M/S. VEDANTA LIMITED (FORMERLY KNOWN AS SESA STERLITE LIMITED AND SUCCESSOR IN INTEREST OF ERSTWHILE Vs M/S EMIRATES TRADING AGENCY LLC
Bench: RANJAN GOGOI,NAVIN SINHA
Case number: C.A. No.-005448-005449 / 2017
Diary number: 33566 / 2015
Advocates: P. S. SUDHEER Vs
Page 1
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs. 5448-5449 OF 2017 (Arising out of S.L.P.(C)Nos.34084-34085 of 2015)
M/s. Vedanta Limited (Formerly known as Sesa Sterlite Limited and successor in interest of erstwhile Sterlite Industries (India) Ltd.) ..........APPELLANT(s)
Versus
M/s. Emirates Trading Agency LLC ......RESPONDENT(s)
JUDGMENT
NAVIN SINHA, J.
Leave granted.
2. The Respondent's Suit for breach of contract and damages was
decreed on 16.04.2013 by the Principal District Court, Thoothukudi in
Original Suit No. 73 of 2009 for a sum of Rs.5,25,55,460/- with
interest @ 8% from the date of the plaint till realisation. First Appeal
by the Appellant was dismissed by the High Court on 04.02.2014. In
Special Leave Petition (Civil) Nos.12687–12688 of 2014 preferred
1
Page 2
against the same, liberty was granted on 12.5.2014 to approach the
High Court in the review jurisdiction, on the issue whether the
agreement dated 26.10.2007 between the parties constituted a
concluded contract or matters rested at the stage of a proposal and a
counter proposal only. Liberty was further granted to approach this
Court again, if aggrieved. Review application No. 160 of 2014 was
dismissed by the High Court on 09.07.2015. Thus, the present
appeal.
3. Sri C.A. Sundaram, learned Senior Counsel appearing for the
Appellant, submitted that the agreement dated 26.10.2007 was a
draft proposal from the Respondent regarding supply of phosphoric
acid by the Appellant in a specified duration. The Appellant made a
counter proposal to the Respondent; both with regard to the quantity
of supplies and the duration of supply. No concluded contract had
arisen between the parties in absence of any final agreement having
been executed. The draft agreement was never signed, stamped and
returned by the Appellant, in confirmation, as asked for by the
Respondent. The defence was taken specifically in the written
statement. The Trial Court and the First Appellate Court, without
proper appreciation of the draft agreement, arrived at a presumptive
2
Page 3
conclusion based on the exchange of correspondence preceding the
same that it reflected a concluded contract between the parties.
4. This Court on 12.05.2014, after perusal of the agreement dated
26.10.2007, having been satisfied with regard to lack of proper
consideration of the issue, granted liberty to the Appellant for
preferring a review application before the High Court. In the review
application, objections were specifically raised that the draft
agreement dated 26.10.2007 did not constitute a concluded contract,
but was merely a communication of a proposal and a counter
proposal. It was also urged that alterations had been made by the
Appellant; both with regard to the quantity and period of supply.
There was no material on record to demonstrate that any final
agreement was arrived at between the parties thereafter. In absence
of a valid acceptance, no concluded contract had come into being.
5. Unfortunately, the High Court relying on its earlier order dated
04.10.2014 that the correspondence preceding the agreement dated
26.10.2007 reflected that the latter was a concluded contract,
dismissed the review petition without examining the corrections made
in the draft proposal with regard to the quantity of supply and period
of supply, the effect on the same, coupled with the Appellant not
3
Page 4
having signed, stamped and returned the same to the Respondent so
as to evince a concluded contract between the parties.
6. Sri Vijay Hansaria, learned Senior Counsel appearing for the
Respondent, submitted that three Courts having returned concurrent
findings from the exchange of correspondence between the parties
that the agreement dated 26.10.2007 constituted a concluded
contract, interference is not called for. It was on the assurance of the
Appellant to deliver supplies of phosphoric acid, coupled with its
promised back up support in writing, that the Respondent had bid in
response to the international tender published by Bangladesh
Chemical Industries Corporation (hereinafter referred to as 'the
BCIC').
7. The breach of promise by the Appellant to make the promised
supplies had resulted in BCIC forfeiting the performance guarantee of
the Respondent in addition to other pecuniary liabilities imposed. The
Suit was then instituted by the Respondent claiming damages with
interest. In a commercial contract, the course of conduct of the
parties, the exchange of correspondences, are all important
considerations for the conclusion whether there existed a concluded
contract or not. Isolated examination of the agreement dated
4
Page 5
26.10.2007 shall, therefore, not be appropriate so as to warrant
interference with the concurrent findings.
8. The respective submissions on behalf of the parties have been
considered by us. Briefly stated, the BCIC floated an international
tender for supply of phosphoric acid. The Respondent submitted its
bid and was awarded an order for supply of 30,000 MT. The
Appellant had signed a backup support agreement with the
Respondent for supplies in case the tender was awarded to the latter,
and which was furnished by the Respondent to the BCIC in support of
its capacity to deliver supplies. The correspondence between the
Appellant and the Respondent culminated in the latter forwarding a
draft agreement dated 26.10.2007, to the Appellant for
Sale/Purchase contract for 3 x 10,000 MT phosphoric acid for supply
to the BCIC during November and December, 2007. The covering
letter, appended to the draft agreement, required the Appellant to
sign, stamp and return the same to the Respondent in confirmation.
The Appellant, in response, made a counter proposal for supply of 3 x
9500 MT (max) and between the period January to March, 2008 by
incorporating necessary corrections in hand in the draft agreement.
Resultantly, while there was a proposal from the Respondent, the
Appellant made a counter proposal both with regard to the quantity
5
Page 6
and the period of supply. There is no material or evidence placed by
the Respondent that the draft agreement ever assumed the form of a
concluded contract by a meeting of minds both with regard to the
quantity of supplies and the duration for the same, much less was the
agreement signed, stamped and returned by the Appellant to the
Respondent in confirmation.
9. The contract between the Respondent and the Appellant was
independent of the contract between the Respondent and the BCIC.
The Appellant had only offered a backup support to supply phosphoric
acid to the Respondent in case the contract was awarded to the latter.
In the written statement, the Appellant had taken a specific defence
regarding absence of any concluded contract between it and the
Respondent. The Trial Court as well as the First Appellate Court did
not specifically deal with the issue of the draft agreement, the
corrections in the same, existence of a proposal and counter proposal
with regard to quantity and time period for supplies, the absence of
any executed contract by virtue of the Appellant having signed,
stamped and returned the agreement to the Respondent, in
confirmation. On a presumptive reasoning, based on the exchange of
correspondence preceding the draft agreement, the First Appellate
6
Page 7
Court affirmed the finding in the Suit of a concluded contract between
the parties.
10. The Appellant challenged the First Appellate Court’s order dated
04.10.2014 earlier in a special leave petition. On 12.05.2014, this
Court considering the plea for absence of a concluded contract and
after perusal of the draft agreement dated 26.10.2007 containing
corrections, in hand, had observed "that these aspects are not
specifically dealt with by the High Court. In this view of the matter, it
would be more appropriate for the petitioner to approach the High
Court by filing a review petition". Observing that the High Court shall
deal with the aspect on merits, liberty was also granted to challenge
any fresh order along with the impugned orders, if aggrieved.
11. In the review petition, a specific plea was taken that the draft
agreement dated 26.10.2007, Exhibit 8-A, did not constitute a
concluded contract in view of the counter proposal made by the
Appellant, both with regard to the quantity of supply and the period
for the same. Reliance on the correspondence preceding the same
was not sufficient in absence of acceptance by the Appellant of the
proposal made by the Respondent coupled with signing, stamping
and returning of the agreement in confirmation of the same.
7
Page 8
12. The High Court, despite noticing the specific plea of the
Appellant with regard to the absence of a concluded contract between
the parties in view of a counter proposal, much less that the
agreement was never signed, stamped and returned, reiterated the
earlier observations of the First Appellate Court of a concluded
contract between the parties based on exchange of correspondence
preceding the draft agreement, and also on the premise that the
Respondent had submitted its offer to BCIC on the assurance of the
Appellant for backup support if the contract was awarded to the
former. The High Court declined to delve further into the agreement
dated 26.10.2017, holding it to be impermissible in the review
jurisdiction and concluding that the grounds urged were superficial in
nature without any material proof, designed to avoid payment, and
dismissed the review application. The High Court failed to notice that
as recent as 28.01.2008, the Respondent was still awaiting
confirmation of its proposal from the Appellant, and soon thereafter
the performance guarantee was invoked by the BCIC against the
Respondent on 13.04.2008.
13. Section 7 of the Indian Contract Act, 1872 (hereinafter referred
to as 'the Act') provides that in order to convert a proposal into a
8
Page 9
contract, the acceptance must be absolute and unqualified. The
existence of a concluded contract is a sine qua non in a claim for
compensation for loss and damages under Section 73 of the Act
arising out of a breach of contract. If instead of acceptance of a
proposal, a counter proposal is made, no concluded contract comes
into existence.
14. U.P. Rajkiya Nirman Nigam Ltd. v. Indure (P) Ltd., (1996)
2 SCC 667, also related to a proposal and counter proposal. Holding
that no concluded contract had come into existence, the Apex Court
observed as follows :-
"9...As seen, the material alterations in the contract make a world of difference to draw an inference of concluded contract...."
15. The fulcrum of the entire controversy is the draft agreement
dated 26.10.2007 marked Exhibit 8-A, for supply of phosphoric acid
by the Appellant to the Respondent. The proposal of the Respondent,
led to a counter proposal by the appellant. There was no acceptance
of the proposal by the Appellant giving rise to a concluded contract.
The quantity and duration of supply, therefore, remained in the realm
of uncertainty and was never agreed upon so as to give rise to a
concluded contract.
9
Page 10
16. In absence of a concluded contract between the parties having
been established by the Respondent, the claim under Section 73 of
the Act was not maintainable. The impugned orders are, therefore,
held to be unsustainable and are set aside.
17. The appeals are accordingly allowed.
………………………………….J. (Ranjan Gogoi)
……….………………………..J. (Navin Sinha)
New Delhi, April 21, 2017
10