GIAN CHAND Vs M/S YORK EXPORTS LTD.
Bench: GYAN SUDHA MISRA,V. GOPALA GOWDA
Case number: C.A. No.-004882-004882 / 2014
Diary number: 36349 / 2012
Advocates: PRAGATI NEEKHRA Vs
UTTARA BABBAR
Page 1
1
NON-REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 4882 OF 2014
(Arising out of SLP(C) No. 35139 of 2012)
GIAN CHAND & ORS. …APPELLANTS VERSUS
M/S. YORK EXPORTS LTD. & ANR. … RESPONDENTS
J U D G M E N T
V. GOPALA GOWDA, J.
Leave granted.
2. This Civil Appeal is directed against the
judgment and order dated 14.6.2012 passed in
Original Side Appeal No.9 of 2005 by the High Court
of Himachal Pradesh at Shimla, whereby it has
dismissed the appeal of the appellants herein by
concurring with the judgment and decree dated
3.10.2005 passed in Civil Suit No. 31 of 1997 by
Page 2
2
the learned Single Judge in decreeing the suit for
payment of money at 39,20,000/- with 6% interest
per annum from the date of institution of the suit
till the date of payment of decretal amount to the
respondents giving its reasons in the impugned
judgment though it did not entirely agree with the
reasonings provided by the learned single Judge.
Correctness of the same with regard to the interest
from the institution of the suit till the date of
payment is questioned by the appellants, urging
various facts and legal contentions.
3. For the sake of brevity and convenience in this
judgment, the parties are referred to as per the
rank assigned to them in the original suit
proceedings.
4. The plaintiffs (the respondents herein) and the
defendants (the appellants herein) executed an
agreement to sell 164 bighas, 7 biswas of land in
Page 3
3
question on 2.8.1995. As pre-condition for sale,
permission from the competent authority under
Section 118 of the Himachal Pradesh Tenancy & Land
Reforms Act (hereinafter referred to as “the Land
Reforms Act”) was necessary. The onus to obtain the
relevant permission was cast on the plaintiffs in
the agreement to sell. The plaintiffs managed to
obtain permission only for 145 bighas of land. As
the stipulated time for obtaining permission for
the entire area expired, the plaintiffs sought
extension of time from the defendants. This
extension was denied which eventually led to filing
of the suit in question. In the suit, the
plaintiffs pleaded frustration of contract and
sought refund of the money already paid with
interest. The learned single Judge decreed the
suit, finding that there was frustration of
contract.
Page 4
4
5. Aggrieved by the same, the defendants filed an
appeal before the Division Bench of the High Court.
The Division Bench held that :- (i) the contract
in question was not “frustrated” as understood in
Indian law in terms of Section 56 of the Contract
Act, 1872; (ii) the plaintiffs were at fault for
their failure to obtain the necessary permission
for the entire area as the obligation to obtain the
permission rested with them. The plaintiffs had
committed breach of the agreement, however, the
defendants had not committed any breach and (iii)
permission having been obtained for at least 145
bighas of land, sale could have been completed with
regard to this substantial portion of the suit
property. Aggrieved by the same, the defendants
have filed this appeal.
6. This Court vide order dated 3.12.2012 passed
the following order in the matter:-
Page 5
5
“
We have heard learned counsel for the petitioners and perused the record. In our view, the impugned judgment as also the judgment of the learned Single Judge does not suffer from any legal infirmity insofar as the decree for payment of the principal amount is concerned.
Issue notice only on the question of payment of interest by the petitioners on the amount which they had received from the respondent in furtherance of the main as well as the additional agreement, returnable on 06.02.2013. Dasti, in addition, is permitted.
Issue notice on the petitioners’ prayer for interim relief, returnable on 06.02.2013. Dasti, in addition, is permitted.
In the meanwhile, operation of the impugned judgment as also the judgment of the learned Single Judge shall remain stayed
Page 6
6
insofar as they relate to award of interest to the respondent.
The petitioners shall pay the principal amount to the respondent within a period of six weeks from today.
It shall be the petitioners' duty to serve the respondent before the next date of hearing failing which the interim order passed today shall stand automatically vacated.”
After service of notice in the Special Leave
Petition, the plaintiffs filed the counter
affidavit and the defendants also filed additional
documents. Thereafter, the matter was listed before
this Court for hearing on 31.01.2014. After hearing
Mr. Jayant Bhushan, the learned senior counsel
appearing on behalf of the defendants and Mr.
Deepak Sibal, the learned counsel for the
plaintiffs, this Court passed the order by
assigning the following reasons.
Page 7
7
7. At the time of issuing notice in the Special
Leave Petition on 03.12.2012, after hearing the
learned counsel on behalf of the defendants, this
Court issued notice only on the question of payment
of interest by the defendants and the amount which
they had received towards the part consideration
from the plaintiffs in furtherance of the principal
as well as the additional agreement. The learned
senior counsel Mr. Jayant Bhushan has questioned
the correctness of the impugned judgment of the
High Court in affirming the award of interest at
the rate of 9% per annum on the part of
consideration amount paid to the defendants. The
interest was to be paid at the rate of 9% per annum
prior to the institution of the suit and 6% on the
said amount from the date of decree till the date
of payment. The learned senior counsel contended
that the defendants are not liable to pay the same
Page 8
8
as the plaintiffs have committed breach of
agreement entered with them in not purchasing the
agricultural land to an extent of 145 bighas of
land in respect of which the State Government in
exercise of its power under Section 118 of the Land
Reforms Act granted permission to purchase the same
by the plaintiffs for the purpose of establishing
their factory, though the agreement of sale was
intended to purchase 164 bighas 7 biswas of land in
Khata Khatauni No. 98/105, Khasra No. 245, Mauza
Beerh Plassi, Pargana Plassi, Tehsil Nalagarh,
District Solan, Himachal Pradesh. The case of the
plaintiffs is that as per the agreement between the
parties entered on 2.8.1995, the defendants agreed
to sell the aforesaid property at the rate of
50,000/- per bigha and further agreed that the
sale deed was to be executed on 31.5.1996 but prior
to that date, the plaintiffs were required to pay a
sum of 15,03,500/- to the defendants.
Page 9
9
Undisputedly, this amount was also paid to the
defendants on 21.8.1995. The sale deed could not be
executed by the defendants in favour of the
plaintiffs by 31.5.1996 as the State Government
granted permission to the plaintiffs for purchase
of only 125 bighas of land under Section 118 of the
Land Reforms Act. Thereafter the parties renewed
the agreement on 31.5.1996. As per the renewed
agreement, the plaintiffs were to pay
18,00,000/- more which was also paid on 4.6.1996.
As per this agreement, the sale deed was to be got
executed by 31.12.1996. The State Government did
not grant permission to the full extent of land,
which is agreed to be sold in favour of the
plaintiffs. On the other hand, the State Government
allowed only to the extent of 145 bighas of land in
all to be purchased by the plaintiffs. The
plaintiffs did not get the sale deed executed. As
to the extent of land for which permission was
Page 10
10
granted by the State Government, according to the
plaintiffs, it was not sufficient for establishing
the factory. Therefore, the plaintiffs contended
that the contract is frustrated and therefore, they
filed Civil Suit No. 31 of 1997 before the learned
single Judge of the High Court for recovery of the
amount paid towards the part consideration along
with interest at the rate of 9% per annum up to the
date of finalization of the suit and 6% per annum
from the date of institution of the civil suit. The
said claim was opposed by the defendants traversing
plaint averments contending that the contract is
not frustrated as pleaded by the plaintiffs under
Section 56 of the Indian Contract Act, 1872 and the
plaintiffs are not entitled for the decree of money
including the interest as claimed by them and hence
they have prayed for dismissal of the suit.
Page 11
11
8. The learned single Judge of the High Court vide
order dated 3.10.2005 in Civil Suit No. 31 of 1997
framed 9 issues for his adjudication. After the
trial, the contentious issues framed in the civil
suit were answered in favour of the plaintiffs and
passed the decree to a sum of 39,20,000/- with 6%
interest per annum from the date of institution of
the suit till the date of payment of money. The
correctness of the reasons and findings answered on
the contentious issues in the judgment of the
learned single Judge was challenged before the
Division Bench of High Court urging various legal
contentions. The Division Bench of the High Court,
on the basis of the rival legal contentions urged
on behalf of the parties formulated the following
two points for its adjudication :-
“1. Whether the contract stood frustrated by the fact that the plaintiff did not get
Page 12
12
permission to purchase 164 bighas 7 biswas of land?
2. Whether the defendants were entitled to retain the amount paid to them by the plaintiff and if so, to what amount?”
After examining the correctness of reasons
recorded by the learned single Judge in holding
that the non-grant of permission by the State
Government to purchase 164 bighas 7 biswas of land
in favour of the plaintiffs in terms of the
agreement entered between the parties amounts to
frustration of contract as provided under Section
56 of the Contract Act was examined by the Division
Bench of the High Court. The Division Bench of the
High Court with reference to the reasons recorded
by the learned single Judge in the civil suit, on
the question of the frustration of the contract
between the parties, after adverting to the
relevant provisions of Section 56 of the Indian
Page 13
13
Contract Act, by assigning its own reasons, has
answered the same by holding that the decision that
the contract between the parties stands frustrated
is erroneous in law.
The Division Bench of the High Court held that
the finding recorded by the learned single Judge on
non-grant of permission to the entire 164 bighas 7
biswas of land as agreed between the parties to
sell in favour of the plaintiffs does not amount to
the frustration of contract for the reason that the
State Government at first granted permission to the
plaintiffs for purchase of 125 bighas and
thereafter granted permission to purchase 145
bighas of land. Further, the Division Bench of the
High Court has held that there is virtually no
material on record to show that after the second
permission was granted, the plaintiff took further
steps to get permission from the State Government
Page 14
14
for purchasing the remaining land. Even if such
permission was not granted and permission was
specifically refused, the contract between the
parties would not stand frustrated. It is further
rightly held by the Division Bench of the High
Court that the parties at the time of agreement
could not have presumed that the permission must be
granted. Further it has observed that supposing the
State Government refused to grant permission for
purchase of land, then obviously, it would be a
case of the contract not being able to be
performed. But, when the State Government grants
the permission for a lesser area of land than the
agreed upon area in the agreement by the
defendants, plaintiffs could not have elected to
purchase the lesser area, i.e. 145 bighas, for
which the permission was granted. Further, the
learned Division Bench of the High Court has
rightly rejected the argument of the plaintiffs
Page 15
15
that permission for purchase of 145 bighas of land
granted by the State Government in favour of the
plaintiffs, was not sufficient to set up the plant
as in this regard no evidence worth the name to
support this plea of the plaintiffs has been
produced before the Court. Further, the High Court
has rightly assigned its reasons on the basis of
the project reports of the plaintiffs, the State
Government and the Department of Industries, taking
all relevant aspects into consideration has decided
that permission should be granted in favour of the
plaintiffs only for purchase of 145 bighas of land.
This fact would clearly indicate that according to
the Industries Department, sale of land of 145
bighas in favour of the plaintiffs by the
defendants was sufficient to set up the industry
for which purpose the plaintiffs have entered into
an agreement with the defendants. Further, in the
impugned judgment the High Court assigned its
Page 16
16
reasons stating that the parties may or may not get
permission for the purchase of the entire land.
However, in the absence of such condition expressed
in the agreement, the contract between the parties
does not frustrate particularly, when the
plaintiffs had alternative to purchase 145 bighas
of land from the defendants. The Division Bench of
the High Court on the issue of frustration of
contract has relied upon the decisions of this
Court and various High Courts in support of its
reasons which are adverted in the impugned
judgment, which need not be referred to in this
judgment.
9. The Division Bench of the High Court did not
accept the finding of the learned single Judge who
had conducted the trial of the suit, who has
erroneously held that the contract stands
frustrated under Section 56 of the Contract Act.
Page 17
17
10. The Division Bench of the High Court has also
examined the said aspect of the matter by
adverting to the provisions of Sections 73, 74 and
75 in Chapter VI of the Indian Contract Act and
also taken into consideration the decisions of
various High Courts and this Court has held that
the defendants have not proved that they sustained
losses on account of the non performance of the
contract by the plaintiffs. The Division Bench of
the High Court with reference to the allegation
made by the defendants in their written statement
that they suffered loss in the liquor business is
not relatable to the contract and the same is not
supported by material evidence on record. It was
further submitted by the learned senior counsel
for the defendants that due to the breach of
contract on the part of the plaintiffs, the sum of
4,00,000/- in the agreement which is the earnest
Page 18
18
money and advance of 4,00,000/- shall be forfeited
towards loss of compensation. The Division Bench
after proper evaluation of the pleadings and
evidence on record has rightly rejected the said
contention and decreed the suit for sum of
39,20,000/- with 6% interest per annum from the
date of institution of the suit till the date of
payment of money and it has rightly recorded the
concurrent finding for grant of the decree in
favour of the plaintiff directing the defendants
for repayment of the consideration amount with
interest as mentioned above after holding that
there is no frustration of contract entered
between the parties though the sale of the land
could not take place for non grant of permission
to the entire extent of 165 bighas 7 biswas of
land, the said finding of fact is accepted by this
Court at the time of issuing notice and therefore,
the correctness of the same has attained finality
Page 19
19
for the reason that this Court at the time of
issuing notice to the plaintiffs has clarified
that this appeal is confined on the issue of
payment of interest awarded on decreetal amount
from the date of institution of the civil suit
till the payment to be made by the defendants to
the plaintiffs. The money being paid as part
consideration to the defendants has been utilised
by them in its liquor business. Therefore, award
of interest in the judgment against the principal
amount upto the date of the institution of the
suit at 9% and 6% thereafter from the date of
institution of case till the date of payment is
legal and valid as the said amount has been
utilized by the defendants in the liquor business
but they have failed to prove not obtaining the
sale deed in respect of the land agreed upon to be
sold in favour of the plaintiffs to the extent of
area for which permission was granted by the State
Page 20
20
Government. For the reasons stated supra, the
award of interest on the principal amount and
decreetal amount in the impugned judgment is
perfectly justifiable on the basis of the facts
and circumstances of the case.
11. In view of the reasons stated supra, we do not
find any reason whatsoever to interfere with the
impugned judgment and decree wherein the award of
interest at the rate of 6% per annum on the amount
decreed by the learned single Judge from the date
of institution of the suit need not be set aside by
this Court. Accordingly, the Civil Appeal is
dismissed, but with no order as to costs.
………………………………………………………………………J.
[GYAN SUDHA MISRA]
………………………………………………………………………J. [V. GOPALA GOWDA]
Page 21
21
New Delhi, April 25, 2014