MAHARASHTRA STATE ELECT.DISTRN.CO.LTD. Vs APPELLATE AUTHORITY .
Bench: HON'BLE MR. JUSTICE R.K. AGRAWAL, HON'BLE MR. JUSTICE ABHAY MANOHAR SAPRE
Judgment by: HON'BLE MR. JUSTICE ABHAY MANOHAR SAPRE
Case number: C.A. No.-003370-003370 / 2007
Diary number: 18439 / 2007
Advocates: A. S. BHASME Vs
ANAGHA S. DESAI
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.3370 OF 2007
Maharashtra State Electricity Distribution Co.Ltd. ….Appellant(s)
VERSUS
The Appellate Authority & Anr. …Respondent(s)
WITH
Civil Appeal Nos. 3377-3381/2007, 3376/2007 and 3371-3375/2007
J U D G M E N T
Abhay Manohar Sapre, J.
1) These appeals are directed against the
common final judgment and order dated 04.05.2007
passed by the High Court of Judicature at Bombay,
Nagpur Bench, Nagpur in Writ Petition Nos.5858 of
2005, 2821, 2705, 2706/2006, 6219/2005,
721/2006, 3737/2005, 3935/2005, 1386, 1389,
1
1586 & 2060/2006 whereby the High Court
dismissed the writ petitions filed by the appellant
herein and partly allowed the writ petitions filed by
respondent-Consumer.
2) The controversy involved in these appeals is
short as it would be clear from the facts mentioned
hereinbelow.
3) For the sake of convenience, the facts
pertaining to C.A. No.3370 of 2007 were taken into
account. Respondent No. 2 is running Oil Mill
having cotton seeds crushing activity at Akola
(Maharashtra). They are consumers of electricity,
which is supplied to them by the State Electricity
Board - the appellant herein (hereinafter referred to
as “the Board”)
4) On 17.03.2003, the sleuths of the Board
visited respondent No.2’s factory and replaced Meter
No.356, installed in the factory with a new Meter
bearing No. MSE 04821. On 02.08.2003, the
2
sleuths again visited the factory and on inspection
found some tampering with the Meter seals. This led
to making of provisional assessment by the
appellant under Section 126 of the Electricity Act,
2003 (for short “the Act”) for the unauthorized use
of electricity. The Board accordingly sent a
provisional bill to respondent No.2 followed by
revised provisional bill dated 16.08.2003 for
Rs.21,38,660/-.
5) Respondent No.2, felt aggrieved, filed a writ
petition and questioned the legality and correctness
of the provisional bill. During the pendency of the
writ petition, the final assessment order was issued
to respondent No.2 on 24.11.2003. However, the
High Court quashed and set aside that order and
remanded the matter to the Authority for giving an
opportunity to respondent No.2 while passing the
final order. It was done and accordingly final order
dated 29-30.04.2004 demanding a sum of
3
Rs.62,52,632/- was passed by the Authority against
respondent No.2.
6) The aforesaid order was challenged by
respondent No.2 under Section 127 of the Act before
the Appellate Authority. The Appellate Authority by
order dated 15.04.2005 disposed of the appeal
giving rise to filing of the writ petition by the Board
as also by the consumer (respondent No.2) in the
High Court of Bombay, Nagpur Bench. The other
similarly situated consumers also filed writ petitions
before the High Court.
7) By impugned common judgment, the High
Court dismissed the writ petitions filed by the Board
whereas partly allowed the writ petitions filed by the
consumers. While setting aside the Appellate Order,
the High Court remanded the case to the Assessing
Authority and directed the parties to abide by the
provisions of Section 126/127 of the Act.
4
8) It is against this judgment, the Board alone
has felt aggrieved and filed these appeals by way of
special leave in this Court.
9) Heard Mr. A.S. Bhasme, learned counsel for
the appellant and Ms. V. Mohana, learned senior
counsel for the respondents.
10) Having heard learned counsel for the parties
and on perusal of the record of the case, we do not
consider it necessary to examine the legal questions
which, according to the learned counsel for the
Board, arise in these appeals and leave them open
for being decided in appropriate case, if they really
arise and found necessary to decide the lis.
11) Leave aside the legal questions, we find
otherwise no reason to interfere in the impugned
judgment of the High Court which, in our opinion,
is sustainable on facts.
12) Suffice it to say, the High Court while allowing
the consumers’ writ petitions and, in consequence,
5
setting aside of the Appellate Order passed under
Section 127 of the Act by the Appellate Authority
rightly remanded the case to the Assessing
Authority for making provisional assessment under
Section 126 of the Act and then to take recourse
under Section 127 of the Act for filing appeal, if
need arises. We do not find any reason to disturb
these directions which, in our opinion, are in
conformity with the scheme of the Act.
13) So far as the applicability of the provisions of
the new Electricity Act, 2003 to the case at hand is
concerned, though some doubts were raised about
its applicability but, in our opinion, it has no
substance. In our opinion, the Act 2003 does apply
to the facts of this case because the Act 2003 came
into force on 10.06.2003 whereas the inspection of
the Meter installed in respondent No.2's factory
premises was made by the sleuths of the Board on
02.08.2003.
6
14) It is, therefore, clear that the Board made an
inspection of the Meter after the Act 2003 came into
force. The cause of action, therefore, accrued to the
Board after the Act 2003 came into force and,
therefore, the case of respondent No.2 was required
to be dealt with in accordance with the procedure
prescribed under the Act of 2003.
15) Since the action was taken by the Board
against respondent No.2 (consumer) under Section
126 of the Act by raising the provisional/final bill
and, therefore, respondent No.2 was well within
their right to file an appeal against such demand
under Section 127 of the Act before the Appellate
Authority.
16) We cannot, therefore, accept the submission of
the learned counsel for the Board that respondent
No.2 had no right of appeal under Section 127 of
the Act to challenge the order/demand raised under
Section 126 of the Act. In other words, respondent
7
No.2 had right of appeal under Section 127 of the
Act to challenge the order passed under Section 126
of the Act.
17) Indeed, once the Act is held applicable to the
controversy in question, a fortiori, all the provisions
of the Act would then be applicable to the case
which would obviously include a provision which
provides a right of appeal to the Appellate Authority.
18) In the scheme of the Act, we find that Section
126 of the Act deals with assessment of electricity
charges payable by such person (consumer) for
unauthorized use of electricity whereas Section 135
deals with the cases of theft of electricity.
19) In other words, once the Board detects the
case of unauthorized use of electricity by any
consumer, in such event, the Board gets a cause of
action to proceed against such person/consumer
under Section 126 or/and 135 under the Act. Both
Sections 126 and 135 are independent in all
8
respects and provide different kind of liability and
consequences. One involves monetary liability
(Section 126) whereas the other involves criminal
liability (Section 135).
20) The Board is, therefore, at liberty to take
recourse to the provisions of Section 126 or/and
135 of the Act against such person/consumer as
provided therein in accordance with law.
21) In these circumstances, if the Board initiates
any action against any person/consumer, then such
action must be brought to its logical end in
accordance with the procedure prescribed under the
Act after affording an opportunity to such
person/consumer.
22) In view of the foregoing discussion and subject
to the observations, we find no merit in the appeals,
which fail and are accordingly dismissed.
23) As a consequence to the dismissal of the
appeals, the authorities are directed to comply with
9
the directions of the High Court and pass
consequential order under Section 126 of the Act in
accordance with law in the case of consumers
(respondents) within three months from the date of
this order.
………...................................J.
[R.K. AGRAWAL]
…...……..................................J.
[ABHAY MANOHAR SAPRE]
New Delhi; February 15, 2018
10