KEYSTONE REALTORS PVT. LTD. Vs ANIL V. THARTHARE
Bench: HON'BLE DR. JUSTICE D.Y. CHANDRACHUD, HON'BLE MR. JUSTICE AJAY RASTOGI
Judgment by: HON'BLE DR. JUSTICE D.Y. CHANDRACHUD
Case number: C.A. No.-002435 / 2019
Diary number: 7891 / 2019
Advocates: Aman Raj Gandhi Vs
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No. 2435 OF 2019
Keystone Realtors Pvt. Ltd. …Appellant
Versus
Shri Anil V Tharthare & Ors. …Respondents
J U D G M E N T
Dr Dhananjaya Y Chandrachud, J
1. The present Civil Appeal arises from an order dated 11 February 2019 of
the Principal Bench of the National Green Tribunal 1 . In its order, the NGT held
that the increase in the total construction area of the appellant‟s project was an
“expansion” under a notification (bearing number S.O. 1533) dated 14 September
2006 2 of the Ministry of Environment and Forests. The NGT found that the
appellant had undertaken an “expansion” as set out in Paragraph 2 of the EIA 1 NGT
2 EIA Notification
2
Notification without complying with the regulatory procedure prescribed. The
appellant was directed to deposit an amount of Rupees one crore with the
Central Pollution Control Board 3 . Noting that the construction at the project site
had been completed, the NGT appointed a five-member expert committee to
study the impact of the appellant‟s expanded project and to suggest remedial
measures.
The facts
2. The appellant is the project proponent of a residential redevelopment,
called „Oriana Residential Project‟ situated at CTS no 646, 646 (Pt) Gandhinagar,
Bandra (East), Mumbai 400050. On 8 June 2010 the appellant received a
Commencement Certificate to carry out the development and erect a building
situated at the project property. The appellant began construction. When the
construction commenced, the total construction area was 8,720.32 square
metres. The ambit of the project was expanded, and the constructed area was
increased to 32,395.17 square metres. Under the EIA Notification, an
Environmental Clearance 4 was necessary if the total construction area exceeded
20,000 square metres. Hence, the appellant applied for an EC under the EIA
Notification.
3. The fourth respondent, the State Level Expert Appraisal Committee for
Maharashtra 5 recommended the grant of an EC for the project. On 2 May 2013
the third respondent, the State Level Environment Impact Assessment Authority
3 CPCB
4 EC
5 SEAC
3
for Maharashtra 6 , based on the recommendations of the SEAC granted an EC. It
is not in dispute that at the time when the EC dated 2 May 2013 was granted, the
total construction area of the project was 32,395.17 square metres. The grant of
the EC was conditional on the appellant obtaining a „consent for establishment‟
from the Maharashtra Pollution Control Board under the Air (Prevention and
Control of Pollution) Act 1981 and the Water (Prevention and Control of Pollution)
Act 1974.
4. By a letter dated 24 September 2013, the appellant informed the
Environment Department of the Government of Maharashtra, the second
respondent, that the construction area was being further increased by 8,085.71
square metres, as a result of which the total construction area of the project
would stand enhanced to 40,480.88 square metres. In its letter, the appellant
sought an „amendment‟ to the EC dated 2 May 2013 by the third respondent to
reflect the increase in the total construction area. On 13 March 2014, the third
respondent granted an „amendment‟ to the EC dated 2 May 2013 on the ground
that there was only a “marginal increase in built up and construction area”. The
third respondent noted the changes in the specification of the project as follows:
Description As per EC dated 2 May 2013
Amendment
FSI area
16,346.32 sq mts 21,365.54 sq mts
Non FSI area
16,048.85 sq mts 19,115.34 sq mts
Total Construction area
32,395.17 sq mts 40,480.88 sq mts
Nos of tenements
Members 64
Sale 61 Members 64
Sale 77
6 SEIAA
4
Building Configuration
Member 2 Basement
Member 2 Basement
5. The first respondent, claiming to be a resident of MIG Colony,
Gandhinagar, Bandra East, Mumbai, challenged the grant of the amended EC
dated 13 March 2014 before the Pune Bench of the NGT. In response, the
appellant filed two applications, challenging the standing of the first respondent
and contending that the challenge was barred by limitation. By an order dated 4
May 2016, the Pune Bench of the NGT rejected the applications questioning the
maintainability of the proceedings and setting up the bar of limitation. The
appellant filed a writ petition before the High Court of Judicature at Bombay to
challenge the decision of the Pune Bench of the NGT. The Bombay High Court,
allowing the writ petition held by an order dated 12 August 2016, that the appeal
was not maintainable at the behest of the first respondent, and the challenge
against the grant of the amended EC dated 13 March 2014 was barred by
limitation. By an administrative order dated 31 July 2018, the dispute was
transferred from the Pune Bench of the NGT to the Principal Bench which heard
the parties and delivered the impugned order.
Relevant clauses of the EIA Notification
6. The present dispute raises important questions regarding the interpretation
the EIA Notification. The EIA Notification seeks to ensure the protection and
preservation of the environment during the execution of new projects and the
expansion or modernisation of existing projects. It imposes restrictions on the
execution of new projects and on the expansion of existing projects, until their
5
potential environmental impact has been assessed and approved by the grant of
an EC. Paragraph 2 of the EIA Notification reads thus:
“2. Requirement for prior Environmental Clearance (EC): -
The following projects or activities shall require prior
environmental clearance from the concerned regulatory
authority, which shall hereinafter be referred to as the Central
Government in the Ministry of Environment and Forests for
matters falling under Category „A‟ in the Schedule and at
State level the State Environment Impact Assessment
Authority (SEIAA) for matters falling under Category „B‟ in the
said Schedule, before any construction work, or preparation
of land by the project management except for securing the
land, is started on the project or activity:
(i) All new projects or activities listed in the Schedule to this
notification;
(ii) Expansion and modernisation of existing projects or
activities listed in the Schedule to this notification with
addition of capacity beyond the limits specified for the
concerned sector, that is, projects or activities which
cross the threshold limits given in the Schedule after
expansion or modernisation;
(iii) Any change in product – mix in an existing manufacturing
unit included in Schedule beyond the specified range.”
(Emphasis supplied)
The Schedule to the EIA Notification classifies potential projects into Category „A‟
and Category „B‟ based on their size and potential environmental impact.
Category „A‟ projects require project proponents to secure an EC from the
Ministry of Environment, Forests and Climate Change. Category „B‟ projects
require project proponents to secure an EC from the SEIAA, based on the
recommendations of the SEAC. Where a project falls within the parameters
stipulated in the Schedule, paragraph 2 of the EIA Notification provides that no
construction work shall begin unless an EC is granted in regard to three types of
activity: (i) new projects or activities provided in the Schedule, (ii) expansion or
6
modernisation of existing projects or activities provided in the Schedule, and (iii)
changes in the product mix in existing manufacturing units provided in the
Schedule beyond the specified range. The present dispute raises questions as to
how the second type of activity, the “expansion” of existing projects, should be
construed under the EIA Notification.
7. In order to secure an EC, the project proponent must submit an application
in the manner set out in Form 1 and Supplementary Form 1A (if applicable) of the
EIA Notification. Under paragraph 7(i) of the EIA Notification, the project
proponent must also submit a pre-feasibility report. However, in the case of
projects under item 8 of the Schedule, only a conceptual plan is required to be
submitted. Paragraph 7(ii) of the EIA Notification states that:
“7(ii) Prior Environmental Clearance (EC) process for
Expansion or Modernisation of Change of product mix in
existing projects:
All applications seeking prior environmental clearance
for expansion with increase in the production capacity
beyond the capacity for which prior environmental
clearance has been granted under this notification or
with increase in either lease area or production capacity in
the case of mining projects or for the modernisation of an
existing unit with increase in the total production capacity
beyond the threshold limit prescribed in the Schedule to this
notification through change in process and or technology or
involving a change in the product mix shall be made in Form
1 and they shall be considered by the concerned Expert
Appraisal Committee or State Level Expert Appraisal
Committee within sixty days, who will decide on the due
diligence necessary including preparation of EIA and
public consultation and the application shall be appraised
accordingly for grant of environmental clearance.”
(Emphasis supplied)
7
Clause (ii) of paragraph 2 of the EIA Notification requires the project proponent to
secure an EC from the relevant regulatory authority prior to undertaking any
“expansion” of an existing project. Paragraph 7(ii) further stipulates that all
applications for an EC in cases of “expansion” resulting in the increase of
production capacity or lease area beyond the capacity/area stipulated in the
previous EC shall be made in the manner set out in Form 1 or 1A (as applicable).
8. The appellant‟s application in Form 1 acknowledges that the project fell
under entry 8(a) of Schedule 1 of the EIA Notification. Entry 8 deals with „Building
and Construction projects having a built-up area of or greater than 20,000 square
metres but less than 1,50,000 square metres.‟ Entry 8 of the Schedule to the EIA
Notification is as follows:
8 – Building / Construction projects / Area Development projects and Townships
8(a) Building and Construction projects
≥20,000 sq mts and <1,50,000 sq mts of built-up area
Built-up area for covered construction: in the case of facilities open to the sky, it will be the activity area
8(b) Townships and Area Development projects
Covering an area ≥ 50 ha and or built up area ≥1,50,000 sq mts
All projects under item 8(b) shall be appraised as Category B1
8
Issue
9. In applying for the original EC, the appellant submitted an application in
Form 1 as required under the provisions of the EIA Notification. The total
construction area identified in the appellant‟s Form 1 was 32,395.17 square
metres. However, in September 2013 the appellant informed the second
respondent of an increase by 8,085.71 square metres as a result of which the
total construction area of the project would be 40,480.88 square metres. In
seeking an „amendment‟ to the EC dated 2 May 2013 the appellant did not submit
an updated Form 1. Further, the „amendment‟ to the EC was granted by the
SEIAA without the recommendations of the SEAC. The issue before this Court is
whether the „amended‟ EC dated 13 March 2014 granted by the SEIAA without
following the procedure stipulated in paragraph 7(ii) of the EIA Notification is
valid.
Submissions
10. Mr Mukul Rohatgi, learned Senior Counsel appearing on behalf of the
appellant submitted that:
(i) When construction began, the total construction area of the
appellant‟s project was 8,720.32 square metres. As the EIA
Notification requires projects with a total built up area of or more
than 20,000 square metres to procure an EC prior to the start of
construction, no EC was required before construction of the
appellant‟s project commenced;
9
(ii) Pursuant to the first increase, when the appellant‟s project crossed
the 20,000 square metre threshold provided for in the EIA
Notification, the appellant submitted a Form 1 and was granted a
valid EC dated 2 May 2013 by the third respondent;
(iii) Pursuant to the second increase, the built up area of the appellant‟s
project only marginally increased by 8,085.71 square metres to a
total construction area of 40,480.88 square metres, which is within
the upper limit of 1,50,000 square metres prescribed by entry 8(a) of
the Schedule to the EIA Notification. Therefore, the second increase
was not an “expansion” within the meaning of clause (ii) of
paragraph 2 of the EIA Notification and no fresh Form 1 or EC was
required at the time of the second increase;
(iv) Clause (ii) of paragraph 2 only applies to situations where the
project crosses the lower or upper threshold limits stipulated in the
Schedule. Any increase in production capacity or construction area
within the limits set out in the Schedule would not constitute an
“expansion” within the meaning of Clause (ii) of paragraph 2 and
does not require compliance with the procedure under paragraph
7(ii) of the EIA Notification;
(v) The increase in the appellant‟s project is only marginal and does not
have an adverse impact on the environment;
(vi) The SEIAA applied its mind to the appellant‟s request for an
„amendment‟; noted that the increase in construction area was only
10
marginal and issued an amendment to the original EC dated 2 May
2013; and
(vii) The NGT had no basis to impose the fine of Rupees one crore on
the appellant.
11. Joining issue with the above submissions, Mr Aditya Pratap, learned
counsel appearing on behalf of the first respondent submitted that:
(i) Under clause (ii) of paragraph 2 read with paragraph 7(ii) of the EIA
Notification, any expansion beyond the “threshold limit” requires a
fresh EC. The appellant‟s project had crossed the threshold limit of
20,000 square metres and the second increase of 8,085.71 square
metres constituted an „expansion beyond the threshold limit‟ and
hence required a fresh EC;
(ii) Once a project breaches the lower threshold limit set out in the
Schedule to the EIA Notification, any expansion or modernisation,
even within the upper threshold set out in the Schedule, will require
the submission of a fresh Form 1 and the matter to be placed before
the Expert Appraisal Committee or the SEAC, as applicable in
accordance with paragraph 7(ii) of the EIA Notification;
(iii) Adopting the appellant‟s interpretation of clause (ii) of paragraph 2
would defeat the object and purpose of the EIA Notification as a
whole. It would allow project proponents to incrementally increase
11
the construction area and over time significantly impinge on the
environmental impact of the project without seeking a fresh EC;
(iv) If the law prescribes an act to be done in a particular manner, it
must be done only in that manner and no other. Under paragraph
7(ii) of the EIA Notification, it was incumbent on the SEIAA to place
the matter before the SEAC for appraisal and recommendations;
and
(v) The EIA Notification is an operationalisation of the precautionary
principle, which forms a part of the environmental law of India. The
EIA Notification must be read in a manner which gives effect to the
precautionary principle.
Interpreting paragraphs 2 and 7
12. The central controversy between the parties to the present dispute is the
manner in which paragraphs 2 and 7 of the EIA Notification should be interpreted.
Clause (ii) of paragraph 2 of the EIA Notification stipulates that a project
proponent shall require an EC prior to the start of construction in the case of an
“expansion”. Clause (ii) uses the phrase “expansion…beyond the limits specified
for the concerned sector”. The first respondent sought to lay emphasis on this
construction to argue that any expansion beyond the lower limit stipulated in the
Schedule would attract the requirement of a prior EC under paragraph 2.
However, the above language in clause (ii) is further qualified by the phrase “that
is, projects or activities which cross the threshold limits given in the Schedule
12
after expansion or modernisation.” A plain reading of the second half of clause (ii)
would indicate that it applies to cases where a project was initially below the
threshold limits stipulated in the Schedule but after the proposed expansion,
would breach the threshold limits. Clause (ii) of paragraph 2 of the EIA
Notification therefore would not appear to cover a case where a project had
already crossed the lower threshold limit set out in the Schedule and the
expansion does not cross the upper limit stipulated by the Schedule.
13. However, clause (ii) of paragraph 2 must be read with paragraph 7(ii) of
the EIA Notification. Paragraph 7(ii) lays down the exact procedure to be followed
by a project proponent in the case of an expansion. Two crucial points must be
noted with respect to paragraph 7(ii). First, it uses the phrase, “expansion with
increase in production capacity beyond the capacity for which prior environment
clearance has been granted”. Second, the qualifying language referring to
breaching the threshold limits “after expansion” is absent. An “expansion” can
occur even after the grant of an EC when the project first crossed the lower limit
stipulated in the threshold and it is not necessary for the project to breach the
upper limit after the expansion. Therefore, a close reading of paragraph 7(ii)
would support the interpretation put forth by the first respondent – that even after
obtaining an EC if the project is expanded beyond the limits for which the prior
EC was obtained, a fresh application would need to be made even if the
expansion is within upper the limit prescribed in the Schedule.
13
14. The dangers effectively articulated by the learned counsel for the first
respondent are real. If clause (ii) of paragraph 2 does not cover a case where the
expansion is within the limits stipulated by the Schedule, a project proponent may
incrementally keep increasing the size of the project area over time resulting in a
significant increase in the project size without an assessment of the
environmental impact resulting from the expansion. Such an outcome would
defeat the entire scheme of the EIA Notification which is to ensure that any new
or additional environmental impact is assessed and certified by the relevant
regulatory authorities. In the present case, the lower limit of Entry 8(a) of the
Schedule is a built up area of 20,000 square metres and the upper limit is
1,50,000 square metres. It cannot be doubted that the environmental impact of a
construction of 1,50,000 square metres is drastically more than construction of
20,000 square metres. If the appellant‟s argument is accepted in totality, a project
proponent could potentially secure an EC for constructing 20,000 square metres
and by „amendment‟ steadily increase the area of construction up to 1,50,000
square metres without submitting an updated Form 1 or any substantive review
by the SEAC.
15. We note that subsequent to the EIA Notification being published in 2006, a
draft notification was issued on 19 January 2009. 7 The draft notification proposed
the following amendment:
“in para 2 [of the EIA Notification], after sub-para (iii), the
following shall be inserted; namely:-
7 Notification S.O. 195 (E) dated 19 January 2009.
14
However modernisation or expansion proposals without any
increase in pollution load, and, or without any additional water
and or land requirement are exempted from the provisions of
this Notification:
Provided that, a self certification, stating that the proposals
shall not involve any additional pollution load, waste
generation or water requirement, be submitted to the
regulatory authority by the project proponent.”
Prior to adopting the draft notification, hearings were conducted and written
comments were solicited from various stakeholders including: (i) Central
Ministries and Departments, (ii) State Governments and their Agencies, (ii)
Industries and their Associations and (iv) Civil Society including NGOs. A
committee was constituted by the Ministry of Environment and Forests,
Government of India which published a report in October 2009. The committee
specifically recommended against the adoption of the above amendment, noting:
“The amendments propose to exempt modernisation and
expansion of projects based on a self certification by project
authorities that there is no increase in pollution load. It is
totally unacceptable that the modernisation and
expansion of projects be removed from the
environmental clearance regime, with or without the
requirement of self certification. There are several
industries operating in critically polluted areas or are in
violation of their environmental clearance conditions, which
need to be considered before the expansion of a project is
considered. What is to be considered is not just whether there
is an increase in pollution load but also the current impact of
the project and its compliance with environmental clearance
conditions. We can provide clear examples wherein the non-
compliance of the clearance conditions has not been
considered while granting clearance for expansion which
includes adding new components to the existing industrial
operations etc. This has allowed several projects to continue
their activities and expand despite blatant non compliance.
Finally, it is only with industrial, thermal power and other such
related operations that one can decide on parameters of
pollution. Development projects like highways, airports
and other infrastructure projects which seek to expand
might have a detrimental impact due to factors such as
15
change in land use (i.e. construction over a wetland,
grassland or agricultural land etc). Despite this, the project
proponent can certify that there is no change in pollution load
and hence expansion is to be allowed. The current process
seeks a detailed EIA report to determine whether impacts
can be mitigated. If the amendment is brought into force,
it will simply do away with this critical and necessary
step in the environmental clearance process. Therefore,
this amendment should not be allowed.
…
The draft notification takes a myopic view of environmental
and social impact of modernisation and expansion. Any
modernisation/expansion projects will necessarily entail
increase in production, increase in transportation,
increase in pressure on the local infrastructure and local
natural resources and increase in the pollution load
during the construction phase. So, even if a
modernisation/expansion does not lead to an increase in the
pollution load or water or land requirement within the factory
premises during the operation phase, it will lead to an
increase in environmental and social impact outside the
premise.”
(Emphasis supplied)
The draft amendment was not adopted in subsequent amendments to the EIA
Notification. We find considerable merit in the observations of the committee that
the requirement of an EC at the time of expansion forms a critical step in the
environmental clearance regime. According to the committee, it assists officials
not just in evaluating and mitigating any adverse impact caused by the expansion
but also in assessing whether the project proponent is in compliance with their
existing obligations. Crucially, any form of expansion necessarily puts a strain on
the local environment and infrastructure and needs to be carefully evaluated in a
holistic manner.
16
16. In a case where the text of the provisions requires interpretation, this Court
must adopt an interpretation which is in consonance with the object and purpose
of the legislation or delegated legislation as a whole. The EIA Notification was
adopted with the intention of restricting new projects and the expansion of new
projects until their environmental impact could be evaluated and understood. It
cannot be disputed that as the size of the project increases, so does the
magnitude of the project‟s environmental impact. This Court cannot adopt an
interpretation of the EIA Notification which would permit, incrementally or
otherwise, project proponents to increase the construction area of a project
without any oversight from the Expert Appraisal Committee or the SEAC, as
applicable. It is true that there may exist certain situations where the expansion
sought by a project proponent is truly marginal or the environmental impact of
such expansion is non-existent. However, it is not for this Court to lay down a
bright-line test as to what constitutes a „marginal‟ increase and what constitutes a
material increase warranting a fresh Form 1 and scrutiny by the Expert Appraisal
Committee. If the government in its wisdom were to prescribe that a one-time
„marginal‟ increase (e.g. 5% or 10%) in project size, within the threshold limit
stipulated in the Schedule, could be subject to a lower standard of scrutiny
without diluting the urgent need for environmental protection, conceivably this
Court may give effect to such a provision. This would be subject to any challenge
on the ground of their being a violation of the precautionary principle. However,
as the EIA Notification currently stands, an expansion within the limits prescribed
by the Schedules would be subject to the procedure set out in paragraph 7(ii).
17
17. At the time of the second increase, the total construction area of the
appellant‟s project was enlarged from 32,395.17 square metres to 40,480.88
square metres. As a result of the expansion, the appellant constructed sixteen
additional flats which were sold at the prevailing market rate. The appellant did
not comply with the procedure set out under paragraph 7(ii) of the EIA
Notification but rather sought an „amendment‟ to the EC. The third respondent did
not require the appellant to submit an updated Form 1 nor was the proposal
processed and evaluated by the fourth respondent. The „amendment‟ to the EC
dated 13 March 2014 does not discuss the potential environmental impact of the
increase in construction area, but merely records that the construction area now
stands at 40,480.88 square metres. The procedure set out under paragraph 7(ii)
of the EIA Notification exists to ensure that where a project is expanded in size,
the environmental impact on the surrounding area is evaluated holistically
considering all the relevant factors including air and water availability and
pollution, management of solid and wet waste and the urban carrying capacity of
the area. This was not done in the case of the appellant‟s project. It was not open
to the third respondent to grant an „amendment‟ to the EC without following the
procedure set out in paragraph 7(ii) of the EIA Notification.
18. We further note that as on the date of the impugned order construction at
the project site had already been completed. A core tenet underlying the entire
scheme of the EIA Notification is that construction should not be executed until
ample scientific evidence has been compiled so as to understand the true
environmental impact of a project. By completing the construction of the project,
18
the appellant denied the third and fourth respondents the ability to evaluate the
environmental impact and suggest methods to mitigate any environmental
damage. At this stage, only remedial measures may be taken. The NGT has
already directed the appellant to deposit Rupees one crore and has set up an
expert committee to evaluate the impact of the appellant‟s project and suggest
remedial measures. In view of these circumstances, we uphold the directions of
the NGT and direct that the committee continue its evaluation of the appellant‟s
project so as to bring its environmental impact as close as possible to that
contemplated in the EC dated 2 May 2013 and also suggest the compensatory
exaction to be imposed on the appellant.
19. The appeal is dismissed. There shall be no order as to costs.
20. Pending application(s), if any, shall stands disposed of.
.……......................................................J [Dr Dhananjaya Y Chandrachud]
.……......................................................J
[Ajay Rastogi]
New Delhi; December 3, 2019.