1 to 3 herein (hereinafter referred to as 'the
applicants'). Respondent Nos. 4 to 7 in these appeals are the State
of Karnataka and other authorities. They were arrayed as
respondent Nos. 1 to 4 in the application. Respondent Nos. 12 and
3
13 herein were subsequently impleaded in the application (for short
'the impleaded respondents').
3. The State of Karnataka has filed Civil Appeal Nos. 4923-4924
of 2017, challenging the general condition and direction No.(1)
contained in the order of the Tribunal dated 04.05.2016. The other
appeals have been filed by different entities, who were not parties
before the Tribunal challenging the order of the Tribunal dated
04.05.2016 insofar as it directs a buffer/green zone of 75 meters in
respect of lakes, 50 meters in respect of primary Rajakaluves, 35
meters in case of secondary Rajakaluves and 25 meters in case of
tertiary Rajakaluves with retrospective effect. According to them,
they are adversely affected by the aforesaid condition in the
impugned order.
4. The applicants filed O.A. No.222 of 2014 by contending that
ecologically sensitive land was allotted by the Karnataka Industrial
Area Development Board (for short 'the KIADB') to respondent Nos.
9 and 10 vide Notifications dated 23.04.2004 and 07.05.2004
respectively for setting up of Software Technology Park, Commercial
and Residential complex, hotel and Multi Level Car Parks. The
Master Plan formulated by the Bangalore Development Authority
4
(for short the 'BDA'), identifies the allotted land as 'Residential
Sensitive', though the same land was identified in the Draft Master
Plan as 'Protected Zone'. It was further contended that the Revenue
Map in respect of properties as referred in the Land Lease
Agreements has multiple Rajakaluves (Storm Water Drains). The
development projects in question sit right on the catchment and
wetland area which feeds the Rajakaluves, which in turn drains
rain water into Bellandur Lake. The project will thus encroach two
Rajakaluves of 1.38 acres and 1.23 acres each.
5. The Satellite Digital Images of the area from the year 2000 to
2012 show encroachment upon these Rajakaluves, as well as the
manner in which they are covered by the construction. The State
Level Expert Appraisal Committee (for short 'SEAC'), which was to
assist the State Level Environment Impact Assessment Authority
(for short 'SEIAA'), held its meetings on various dates to examine
the project. It had required the appellant No.9 to submit a revised
NOC from the Bangalore Water Supply and Sewerage Board (for
short 'BWSSB') for the project in question. It was also observed
that the project lies between the Bellandur Lake and the Agara
Lake. Respondent No.9 was also directed to take protective
5
measures to spare the buffer zone around Rajakaluves and also to
commit that no construction would be carried out in the buffer
zone. In the meeting of 11.11.2011, it was recorded that the project
proposes car parking facility for 14,438 cars in that environmentally
sensitive area.
6. It was alleged that NOC was issued covering an area of 17,404
sq. mtrs. whereas the built up area, as noted by SEAC, is
13,50,454.98 sq. mtrs. Respondent No.9 obtained NOC from
BWSSB by concealing material facts and by misrepresenting that
NOC is required only for residential units which form a very
minuscule part of the total project. Respondent No.9 had
approached the Karnataka State Pollution Control Board (for short
'the KSPCB') for obtaining clearance, which was granted on
04.09.2012 subject to the fulfillment of the conditions stated in the
consent order which included leaving the buffer zone all along the
valley and towards the lake. It is further contended that the grant of
consent by the KSPCB to respondent No.9 also contained a
condition with regard to obtaining Environmental Clearance from
the Competent Authority and no construction was to commence
until such clearance was granted.
6
7. Applicants further contended that respondent No.9 violated
the conditions and commenced construction of the project. There
was also violation of the stipulations stated in the approval of SEAC
in relation to buffer zone and construction over Rajakaluves. The
construction had been commenced over the ecologically sensitive
area of the lake catchment area and valley, with utter disregard to
the statutory compliances. Referring to these blatant irregularities,
the applicant submitted that the conversion of land from 'Protected
Zone' to 'Residential Sensitive Area' is violative of the law. The
project is right in the midst of a fragile wetland area which ought
not to have been disturbed by the development activity. The fragile
environment of the catchment area has been exposed to grave and
irreparable damage. It has severely disturbed and damaged the
Rajakaluves. Respondent Nos. 9 and 10 started to level the land by
filling it with debris, thus causing damage to the drains. The
conditions with regard to no-disturbance to the Storm Water
Drains, natural valleys and buffer area in and around the
Rajakaluves have been violated. It has in turn, affected the ground
water table and bore wells which are the only source of water for
thousands of households. Fishing and agriculture which depends
7
on Bellandur Lake are also severely affected. The construction over
the wetland between the two lakes is in violation of Wetlands
(Conservation of Management) Rules, 2010 (for short 'Rules of
2010').
8. It was submitted that SEIAA in its meeting dated 29.09.2012,
decided to close the file pertaining to respondent No. 10 due to non-
submission of requisite information and the application thereof was
rejected in November, 2012. Despite the rejection, respondent
No.10 commenced construction on the project in full swing.
9. The applicants also relied upon the findings of the Joint
Legislative Committee, constituted under the Chairmanship of Shri
A.T. Ramaswamy in the month of July 2005, which stated that
there were 262 water bodies in the Bangalore city in 1961 which
drastically came down because of trespass and encroachments. It
was also affirmed that about 840 kms. of Rajakaluves have been
encroached upon in several places and have become sewage
channels. The applicants also relied on the Report of the Committee
under the Chairmanship of Hon'ble Mr. Justice N.K. Patil
suggesting immediate remedial action in order to remove
encroachments on the lake area and the Rajakaluves and
8
preservation of the lakes in and around Bangalore city. It was
further contended that other Expert Committees, including
Lakshman Rau Expert Committee had also submitted proposals for
preservation, restoration or otherwise of the existing tanks in
Bangalore Metropolitan Area which recommended to maintain good
water surface in Bellandur tank and to ensure that the water in the
tank is not polluted. The Central Government in August 2013 had
issued an advisory on conservation and restoration of water bodies
in the urban areas. The applicants claim to have obtained
monitoring report of the project by respondent No.5, Ministry of
Environment and Forests, through RTI on 21.08.2013. The report
dated 14.08.2013 revealed that the project proponents are in clear
breach of their undertaking to carry out all precautionary measures
to ensure that the Bellandur lake is not affected by the construction
and operational phase of the project. This approach is particularly
with regard to the major alteration in natural sloping pattern of the
project site and natural hydrology of the area.
10. The Lake Development Authority (for short ‘the LDA’), after
inspection in the catchment area of the Bellandur Lake submitted
its report dated 12.06.2013 which confirms that the project will
9
have disastrous impact, including deleterious effect on the
Bellandur Lake. This report was brought to the notice of KIADB.
The LDA has also opined that the land should be classified and
maintained as sensitive area. The KIADB called upon respondent
No. 9 to comply with the rules of Ecology and Environment
Department and to obtain necessary approval from KSPCB and
LDA. Despite all this, respondent Nos. 9 and 10 have continued
with their illegal constructions and have caused damage to the
ecology and the environment by irreparably jeopardizing the
ecological balance in this sensitive area. The applicants rely upon
the Revised Master Plan, 2013 issued by BDA which specifically
provides that 30 meters buffer zone is to be created around the
lakes and 50 meters buffer zone to be created on either side of the
Rajakaluves. It was also pleaded that respondent No. 9 had
obtained the NOC from BWSSB only with regard to residential units
and not for the entire project and that the Environmental Clearance
obtained by respondent No.9 is based upon the partial NOC issued
by BWSSB which itself is a misrepresentation. It was contended
that the projects are bound to create water scarcity as the
requirement of the project of respondent No. 9 alone is
10
approximately 4.5 million liters per day, i.e. 135 million liters per
month, which is more than what the BWSSB supplies to the entire
Agaram Ward. The construction of respective projects by
respondent Nos.9 and 10 respectively, besides having commenced
without permission from the authorities and being in violation of
the conditions imposed for grant of permission/consent, is bound to
damage the environment, resulting in change in the topography of
the area, posing potential threat of extinction of the Bellandur lake,
causing traffic congestion, shortening and wiping out the wetlands,
extinction of Rajakaluves and causing serious and potential threat
of flooding and massive scarcity of water in the city of Bangalore,
particularly the areas located near the water bodies.
11. Respondent No.9 in its objections contended that it was
incorporated with the objective of establishing an Information
Technology Park and R & D Centre with facilities such as
residential complexes, parks, education centres and other allied
infrastructure within a single compound. It had submitted the
proposal to establish such Information Technology Park and other
facilities to the State Government and requested for allotment of
land for the project. Its proposal was considered in 78th High Level
11
Committee meeting held on 21.06.2000 and after examining the
proposal, it was approved by the Government on 06.07.2000. Before
the State High Level Committee, it had informed that its
requirement was 110 acres of land, 25 MW of power from the
Karnataka Power Transmission Corporation Limited (for short the
‘KPTCL’), and four lakh litres of water per day from BWSSB. The
lands for the project were initially notified vide Notification dated
10.02.2004. Subsequently, the lands were allotted vide letter dated
28.06.2007 for which Lease-cum-Sale Agreement was signed on
30.06.2007. Considering the overall development of the State of
Bangalore, this respondent proposed a Mixed Use Development
Project consisting of an Information Technology Park, residential
apartments, retail, hotel and office buildings with a total built up
area of 13,50,454.98 sq mtrs. The Project was conceived as a zero
waste discharge project. The project is located one and a half kms.
away from the southern-side of the Bellandur Lake. Towards the
North, adjacent to the Project, lies vast stretches of lands belonging
to the Defence and towards the East, lies the Project of respondent
No. 10 and another developer is also developing a project on the
12
western side. It has obtained sanction plan on 04.07.2007 which
was renewed from time to time.
12. Respondent No. 9 claims that it has obtained NOC from
Airport Authority of India on 09.04.2010. Bharat Sanchar Nigam
Ltd, vide its communication dated 16.04.2010, granted clearance
for the project construction. BWSSB, vide its communication dated
26.04.2011 issued NOC for portion of the proposed construction to
be built. The Bangalore Electricity Supply Company Ltd. also
granted NOC for arranging power supply to the proposed residential
and commercial building in its favour. Environmental Clearance
was granted by SEIAA vide communication dated 17.04.2012. The
Director General of Police has issued NOC and KSPCB vide order
dated 04.09.2012 accorded its consent for construction of the said
project subject to the conditions stated therein. It was further
stated that after grant of the Environmental Clearance on
17.09.2012, the same was published in the leading newspapers
“Kannada Prabha” and "The Indian Express” on 12.03.2012 and
14.03.2014 respectively.
13. It submitted a modified the building plan which was approved
by KIADB vide its letter dated 30.08.2012, which was valid up to
13
10.08.2014. It started the construction of the project in November
2012, taking all precautions as per terms and conditions of the
orders issued by the competent authorities. It was also submitted
that it has raised the constructions in accordance with the plans
and conditions of the Environmental Clearance and consent orders
and that it has not violated any of the conditions and has not
caused any adverse impact on the ecology and environment of the
area. It has denied the contention that its construction activity has
blocked the Rajakaluves and has adversely affected the lake. It has
already spent a sum of Rs 306.73 crores on the project towards
procurement of men and materials, machinery, infrastructure,
medical and sanitary facilities, etc. and that it has availed financial
assistance from various banks and financial institutions towards
the construction and execution of the project and that various
contracts have been signed with the third parties. It is specifically
pleaded that the petition is barred by time and suffers from defects
and laches.
14. Respondent No.10 pleaded that the applicants raised
multifarious proceedings against it which is an abuse of the process
of law and mala fide. It had submitted a revised proposal in respect
14
of its project in question and to obtain fresh clearance on
31.08.2007 with an investment of Rs. 179.22 crores. The State High
Level Committee had cleared the project which was communicated
to it on 25.01.2008. Its properties are located in between Bellandur
Lake and Agara Lake but there are no primary storm water drains
and secondary storm water drains that exist in its properties. It
has clearances from various authorities, including Environmental
Clearance and consent for establishment.
15. KIADB stated that after possession of the land was handed
over to respondent Nos. 9 and 10, one year time was granted for the
implementation of the project which was extended from time to
time. The building drawings were approved on 04.07.2007, and the
modified building drawings were approved on 26.04.2011 and
30.08.2012 with specific conditions. In its meeting held on
16.07.2013, it was resolved to inform respondent No. 9 to fully
comply with the Ecology and Environment Rules and to obtain
approvals from the LDA and KSPCB. LDA vide its letter dated
24.09.2013, had informed KIADB that the construction activity in
the catchment area in the Bellandur Lake could drastically impact
the Lake with deleterious effects and asked it to stop construction
15
activity of respondent Nos. 9 and 10. However, the validity of the
building drawings was again extended up to 10.08.2014. The
Lokayukta on 17.12.2013 had written a letter in respect of
complaint filed by the South East Forum for Sustainable
Development where it had been averred that the decision had been
taken by the Board on 21.12.2013 to keep in abeyance the approval
accorded and even the re-validations of plans. This was also
informed to respondent No.9. The Board took a decision which
was communicated to respondent No.9 on 02.01.2014, wherein it
asked the respondent No.9 to stop all construction activities on the
allotted lands. The said communication was challenged by
respondent No. 9 and on the stop-work notice, stay was granted by
the High Court of Karnataka. The stop-work notice dated
23.12.2013 issued by Bruhat Bengaluru Mahanagara Palike (for
short 'BBMP') was also stayed vide order dated 21.01.2014. The
proposal submitted by respondent Nos. 9 and 10 had been
approved by the State Government. The land allotted to respondent
Nos. 9 and 10 does not consist of any Rajakaluves.
16. The LDA took a stand that it was not at all aware of the project
initiated by KIADB. It came to know about the entire project only
16
when certain newspaper reports surfaced during the month of
June, 2013 and till that time it was in the dark. After the
complaints, it inspected the Bellandur Lake and the Agara Lake on
12.06.2013 and prepared an inspection report. In the report, it was
noticed that large scale construction activities were going on in the
catchment area of Bellandur Lake and that there was a change in
the land use, which in turn has directly affected the catchment of
Bellandur Lake. The wetland area of Agara Lake had also shrunk,
which originally formed the irrigation area for the adjoining
agricultural lands. Therefore, it had questioned the decision of
KIADB vide letter dated 06.07.2013 and even requested it to stop
the construction activity and to re-classify the land as non-SEZ
area. It was thereafter on 31.08.2013, that respondent No. 9 wrote
a letter for according approval for the proposed development
projects. However, vide its letter dated 23.09.2013, LDA informed
KIADB that it had no authority to grant or deny construction
projects, but it also communicated its objections to KIADB
mentioning that construction activity would be in contravention of
the directions of the Supreme Court. Despite these warnings,
KIADB granted approval to the extension of the building drawings of
17
the project in favour of the project proponents with certain
conditions, like ensuring that all natural valleys, valley zone,
irrigation tanks and existing roads leading to villages in the said
land should not be disturbed. Further, the natural sloping pattern
of the project site was not to be altered and the lakes and other
water bodies within and/or at the vicinity of the project area should
be protected and conserved. Despite the objections, the plans were
approved and approvals were extended from time to time. It has
taken a categorical stand that the projects as approved by the
KIADB would have adverse impact on Bellandur and Agara Lakes.
17. On the basis of the pleadings of the parties, the Tribunal
framed the following questions for consideration and determination:
1. Whether the application filed by the applicants and
supported by respondent Nos. 11 and 12, is barred by
time and thus, not maintainable?
2. Whether the petition as framed and reliefs claimed
therein, disclose a cause of action over which this
Tribunal has jurisdiction to entertain and decide the
application under the provisions of the NGT Act, 2010?
3. Whether the present application is barred by the
principle of res judicata and/or constructive res judicata?
18
4. Whether the application filed by the applicants should
not be entertained or it is not maintainable before the
Tribunal, in view of the pendency of the Writ Petitions
36567-74 of 2013, before the Hon'ble High Court of
Karnataka? and
5. What relief, if any, are the applicants entitled to?
Should or not the Tribunal, in the interest of
environment and ecology issue any directions and if so,
to what effect?
18. The Tribunal by its order dated 07.05.2015 at Annexure A-2,
disposed of the applications with the following directions:
1) We decline to pass any direction or order to stop
further progress and/or demolition of the project or any
part thereof at this stage. However, we constitute the
following Committee to inspect the projects in question
and submit a report to the Tribunal inter alia but
specifically on the issues stated hereinafter:
a) Advisor in the Ministry of Environment and Forest
dealing with the subject of wetlands.
b) CEO of the Lake Development Authority, Karnataka
State.
c) Chief Town Planner of BBMP, Bangalore.
d) Chairman of SEAC which recommended the grant of
Environmental Clearance to the projects in
question.
19
e) Sr. Scientist (Ecology) from the Indian Institute of
Sciences, Bangalore.
f) Dr. Siddharth Kaul, former Advisor to MoEF.
g) A Senior Officer from the National Institute of
Hydrology, Roorkee.
2) Member Secretary of the Karnataka State Pollution
Control Board shall act as the Convener of the
Committee and would submit the final report to the
Tribunal.
3) The Committee shall inspect not only the sites
where the projects in question are located but even other
areas of Bangalore which the Committee in its wisdom
may consider appropriate, in order to examine the
interconnectivity of lakes and impact of such activities
upon the water bodies with particular reference to lakes.
4) The Committee shall submit whether the projects in
question have encroached upon or are constructed on the
wetlands and Rajakaluves. If so, are there any adverse
environmental and ecological impact of these projects on
the lake, particularly Bellandur Lake and Agara Lake, as
well the Rajakaluves. The report should specify, if any
Rajakaluves have been covered by the construction
activities of respondent Nos. 9 and 10 or by any of the
projects in the area in question.
5) Committee should submit in its report, if these
projects have any adverse impacts upon the surrounding
20
ecology and environment, with particular reference to
lakes and wetlands. If yes, then whether any part of the
project is required to be demolished. If so, details thereof
along with reasons.
6) The Committee shall substantially notice if any of
the conditions of the Environmental Clearance order in
each case of respondent Nos. 9 and 10 have been
violated. If so, to what extent and suggest remedial
measures in that behalf to restore the ecology of the area.
7) The Committee would also recommend what should
be the buffer zone around the lake(s) and interconnecting
passages and wetlands. The Committee shall also report,
whether activities of multipurpose projects which have
serious repercussions on traffic, air pollution,
environment and allied subjects should be permitted any
further or not, particularly, in wetlands and catchment
areas of water bodies.
8) Recommendations should be made with regard to
the steps and measures that should be taken for
restoration of lakes, particularly in the city of Bangalore.
9) The Committee shall also find out that whether the
construction of the projects is in accordance with the
sanctioned drawings and bye-laws in accordance with the
letters dated 4th July, 2007 and 22nd April, 2008
respectively. Further, the Committee would also report
whether both respondent Nos. 9 and 10 have installed
21
ETP/STP and have taken full measures for recycling of
used water for washing and flushing, etc. in terms of
letters dated 11th October, 2013 and 3rd January, 2013,
issued by the Karnataka Industrial Area Development
Board to respondent Nos. 9 and 10 respectively.
10) In the event, the Committee is of the opinion that
the adverse impacts noticed are redeemable, then what
directions need to be issued in that behalf and the cost
involved for achieving the said conservation and
restoration of lakes and water bodies.
11) Till the submission of the report by the Committee
and directions passed by the Tribunal in that regard,
both respondent Nos. 9 and 10 are hereby restrained
from creating any 3rd party interests or part with the
possession of the property in question or any part
thereof, in favour of any person.
12) The Committee shall submit its report to MoEF and
to this Tribunal as expeditiously as possible and in any
case not later than three months from today. During
that period we restrain MoEF, SEIAA and/or any public
authority from sanctioning any construction project on
the wetlands and catchment areas of the water bodies in
the city of Bangalore.
13) The Committee shall report if the project proponents
are proposing to discharge their trade or domestic
22
effluents into the lake or any of the water bodies in and
around of the area in question.
14) For the reasons stated in the judgment, respondent
No. 9 is liable and shall pay a sum of Rs. 117.35 crores,
while respondent No. 10 shall pay a sum of Rs. 22.5
crores respectively being 5 per cent of the project value,
within two weeks from today. The said amount would be
paid to the KSPCB, which shall maintain a separate
account for the same and would spend this amount for
environmental and ecological restoration, restitution and
other measures to be taken to rectify the damage
resulting from default and non–compliance to law by the
Project Proponent in that area, after taking approval of
the Tribunal.
15) We make it clear that the said respondents would
not be entitled to pass on the amount in terms of
direction 14, on to the purchasers because this liability
accrues as a result of their own intentional defaults,
disobedience of law in force and carrying on project
activities and construction illegally and unauthorizedly.
19. Feeling aggrieved by the said order, respondent Nos. 9 and 10
filed Civil Appeal Nos. 4829 and 4823 of 2015 before this Court.
This Court by its Order dated 20th May, 2015 passed the following
order:
23
"One of the main contentions raised by
the Appellants in these Appeals is that though
the Tribunal had heard the matter only on
preliminary issues and no arguments on merit
were advanced, final judgment decides the
merits of the disputes as well and above all a
penalty of Rs.117.35 crores against the
original Respondent No.9 (the Appellant in
C.A. No. 4832 of 2015) and Rs. 22.5 crores
against Original Respondent No. 10 (the
appellant in C.A. No. 4829/2015) is imposed.
On the aforesaid averment, we feel that it
would be more appropriate for the appellant to
file an application before the Tribunal with the
prayer to recall the order on merits and decide
the matter afresh after hearing the counsel for
the parties, as the Tribunal knows better as to
what transpired at the time of hearing.
With the aforesaid liberty granted to the
petitioners, the appeals are disposed of.
Certain preliminary issues are decided against
the appellants which are also the subject
matter of challenge. However, it is not
necessary to deal with the same this stage. We
make it clear that in case the said application
is decided against the appellants or if
24
ultimately on merits, it would be open to the
appellants to challenge those orders by filing
the appeal and in that appeal all the issues
which are decided in the impugned judgment
can also be raised.
The counsel for the appellants state that
they would file the requisite application within
one week. Till the said application is decided
by the Tribunal, there shall be stay of the
direction pertaining the payment of aforesaid
penalty. Mr. Raj Panjwani points out that the
Tribunal has allowed the appellants to proceed
with the construction only on the payment of
the aforesaid fine/penalty. We leave it to the
Tribunal to pass whatever orders it deems fit
in this behalf, after hearing the parties."
20. In relation to Issue No.5, an opportunity of hearing was
granted to the respondents. The Tribunal passed order dated
06.04.2016 on these applications as under:
"M.A. No. 603 of 2015 and M.A. No. 596 of 2015
These Applications have been filed on
behalf of the Respondent 9 & 10 respectively.
It is not necessary for us to refer to any details
25
in view of the directions that we propose to
issue in this case.
Without prejudice to the rights and
contentions of the parties and subject to just
exception we would hear the parties in terms
of the order of the Hon'ble Supreme Court of
India primarily on the question of imposition of
Environmental Compensation and merits
attached in relation thereto. Parties are given
liberty to address their submissions on that
behalf.
With the above directions the M.A. No.
603 of 2015 and M.A. No. 596 of 2015 stand
disposed of without any order as to cost."
21. It is evident from the above orders that the Tribunal had
granted opportunity to the parties to address it "limited question",
as aforementioned. The Tribunal after hearing the parties passed an
order dated 04.05.2016 as under:
“General Conditions or directions:
1. In view of our discussion in the main
Judgment, we are of the considered view that
the fixation of distance from water bodies
(lakes and Rajkalewas) suffers from the inbuilt
26
contradiction, legal infirmity and is without
any scientific justification. The RMP – 2015
provides 50m from middle of the Rajkalewas as
buffer zone in the case of primary Rajkalewas,
25m in the case of secondary Rajkulewas and
15m in the tertiary Rajkulewas in
contradiction to the 30m in the case of lake
which is certainly much bigger water body and
its utility as a water body/wetland is well
known certainly part of wet land. Thus, we
direct that the distance in the case of
Respondents Nos. 9 and 10 from Rajkulewas,
Waterbodies and wetlands shall be maintained
as below:-
(i) In the case of Lakes, 75m from the
periphery of water body to be maintained
as green belt and buffer zone for all the
existing water bodies i.e. lakes/wetlands.
(ii) 50m from the edge of the primary
Rajkulewas.
(iii) 35m from the edges in the case of
secondary Rajkulewas
(iv) 25m from the edges in the case of
tertiary Rajkulewas
This buffer/green zone would be treated
as no construction zone for all intent and
27
purposes. This is absolutely essential for the
purposes of sustainable development
particularly keeping in mind the ecology and
environment of the areas in question.
All the offending constructions raised by
Respondents Nos. 9 and 10 of any kind
including boundary wall shall be demolished
which falls within such areas. Wherever
necessary dredging operations are required,
the same should be carried out to restore the
original capacity of the water spread area
and/or wetlands. Not only the existing
construction would be removed but also none
of these Respondents - Project Proponent
would be permitted to raise any construction
in this zone.
All authorities particularly Lake
development Authority shall carry out this
operation in respect of all the water bodies/
lakes of Bangalore.
2. The capacity of the existing STPs to treat
sewage is 729 MLD, whereas another 500 MLD
sewage is proposed to be treated in 10
upcoming STPs. In this context, all the STPs
operating in the area whether Government or
28
privately owned, should meet the revised
standards notified by CPCB/MoEF.
3. Bangalore city receives treated potable
water of 1360 MLD from river Cauvery whereas
the requirement is for another 750 MLD and
the entire area falls in critical zone in terms of
ground water exploitation. Information reveals
that only one million litre per month of STP
treated water is used by builders for
construction purposes. For this reason, the
BWSSB issues partial NOC to various
residential and commercial projects in respect
of supply of potable water. In this context,
following directions need to be issued:
i. At the time of grant of EC, the water
requirement for the construction
phase and operation phase should be
considered separately. Due
consideration should also be given for
identification of source of supply of
water and this should be a pre-
requisite for grant of EC.
ii. All the project proponents should
necessarily use only treated sewage
water for construction purpose and
29
this should be reflected in EC as a
condition for construction phase.
iii. Wherever the quality of treated sewage
water does not conform to the quality
needed for construction, necessary
upgradation in STP should be
undertaken immediately.
Specific Conditions/ Directions for
Respondent 9;
In addition to the above directions which
should be equally part of EC condition in
respect of respondents nos. 9 & 10, following
specific conditions shall apply to respondent
no. 9:
i. Reclaimed area of the lake to the
extent of 3 acres 10 guntas in
survey No. 43 should be restored to
its original condition at the cost of
project proponent. The possession of
this area should be restored by
Respondent No. 9 to the concerned
Authorities immediately. In addition,
a buffer zone of 75 m should be
provided between the lake and the
project area and this should be
maintained as green area.
30
ii. In the remaining area, where
primary Rajkalewa is abutting the
project area, 50 m buffer zone on
the side of the project area from the
edge of the rajkalewa should be
maintained as green belt.
iii. Several irrigation canals or tertiary
rajkalewas taking off from the Agara
tank were passing through the area
of respondent No. 9, and serve the
dual purpose of irrigating paddy
fields and disposal of surface run off
(storm water drains) during rainy
season. However on account of the
activities of the project, these drains
have been totally obliterated. For the
purpose of proper disposal of storm
runoff from the entire area falling
between the Agara lake and the
Belandur Lake, respondent No. 9
must provide required number of
storm water drains based on proper
hydrological study. These storm
drains should have a buffer zone of
15 m on either bank maintained as
green belt.
31
iv. The cumulative quantity of earth
excavated for the construction of
project is around 4 lakhs cubic
meters in the depth range of 0 to 9
meters. This has created huge
hillock like structure obstructing the
natural flow pattern of surface
runoff from Agara Lake side to
Balendur Lake side or primary
Rajkalewas. For this purpose,
during construction phase garland
drain should be constructed around
the existing dumping site for safe
disposal of runoff to the Rajkalewas.
For the disposal of excavated
material, a proper muck disposal
plan duly approved by SIEAA shall
be prepared. In any case the plan
should ensure that no
muck/sediment flows into
Rajkalewas and/or Belandur lake.
v. The Kharab land identified by
Revenue Dept. admeasuring 1 acre
2 guntas should be demarcated and
maintained separately as green belt.
32
vi. The entire green belt created under
the directions of this Tribunal
should not to be considered as part
of green belt of the project as part of
EC condition and will be over and
above the green belt as indicated in
the EC.
vii. In view of the heavy traffic load in
the adjoining Sarjapur road, a
proper study on the basis of traffic
density,foot falls expected, etc., a
proper plan needs to be prepared
and the concept of service road
exclusively for the project needs to
be worked out and additional
parking space created within the
project area and incorporated as a
part of the overall project layout,
within a period of 3 months.
10. Though, at the time of hearing prior to
passing the Judgment, we had heard the
parties on all aspects but still we have
provided re-hearing to the parties on all issues
with emphasis on imposition of environmental
compensation including the quantum. Upon
hearing, we are of the considered view that
33
environmental compensation imposed upon
Respondent No. 9 calls for no variation and the
Respondent No. 9 should be called upon to pay
the said amount of Rs. 117.35 Crores
determined under the Judgment prior to
commencement of any project activity at the
site. Respondent No. 10 has not commenced
any actual construction activity but has
carried out various preparatory steps including
excavation and deposition of huge earth by
creating a hillock at the premises in question
and a site office.
Thus, considering cumulative effect on
environment and ecology due to various
breaches in that behalf by Respondent No. 10
and the fact that the remedial measures can
more effectively be taken by the Respondent
No.10, we reduce environmental compensation
payable by Respondent No. 10 to Rs. 13.5
crores (3% of the stated project cost instead of
5% as imposed in the original judgment).
General Directions:
1. We direct SEIAA, Karnataka to issue
amended order granting Environmental
Clearance within four weeks from today
incorporating all the conditions stated in this
34
judgement and such other conditions as it may
deem appropriate in light of this judgment and
Inspection Note of the Expert Members. The
Project Proponents would be permitted to
commence activity only after issuance of
amended Environmental Clearance order.
2. SEIAA Karnataka and MoEF shall ensure
regular supervision and monitoring of the
project and during the construction and even
upon completion to ensure that activity is
carried out strictly in accordance with the
conditions of the order granting Environmental
Clearance, this Judgment, Notification of 2006
and other laws in force.
3. The distances in respect of buffer zone
specified in this judgment shall be made
applicable to all the projects and all the
Authorities concerned are directed to
incorporate such conditions in the projects to
whom Environmental Clearance and other
permissions are now granted not only around
Belandur Lake, Rajkulewas, Agara Lake, but
also all other Lakes/wetlands in the city of
Bengluru.
4. We hereby direct the State of Karnataka
to submit a proposal to the MoEF for
35
demarcating wetlands in terms of Wetland
Rules 2010 as revised from time to time. Such
proposal shall be submitted by the State
within four weeks from today and the MoEF
shall consider the same in accordance with law
and grant its approval or otherwise within four
weeks thereafter. After such approval is
granted by MoEF, the State would issue
notification notifying such areas immediately
thereafter in accordance with Rules and law.
5. Both the Respondents Nos. 9 and 10
shall ensure that debris or any construction
material that has been dumped into the
Rajkulewas, or on their Banks and on the
buffer zone of wetlands should be removed
within four weeks from today. In the event they
fail to do so, the same shall be removed by the
Lake Development Authority along with the
State Administration and recover charges
thereof from the said Respondents.
6. There is a serious discrepancy even in
regard to the measurement of land as far as
Respondent No. 9 is concerned. Admittedly the
Respondent has been allotted and is in
possession of land admeasuring 63.94 acres,
though Environmental Clearance has been
36
granted for 2,92,636.03 Sq. Meters which is
equivalent to 72.22 acres. For this reason
alone, Environmental Clearance cannot be
given effect to. While issuing the amended
Environmental Clearance, SEIAA Karnataka
shall take into consideration all these aspects
and, if necessary, would require Respondent
No. 9 to submit a fresh layout plant and the
entire project may be revised in accordance
with law.
7. Both the Respondents (Project
Proponents) shall submit an appropriate plan
in view of the conditions imposed in this
judgment and the amended Environmental
Clearance that would be issued.
8. The amount of environmental
compensation will be deposited prior to
issuance of amended Environmental
Clearance.
With the above directions, the Original
Application No. 222 of 2014 and Misc.
Applications Nos. 596/2016 and 603/2016 are
finally disposed of while leaving the parties to
bear their own costs."
22. Appearing for the appellants in C.A. No.5016 of 2016, Shri
Mukul Rohatgi, learned senior counsel, has submitted that the
37
State Government in exercise of the power conferred under the
Karnataka Industrial Areas Development Act (for short 'KIAD Act')
declared the land in question as an industrial area. Thereafter, the
land in question has been acquired by the State Government in the
year 2004. Following the acquisition, on 28.06.2007, the land was
allotted to the appellant by the KIADB. The SEIAA granted
environmental clearance which was followed by public notice
concerning clearance on 14.03.2012. Neither the allotment of land
nor the environmental clearance was challenged before the
Tribunal. Thus, none of the statutory decisions or processes, are
the cause of action for the purpose of the application. The
averments made in the original application does not satisfy or meet
the requirements of Section 14(1) and (3) of the NGT Act and the
original application does not spell out the cause of action relevant
for the purpose of said provision. Since the statutory processes and
clearances could not have been challenged for being hit by Section
14(3), the construction activities which were the alleged cause of
action could not have been challenged. Therefore, the Tribunal
ought to have held that the application was not maintainable.
38
23. Further the application is barred by limitation. Though
environmental clearance was granted on 17.02.2012 and it was
published in two leading newspapers on 12.03.2012 and
14.03.2012, modified plan was approved by the KIADB on
30.08.2012, the application ought to have been filed within six
months from the date on which cause of action for the dispute first
arose in terms of Section 14 of the NGT Act. The present
application has been filed in March, 2014 which was much beyond
the prescribed period of limitation. No application seeking
condonation of delay has been filed accompanying the
application. Hence, the Tribunal ought to have dismissed the
application on the ground that as it is barred by time.
24. It was also argued that buffer zone laid down by the NGT is
substantially higher as compared to buffer zone which is required to
be maintained as per the Revised Master Plan, 2015 issued on
22.06.2007. This is contrary to the Karnataka Town and Country
Planning Act, 1961 (for short 'the Planning Act').
25. Shri Neeraj Kishan Kaul and Shri R.Venkataramani, learned
senior counsel appearing for the appellants, in this case have also
made similar submissions. It was argued that the direction
39
imposing penalty/compensation is illegal on the ground that the
applicants did not allege that the construction work of the project
has caused environmental wrong. No wrong or injury either to
Bellandur lake water body or to Bellandur lake area, has been
alleged and established. As such, there is no question of any
enquiry relating to imposition of penalty or any compensation.
26. Shri Maninder Singh, learned senior counsel appearing for the
appellants, in C.A. Nos.5016 and 10995 of 2016, while supporting
the submissions made by Shri Rohatgi, has submitted that the
appellant has obtained sanction and approvals for the project from
the competent authorities. It could not start construction despite
grant of all the permissions, including environmental clearance as
early as possible i.e. 30.09.2013. Hence, imposing
penalty/compensation is entirely unsustainable.
27. Learned Advocate General, Shri Udaya Holla, appearing for the
appellant-State of Karnataka in C.A.Nos.4923-4924 of 2017, has
submitted that the State of Karnataka is also aggrieved by the order
of the NGT to the extent of setting aside the buffer zone in respect of
water bodies and drains specified in the Revised Master Plan, 2015,
and enlargement of the buffer zone in respect of lakes and
40
Rajakaluves. It is also aggrieved by the order of the NGT directing
the authorities to demolish all the offending constructions
raised/built in the buffer zone, which will result in demolition of
95% of the buildings in Bengaluru. It is submitted that the Revised
Master Plan is statutory in nature and NGT has no power,
competence or jurisdiction to consider the validity or vires of any
statutory provision/regulation. Therefore, the order of the NGT to
that extent is liable to be set aside.
28. Learned senior counsel appearing for the appellants in other
cases, have also supported the arguments of the learned Advocate
General. It was contended that the Revised Master Plan provides
for a 30 meters buffer zone around the lakes and a buffer zone of 50
meters, 25 meters and 15 meters from the primary, secondary and
tertiary drains, respectively to be measured from the centre of the
drain. Vide the impugned judgment, the NGT has revised these
buffer zones and has directed that the buffer zone be maintained for
75 meters around the lake and 50, 35 and 25 meters respectively
from the primary, secondary and tertiary drain, respectively.
Variation of buffer zone, as directed by the NGT is without any legal
and scientific basis and has the effect of amending the Revised
41
Master Plan, 2015, without there being any challenge to the same
or any relief sought with respect to the said Revised Master Plan.
29. On the other hand, Shri Sajan Poovayya, learned senior
counsel, appearing for the applicants, has fairly submitted that the
applications were filed only against the appellants in C.A Nos. 5016
of 2016 and 8002-8003 of 2016 (respondent Nos. 9 & 10). He has
no objection to set aside the order in so far as the appellants in
other appeals including the State of Karnataka are concerned. He
has also no objection to set aside the general conditions and
directions of the NGT in paragraph (1) of the order dated
04.05.2016 except the directions issued against respondent Nos. 9
and 10. In view of the above, it is not necessary to examine the
contentions of the learned Advocate General in Civil Appeal Nos.
4923-4924 of 2017. It is also not necessary to consider the
contentions urged in the other civil appeals except the appeals filed
by respondents Nos. 9 and 10.
30. Shri Poovayya has strongly opposed the submissions made by
the learned senior counsel appearing for the appellants in C.A. No.
5016 of 2016 and C.A. Nos. 8002-8003 of 2016. It is submitted
that the Tribunal is a specialized body for effective and expeditious
42
disposal of cases relating to environmental protection and
conservation of forests and other natural resources including
enforcement of any legal right relating to environment. The
jurisdiction of the Tribunal is provided under Sections 14, 15 and
16 of the NGT Act. Section 14 provides for the jurisdiction over all
civil cases where a substantial question relating to environment is
involved. However, such question should arise out of
implementation of the enactments specified in Schedule I. The
Tribunal has the jurisdiction under Section 15(1)(a) of the NGT Act
to provide relief and compensation to the victims of pollution and
other environmental damage arising under the enactments specified
in Schedule I. Under Sections 15(1)(b) and 15(1)(c), the Tribunal
can provide for restitution of property damaged and for restitution
of the environment for such area or areas, as the Tribunal may
think fit. Sections 15(1)(b) and 15(1)(c) have not been made
relatable to enactment specified in Schedule I of the Act. Section
15(1)(c) is an entire island of power and jurisdiction read with
Section 21 of the Act. He submits that whenever ecology is being
compromised and jeopardized, the Tribunal can apply Section 20
for taking restorative measures in the interest of environment. The
43
limitation provided in Section 14 is period of six months from the
date on which cause of action first arose whereas in Section 15 it is
five years. Therefore, the petition is not barred by time.
31. He has further submitted that the provisions of Section 33
shall have the effect notwithstanding anything inconsistent
contained in any other law for the time being in force. This gives
the Tribunal overriding powers over anything inconsistently
contained in KIAD Act, Planning Act, Revised Master Plan of
Bangalore, 2015 and Karnataka Municipal Corporation Act, 1976
(for short 'KMC Act'). Therefore, the Tribunal while providing for
restoration of environment in an area can specify buffer zone
around specific lakes and water bodies in contravention with zoning
regulation.
32. Regarding limitation, he has submitted that the application
filed by respondents 1 to 3 was not an application simplicitor under
Section 14 of the Act. It was an application where a specific prayer
has been made with reference to Lake Development Authority's
report dated 12.06.2013 and the Ministry of Environment Forest
and Climate Change Monitoring Committee report dated
14.08.2013 for restoration of ecologically sensitive land and for
44
maintaining sensitive area in its natural condition so that ecological
balance of the area is not disturbed. Therefore, the petition was
under Section 15 of the Act and it can be filed within five years from
the date on which the cause for such compensation or relief first
arose.
33. It was further submitted that right to appeal under Section 22
is not a vested right unless provided by statute. Exercise of
Appellate Jurisdiction without the fulfillment of statutory mandate
would be without jurisdiction. Section 22 of the Act provides for an
appeal on the ground specified in Section 100 of the Code of Civil
Procedure, 1908 (for short 'the CPC'). Under Section 100 of the
CPC, an appeal can be filed only on the ground that the case
involves a substantial question of law as may be framed by the
Appellate Court. In the instant case, the appeal does not involve
any substantial question of law hence it has to be dismissed in
limine. He has taken us through various materials placed on record
in order to substantiate that the direction passed and penalty
imposed by the Tribunal upon to project proponents are
sustainable. He prays for dismissal of the appeals.
45
34. We have carefully considered the submissions of the learned
counsel of the parties and perused the materials placed on record.
35. Before considering the other contentions of the learned
counsel for the parties, let us first consider the scope of enquiry in
appeals filed under Section 22, which is as under:
"22. Appeal to Supreme Court.- Any person
aggrieved by any award, decision or order of the
tribunal, may, file an appeal to the Supreme
Court, within ninety days from the date of
communication of the award, decision or order of
the Tribunal, to him, on any one or more of the
grounds specified in section 100 of the Code of
Civil Procedure, 1908 (5 of 1908):
Provided that the Supreme Court may,
entertain any appeal after the expiry of ninety
days, if it is satisfied that the appellant was
prevented by sufficience cause from preferring
the appeal."
36. It is settled that there is no vested right of appeal unless the
statute so provides. Further, if a statute provides for a condition
subject to which the appropriate Appellate Court can exercise
jurisdiction, the Court is under an obligation to satisfy itself
46
whether the condition prescribed is fulfilled. Exercise of appellate
jurisdiction without the fulfillment of statutory mandate would be
without jurisdiction. Therefore, the right of appeal provided under
Section 22 is to be read subject to the conditions provided therein.
37. Section 22 provides for an appeal to the Supreme Court on the
grounds specified in Section 100 of the CPC. Under Section 100
CPC, an appeal can be filed only on the ground that the case
involves a substantial question of law as may be framed by the
Appellate Court. The scope of appeal under Section 22, therefore, is
restricted to substantial question of law arising from the judgment
of the Tribunal. The test to determine whether the question is
substantial question of law or not was laid down by a Constitution
Bench of this Court in Sir Chunilal V. Mehta and Sons, Ltd. v.
Century Spinning and Manufacturing, 1962 Supp. (3) SCR 549.
This Court has laid down the test as under:
"The proper test for determining whether a question of law raised in the case is substantial would, in our opinion, be whether it is of general public importance or whether it directly and substantially affects the rights of the parties and if so whether it is either an open question in the sense that it is not finally settled by this Court or by the Privy Council or by the Federal Court or is not free from difficulty or calls for discussion of alternative
47
views. If the question is settled by the highest court or the general principles to be applied in determining the question are well settled and there is a mere question of applying those principles or that the plea raised is palpably absurd the question would not be a substantial question of law."
38. It is equally settled that merely because the remedy of appeal
is provided against the decision of the Tribunal on a substantial
question of law alone, that does not ipso facto permit the appellants
to agitate their appeal to seek re-appreciation of the factual matrix
of the entire matter. The appellants cannot seek to re-argue their
entire case to seek wholesale re-appreciation of evidence and the
factual matrix that has been considered by the Tribunal is ex facie
impermissible under Section 22. There cannot be fresh appreciation
or re-appreciation of facts and evidence in a statutory appeal under
this provision.
39. The first question raised by the learned counsel is in relation
to the maintainability of the application before the Tribunal.
40. The Tribunal has been established under a constitutional
mandate provided in Schedule VII List I Entry 13 of the
Constitution of India, to implement the decision taken at the United
Nations Conference on Environment and Development. The
48
Tribunal is a specialized judicial body for effective and expeditious
disposal of cases relating to environmental protection and
conservation of forests and other natural resources including
enforcement of any legal right relating to environment. The right to
healthy environment has been construed as a part of the right to
life under Article 21 by way of judicial pronouncements. Therefore,
the Tribunal has special jurisdiction for enforcement of
environmental rights.
41. The jurisdiction of the Tribunal is provided under Sections 14,
15 and 16 of the Act. Section 14 provides the jurisdiction over all
civil cases where a substantial question relating to environment
(including enforcement of any legal right relating to environment) is
involved. However, such question should arise out of
implementation of the enactments specified in Schedule I.
42. The Tribunal has also jurisdiction under Section 15(1)(a) of the
Act to provide relief and compensation to the victims of pollution
and other environmental damage arising under the enactments
specified in Schedule I. Further, under Section 15(1)(b) and 15(1)(c)
the Tribunal can provide for restitution of property damaged and for
restitution of the environment for such area or areas as the
49
Tribunal may think fit. It is noteworthy that Section 15(1)(b) & (c)
have not been made relatable to Schedule I enactments of the Act.
Rightly so, this grants a glimpse into the wide range of powers that
the Tribunal has been cloaked with respect to restoration of the
environment.
43. Section 15(1)(c) of the Act is an entire island of power and
jurisdiction read with Section 20 of the Act. The principles of
sustainable development, precautionary principle and polluter pays,
propounded by this Court by way of multiple judicial
pronouncements, have now been embedded as a bedrock of
environmental jurisprudence under the NGT Act. Therefore,
wherever the environment and ecology are being compromised and
jeopardized, the Tribunal can apply Section 20 for taking restorative
measures in the interest of the environment.
44. The NGT Act being a beneficial legislation, the power bestowed
upon the Tribunal would not be read narrowly. An interpretation
which furthers the interests of environment must be given a
broader reading. (See Kishsore Lal v. Chairman, Employees' State
Insurance Corpn. (2007) 4 SCC 579, para 17). The existence of the
Tribunal without its broad restorative powers under Section 15(1)(c)
50
read with Section 20 of the Act, would render it ineffective and
toothless, and shall betray the legislative intent in setting up a
specialized Tribunal specifically to address environmental concerns.
The Tribunal, specially constituted with Judicial Members as well
as with Experts in the field of environment, has a legal obligation to
provide for preventive and restorative measures in the interest of
the environment.
45. Section 15 of the Act provides power & jurisdiction,
independent of Section 14 thereof. Further, Section 14(3)
juxtaposed with Section 15(3) of the Act, are separate provisions for
filing distinct applications before the Tribunal with distinct periods
of limitation, thereby amply demonstrating that jurisdiction of the
Tribunal flows from these Sections (i.e. Sections 14 and 15 of the
Act) independently. The limitation provided in Section 14 is a
period of 6 months from the date on which the cause of action first
arose and whereas in Section 15 it is 5 years. Therefore, the
legislative intent is clear to keep Section 14 and 15 as self contained
jurisdictions.
46. Further, Section 18 of the Act recognizes the right to file
applications each under Sections 14 as well as 15. Therefore, it
51
cannot be argued that Section 14 provides jurisdiction to the
Tribunal while Section 15 merely supplements the same with
powers. As stated supra. the typical nature of the Tribunal, its
breadth of powers as provided under the statutory provisions of the
Act as well as the Scheduled enactments, cumulatively, leaves no
manner of doubt that the only tenable interpretation to these
provisions would be to read the provisions broadly in favour of
cloaking the Tribunal with effective authority. An interpretation
that is in favour of conferring jurisdiction should be preferred
rather than one taking away jurisdiction.
47. Section 33 of the Act provides an overriding effect to the
provisions of the Act over anything inconsistent contained in any
other law or in any instrument having effect by virtue of law other
than this Act. This gives the Tribunal overriding powers over
anything inconsistent contained in the KIAD Act, Planning Act,
Karnataka Municipal Corporations Act, 1976 (“KMC Act”); and the
Revised Master Plan of Bengaluru, 2015 (“RMP”). A Central
legislation enacted under Entry 13 of List I Schedule VII of the
Constitution of India will have the overriding effect over State
legislations. The corollary is that the Tribunal while providing for
52
restoration of environment in an area, can specify buffer zones
around specific lakes & water bodies in contradiction with zoning
regulations under these statutes or the RMP.
48. The second question raised by the appellants is that the
petition is barred by time. According to appellants, environmental
clearance was granted to the respondent No. 9 on 17.02.2012 for
which notice was published in the leading newspaper on
12.03.2012 and 14.03.2012. Modified building plan was approved
on 30.08.2012, which was followed up to 10.08.2014. Similar
events had taken place in regard to the project of respondent No. 10
who had been granted environmental clearance on 30.09.2013. The
application had to be filed within a period of six months from the
date on which cause of action for such dispute has first arisen in
terms of Section 14 of the NGT Act. Admittedly, the present
application has been filed in March, 2014 and according to them, it
is much beyond the prescribed period of limitation. Also, there is
no application for condonation of delay accompanying the main
application. Therefore, the Tribunal will not have jurisdiction to
condone the delay.
53
49. The OA No. 222 of 2014 was not an application simpliciter
under Section 14 of the Act. It was an application where a specific
prayer has been made with reference to Lake Development
Authority's ("LDA") Report dated 12.06.2013 and the Ministry of
Environment, Forest and Climate Change ("MoEF") Monitoring
Committee Report dated 14.08.2013 for restoration of ecologically
sensitive land and for maintaining the sensitive in its natural
condition so that the ecological balance of the area is not disturbed.
It is clear from the documentary evidence supported by data, that
the project proponents have committed breaches and the
implementation of the project is bound to have serious adverse
impact on the ecology, hydrology and the environment in the
catchment area of Bellandur Lake. The environmental degradation
as established from the documents would give rise to an
independent cause of action. Therefore, this was a petition under
Section 15 of the Act and thus it could be filed within 5 years from
the date on which the cause for such compensation or relief first
arose.
50. In fact, in the original application before the Tribunal there
was no mention of the provision under which it was being filed. It is
54
well settled principle of law that non-mention of or erroneous
mention of the provision of law would not be of any relevance, if the
Court had the requisite jurisdiction to pass an order. It would be a
mere irregularity and would not vitiate the application or the
judicial order of the Tribunal.
51. Shri R. Venkataramani, learned senior counsel, appearing for
the appellant in CA No.5016 of 2016 has submitted that the
constructions had not commenced before the grant of environment
clearance. The inspection report dated 11.01.2012 of the Chairman
of the KSPCB observes that "no construction" had commenced on
the date of inspection. This report cannot be overlooked on the
basis of some dumping of debris which could not be attributed to
the appellant. He has pointed out the report of the Committee
appointed by the Tribunal in the month of August 2015, wherein it
was stated that "it started construction after obtaining clearance".
In this regard he has also taken us through various documents
placed on record and submits that there is absolutely no
justification in imposing monitoring penalty/compensation without
assessment of impact.
55
52. The Tribunal has pointed out on the basis of the Committee
report of August 2015, that the appellant had encroached 3 acres
10 guntas of Bellandur Lake and a boundary wall has been raised
around the said land. The Tribunal has also found that the project
proponents have violated the Master Plan. They have not obtained
the mandatory clearance from the Sensitive Zone Committee
constituted by the Government of Karnataka. It is also clear from
the materials on record that there are several other violations by the
project proponents. The Tribunal has discussed all these issues
from para 52 onwards. It is also clear from the materials on record
that there is a definite possibility of environment, ecology, lakes,
and wetland being adversely affected by these projects. That is why,
the Tribunal has observed as under:
"72. In light of the above scope of the project
and records before the Tribunal and the
defaults on the part of the Project Proponents,
the cumulative adverse effects of the activities
undertaken by the respondents before us can
be summed up as under:
1) The construction of both the projects had
started prior to the grant to Environmental
Clearance.
56
2) The EIA Notification of 2006 requires that
without grant of Environmental Clearance, no
project can commence its activity. This
restriction applies not only to
operationalization of the project but even for
the purposes of establishment.
3) Revenue Map images shows multiple
Rajakaluves flowing through the project(s) in
question. The images further show
encroachment on Rajakaluves.
4) Digital images of the land available on
Google satellite images showing encroachment
on two major Rajakaluves.
5) Google Satellite images retrieved from
Google archives clearly reflect two distinct
features. Firstly, change in the wetland area
between the period of 13th November, 2000
and 23rd November, 2010. Secondly, it reveals
the excavation work carried out by Respondent
Nos. 9 and 10 commenced prior to obtaining
Environmental Clearance.
6) Restriction in regard to extraction of ground
water was not strictly complied with as
permission of Central Ground Water Authority
was not obtained before construction.
57
7) The conditions with regard to the natural
slopping pattern of the project site to remain
unaltered and natural hydrology of the area to
be maintained as it is, to ensure natural flow
of storm water as well as in relation to Lakes
and other water bodies within and/or at the
vicinity of the project area to be protected and
conserved: The inspection report by the MoEF
clearly notes that condition nos. (xxxix) and
(xl) in the Environmental Clearance of
respondent no. 9 cannot be complied with as it
will necessarily result in some alteration of the
natural slopping pattern of the project site and
the natural hydrology of the area. It noted that
the project area is located in the catchment
area of the Bellandur Lake and the project
authorities have informed that they will take
all precautionary measures to ensure that the
lake will not be affected by project activities
either during construction or operation phase."
53. In paragraph 81, the Tribunal has observed as under:
"81. …………Another very important
aspect which cannot be overlooked by the
Tribunal is with regard to the respondent
nos. 9 & 10 carrying on their project activity
58
fully knowing that they were incapable of or
it was not possible for them to comply with
condition no. xxxix and xl (or alike
conditions) in the order granting the
Environmental Clearance. This has even
been noticed by the MoEF in its monitoring
report dated 14th August, 2013. These
respondents never applied for variation or
amendment of these conditions and
continued with their construction activities.
This renders these respondents entirely
liable for environmental and ecological
damage and the restoration and restitution
thereof."
54. In our view, the findings arrived at by the Tribunal are not
only based on the documents that were available on record but also
on the pleadings that were made by the parties buttressed by the
Committee's report and the inspection note of the Expert Members.
Therefore, the directions passed and the penalty imposed by the
Tribunal on both project proponents are valid and sustainable and
do not suffer from any perversity.
55. We are also of the view that it is impermissible for the
appellants to seek a factual review through the methodology of re-
59
appreciation of factual matrix by this Court under Section 22 of the
NGT Act.
56. Shri R.Venkataramani, learned senior counsel has also raised
a subsidiary issue relating to res judicata. According to him,
respondent Nos. 12 and 13 filed Writ Petition Nos.3656-57/2013
seeking similar reliefs in a representative capacity. The issues
raised therein are same as those canvassed in the application
before the Tribunal. The reliefs sought for are essentially the same.
Hence, the applications are barred by the principle of res judicata.
57. The Tribunal has answered this issue in paragraphs 47 to 51
of the order. There was no dispute in so far as filing of the writ
petitions is concerned. However, the parties are not common nor
the issues in application and the writ petitions are directly and
substantially the same. After examination of the pleadings, the
Tribunal has recorded a finding of fact that there is no
commonality of a cause of action or likelihood of a conflict between
the judgments. The prayers and the geneses of the respective
proceedings are entirely distinct and different in their scope and
relief. The issues before the Tribunal would essentially relate to
environment ecology and its restoration while the proceedings
60
before the High Court relate to entirely different issues with
acquisition of land, its allotment and transfer to the third party.
These issues in both the proceedings are neither substantial nor
materially identical.
58. After elaborately considering this question, the Tribunal has
concluded as under:
"51.….For these reasons, we find no merit in
this contention of respondent Nos. 9 and
10. The purpose of the doctrine of res
judicata is to provide finality and
conclusiveness to the judicial decisions as
well as to avoid multiplicity of litigation. In
the present case, the question of re-
agitating the issues or agitating similar
issues in two different proceedings does not
arise. The ambit and scope of jurisdiction is
clearly decipherable. The jurisdictions of the
Hon’ble High Court of Karnataka and this
Tribunal are operating in distinct fields and
have no commonality in so far as the issues
which are raised directly and substantially
in these petitions, as well as the reliefs that
have been prayed for before the Hon’ble
High Court and the Tribunal are concerned.
61
There is no commonality in parties before
the Tribunal and the High Court. The ‘cause
of action’ in both proceedings is different
and distinct. The matters substantially and
materially in issue in one proceedings are
not the same in the other proceeding. There
is hardly any likelihood of conflicting
judgments being pronounced by the
Tribunal on the one hand and the High
Court on the other. Therefore, we are of the
considered view that the present
applications are neither hit by the principles
of res judicata nor constructive res judicata.
We also hold that culmination of
proceedings before the Tribunal into a final
judgment would not offend the principle of
‘judicial propriety’, because of the Writ
Petitions pending before the Hon’ble High
Court of Karnataka."
59. We do not find any error in the aforesaid conclusion of the
Tribunal. We are of the view that the Tribunal was justified in
holding that the objections taken by the respondent Nos. 9 and 10
do not satisfy the basic ingredients to attract the application of res
judicata or constructive res judicata.
62
60. The State of Karnataka is aggrieved by the following offending
portion of the order dated 04.05.2016:
"1. In view of our discussion in the main
Judgment, we are of the considered view
that the fixation of distance from water
bodies (lakes and Rajkalewas) suffers from
the inbuilt contradiction, legal infirmity and
is without any scientific justification. The
RMP – 2015 provides 50m from middle of
the Rajkalewas as buffer zone in the case of
primary Rajkalewas, 25m in the case of
secondary Rajkulewas and 15m in the
tertiary Rajkulewas in contradiction to the
30m in the case of lake which is certainly
much bigger water body and its utility as a
water body/wetland is well known certainly
part of wet land. Thus, we direct that the
distance in the case of Respondents Nos. 9
and 10 from Rajkulewas, Waterbodies and
wetlands shall be maintained as below:-
(i) In the case of Lakes, 75m from the
periphery of water body to be maintained as
green belt and buffer zone for all the
existing water bodies i.e. lakes/wetlands.
63
(ii) 50m from the edge of the primary
Rajkulewas.
(iii) 35m from the edges in the case of
secondary Rajkulewas
(iv) 25m from the edges in the case of
tertiary Rajkulewas
This buffer/green zone would be
treated as no construction zone for all intent
and purposes. This is absolutely essential
for the purposes of sustainable development
particularly keeping in mind the ecology and
environment of the areas in question.
All the offending constructions raised
by Respondents Nos. 9 and 10 of any kind
including boundary wall shall be
demolished which falls within such areas.
Wherever necessary dredging operations are
required, the same should be carried out to
restore the original capacity of the water
spread area and/or wetlands. Not only the
existing construction would be removed but
also none of these Respondents - Project
Proponent would be permitted to raise any
construction in this zone.
All authorities particularly Lake
development Authority shall carry out this
64
operation in respect of all the water bodies/
lakes of Bangalore."
61. We have already noticed that Shri Poovayya has no objection
to set aside the aforesaid impugned portion of the order in so far as
the appellants in all the appeals except the appeals filed by
respondent Nos.9 and 10. The aforesaid portion of the order
contains not only general directions but also certain directions
against respondent Nos. 9 and 10. Therefore, only that portion of
the order which does not pertain to respondent Nos. 9 and 10 needs
to be quashed.
62. In the light of the above discussion, we pass the following
order:
i) Civil Appeal No. 5016 of 2016 and Civil Appeal
Nos. 8002-8003 of 2016 filed by the
appellants/respondent nos. 9 and 10 are
hereby dismissed. The impugned judgment
and order in so far as appellants/respondent
Nos. 9 and 10 are concerned is sustained.
ii) All the other appeals are hereby allowed and
the direction/condition No. (1) in the order
65
dated 4.5.2016 is hereby set aside except the
direction issued against respondent Nos. 9 and
10.
63. There will be no order as to costs.
…………………………………J.
(A.K. SIKRI) …………………………………J.
(S. ABDUL NAZEER)
…………………………………J. New Delhi; (M.R. SHAH) March 5, 2019.