M/S DYNA TECHNOLOGIES PVT.LTD. Vs M/S CROMPTON GREAVES LTD.
Bench: HON'BLE MR. JUSTICE N.V. RAMANA, HON'BLE MR. JUSTICE V. RAMASUBRAMANIAN
Judgment by: HON'BLE MR. JUSTICE N.V. RAMANA
Case number: C.A. No.-002153-002153 / 2010
Diary number: 25684 / 2007
Advocates: DIKSHA RAI Vs
BIJOY KUMAR JAIN
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 2153 OF 2010
M/S. DYNA TECHNOLOGIES PVT. LTD. …APPELLANT(S)
VERSUS M/S. CROMPTON GREAVES LTD. …RESPONDENT(S)
JUDGMENT N. V. RAMANA, J.
1. The question involved herein revolves around the requirement of
reasoned award and the cautionary tale for the parties and
arbitrators to have a clear award, rather than to have an award
which is muddled in form and implied in its content, which
inevitably leads to wastage of time and resources of the parties to
get clarity, and in some cases, frustrate the very reason for going for
an arbitration.
2. This appeal is filed against the final order and judgment dated
27.04.2007, passed by the High Court of Judicature at Madras
whereby the High Court partly allowed the appeal filed by the
respondent and set aside the award of Arbitral Tribunal relating to
1
Reportable
claim no. 2 for payment of compensation for the losses suffered due
to unproductive use of machineries.
3. Brief facts of the case are that a contract was entered into between
DCM Shriram Aqua Foods Limited (hereinafter referred to as ‘DCM’
in short) and M/s. Crompton Greaves Limited (hereinafter referred
to as “CGL” in short) for an aquaculture unit to be set up by such
Principal, namely, DCM. CGL invited tenders for carrying out
certain works for construction of ponds, channels, drains and
associated works. The appellant M/s Dyna Technologies Pvt. Ltd.
gave its proposal, estimate and quotation for carrying out the work.
Thereafter, the respondent CGL placed a letter of intent dated 25th
July, 1994, relevant portions of which are as under:
“10. In the event that you are forced to keep your equipment and manpower idle due to non availability of work fronts due to reasons attributable to DCM or due to legal disturbances not connected with you, you shall be compensated as follows:
(i) Maximum seven days of stoppage of work without any compensation.
(ii) CGL reserves the right to advice you to demobilize partially or fully in lieu of paying compensation for such delays. Under such circumstances, you shall be paid such
2
compensation towards transportation of equipment to Site at mutually agreed rates.
(iii) Suitable time extension shall be given to complete the work to compensate the delay caused due to the stoppage of work.
11. Storage & Security: you will be responsible to provide necessary stores, office and labour camps for your staff at site. Only open area for construction of above will be given to you. Electricity will be provided at one point on chargeable basis at actuals. You will be responsible to tap the same to your required place.
A format work order will be charged subsequently which will cover other General Terms and Conditions. Labour rules, Workmen Compensation etc. which may not be covered by this LOI and the same shall also be part of this LOI.”
4. The appellant made certain queries and clarifications, and by letter
dated 10th October, 1994, CGL amended the contract as suggested
by the appellant company. Thereafter, CGL issued work order on
15th November, 1994 setting out the terms and conditions of the
work, material portions of which are stated as under:
“2. Termination of contract: The Company reserves the right to terminate this work at any stage without payment of compensation due to any of the following reasons:
a. If the original contract between the client and the company is terminated/suspended.
3
b. The company is unable to proceed with the work due to reasons like nonavailability of work fronts, delay in availability of materials or delay in receipt of payments from clients etc.
c. If the contractor is not able to carry out work to the satisfaction of the company’s clients representatives.
d. If the contractor is unable to ensure adequate progress as required by the company and their purchaser.
e. Upon termination of this contract/work order, all rights and obligation of the parties, shall cease provided that the termination shall not relieve the contractor of any of his obligations which may have accrued upto the date of termination.
Upon termination of this contract/work order due to default on the part of the contractor, he /it shall indemnify the company against all losses incurred by the company as a result of such termination.”
5. After commencement of the work, the respondent CGL on 5th
January, 1995 instructed the employees of the appellant company
to stop the work.
6. The appellant company claimed compensation for such premature
termination of the contract and ultimately the dispute was referred
to Arbitral Tribunal consisting of three Arbitrators.
7. The appellantclaimant made the following claims:
(1)Losses due to idle charges.
4
(2)Losses due to unproductivity of the men and machineries which could not work due to hindrances.
(3)Loss of profit as the contract got dissolved and (4)Interest on the above claims and (5)Costs.
8. The aforementioned claims are listed in the statement of claims
totalling to Rs. 54,21,170.45 initially on 21st June, 1997 and
revised to Rs. 53,83,980.45 on 5th July, 1997.
9. The following is a summary of the final claims:
(1) Idle Charges for machineries and demobilisation as approved by Respondent
…Rs. 4,18,551.50
(2)Losses due to unproductive use of machineries …Rs. 45,85,286.00
(3)Loss of profit …Rs. 20,89,925.00 (4)And (5) Interest and Costs
Deduct Payment already received
… to be assessed
Rs. 70,93,763.33 Rs. 17,09,782.88 _____________________
Balance due Rs. 53,83,980.45 +
Interest and costs
10. It may be relevant to note at this stage that so far as claim no.
1 in reference to the losses due to idle charges is concerned, it was
5
finally settled amicably by the parties and the balance towards the
interest component also stands paid.
11. So far as claim no. 3 in reference to loss of profit is concerned,
the same was disallowed by the Arbitral Tribunal and it was later
not questioned by the appellantclaimant and that attained finality.
12. The only objection is in reference to claim no. 2, i.e., losses
due to unproductive use of machineries which was accepted by the
Arbitral Tribunal for a sum of Rs. 27,78,125/ with interest @ 18%
p.a. vide its award dated 30th April, 1998 and Correction to award
dated 5th May, 1998.
13. Aggrieved by the award passed by the Tribunal, an original
petition was filed before the learned Single Judge of the High Court
of Judicature at Madras, questioning the award under Section 34 of
the Arbitration and Conciliation Act, 1996 (hereinafter “Arbitration
Act”), by the respondent. The learned Single Judge, while upholding
the award of the Tribunal, observed as under:
“7. Thus the Arbitrators have given a specific finding that the amount paid as compensation is actually the amount expended by the fourth
6
respondent and therefore the petitioner is liable to reimburse the loss sustained by the fourth respondent. Therefore, this contention is also not acceptable.
… 9. Further, the learned counsel for the petitioner took this court to various portions of the Award and tried to convince this Court that the Arbitrators have not decided the issue fully appreciating the evidence on record. In the judgment of the Supreme Court reported in M/s Sundarsan Trading Company v. Government of Kerala (AIR 1989 Supreme Court 890) it has been clearly held that the power of the Arbitrator in respect of the interpretation of the contract in a matter for arbitration, the Arbitrator can pass the Award by taking a particular view of the contract and hence, the Court cannot substitute its own decision. Therefore, this Court cannot reappraise the evidence and substitutes its views and set aside the Award. Also in the case of Tamil Nadu Civil Supplies Corporation Limited v. Albert and Company (2000 (III) CTC 83), this Court has held that as per Section 34 of the Act, the Award of the Arbitrator can be set aside only on the limited grounds and the Award cannot be interfered with simply because another view is possible on the available materials. The arbitrator is a Judge of choice of parties and this Court cannot set aside unless it suffers from error apparent on the face of the record. It cannot be set aside even if the Court can come to different conclusion on the same facts. The learned counsel for the petitioner has not pointed out any such ground. It cannot also be said that the Award is perverse or has error apparent on the face of the record. Therefore, the Award passed by the Arbitrator is not illegal or invalid and cannot be set aside. Therefore, the petition is dismissed.”
7
(emphasis supplied)
14. Aggrieved by the aforesaid decision of the learned Single
Judge, the respondent appealed before the Division Bench in O.S.A
No. 234 of 2001. As aforementioned, the High Court vide impugned
order partly allowed the appeal and set aside the award of the
Tribunal relating to claim no. 2. The High Court was of the opinion
that the award does not contain sufficient reasons and the
statements contained in paragraph 3.1 (a) to 3.1 (g) of the award
does not provide any reasons, discussions or conclusion. The High
Court has observed in the following manner:
“18. It is of course true that an Arbitrator cannot be expected to write a detailed judgment as in a law Court. However, the present Act contemplates that the award of the Arbitrator should be supported by reason. The decision relied upon by the counsel for the respondent, rendered on the basis of the Arbitration Act, 1940, cannot be pressed into service keeping in view the specific provision contained in the Act. Moreover, even assuming that the ratio of the said decision is applicable, we cannot cull out any underlying reason in the award for directing payment of compensation. The basis for the right of the claimant and the basis of the liability of the present appellant have not been indicated anywhere within four corners of the award
8
and in spite of the best efforts it is not possible to discover even any latent reason in the award.
19. It was also contended that the discussion in para 3.1(g) of the award contains the basis and reason given by the Tribunal.
We have carefully gone through such paragraph as well as the preceding and subsequent paragraphs. In our considered opinion, the statements recited in para 3.1 including para 3.1(g) are only substance of the submissions/claim made by the claimant and para 3.1(g) cannot be construed as a conclusion or even the reasoning given by the Tribunal.”
15. Having come to a conclusion that the arbitral award was
deficient due to the lack of reasoning, the High Court proceeded
further to note that the option of Section 34 (4) of the Arbitration
Act was not necessary as the compensation could not have been
claimed considering the fact that the work order has provision
barring claim no. 2, in the following manner:
“20. Learned counsel for the respondent has relied upon Section 34(4) of the Arbitration Act and has submitted that in case if this Court finds that the Arbitral Tribunal has not given reason, even though it is so required under Section 31(3) by invoking jurisdiction under Section 31(4), this Court can give opportunity to the Arbitral Tribunal to resume the arbitral proceedings or to take action as in the
9
opinion of the Arbitral Tribunal would eliminate the grounds for setting aside the arbitral award.
21. We do not think that the present case is a fit case where the Arbitral Tribunal can be called upon to give reasons in support of its conclusion. This is because, in our considered opinion, the terms of the contract clearly exclude the possibility of payment of any compensation on account of premature termination of the contract as envisaged in para C. 2(a).”
16. Thereafter, the High Court proceeded further to note that the
arbitral proceeding was beyond the competence of the Tribunal by
considering the conditions under the work order.
17. Learned counsel for the appellant submits that the Arbitral
Tribunal comprising of three Arbitrators has looked into the entire
material available on record and recorded a finding in reference to
claim no. 2 (losses suffered due to unproductive use of machineries)
based on the case set up by the parties taking note of Section 73 of
the Indian Contract Act, 1872 (hereinafter “Contract Act”) and
relying on the evidence including appraisal of the log books
approved by the respondent and held that actual losses/expenses
were incurred by the appellant. In the given circumstances it was
not open for the High Court in appeal to reappraise and substitute
10
its own view in contravention of the clause of the agreement
pursuant to which the arbitral dispute was raised and a finding
came to be recorded in acceptance of the claim with regard to the
losses suffered by the appellant due to unproductive use of
machineries and the interference made by the High Court is beyond
the scope of Section 37 of the Arbitration Act.
18. Learned counsel further submits that the Division Bench of
the High Court did not hold that the evidence relied upon by the
Arbitral Tribunal, i.e., the log books were not proper or were lacking
quality. As a matter of fact, there was no challenge to the same in
the appeal filed by the respondent under Section 37 of the
Arbitration Act and only the liability was questioned. The learned
counsel further submitted that the only submission of the learned
counsel for the respondent before the Arbitral Tribunal and also
before the learned Single Judge of the High Court was that there
was no provision under the contract granting compensation for loss
incurred for unproductive use of machinery and that the Arbitral
Tribunal has exceeded its jurisdiction. This issue was examined by
the Tribunal and confirmed by the Single Judge of the High Court,
11
after examining the objections raised by the respondent under
Section 34 of the Arbitration Act. The learned counsel for the
appellant contented that interference at the appellate stage is
beyond the scope of Section 37 of the Arbitration Act and in the
given circumstances, claim no. 2 which has been set aside by the
Division Bench of the High Court under the impugned judgment
deserves to be interfered by this Court.
19. Learned counsel also submits that Section 73 of the Contract
Act confers a right which is for public interest/benefit and
contractual clause, if any, which takes away such a right
unilaterally of a party is violative of Section 23 of the Contract Act.
The law which is made for an individual’s benefit can be waived by
only by such individual, however, where law is for public interest or
has policy element, then such rights cannot be waived by an
individual person inasmuch as such rights are a matter of public
policy/public interest.
20. Learned counsel further submits that a contractual provision
which is in contravention of a specific statutory provision, if
allowed to be implemented, the same will result in frustration of a
12
right conferred by law or if the contractual clause is immoral or
opposed to public policy, in such cases the contractual clause is
invalid and void ab initio and cannot be enforced to disentitle
appellant in claiming the actual loss which has been suffered by it
and established before the Arbitral Tribunal and which the
respondent is under an obligation to reimburse. In the given
circumstances, claim no. 2 which has been set aside by the High
Court needs interference by this Court. The learned counsel in
support has placed reliance on the judgment of this Court in K.N.
Sathyapalan (Dead) by Lrs. v. State of Kerala, (2007) 13 SCC
43.
21. Per contra, learned counsel for the respondent, while
supporting the findings recorded by the High Court in the
impugned judgment, submits that the claim which has been
disallowed by the High Court in the impugned judgment is basically
a claim for payment of compensation or damages on account of
premature termination of contract and neither the Arbitral Tribunal
nor the learned Single Judge of the High Court has
considered/examined the terms of the contract in appreciating the
13
right of the claimant to claim compensation of damages and the
corresponding liability of the respondent to pay/settle the claim.
According to him, as per the terms of contract, no such
compensation was payable.
22. Learned counsel further submits that it is well settled that the
Arbitral Tribunal cannot travel beyond the terms of contract to
award compensation. As a matter of fact, in the present case, the
terms of contract expressly prohibit that no compensation is
payable if the contract is terminated on account of termination of
the project. In the face of such express prohibition, the Arbitral
Tribunal has exceeded its jurisdiction and committed a manifest
error in directing the payment of compensation even without
disclosing the basis of arriving at such a conclusion.
23. Learned counsel for the respondent submits that Section 34(2)
(a)(iv) of the Arbitration Act clearly envisages that such an award
can be set aside if the award deals with a dispute not contemplated
by or not falling within the terms of the submission to arbitration.
When there is a specific exclusion/prohibition in the contract, it
was not open for the Tribunal to travel beyond the terms of contract
14
in passing an award which has been taken note of by the Division
Bench of the High Court in the impugned judgment and has been
rightly set aside, supported by cogent reasons. The learned counsel
further submitted that what has been observed by the Division
Bench of the High Court in the impugned judgment is based on
settled principles of law and needs no interference.
24. We have heard learned counsel for the parties and with their
assistance perused the material available on record.
25. Before we devolve into the contractual issues, we need to
observe certain pointers on the jurisdiction of the court under
Section 34 of the Arbitration Act. Section 34 as it stood before the
Amendment Act of 2015, was as follows
“34 Application for setting aside arbitral award. — (1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with subsection (2) and subsection (3).
(2) An arbitral award may be set aside by the Court only if—
(a) the party making the application furnishes proof that—
(i) a party was under some incapacity, or
15
(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or (iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or (iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration:
Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or
(v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or
(b) the Court finds that—
(i) the subjectmatter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or (ii) the arbitral award is in conflict with the public policy of India.
Explanation. —Without prejudice to the generality of subclause (ii) it is hereby declared, for the avoidance of any doubt, that an award is in conflict with the
16
public policy of India if the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81.
(3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal: Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.
(4) On receipt of an application under subsection (1), the Court may, where it is appropriate and it is so requested by a party, adjourn the proceedings for a period of time determined by it in order to give the arbitral tribunal an opportunity to resume the arbitral proceedings or to take such other action as in the opinion of arbitral tribunal will eliminate the grounds for setting aside the arbitral award.
26. There is no dispute that Section 34 of the Arbitration Act
limits a challenge to an award only on the grounds provided therein
or as interpreted by various Courts. We need to be cognizant of the
fact that arbitral awards should not be interfered with in a casual
and cavalier manner, unless the Court comes to a conclusion that
the perversity of the award goes to the root of the matter without
17
there being a possibility of alternative interpretation which may
sustain the arbitral award. Section 34 is different in its approach
and cannot be equated with a normal appellate jurisdiction. The
mandate under Section 34 is to respect the finality of the arbitral
award and the party autonomy to get their dispute adjudicated by
an alternative forum as provided under the law. If the Courts were
to interfere with the arbitral award in the usual course on factual
aspects, then the commercial wisdom behind opting for alternate
dispute resolution would stand frustrated.
27. Moreover, umpteen number of judgments of this Court have
categorically held that the Courts should not interfere with an
award merely because an alternative view on facts and
interpretation of contract exists. The Courts need to be cautious
and should defer to the view taken by the Arbitral Tribunal even if
the reasoning provided in the award is implied unless such award
portrays perversity unpardonable under Section 34 of the
Arbitration Act.
28. Having established the basic jurisprudence behind Section 34
of the Arbitration Act, we must focus on the analysis of the case.
18
The primary contention of the learned counsel appearing on behalf
of the appellant is that the award by the learned Tribunal was
perverse for want of reasons. The necessity of providing reasons has
been provided under Section 31 of the Arbitration Act, which reads
as under:
“31. Form and contents of arbitral award.
…
(3) The arbitral award shall state the reasons
upon which it is based, unless—
(a) the parties have agreed that no reasons are to be given, or (b) the award is an arbitral award on agreed terms under section 30.”
(emphasis supplied)
Under the UNCITRAL Model Law the aforesaid provision is provided
as under:
“(2) The award shall state the reasons upon which it is based, unless the parties have agreed that no reasons are to be given or the award is an award on agreed terms under article 30.”
29. Similar to the position under the Model Law, India also adopts
a default rule to provide for reasons unless the parties agree
19
otherwise. As with most countries like England, America and Model
Law, Indian law recognizes enforcement of the reasonless award if it
has been so agreed between the parties.
30. There is no gainsaying that arbitration proceedings are not per
se comparable to judicial proceedings before the Court. A party
under Indian Arbitration Law can opt for an arbitration before any
person, even those who do not have prior legal experience as well.
In this regard, we need to understand that the intention of the
legislature to provide for a default rule, should be given rational
meaning in light of commercial wisdom inherent in the choice of
arbitration.
31. A fiveJudge Constitution Bench of this Court in the case of
Raipur Development Authority v. Chokhamal Contractors, AIR
1990 SC 1426, considered the scope of Section 30 of the Arbitration
Act, 1940 and held as under:
20
“It is now well settled that an award can neither be remitted nor set aside merely on the ground that it does not contain reasons in support of the conclusion or decisions reached in it except where the arbitration agreement or the deed of submission requires him to give reasons. The arbitrator or umpire is under no obligation to give reasons in support of the decision reached by him unless under the arbitration agreement or in the deed of submission he is required to give such reasons and if the arbitrator or umpire chooses to give reasons in support of his decision it is open to the Court to set aside the award if it finds that an error of law has been committed by the arbitrator or umpire on the face of the record on going through such reasons. The arbitrator or umpire shall have to give reasons also where the court has directed in any order such as the one made Under Section 20 or Section 21 or Section 34 of the Act that reasons should be given or where the statute which governs an arbitration requires him to do so.”
32. A threeJudge Bench of this Court in another case of S.
Harcharan Singh v. Union of India, (1990) 4 SCC 647, reiterated
its earlier view that the arbitrator's adjudication is generally
considered binding between the parties for he is a Tribunal selected
by the parties and the power of the Court to set aside the award is
restricted to cases set out in Section 30 of the Arbitration Act, 1940.
21
33. However, the ratio of Chokhamal case (supra) has not found
favour of the Legislature, and accordingly Section 31(3) has been
enacted in the Arbitration Act. This Court in Som Datt Builders
Ltd. v. State of Kerala, (2009) 4 ARB LR 13 SC, a Division Bench
of this Court has indicated that passing of a reasoned award is not
an empty formulation under the Arbitration Act.
34. It may be relevant to note Russell on Arbitration, 23rd edn.
(2007), wherein he notes that:
“If the Court can deduce from the award and the materials before it, which may include extracts from evidence and the transcript of hearing, the thrust of the tribunal’s reasoning then no irregularity will be found….Equally, the court should bear in mind that when considering awards produced by non lawyer arbitrators, the court should look at the substance of such findings, rather than their form, and that one should approch a reading of the award in a fair, and not in an unduly literal way.”
(emphasis supplied)
35. The mandate under Section 31(3) of the Arbitration Act is to
have reasoning which is intelligible and adequate and, which can in
22
appropriate cases be even implied by the Courts from a fair reading
of the award and documents referred to thereunder, if the need be.
The aforesaid provision does not require an elaborate judgment to
be passed by the arbitrators having regards to the speedy resolution
of dispute.
36. When we consider the requirement of a reasoned order three
characteristics of a reasoned order can be fathomed. They are:
proper, intelligible and adequate. If the reasoning in the order are
improper, they reveal a flaw in the decisionmaking process. If the
challenge to an award is based on impropriety or perversity in the
reasoning, then it can be challenged strictly on the grounds
provided under Section 34 of the Arbitration Act. If the challenge to
an award is based on the ground that the same is unintelligible, the
same would be equivalent of providing no reasons at all. Coming to
the last aspect concerning the challenge on adequacy of reasons,
the Court while exercising jurisdiction under Section 34 has to
adjudicate the validity of such an award based on the degree of
particularity of reasoning required having regard to the nature of
23
issues falling for consideration. The degree of particularity cannot
be stated in a precise manner as the same would depend on the
complexity of the issue. Even if the Court comes to a conclusion
that there were gaps in the reasoning for the conclusions reached
by the Tribunal, the Court needs to have regard to the documents
submitted by the parties and the contentions raised before the
Tribunal so that awards with inadequate reasons are not set aside
in casual and cavalier manner. On the other hand, ordinarily
unintelligible awards are to be set aside, subject to party autonomy
to do away with the reasoned award. Therefore, the courts are
required to be careful while distinguishing between inadequacy of
reasons in an award and unintelligible awards.
37. At this juncture it must be noted that the legislative intention
of providing Section 34 (4) in the Arbitration Act was to make the
award enforceable, after giving an opportunity to the Tribunal to
undo the curable defects. This provision cannot be brushed aside
and the High Court could not have proceeded further to determine
the issue on merits.
24
38. In case of absence of reasoning the utility has been provided
under of Section 34(4) of the Arbitration Act to cure such defects.
When there is complete perversity in the reasoning then only it can
be challenged under the provisions of Section 34 of the Arbitration
Act. The power vested under Section 34 (4) of the Arbitration Act to
cure defects can be utilized in cases where the arbitral award does
not provide any reasoning or if the award has some gap in the
reasoning or otherwise and that can be cured so as to avoid a
challenge based on the aforesaid curable defects under Section 34
of the Arbitration Act. However, in this case such remand to the
Tribunal would not be beneficial as this case has taken more than
25 years for its adjudication. It is in this state of affairs that we
lament that the purpose of arbitration as an effective and
expeditious forum itself stands effaced.
39. It may be noted that when the High Court concluded that
there was no reasoned award, then the award ceased to exist and
the Court was functus officio under Section 34 of the Arbitration Act
for hearing the challenge to the award under the provisions of
Section 34 and come to a conclusion that the arbitration award was
25
not in terms of the agreement. In such case, the High Court ought
to have considered remanding the matter to the Tribunal in the
usual course. However, the High Court analyzed the case on merits,
but, for different reasons and we need not go into the validity of
High Court’s interference.
40. Coming back to the award, we need to see whether the award
of the Arbitral Tribunal can be sustained in the instant case.
Although the Arbitral Tribunal has dealt with the claims separately
under different subheadings, the award is confusing and has
jumbled the contentions, facts and reasoning, without appropriate
distinction. The Tribunal rendered the award with narration of facts
with references to the annexures wherever it relied upon by it. The
Tribunal abruptly concluded at the end of the factual narration,
without providing any reasons, in the following manner:
“(3) Claim for unproductive usage of machineries …. (g) All the above facts clearly establish that the machineries deployed by the Claimant had to do unproductive work by shifting from one place to another to suit the availability of work.The contract contemplates only payment for actual turnover of earthwork and for this they had received amount totaling to Rs. 1709782.88. The
26
Claimant claims that the hire charges paid to the machineries, men and engineers should be reimbursed to him. He has given the actual expenses in his claim statement.
(emphasis supplied)
41. Interestingly, the factual narration is coupled with the
claimant’s argument, which is bundled together. A close reading of
the same is required to separate the same wherein the Arbitral
Tribunal has mixed the arguments with the premise it intended to
rely upon for the claimant’s claim. Further, it has reduced the
reasons for respondent’s defense. In spite of our independent
application of mind based on the documents relied upon, but
cannot sustain the award in its existing form as there is a
requirement of legal reasoning to supplement such conclusion. In
this context, the complexity of the subject matter stops us from
supplementing such legal reasoning and we cannot sustain the
aforesaid award as being reasoned.
42. It may be beneficial to reduce the concluding paragraph of the
award, which reads as under:
“3.4. The above arguments and various authorities quoted by them have been studied by the Tribunal and we are convinced that the compensation is
27
payable on the hire charges and expenses incurred by the claimant based on the claims made by him in June 95 and now submitted by the claimant in his revised claim petition on 05.07.1997. We are convinced that the machineries have been actually mobilized from the letter R3, R8 and R10 issued by DCM reporting on the number of machineries deployed by Claimant. The Claimants have produced the log books and bills for the various machineries and modified their claims. The tribunal had perused the log books and idle wages approved in C7 by Respondent and the claims made in R17.”
(emphasis supplied)
43. From the facts, we can only state that from a perusal of the
award, in the facts and circumstances of the case, it has been
rendered without reasons. However, the muddled and confused
form of the award has invited the High Court to state that the
arbitrator has merely restated the contentions of both parties. From
a perusal of the award, the inadequate reasoning and basing the
award on the approval of the respondent herein cannot be stated to
be appropriate considering the complexity of the issue involved
herein, and accordingly the award is unintelligible and cannot be
sustained.
28
44. In any case, the litigation has been protracted for more than
25 years, without any end for the parties. In totality of the matter,
we consider it appropriate to direct the respondents to pay a sum of
Rs. 30,00,000/ (Rupees Thirty Lakhs only) to the appellant in full
and final settlement against claim No. 2 within a period of 8 weeks,
failing which the appellant will be entitled to interest at 12% per
annum until payment, for providing quietus to the litigation.
45. In view of the conclusions reached, the appeal is disposed of to
the extent indicated herein. There shall be no orders as to the costs.
..............................................J. (N.V. RAMANA)
..............................................J. (MOHAN M. SHANTANAGOUDAR)
..............................................J. (AJAY RASTOGI)
NEW DELHI; DECEMBER 18, 2019.
29
30