HARYANA URBAN DEVELOPMENT AUTHORITY Vs VIRESH SANGWAN
Bench: G.S. SINGHVI,SUDHANSU JYOTI MUKHOPADHAYA
Case number: C.A. No.-009691-009691 / 2011
Diary number: 36425 / 2010
Advocates: Vs
GAGAN GUPTA
1
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.9691 OF 2011 (Arising out of SLP(C)No.33789 OF 2010)
HARYANA URBAN DEVELOPMENT AUTHORITY .......APPELLANT
VERSUS
VIRESH SANGWAN & ANR ......RESPONDENTS
J U D G M E N T
Whether the appellant - Haryana Urban Development
Authority (HUDA) is obliged to ensure that no encroachment is
made on the plot allotted by it after possession thereof has
been delivered to the allottee is the question, which arises
for consideration in this appeal filed against the order of the
National Consumer Disputes Redressal Commission (for short,
'the National Commission') whereby the revision filed by the
appellant was dismissed and the orders passed by the State
Consumer Dispute Redressal Commission, Haryana (for short, 'the
State Commission') and District Consumer Disputes Redressal
Forum, Gurgaon (for short, 'District Forum') were approved.
Plot No. 478 (measuring 335.50 square meters), Sector
12-A was allotted by the competent authority of HUDA to Shri
Champat Jain in January 1986 subject to the terms and
conditions specified in allotment letter dated 23.1.1986 issued
2
under Regulation 5 (3) of the Haryana Urban Development
(Disposal of Land and Buildings) Regulations, 1978 (for short,
'the Regulations'). The possession of the plot was handed over
to Shri Champat Jain on 27.2.1998 by Shri Om Prakash, Junior
Engineer, HUDA, Gurgaon. The allottee accepted the possession
and signed the possession certificate, the relevant portions of
which are extracted below
“POSSESSION CERTIFICATE
Certified that I Om Prakash Junior Engineer Office of the Estate Officer, Gurgaon have carefully check the relevant paper and the Dimension of plot no. 478 sector 12-A Urban Estate Gurgaon and the size of the plot allotted to Shri Champat Jain s/o___________________ is given as under:-
1. Length of the plot 22.0 m
2.Breadth of the plot 17.0+13.50 - 15.25 m 2
3. Area 335.50 sq.m.
4. Rear set Back As per demarcation plan
5. Front set Back
Accordingly, on the basis of above details the possession of the plot has been given to the said allottee/Authorised person.
Sd/-
Junior Engineer
For Estate Officer
HUDA, Gurgaon.
I Champat Jain s/o Sh. J.C Jain the above named allottee of the Urban Estate, Gurgaon have taken the possession of the said plot as per above dimension, as allotted to me vide Estate Officer Allotment letter No. 1309 dated 23.01.1986.
As per the provision of Regulation 10 of the HUDA (Erection of Building) Regulations, 1979, I hereby note that I will give at least one week's notice to the Estate Officer before actually
3
commencing the erection of the building on the said site.
Memo No. 1477
Dated 27.02.1998
Name & signature of allottee”
After some time, Shri Champat Jain sold the plot to
Devender Yadav and Narender Yadav (both sons of Karan Singh)
and revised allotment letter dated 17.11.1999 was issued in
their names. After 6 years and 2 months, conveyance deed
dated 18.1.2006 was executed between HUDA acting through
Estate Officer, Gurgaon and the transferees as per the
requirement of Regulation 20 of the Regulations.
Within a week of the execution of conveyance deed,
the transferees sold the plot to the respondents by
registered sale deed dated 24.1.2006 and re-allotment letter
dated 3.3.2006 was issued in their favour.
At the time of execution of the sale deed, the
respondents did not raise any objection about the total area
of the plot or any encroachment made by the villagers. Even
after receiving the re-allotment letter, they did not make a
grievance about the encroachment allegedly made by the
villagers. However, after 1 year and 3 months, they filed a
petition under Section 12 of the Consumer Protection Act,
1986 for issue of a direction to HUDA to allot alternative
plot to them by asserting that there was deficiency in
service inasmuch as the actual area of the plot re-allotted
4
to them was less than 335.50 square meters and there was
encroachment on the plot. In support of their plea, the
respondents relied upon report dated 20.4.2007 allegedly
prepared by the Junior Engineer of HUDA.
In the reply filed on behalf of the appellant, the
respondents' assertion about fresh demarcation of the plot by
the Junior Engineer was disputed and it was denied that
gates of two houses of inhabitants of the village were found
in the area of the plot and chabutra and chhajja had been
constructed over the plot. It was also denied that the plot
was being used as passage and the Junior Engineer had
expressed his inability to get the encroachments removed.
By an order dated 19.11.2009, the District Forum
allowed the petition of the respondents and directed the
appellant to allot them alternative plot of the same size in
the same sector or in an adjoining sector. For coming to the
conclusion that the plot re-allotted to the respondents had
been encroached, the District Forum relied upon report dated
20.4.2007 of the Junior Engineer. This is evinced from the
following portion of order dated 19.11.2009:
“A perusal of case file shows that re-allotment letter bearing no. 1280 dated 03.03.2006 regarding plot no. 478, Sector 12-A measuring 335.50 Sq. Mtrs. was issued in favour of the complainants. A perusal of report dated 20.04.2007 given by Junior Engineer shows that he has gone to the plot No.478, Sector 12-A for demarcation. After giving demarcation it was found that the doors of the houses of the villages were opened in the plot no. 478 Sector 12-A, Gurgaon and Chabutra and Chajje
5
also existed there. The owners of those houses were creating obstruction in the demarcation of the plot no. 478 as there was no way going the their houses. Previously, a rasta of the village existed at that place.
In view of the above said report given by the junior engineer of the opposite parties, we hold that there was deficiency in service on part of the opposite parties. The complainants are entitled to an alternate plot of the same size in the same sector i.e. Sector 12-A or in a sector adjoining Sector 12-A on the same rates. The present order is ordered to be complied with within one month from the date of passing of this order. File be consigned to the records after making due compliance.”
The State Commission dismissed the appeal by simply
repeating the observations made by the District Forum that as
per the report of the Junior Engineer, there was encroachment
on the plot allotted to the respondents.
The National Commission negatived the appellant's
challenge to the order of the State Commission and dismissed
the revision filed by the appellant.
We have heard Ms. Anubha Agarwal, learned counsel for
the appellant and Mr. Gagan Gupta, learned counsel for the
respondents and carefully scrutinized the record.
In our view, the finding recorded by the District
Forum that there was deficiency in service on the appellant's
part is ex facie erroneous and the Sate Commission and the
National Commission committed serious error by confirming the
direction given by the District Forum for allotment of
alternative plot to the respondents. Unfortunately, none of
6
the consumer forums adverted to the fact that possession of the
plot was delivered to the original allottee Shri Champat Jain
on 27.2.1998 free from all encumbrances and there is no
provision in the Haryana Urban Development Authority Act, 1977
and the Regulations for redelivery of possession to the
transferees. One can easily visualise that after taking
possession of the plot allotted to him, Shri Champat Jain did
not take steps to protect the same and by taking advantage of
his absence at the site, the people from the neighbouring areas
may have opened their doors towards the plot or made some
encroachment. However, the appellant cannot be blamed for the
encroachment, if any, made after possession of the plot was
delivered to the original allottee. The respondents must have
executed the sale deed after inspecting the site. If there was
any encroachment or the area of the plot was less than the one
specified in the allotment/re-allotment letter, they would have
immediately lodged a protest with the vendor. However, the
fact of the matter is that the respondents did not raise any
objection in this regard and by taking shelter of a
manipulative report prepared by the Junior Engineer, they filed
complaint and succeeded in convincing the District Forum to
ordain allotment of an alternative plot.
In our considered opinion, the appellant cannot be
held responsible for the encroachment, if any, made after
possession of the plot had been delivered to Shri Champat Jain
7
and neither Devender Yadav and Narender Yadav, who purchased
the plot from Shri Champat Jain nor the respondents could
possibly accuse the appellant of deficiency in service in the
matter of allotment of plot on the ground that some people had
made encroachment on it.
In the result, the appeal is allowed, the impugned
order as also orders passed by the District Forum and the Sate
Commission are set aside and the complaint filed by the
respondents is dismissed. The parties are left to bear their
own costs.
...........................J. (G.S.SINGHVI)
...........................J. (SUDHANSU JYOTI
MUKHOPADHAYA) NEW DELHI; NOVEMBER 8, 2011.
8