27 August 2019
Supreme Court
Download

JAYESH H.PANDYA Vs SUBHTEX INDIA LIMITED THROUGH ITS DIRECTOR

Bench: HON'BLE MR. JUSTICE N.V. RAMANA, HON'BLE MR. JUSTICE MOHAN M. SHANTANAGOUDAR, HON'BLE MR. JUSTICE AJAY RASTOGI
Judgment by: HON'BLE MR. JUSTICE AJAY RASTOGI
Case number: C.A. No.-006300-006300 / 2009
Diary number: 18319 / 2008
Advocates: VIKAS MEHTA Vs URMILA SIRUR


1

REPORTABLE

IN THE SUPREME COURT OF INDIA

 CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO(s). 6300 OF 2009

JAYESH H. PANDYA & ANR. ….APPELLANT(S)

VERSUS

SUBHTEX INDIA LTD. & ORS.     ….RESPONDENT(S)

J U D G M E N T

Rastogi, J.

1. The  instant appeal is  directed against  the  final judgment

and Order dated 14th March, 2008 passed by the High Court of

Judicature at Bombay whereby the High Court while dismissing

the Arbitration Petition held that the appellants had waived their

right to the extension of time for completion of the arbitration

proceedings and making the award, beyond the stipulated period

of four months.

1

2

2. The seminal facts in brief relevant for the present purpose

are that the appellants are partners of a partnership firm by the

name Hetali Construction Company.   The first respondent is a

company incorporated under the Companies Act, 1956 and is a

claimant in the arbitral proceedings which was initiated pursuant

to  the arbitration agreement dated 28th  April,  2000.   The  first

respondent Subhtex India Limited instituted an application

under Section 11 of the Arbitration and Conciliation Act,

1996(hereinafter being referred to as the “Act 1996”) for

appointment of an Arbitrator in A.P. No. 150 of 2003 before the

High Court of  Judicature at Bombay despite resistance by the

present appellants that the agreement dated 28th April, 2000 was

a collusive and a forged document.   Initially, by an Order dated

14th November, 2003, late Shri Justice V.D. Tulzapurkar, former

Judge of this Court was appointed as a sole Arbitrator without

prejudice to the rights and contentions of the parties and it was

clarified that the views expressed in the order dated 14th

November,  2003 about the existence,  validity and effect of the

arbitration agreement were prima facie and it would be open to

be examined by the learned Arbitrator under Section 16 of the

Act,  1996.   The order passed by the Single Judge of the High

2

3

Court dated 14th  November, 2003 was a subject matter of

challenge in a writ petition filed under Article 226 of the

Constitution of India which was dismissed vide judgment  and

order dated 20th  January, 2004 with an observation that

adequate remedies are available under Section 16 of raising all

contentious issues relating to the existence of the arbitration

agreement and constitution of the Arbitral Tribunal, before the

Tribunal.

3. The order of the Division Bench of the High Court dated 20th

January, 2004 came to be challenged in a Special Leave Petition

(Civil)  No.  3919 of  2004 before this Court.  This Court  issued

notice on  8th  March,  2004  and stayed  proceedings  before the

learned Arbitrator until further orders.   Unfortunately, the sole

Arbitrator appointed  pursuant to  Order dated  14th  November,

2003 died in October, 2004. The said special leave petition was

dismissed on 24th  April, 2007 with the following observation as

under:­

“Heard.

In the facts  and circumstances  of the  present case,  we are not  inclined to exercise our  jurisdiction

3

4

under Article 136 of the  Constitution of India. The special leave petition is dismissed.

We are informed that Mr. Justice V.D. Tulzapurkar, former Judge of this Court, who was appointed as the Arbitrator, has passed away.

Counsel for the parties are agreed that Hon’ble Mr. Justice S.N. Variava, a former Judge of this Court be appointed in place of Mr. Justice V.D. Tulzapurkar, as the Arbitrator. We order accordingly. Learned Arbitrator shall fix his remuneration etc.

All the points including the existence, validity and enforceability of the contract, as indicated by the Division Bench in  its Judgment,  shall  be decided by the learned Arbitrator.

Parties are directed to appear before the learned Arbitrator on 4th of May, 2007 with a certified copy of this order for further directions. The address and contact numbers of the learned Arbitrator are as under:

7­B, Rockside, 116, Walkeshwar Road, Mumbai – 400 006.

Phone Nos. (022) 23620614, 23620598

Copy of this order be sent to the learned Arbitrator.”

4. It will be apposite to take note of the terms of the Arbitration

Agreement dated 28th April, 2000 relevant for the purpose which

are extracted hereunder:­

“1….

2….

3…

4

5

4. Arbitrator shall follow the procedure of allowing parties to  file  their  respective claims & contention and to file documents within reasonable time as the arbitrator may deem fit.

5.The arbitrator will make his award within a period of 4  months from the date of service of copy of agreement.

6.The arbitrator shall have power to extend the period  for  making  and publishing  the award  from time to time, with the consent of both the parties.

7.The Arbitrator shall give reasons for his award.

8.The arbitrator will follow provisions of Arbitration & Reconciliation Act, 1996.

The parties here to and the parties represented by party of the first part be bound by the award that will be given by arbitrator.”

5. In terms of the conditions of the agreement dated 28th April,

2000, apart from the procedure to be followed by the Arbitrator,

he was under an obligation to make his award within a period of

four months from the date of service of copy of agreement with a

proviso that the Arbitrator would have the power to extend the

period for making and publishing the award, with the consent of

both the parties.

6. Indisputedly, the first preliminary meeting before the

Arbitrator was held on 4th  May, 2007.   As per clause 5 of the

terms of the agreement dated 28th  April, 2000, four  months

5

6

period which was available at the disposal of the Arbitrator for

passing of an award in the ordinary course of his business

subject to extension with the consent of both the parties was to

expire on 4th  September, 2007.   The claimant was permitted to

file its statement of claims and a compilation of documents and

the defendants to the arbitral proceedings(appellants) were to file

written statement and counter claims on or before 6th July, 2007

and thereafter a discovery and inspection was to be completed by

27th  July, 2007 and the parties  were directed to  make their

statements of admission and/or denials by 10th August, 2007, in

respect of the documents disclosed.   A preliminary meeting was

to be held on 13th August, 2007.  The fact which came on record

is that the appellants alleged that they had received the

statement of claim on 6th June, 2007 and extension of time was

sought for compilation of documents in order to file their written

statement.   The compilation of documents was received on 15th

June, 2007.  The fact is that the time was consumed in exchange

of claims and counter claims and compilation of documents.

Date of 27th  August, 2007 was fixed for hearing before the

Arbitrator.   In the course of hearing, it was urged by the

appellants that even if the agreement dated 28th April, 2000 for

6

7

the sake for submission is to be taken as a genuine agreement,

arbitration proceedings have to be culminated within a period of

four months from the date of service of a copy of the agreement

and the time could be extended only with the consent of both the

parties.  He further contended that the appellants had refused to

consent to an extension of time; and since the Tribunal held its

first meeting on 4th May, 2007, the arbitral proceedings could not

be concluded within a period of four months; and no purpose is

going to be served to continue the arbitral proceedings further,

even with the hearing on the applications filed by the parties.

7. On objection being raised by the appellants before the

learned Arbitrator, in his meeting on 27th  August, 2007, it was

observed  that  had  this  point  been urged on 4th  May,  2007,  a

shorter time frame could have been fixed and dates would have

been allotted and proceedings could have been completed within

time.  In the given circumstances, it would be more appropriate if

the claimants obtain an extension of time or a clarification from

this Court that the time could be extended of the Tribunal even

without  the consent of the parties  to  the arbitral  proceedings.

7

8

The matter was adjourned for obtaining extension of time or a

clarification from this Court.

8. Indisputedly, no interim application was filed for extension

of time or a clarification in this Court, as a result, jurisdiction to

continue with the proceedings came to an end by passage of time

on 4th  September, 2007 and it was observed by the learned

Arbitrator  to continue with the arbitral  proceedings and  if the

issue so urged by  the parties is  raised  in writing, it  could be

decided at the appropriate stage.  Accordingly, learned Arbitrator

fixed a  meeting on 26th  October, 2007 in pursuance of the

communication dated 3rd  October, 2007.   At this stage, the

appellants filed a written application before the Arbitrator stating

therein that the  period of four  months from  the  date of first

preliminary meeting had expired on 4th September, 2007 and the

Arbitral  Tribunal  has become functus officio  with no power to

proceed with the arbitral proceedings any more.   But that came

to  be rejected  by the learned Arbitrator  vide  Order  dated 31st

December, 2007 which came to be challenged by the appellants

in Arbitration Petition( L) No. 59 of 2008 before the High Court of

Judicature at Bombay invoking Section 14 of the Act, 1996

8

9

seeking a  declaration that the  Arbitrator  has become  de jure

unable to perform his functions and the mandate to act as an

Arbitrator in the  arbitral  proceedings  between the  parties  has

terminated.   The arbitration petition filed at the instance of the

present appellants came to be dismissed by the High Court under

its Order dated 14th March, 2008 holding that the appellants by

their conduct have waived their defence to enforce a punctilious

observance of the time schedule of four months; and sustaining

objection would frustrate the object and purpose of the arbitral

proceedings and will bring the whole machinery provided by the

Act to facilitate an efficacious recourse to arbitration into a grave

peril which is a subject matter of challenge in the instant

proceeding before us.

9. Learned counsel for the appellants submits that there is no

dispute on facts that after Mr. Justice S.N. Variava, former Judge

of this Court, was appointed as a substitute Arbitrator pursuant

to the Order of this Court dated 24th  April, 2007, the first

preliminary meeting was held by the Arbitrator on 4th May, 2007

and in the hearing which took place before the Arbitrator on 27th

August, 2007, an objection was raised by the appellants that the

9

10

Arbitrator has to make his award within a period of four months

from the date of service of copy of the agreement and the time

could only be extended with the consent of both the parties.  The

appellants had instructed to refuse to consent to an extension of

time, and despite their specific objection, followed with an

application being filed at a later stage, noticing refusal to consent

for extension of time which had been arbitrarily rejected by the

Arbitrator,  and genesis of the terms of the agreement has not

been looked into by the learned Single Judge of the High Court

under the impugned judgment and after the expiry of four

months, in the absence of time being extended with the consent

of both the parties, the Arbitrator becomes functus officio and all

subsequent proceedings stands abated and has placed reliance

on the judgment of this Court in  NBCC Limited  Vs.  J.G.

Engineering  Private  Limited   1  and  submits that  order  of the

High Court of Bombay impugned herein is not sustainable in law

and deserves to be interfered by this Court.

10. Per contra, learned counsel for the respondents, while

supporting the finding recorded by the High Court in the

1 2010(2) SCC 385

10

11

impugned judgment submits that once the appellants have

participated in the arbitration proceedings which for all practical

purposes could not be concluded within a period of four months

and it reveals from the proceedings that delay in furnishing

written statements/counter claims were attributable to the

appellants and in the given circumstances, the very participation

in the arbitration proceedings with their right to claim objection

for extension of time for the Arbitrator to complete the arbitral

proceedings in submitting an award stands waived by their

implied consent and this has been noticed by the High Court in

the impugned judgment and submits that if the objection which

has been raised by the appellants is taken to its logical

conclusion the very object and intent of the Parliament in

enacting the law to facilitate an efficacious recourse to arbitration

will be in jeopardy and the High Court has rightly observed that

the Arbitrator is  justified in coming to the conclusion that the

appellants with their conduct waived their objection to enforce a

punctilious observance of the time schedule of four  months

under the terms of the agreement for the Arbitrator to conclude

the arbitral proceedings and it needs no interference by this

Court.

11

12

11. We  have  heard learned  counsel for the  parties  and  with

their assistance perused the material available on record.

12. As noted herein earlier, an application  was filed by the

appellants  under  Section 14 of the Act,  1996 before the  High

Court of Bombay with a declaration that the Arbitrator has

become de jure unable to perform his functions and the mandate

of the Arbitrator to act as an Arbitrator in the arbitral

proceedings between the parties stood terminated.  As already

mentioned, that came to be rejected by the High Court under its

Order dated 14th March, 2008 and because of the interim Order

passed by this Court dated 1st September, 2008, Arbitrator was

unable to conduct arbitral proceedings and the same is lying in

the storage for the last eleven years.

13. The indisputed facts manifest from the record are that after

the  appointment  of a substituted  Arbitrator, in compliance  of

Order of this Court dated 24th April, 2007, the first preliminary

meeting was held before the learned Arbitrator on 4th May, 2007

and four months from the date of first preliminary meeting was to

12

13

expire  on 4th  September,  2007 and  in  the hearing which took

place before the Arbitrator on 27th  August, 2007, objection was

raised by the appellants that apart from their objection that the

agreement dated 28th  April, 2000 is a collusive and forged

document, even if taken  at its face value, taking  note of the

clause of arbitration under the agreement dated 28th April, 2000,

the  Arbitrator  has to  make his  award within a  period of four

months from the date of service of a copy of the agreement and

time may be extended only with the consent of both the parties;

and despite an opportunity being granted by the learned

Arbitrator on their objection,  recording refusal  for extension of

time to the parties to obtain an extension of time or clarification

from this Court, no such application was filed by the

respondents/claimants either for seeking extension of time or for

clarification from this  Court.   The respondents, on the other

hand, vide application dated 1st October, 2007 expressly refused

not to file any application seeking extension or clarification from

this Court and when the Arbitrator proceeded with the

proceeding, a written application  was filed by the appellants

before the Arbitrator stating  inter alia  that four months period

had expired and the Arbitral Tribunal has become de jure unable

13

14

as an Arbitrator in this matter which came to be rejected by the

learned Arbitrator vide Order dated 31st December, 2007.

14. From the records before us, it is established that the

Arbitrator was unable to complete the arbitral proceedings within

four months from the date of the first preliminary meeting held

on 4th  May, 2007 in terms of clause (5) of the arbitration

agreement and objection to extend the time was recorded by the

appellants before the Arbitrator.   The Arbitrator having failed to

do so rejected their application by an Order dated 31st December

2007 that came to be challenged by the appellant invoking

Section 14 of the Act 1996 by filing an Arbitration Petition in the

High Court of Bombay with a declaration that the Arbitrator has

become je jure unable to perform his functions and the mandate

to act as an Arbitrator in the arbitral proceedings between the

parties stood terminated which came to be dismissed by the High

Court under the impugned judgment dated 14th March, 2008.

15. It is  necessary to mention Section 14 and 15 of the Act,

1996 for the sake of convenience which is as under:­

14

15

“14. Failure or impossibility to act—(1) The mandate of an arbitrator shall terminate and he shall be substituted by another arbitrator, if—

(a) he becomes de jure or de facto unable to perform  his functions or for other reasons fails to act without undue delay; and

(b) he withdraws from his office or the parties agree to the termination of his mandate.

(2) If a controversy remains concerning any of the grounds referred to in clause (a) of sub­section (1), a party  may, unless otherwise agreed by the parties, apply to the Court to decide on the termination of the mandate.

(3) If, under this section or sub­section (3) of Section 13, an arbitrator withdraws from his office or a party agrees to the termination of the mandate of an arbitrator, it shall not imply acceptance of the validity of any ground referred to in this section or sub­section (3) of Section 12.

15. Termination of  mandate  and substitution of arbitrator  — (1) In addition to the circumstances referred to in Section 13 or Section 14, the mandate of an arbitrator shall terminate—

(a)  where  he  withdraws from office for  any reason; or

(b) by or pursuant to agreement of the parties.

(2) Where the mandate of an arbitrator terminates, a substitute  arbitrator  shall  be  appointed according  to the rules that were applicable to the appointment of the arbitrator being replaced.

(3) Unless otherwise agreed by the parties, where an arbitrator is replaced under sub­section (2), any hearings previously held may be repeated at the discretion of the Arbitral Tribunal.

15

16

(4) Unless otherwise agreed by the parties, an order or ruling of the Arbitral Tribunal made prior to the replacement of an arbitrator under this section shall not be invalid solely because there has been a change in the composition of the Arbitral Tribunal.”

16. It is clear from the bare reading of sub­section 1(a) of

Section 14 that mandate of an arbitrator shall terminate if it fails

to act without undue delay.   In the present case, the first

preliminary meeting was held on 4th May, 2007 and the Arbitrator

in terms of the agreement was supposed to conclude and pass

the  award  within  a  period  of four  months  which  indisputedly

stood expired on 4th  September, 2007 and in the meantime the

appellants recorded their objection of not consenting for

extension of time beyond 4th   September, 2007 and thus, it can

be construed that parties were not in agreement for extension to

the mandate of the Arbitrator failing which the arbitral

proceedings automatically stood terminated.

17. Sub­section(2) of Section 14 clearly stipulates that if a

controversy remains concerning any of the grounds referred to in

clause (a) of sub­section (1), the  party  may,  unless  otherwise

agreed by the parties, apply to the Court to decide on the

16

17

termination of the mandate and the appellants rightly applied to

the Court for termination of the mandate of the Arbitrator

pursuant to the  provisions of this  Section and  the  Court  was

within its jurisdiction to decide accordingly.

18. It is true that the object of the scheme of the Act, 1996 is to

secure expeditious resolution of disputes and it is based on the

fulcrum of promptitude but at the same time the Arbitrator is

required to adjudicate the disputes in view of the agreed terms of

contract and the procedure.   Therefore, the arbitration

proceedings are supposed to be governed and run by the terms

as agreed by the parties.   The Arbitrator,  therefore, cannot go

beyond the clause of the arbitration agreement.   We all need to

respect the legislative intent underlying the Act.  The speedy and

alternative resolution to the dispute thus cannot be overlooked

but at the same time, proceedings have to be governed and run

by the terms agreed between the parties in concluding the

arbitral proceedings failing which it will frustrate the mandate of

the object of the Act with which  it  has been  legislated by the

Parliament to act upon on agreed terms and conditions of the

agreement in concluding the arbitral proceedings.  The exposition

17

18

of law has been considered by this Court in  NBCC  Limited

case(supra) in para 12 and 22 as under:­

“12. A perusal of the arbitration agreement quite clearly reveals that the arbitrator  has the  power to enlarge the  time to make and publish the award by mutual consent of the parties. Therefore, it is obvious that the arbitrator has no power to further extend the time beyond that which is fixed without the consent of both the parties to the dispute. It is an admitted position that the respondent did not give any consent for extension of time of the arbitrator. Thus given the situation, the arbitrator had no power to further enlarge the time to make and publish the award and therefore  his  mandate  had automatically terminated after the expiry of the time fixed by the parties to conclude the proceedings.

22. Taking into consideration the arguments of the appellant, it is necessary to  mention here that the Court does  not  have any  power to extend the time under the Act unlike Section 28 of the 1940 Act which had such a provision.  The Court  has therefore been denuded of the power to enlarge time for making and publishing an award. It is true that apparently there is no provision under the Act for the Court to fix a time­ limit  for  the conclusion of  an arbitration proceeding, but the Court can opt to do so in the exercise of its inherent power on the application of either party. Where however the arbitration agreement itself provides the procedure for enlargement of time and the parties have taken recourse to it, and consented to the enlargement of time by the arbitrator, the Court cannot exercise its inherent power in extending the time fixed by the parties in the absence of the consent of either of them.”

19. In the instant case, from the pleadings on record and

noticed by the High Court in its impugned judgment dated 14th

March, 2008, the proceedings stood terminated as the appellants

18

19

have not recorded their consent for extension of time which was

the requirement and essence of the conditions of the agreement

and the Arbitrator became  de jure  unable to perform his

functions after the expiry of four months from the date of first

preliminary meeting held on 4th May, 2007 but that was declined

by the High Court on the premise that after the appellants have

participated in the arbitral proceedings, that waived their right to

question extension of time as it was inpracticable for the

Arbitrator to  conclude the proceedings within a  period of four

months and the High Court was of the view that the Act has been

legislated with an object to  facilitate an efficacious recourse to

arbitration failing which it will be in grave peril.

20. The essential element  of  waiver is that there  must  be  a

voluntary and intentional relinquishment of a right.   The

voluntary choice is the essence of waiver.  There should exist an

opportunity for choice between the relinquishment and an

enforcement of the right in question.  It cannot be held that there

has been a waiver  of  valuable  rights where  the circumstances

show that  what  was done  was involuntary.   That apart, the

doctrine of “waiver” or “deemed waiver”   or “estoppel” is always

19

20

based on facts and circumstances of each case, conduct of the

parties in each case and as per the agreement entered into

between the parties and this exposition has been affirmed by this

Court in NBCC Ltd.(supra) regarding adherence to the imposition

of time limit for the conclusion of the arbitral proceedings.   The

parties  have to stand  by the terms of contract including the

Arbitrator.

21. The clause so referred indicates that the parties have

admittedly agreed and the time period so prescribed is final and

binding.  It means the arbitration proceedings should commence

and end within the prescribed period of time which in the instant

case was of four months and expired on 4th September, 2007 and,

there was no occasion for either party to raise an objection as

long as the time was available at the command of the Arbitrator

to conclude the arbitral proceedings and pass an award within

the time schedule fixed under the terms of contract as agreed by

the parties.

22. That apart, there is no provision under the arbitration

agreement to  condone the  delay  when agreement  between  the

20

21

parties binds them to see that the arbitration proceedings should

be concluded within the time prescribed.  This time restriction is

well within the scope and purport of the Act, 1996 at national

and international arbitrations.

23. The time fixed for the arbitration and/or schedule of time

limit in such arbitration proceedings, as it is recognised by law,

there is no reason not to accept the same, basically in the

present facts  and circumstances  where the  parties themselves

agreed to bind themselves by the time limit.  Section 14 read with

Section 15 of the Act, 1996 also recognise this mechanism and

after the expiry of four  months period from the date of first

preliminary meeting held on 4th May, 2007, the Arbitrator indeed

became de jure unable to perform his functions and the mandate

to act as an Arbitrator in the arbitral proceedings between the

parties as prayed for stood terminated.  

24. Consequently, in our considered view, the appeal deserves

to succeed and is accordingly allowed.   The judgment and order

of the High Court dated 14th  March, 2008 is hereby set aside.

21

22

The respondents are at liberty to ventilate their grievance as

admissible under the law.  No costs.

25. Pending application(s), if any, stand disposed of.

…………….………………………….J. (N.V. RAMANA)

……………..…………………………J. (MOHAN M. SHANTANAGOUDAR)

……………………………………….J. (AJAY RASTOGI)

NEW DELHI AUGUST 27, 2019

22